Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Anil Puranmal Bansal vs Leena Tulsi Bhimjiyani
2025 Latest Caselaw 218 Bom

Citation : 2025 Latest Caselaw 218 Bom
Judgement Date : 8 May, 2025

Bombay High Court

Anil Puranmal Bansal vs Leena Tulsi Bhimjiyani on 8 May, 2025

  2025:BHC-OS:7773


                                                                                        ARBPL-13399-2025 - FINAL.docx



                                         IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                              ORDINARY ORIGINAL CIVIL JURISDICTION
                                            ARBITRATION PETITION (L.) NO. 13399 OF 2025
                      Anil Puranmal Bansal                                    .. Petitioner
         Digitally
         signed by
         SHRADDHA
SHRADDHA KAMLESH
KAMLESH TALEKAR
                            Versus
TALEKAR  Date:
         2025.05.08
         14:19:58
         +0530        Leena Tulsi Bhimjiyani                                  ..Respondent



                           Mr. Sanjay Jain, Counsel a/w. Krutika Kadam i/b LJ Law, for Petitioner.
                           Mr. Sharan Jagtiani, Senior Counsel a/w. Mayur Khandeparkar, Akshay
                           Doctor, Dhawani Bokaria , Kartikeya Awasthi i/b Purnanand & Co.,
                           Advocates for Respondent No. 1 to 3.
                           Mr. Karl Tamboly a/w. Ms. Naira Jejeebhoy, Mr. Malcolm Siganporia, Mr.
                           K. K. Billimoria and Ms. Leandra Silveira i/b Desai Billimoria & Associates,
                           for Respondent No. 4.


                                        CORAM                : SOMASEKHAR SUNDARESAN, J.
                                        Date                 : May 8, 2025


                      ORAL JUDGEMENT:

                      Context and Factual Background:


1. This Petition has been filed by the Petitioner, Anil Puranmal Bansal

("Bansal") under Section 37 of the Arbitration and Conciliation Act, 1996 (" the Act")

challenging an order dated April 25, 2025 (" Impugned Order") passed by a Learned

Arbitral Tribunal under Section 17 of the Act. The Impugned Order directs a

Commissioner to visit Bansal's flat (and one other flat), which is part of a building

whose redevelopment is subject matter of the arbitration proceedings. The

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

Commissioner is to inspect the renovation work carried out therein and make a

report.

2. Bansal is entitled to Flat No. 301 in a building of Respondent No. 4, Sea

Green Co-operative Housing Society (" Society") in Worli. The disputes between the

parties relate to a Development Agreement dated September 23, 2006

("Development Agreement"). Respondents No. 1 to 3 (collectively, " Developer") are

counterparties to the Development Agreement. The Society and all its members are

Respondent Nos. 4 to 29.

3. The cause of action pursued in this Petition is a very specific and narrow one.

Bansal is of the view that the Impugned Order directing that the Commissioner to

inspect his Flat No. 301 deserves to be interfered with, since it has been passed

without him having filed a reply to an application seeking the very same relief.

Bansal would also submit that the Impugned Order has been passed in a tearing

hurry without any justification as to why such an order had to be passed without

waiting for a reply and a final hearing in the matter.

4. Disputes and differences over the Development Agreement had led to the

initiation of arbitration proceedings. Eleven floors were constructed and the

members were accommodated on them. A partial occupation certificate was

obtained for these floors. The disputants entered into discussions for an amicable

settlement and this had continued from time to time, also intermittently leading to

the mandate of the Learned Arbitral Tribunal being extended.

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

5. Currently, the Society and all but some members appear to have resolved

their differences, leaving out Bansal (Original Claimant No. 3) and one more

member (one Mr. Dilip Sujan, Original Claimant No. 6, who is entitled to Flat No.

601). These two members are not interested in settling the disputes with the

Developer, insisting as they do that the Developer is in gross violation of

commitments made in the Development Agreement and would need to account for

such breaches. These two members are now the Claimants in the arbitral

proceedings and the rest of the members and the Society are transposed in form, as

respondents.

6. There is a long legacy of litigation in the matter including a stop work notice

from environmental authorities which led to a full round of parallel litigation. For

purposes of this Petition and this judgment it is not necessary to set out a prolix

description of all that has transpired during the course of the Development

Agreement.

Alleged Structural Changes and Renovation:

7. In the course of the arbitral proceedings, an application dated April 29, 2023

had been filed by the Developer under Section 17 of the Act, alleging that illegal

alterations and structural changes were being effected in a few flats including Flat

No. 301. That led to an order dated July 13, 2023 (" July 2023 Order") by the

Learned Arbitral Tribunal appointing a Commissioner who was meant to inspect

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

the flats alleged to have undergone structural changes and alterations. Status quo

obtaining as of that date was ordered to be maintained.

8. Since the parties were exploring settlement, they agreed to keep the survey

and inspection of various flats in abeyance. This was recorded by an order dated

September 27, 2023 ("September 2023 Order").

Section 17 Application:

9. On February 18, 2025, Bansal filed an application under Section 17 of the Act

("Section 17 Application"), alleging that the Developer's conduct would show that

the Society and its members were merely being strung along in the name of a

settlement. The Section 17 Application sought a deposit of various sums said to be

owed under the Development Agreement to secure these amounts in aid of the

arbitration proceedings.

Contempt Application:

10. More recently, the Developer filed an application dated April 11, 2025,

("Contempt Application"), alleging contempt of the July 2023 Order. It was alleged

that various structural changes had been effected by owners of Flats, 101, 102, 201,

301 and 302 that was in conflict with the plans on which the partial occupation

certificate was based. It was alleged that in respect of Flat No. 301, Bansal had

modified the flower bed and filled it up to expand the kitchen, changed a sloping

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

roof by demolishing a niche between the roof and the flat, and had expanded the

carpet area illegally. The Developer alleged that such changes would jeopardise the

Developer's ability to obtain the final complete occupation certificate. In the

Contempt Application, urgent interim relief of restraint on further changes were

sought. The Contempt Application also contains a prayer to direct Bansal to restore

Flat No. 301 to its original compliant position, or in the alternative to permit the

Developer to carry out such restoration work to bring it in compliance.

Modification Application:

11. On the same date i.e. April 11, 2025, the Developer also filed an application

seeking modification of the July 2023 Order read with the September 2023 Order.

Since the Society has settled with the Developer and only the owners of two flats

were holding out, it was prayed that these two orders of the Learned Arbitral

Tribunal be modified to restrict the survey and inspection to only Flat No. 301 and

Flat No. 601 i.e. the members who were still in dispute with the Developer.

Analysis and Findings:

12. The Impugned Order is a common order passed on the Contempt

Application and the Modification Application. These applications were mentioned

as a matter of urgency by the Developer on a WhatsApp Group titled "Sea Green

Arbitration" comprising all the parties to the arbitration proceedings. The Petition

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

has appended a transcript of the written conversations and applications contained

in the WhatsApp Group. The Developer has tendered across the bar, an email sent

prior to the WhatsApp chat transcript appended to the Petition, which is the email

referred to in the WhatsApp Group chat. The Developer would also tender a copy of

the reply filed by Bansal in response to the Contempt Application.

13. I have heard at length, Mr. Sanjay Jain, Learned Counsel on behalf of Bansal,

Mr. Karl Tamboly, Learned Counsel on behalf of the Society and Mr. Sharan

Jagtiani, Learned Senior Counsel on behalf of the Developer. With their assistance I

have examined the record appended to the Petition and the material tendered

across the bar. In my opinion, it was unnecessary to add bulky pleadings in

response to the Petition, and therefore, with the consent of the parties, the Petition

was taken up for final hearing and disposal.

14. The parties have attempted to indicate the sequence of events necessary for

adjudication of this Petition. In particular, events after the two applications were

filed on April 11, 2025, lie at the heart of the attack to the Impugned Order. Bansal's

premise is that the Learned Arbitral Tribunal has rendered the Modification

Application meaningless and infructuous when Bansal had not even filed a reply to

it. Mr. Jain would submit that in fact only the Contempt Application was meant to

be listed and heard by the Learned Arbitral Tribunal, which even fixed dates for

filing replies and rejoinders, but went on to direct inspection by the Commissioner,

which is in the nature of final disposal of the Modification Application.

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

15. Pointing to the WhatsApp group transcript, Mr. Jain would point to the

request made by the attorneys of the Developer on April 15, 2025, referring to an

email sent earlier, and requesting for an early date for hearing of the Contempt

Application filed by the Developer for ad interim reliefs. The request alleged that

Bansal was continuing to carry out works in Flat No. 301 in violation of the plans on

which the partial occupation certificate was issued, and also in violation of the July

2023 Order. After a reminder on April 16, 2025, the Learned Arbitral Tribunal

confirmed that Bansal and the other member would need to file a reply by April 25,

2025 and the Developer may file a rejoinder by May 4, 2025.

16. Mr. Jain would submit, this exchange would point to any reasonable person

reading it to mean that it was the Contempt Application that was mentioned as

needed urgent consideration. Pleadings in the Contempt Application were to be

completed in the time frame permitted by the Learned Arbitral Tribunal.

Thereafter, a hearing would be held, and a decision would be taken on the

Contempt Application. The Modification Application, was not even under

consideration at this stage, according to Mr. Jain.

17. In response to the dates for pleadings being fixed by the Learned Arbitral

Tribunal, the attorneys for the Developer once again requested for an early date for

hearing on ad interim reliefs. The attorney once again alleged that Bansal was

carrying out major illegal works in the flat which was ongoing even as of that

morning (April 17, 2025). It was urged that the Developer's "Application be heard

on urgent basis and prior to any other Application of the other side". The Learned

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

Arbitral Tribunal then sought the dates, and on April 18, 2025, it was indicated that

the Developer's counsel was available on April 25, 2025. The Learned Arbitral

Tribunal firmed up the time for the hearing on ad interim relief for 6:50 PM.

18. This scheduling on April 18, 2025 was sought to be changed by Bansal's

attorneys on April 22, 2025, by stating that their Counsel (although referred to in

the chat as the client) was scheduled to be in the Supreme Court on April 25, 2025

and therefore requested that the matter be kept on any other date after April 28,

2025. This request was opposed on behalf of the Developer on the ground that the

hearing scheduled for April 25, 2025 had been filed in advance on April 18, 2025. It

was reiterated that there was documentary proof of illegal works in violation of the

plan on which the partial occupation certificate was issued were still underway. The

attorneys expressed an apprehension that the illegal work would be expeditiously

completed and this would cause harm to the Society and to the other members.

19. The next day, the Learned Arbitral Tribunal indicated that the Developer's

counsel would be heard as scheduled on April 25, 2025 and to hear Bansal's

counsel, another date may be fixed. The Learned Arbitral Tribunal also offered to

have a recording of the hearing on April 25, 2025 to enable Bansal's counsel to

know what was argued.

20. It is the assurance flowing from this exchange that is assailed on behalf of

Bansal as being an inexplicable and utter violation of the principles of natural

justice. Mr. Jain would submit that the entire transcript would indicate all these

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

exchanges pertained to the Contempt Application. He would contend that while

another date was to be fixed to hear Counsel for Bansal, immediately after the very

first date of hearing, inspection and survey by the Commissioner in respect of Flat

No. 301 and Flat No. 601 had been ordered, which amounts to allowing the

Modification Application. There is not even a whisper of an allegation in respect of

Flat No. 601, but inspection of that flat too has been ordered. That apart, Mr. Jain

would submit, the abject violation of natural justice is evidenced by the fact that

nobody could have expected the Impugned Order which is in the nature of a final

order on the Modification Application would be passed upon hearing the Contempt

Application, and that too without a reply from Bansal on the Modification

Application and even while having held out a promise for fixing a date to hear

Bansal's counsel on another date.

21. Mr. Tamboly on behalf of the Society would indicate that the Learned

Arbitral Tribunal was the master of the proceedings and all that has been done is to

enable getting inputs to ascertain the factual position in relation to the two flats. He

would submit that nothing in the Impugned Order is worthy of intervention at this

stage of the matter.

22. Mr. Jagtiani on behalf of the Developer, would strongly oppose the notion

that only the Contempt Petition was meant to be heard. He would point to the

email dated April 11, 2025, which appended both the Contempt Application and the

Modification Application, with a request to hear the applications (in plural) on an

early date. It was this email that is referred to in the WhatsApp Group on April 15,

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

2025, asking for an urgent consideration of ad interim reliefs. He would therefore

indicate that one could never reasonably conclude that just the Contempt

Application was being pressed and was meant to be heard.

23. Mr. Jagtiani would also point out that Bansal had been given an opportunity

to file replies but he chose to file a reply to the Contempt Application and chose not

to file a reply to the Modification Application, despite knowing that both

applications were meant to be considered. He would tender a copy of Bansal's reply

dated April 25, 2025, received before the hearing scheduled on that day. Therefore,

he would submit, no case is made out to allege violation of natural justice.

24. I have given my anxious consideration to the issues raised by Learned

Counsel for all sides. The Petition has been taken up for final hearing by consent of

the parties. As rightly submitted by Mr. Jain, the Impugned Order is referable to the

provisions of Section 17 of the Act, and therefore, an appeal would indeed lie under

Section 37 of the Act.

25. It would be necessary to focus on the primary plank of the appeal, namely,

that the Impugned Order is a product of violation of natural justice. For the reasons

spelt out below, I am not persuaded to agree with the Petitioner.

26. First, in my opinion, prayers for ad interim reliefs were clearly contained in

the Contempt Application and even if one were to consider only that application as

being relevant for the hearing scheduled for April 25, 2025, the reliefs sought and

the measures granted, fall within the scope of the Contempt Application. Evidently,

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

Bansal has filed a detailed reply to the Contempt Application. The Impugned Order

merely seeks a verification of the factual position by asking the Commissioner to

inspect two flats. This is only in aid of the reliefs sought in the Contempt

Application and one cannot find fault with it.

27. Second, one of the specific defenses taken by Bansal is that the restriction on

members of the Society from carrying out structural changes was contained in the

Consent Terms dated October 14, 2021 and was valid for only 120 days. The

Consent Terms were entered into by the parties and accepted by a Learned Single

Judge of this Court by an order dated October 21, 2021. It is the Consent Terms

that led to the creation of the arbitration agreement. The approval of the Consent

Terms disposed of Suit No. 342 of 2015. The 120-day period of restraint on carrying

out structural changes committed to in the Consent Terms expired in February

2022. The Developer was meant to apply for the Occupation Certificate within the

same 120-day period, which he had not done. Therefore, having breached his side

of the bargain, the Developer would not be entitled to claim performance by Bansal.

In any event, Bansal has contended, the members were free to carry out structural

changes after 120 days. Therefore, Bansal is quite clear-headed that he was entitled

to make structural changes and therefore ought not to flinch about a direction to the

Commissioner to merely inspect and record the structural changes he has made

when holding the firm view that such changes were legitimately permitted.

28. Third, Bansal has also contended in his reply that even if there were

structural changes that are deviations from sanctioned plans, at the time of

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

obtaining the full occupation certificate, they can be regularised. In view of

violations of the Development Agreement by the Developer, it would be the

Developer's obligation to get them regularised, his reply contends. The reply also

indeed denies any violative alteration that could impact the receipt of the full

occupation certificate. Poor workmanship, the obligation to provide a garden area,

and bad design of windows are cited. The renovations are not borne out of any

malice to the Developer, Bansal has contended, but by the need to address water

seepage, and to address the inconvenience being caused by the poor and violative

work of the Developer. It was submitted that the Contempt Application was simply

a counter-blast to the Section 17 Application and in fact it must be considered only

after the Section 17 Application is considered. All that the Impugned Order does is

to have the Commissioner inspect the nature of the structural changes, which could

only bear out the defence taken by Bansal.

29. Fourth, from a plain reading of the Impugned Order, it is apparent that this

reply from Bansal to the Contempt Application has been noticed by the Learned

Arbitral Tribunal. The Learned Arbitral Tribunal is the master of the proceedings

and one must give the Learned Arbitral Tribunal a free play in the joints to conduct

the proceedings in the manner thought fit, so long as the conduct is in accordance

with law. The time to consider grievances about the conduct being violative of law,

normally is when a challenge is mounted under Section 34 of the Act. However,

indeed, decisions under Section 17 of the Act are appealable, which is why this

Petition has been heard and considered. When hearing such an appeal what must

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

be examined is whether the order impugned contains an implausible view or

whether it contains a bona fide view that is reasonably plausible. If the Learned

Arbitral Tribunal is of the view that the ends of justice would be met to have a fair

inspection of the factual position being conducted, this Court ought not to interfere

with the proceedings mid-course. Merely because another view may be possible

and that the Court may arrive at an alternate view, the view of the Learned Arbitral

Tribunal ought not to be substituted by the Section 37 Court.

30. Fifth, Bansal and Mr. Sujan (owner of Flat No. 601) were personally present

at the hearing held on April 25, 2025 and they were indeed also represented by

advocates at the hearing. They were heard. The reply filed on their behalf was part

of the record. The Learned Arbitral Tribunal has taken on record the submission on

behalf of Bansal that as of that date, no further work was being carried out. All that

the Learned Arbitral Tribunal has done is come to a view that examination of the

repairs work carried out by the Commissioner would be in aid of the arbitral

proceedings. By doing so, the Learned Arbitral Tribunal would know the precise

status of the work done and that would enable an appropriate adjudication of the

Contempt Application.

31. Sixth, it is noteworthy that Bansal was of the view that only the Contempt

Application was meant to be heard. That is the application in which prayers for ad

interim reliefs were contained. It was clear that the hearing was meant to be for ad

interim reliefs. The Learned Arbitral Tribunal had offered to keep another date for

hearing Counsel for Bansal but in fact, Bansal too was represented by advocates at

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

the hearing. They submitted that the reply was filed to the Contempt Application

but the reply to the Modification Application was still under preparation. A reply to

the Modification Application would relate to whether just two flats should be

singled out or whether the entire building should be examined. That brings me to

the relevance of the Modification Application.

32. I have perused the Modification Application. The modification sought is that

the survey and inspection must be curtailed to Flat No. 301 and Flat No. 601,

instead of the entire building, on the premise that these are the only two flats that

were still in dispute with the Developer while the Society and its other members had

moved on. Whether or not the Modification Application was meant to be

considered at the hearing held, in my opinion, the prayer in that application is to

modify and alter the scope of who is meant to be covered. However, a prayer for ad

interim relief in the form of examining what repairs have been carried out in Flat

No. 301 is indeed contained in the Contempt Application and that was clearly meant

for consideration and was also replied to. Besides, evidently, Bansal had made

arrangements and a reputed advocate was briefed and was present at the hearing,

and also made submissions. The Learned Arbitral Tribunal could still be told that

since the premise of grievances against Bansal is that renovation made by him could

hurt the ability to secure the occupation certificate, if the renovations made by

others are similar to those made by Bansal, and the Developer is happy to ignore

their renovations, it would stand to reason that Bansal's renovations are irrelevant.

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

All that the Impugned Order has done at this stage is to direct an inspection of the

renovation by Bansal. It is purely a fact-finding exercise and cannot be faulted.

33. The Learned Arbitral Tribunal has arrived at a prima facie view that the work

carried out in Flat No. 301 appeared to be substantive in nature. All he has desired

to ascertain is the actual work done and the status of what has been done. The

observation and analysis in Paragraph 6 to Paragraph 11 of the Impugned Order

bear iteration and are extracted below:-

6. Presently, after considering the material on record including the photographic evidence in the form of Exhibits to the contempt application and also considering the reply filed by the Claimant No. 3 to the contempt application, I find that there is prima-facie clearly work of a very substantial nature which is being carried out and has been carried out evidently from the Exhibits to the application for contempt. The reply to the application for contempt by Claimant No. 3 seeks to justify the work but does not deny that there is work which is ongoing. I am presently not judging the nature of the work, but it does not appear to be merely tenantable repairs but extensive work, however since the Tribunal has the assistance of a Commissioner and since the order of the Commissioner itself was passed on the application of Respondent Nos. 1 to 3 under Section 17 by consent as narrated in paragraph 5 and since considering there are disputes ongoing between the contesting parties, the direction for the Commissioner is required to be given effect to immediately. The case that no prejudice will be caused to Respondent Nos. 1 to 3 cannot be accepted since the construction work if found to be in violation of

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

regulations and the Part OC plan would have a serious impact on the regularization and also on the overall settlement between Respondent Nos. 1 to 3 and Claimants other than Claimant Nos. 3 and 6, it is necessary that the Tribunal should have the benefit of a Commissioner's report in line with the mandate and directions contained in the direction of 13th July 2023. The Comunissioner to take steps forthwith on receipt of these Minutes and directions.

7. Claimant Nos. 3 and 6 have not, although they could have, filed a response to the application. In any event, I do not see how any prejudice will be caused by the mere visit of a Commissioner only to report on the nature of the construction in terms of Flat Nos. 301 and 601. In respect of Flat No. 601, no reply has been filed in the application for continuation of the directions.

8 Taking an overall view of the material before me today and considering the urgency, I find it necessary to re-activate the directions contained in the directions of 13th July 2023 restricted to Flat Nos. 301 and 601. The Commissioner, Mr. Sanjay M. Jadhav of S.J. Associates, who is already appointed to visit Flat Nos. 301 and 601 forthwith and at the earliest. In case, the Commissioner faces any opposition, a report should be made to the Tribunal. The Commissioner to consider the mandate and act according to the directions contained in the Mirnutes of 13 th July 2023, however the same should be restricted to Flat Nos. 301 and

9. In respect of Flat No. 601, I have considered that even though there is no allegation, there can be no prejudice caused if the Commissioner visits the same and the Commissioner is only carrying out inspection.

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

10. Report of the Commissioner should be made availablewithin seven days or such extended time as the Commissioner indicates, if at all.

11 I have passed the directions as above without waiting for Claimant Nos. 3 and 6 to file a reply to the application for continuation of directions since the application was served almost two weeks back and the reply to the contempt application was filed but not to the continuation application. I have also passed directions after considering the urgency of the situation to ensure that the Commissioner has an opportunity to visit and report the position at site at the earliest before any cover-up or further alterations, modifications, etc., are carried out.

34. Even a plain reading of the foregoing would show that this is a measure

eminently within the domain and power of the Learned Arbitral Tribunal. That

apart, it is a reasonable approach that does not hurt the interests of Bansal or for

that matter Mr. Sujan. All that the Impugned Order does is to ascertain the factual

position.

35. Seventh, Section 17 is aimed at protecting the subject-matter of the

arbitration agreement. Specifically, Section 17(1)(c) enables any party to an

arbitration proceedings to apply to the arbitral tribunal for an interim measure in

respect of, among others, inspection of any property that is the subject-matter of the

dispute in the arbitration. Towards this end, the Learned Arbitral Tribunal is fully

empowered to exercise its discretion to authorise any person to enter upon any

property to obtain full information or evidence. This is precisely what the Learned

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

Arbitral Tribunal has done. I find no basis to find fault with the Learned Arbitral

Tribunal.

36. Eighth, the argument that principles of natural justice were violated stands

undermined since the Learned Arbitral Tribunal did permit the filing of a reply to

the request for ad interim reliefs. Bansal too indeed filed a reply to the Contempt

Application within the deadline, but chose to defer filing of a reply to the

Modification Application although he could have filed that too. Be that as it may,

the measure of getting the Commissioner to examine the property to file a report is

evidently a reasonable measure to get information relevant to preservation of the

subject-matter of the dispute in arbitration. I see no basis to interfere with the

same. Had there been material to convince the Learned Arbitral Tribunal even on a

prima facie basis, underlining the need to examine the facts through a

Commissioner, it would have been open to the Learned Arbitral Tribunal to direct

so even on an ex parte basis.

37. The Learned Arbitral Tribunal has not had to do so ex parte in this case.

Bansal filed his reply, and he along with advocates were indeed present at the

hearing to present their say. In fact the reply to the Contempt Application asserts

the right to make such structural changes. That is a matter of merits that the

Learned Arbitral Tribunal would need to hear at a later stage. All that the Learned

Arbitral Tribunal has done at this stage is enabled the obtaining of information on

what precisely has been done and that can only be in aid of arriving at the truth in

the proceedings. Bansal, who asserts that nothing wrong has been done ought not

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

to be agitated about the ascertainment of the factual position at the hands of the

Commissioner.

38. Ninth, since much has been made about the WhatsApp message from the

attorney of the Developer purportedly referring only to the Contempt Application, I

must deal with Mr. Jagtiani's explanation in response. He is right in drawing

reference to the email dated April 11, 2025 by which the two applications, namely

the Contempt Application and the Modification Application, were filed. The request

for an urgent hearing made by attorneys of the Developer on the WhatsApp Group

chat, indeed referred to this email and sought a hearing of the applications filed

pursuant to that email. Therefore, a conversation in the WhatsApp Group (in itself a

medium that should lead the parties to expect focus on the substance of the

communication rather than fine form of chiseled content) would indicate that it is

unreasonable to conclude that the Modification Application was not meant to be

heard. In any case, the Learned Arbitral Tribunal took note of the fact that no reply

had been filed to the Modification Application.

39. Finally, as briefly alluded to earlier, the conduct of the examination by the

Commissioner would also not render the Modification Application infructuous or

redundant. Whether the examination should be truncated to just two flats or

whether it should extend to all flats is still a matter that the Learned Arbitral

Tribunal would need to examine. If the Learned Arbitral Tribunal comes to a view

that others have carried out the same type of renovation work that has been carried

out in Flat No. 301 and finds that the Developer is not making any grouse of the

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

same only because they have settled with the Developer, the Learned Arbitral

Tribunal may arrive at a view that the objections to Bansal's renovations are not

worthy of acceptance. Towards this end, the Learned Arbitral Tribunal may well

direct the Commissioner to examine all flats and the renovations carried out in

them at a later date. At this stage one must not speculate and one also cannot rule

out what the Learned Arbitral Tribunal could rule, when considering the

Modification Application. Therefore, in my opinion, the Modification Application is

not at all rendered infructuous by reason of the Impugned Order.

40. I am informed that the Commissioner has already inspected Flat No. 601.

The Commissioner ought to examine Flat No. 301 as well, particularly since much

has been made about the nature of the renovations in that flat. The truth may even

help Bansal in his case against the Developer and ascertaining the truth must not be

interfered with on the premise of sequence of filing of applications, and the

sequence of their consideration (Bansal's Section 17 Application having been prior

in time to the Contempt Application). Those are all facets of conduct of proceedings

for which the Learned Arbitral Tribunal is the master and is fully empowered to

take such view as may be appropriate for a smooth, fair and efficient conduct of the

proceedings.

Conclusion:

41. In these circumstances, for the reasons set out above, in my opinion, there is

no case made out to argue that the Impugned Order suffers from any patent

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

illegality or manifest perversity, or for that matter, violates public policy or

exceeded its jurisdiction on the ground of denial of natural justice. The Learned

Arbitral Tribunal has taken a reasonable interim measure of obtaining full

information about the nature of the work done in Bansal's flat. The adoption of

such a measure does not render the Modification Application infructuous. The

adoption of such a measure is within the scope of a fair and reasonable moulded ad

interim measure under the Contempt Application. The adoption of this interim

measure also does not undermine Bansal's own Section 17 Application, which can

also be considered on merits.

42. The principle of minimal judicial interference in the course of conduct of

arbitration proceedings, also informs my thinking in dealing with this Petition. Any

interference with such a sound, reasonable and plausible view as contained in the

Impugned Order would be inappropriate. Therefore, I have no hesitation in

dismissing this Petition.

43. Before parting with the matter, I must mention that in trenchant proceedings

such as these, the Learned Arbitral Tribunal must be mindful of costs inflicted upon

and incurred by every party to such proceedings. Every application and pleading

has a ripple effect on all the parties and they all have to incur costs. I trust the

Learned Arbitral Tribunal to apply its mind to each such step and sub-step of the

nature that parties have taken in these proceedings, and consider an appropriate

imposition of costs in such manner and at such stage or stages as the Learned

Arbitral Tribunal deems necessary in the interests of justice. After all in commercial

May 8, 2025 Shraddha

ARBPL-13399-2025 - FINAL.docx

matters, there should ordinarily be no free ride for litigation for any party. I hasten

to iterate and clarify that this paragraph relates to every party and just the party

who has not prevailed in this Petition. Ordinarily, costs must follow the event.

44. All actions required to be taken pursuant to this order, shall be taken upon

receipt of a downloaded copy as available on this Court's website.

[SOMASEKHAR SUNDARESAN J.]

May 8, 2025 Shraddha

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter