Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Villa Realcon Llp. A Limited Co. vs Chandrish Parbat Gothi And Ors.
2025 Latest Caselaw 8451 Bom

Citation : 2025 Latest Caselaw 8451 Bom
Judgement Date : 3 December, 2025

[Cites 11, Cited by 0]

Bombay High Court

Villa Realcon Llp. A Limited Co. vs Chandrish Parbat Gothi And Ors. on 3 December, 2025

2025:BHC-AS:52791


                                                                               ARAST-30899-2025 - F-.docx



                                 IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                         CIVIL APPELLATE JURISDICTION
                                     ARBITRATION APPEAL (ST) NO. 30899 OF 2025

                           Villa Realcon LLP                                           ...Appellant
                                  Versus
         Digitally
         signed by
         SHRADDHA
SHRADDHA KAMLESH
KAMLESH TALEKAR
                           Chandresh Parbat Gothi
TALEKAR  Date:
         2025.12.03
         18:07:50
                           and 11 Ors.                                                 ...Respondents
         +0530




                           Mr. Vineet Naik, Senior Advocate a/w Mr. Akhilesh Dubey, Mr.
                           Amit Dubey, Mr. Uttam Dubey, Mr. Shubham Sharma, Mr.Alex
                           D'souza i/b Law Counselors, for Appellant.
                           Dr. Virendra Tuljapurkar, Senior Advocate a/w Mr. Onkar
                           Chandurkar, Mr. Nachiket Khaladkar, for Respondent No.1.
                           Mr. Rahul Sinha a/w Mr. Soham Bhalerao and Mr. Harshit Tyagi
                           i/b DSK Legal, for Respondent Nos.3 to 8-CIDCO.


                              CORAM             :       SOMASEKHAR SUNDARESAN, J.
                              Date                      December 3, 2025

                      JUDGEMENT:

Context and Factual Background:

1. This is an Appeal filed under Section 37 of the Arbitration and

Conciliation Act, 1996 ("the Arbitration Act") impugning an order dated

September 4, 2025, by which the Learned 2 nd Joint Civil Judge, Senior

Division, Panvel rejected an Application filed by the Appellant under

Section 8 of the Arbitration Act.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

2. An Application under Section 8 of the Arbitration Act had

been filed in Special Civil Suit No. 130 of 2025 (" Suit 130") filed by

Respondent No.1, Chandresh Parbat Gothi ("Chandresh"). Villa Modern

Constructions L.L.P. ("Villa Modern") was Defendant No.1. and Villa

Realcon LLP was Defendant No.2 ("Villa Realcon") in Suit 130.

3. City and Industrial Development Corporation Limited

("CIDCO") was Defendant No.3 and its various office bearers were

Defendant Nos. 4 to 8. The Panvel Municipal Corporation (" PMC") was

Defendant No.9 while Director, Town Planning of PMC was Defendant

No.10. There were two other Defendants namely Abhijeet Prabhakar

Jail, Defendant No.11 ("Abhijeet") and James Pascal D'Silva, Defendant

No.12 ("D'Silva").

4. At the heart of Suit 130 is a scheme popularly known as

"12.5% Scheme" under which landowners whose land had been acquired

by the State of Maharashtra and CIDCO would be allotted land of an

area equal to 12.5% of the acquired land as project affected persons, at

concessional rates. One Smt. Radhabai Janardan Jail ("Radhabai"),

mother of Mr. Prabhakar Jail ("Prabhakar") had been entitled to such

allotment of additional land under the 12.5% Scheme.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

5. According to pleadings by Chandresh in Suit 130, the land to

be so made available had been estimated by Prabhakar at about 9800

square meters. Prabhakar entered into an agreement on November 28,

2002 with M/s D'silva Corporation, through its sole proprietor D'Silva,

for assignment and development of such potential land, for a

consideration of Rs. 81 Lakhs and other terms and conditions contained

therein. Thereafter, Prabhakar and D'Silva are said to have executed an

agreement dated December 19, 2007, to enhance the consideration to

Rs.8.41 Crores.

6. Prabhakar died on August 3, 2012 and his entitlement under

12.5% scheme was inherited by Abhijeet, his son. Abhijeet is pleaded as

having executed one more Agreement with D'Silva on December 07,

2012 with a re-estimation of the land potentially to be allotted to him at

14,500 square meters confirming that all such land would be transferred

and assigned to D'Silva.

7. Owing to financial constraints, D'Silva and Abhijeet are

pleaded as having executed a Memorandum of Understanding dated

October 17, 2013 ("2013 MoU") with Chandresh on the terms set out

thereof. It is pleaded that the actual entitlement was far more than even

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

14,500 square meters. Under the 2013 MoU, the assignment was meant

to cover 34,500 square meters on the terms set out therein.

8. Chandresh is said to have complied with all the obligations

under the 2013 MoU and also engaged with CIDCO and its authorities

for allotment of the said land. It is contended by Chandresh that CIDCO

executed diverse lease agreements on January 5, 2017 allotting land

admeasuring 8323.55 square meters ("Allotted Land") in village

Kamothe. Since Abhijeet and D'Silva had agreed to assign their entire

entitlement under the 12.5% scheme in favour of Chandresh, they were

meant to execute a tripartite agreement and transfer the aforesaid land

of 8323.55 square meters to Chandresh.

9. The claim for entitlement of additional land over and above

the Allotted Land is pleaded as not having been acted upon by CIDCO

on the premise that there arose competing claims to such land made by

persons who had been agricultural tenants of Radhabai. The disputes

over non-compliance with the 2013 MoU found its way to court in the

form of Special Civil Suit No. 44 of 2018 ("Suit 44") before the Civil

Judge, Senior Division, Panvel, with Chandresh seeking specific

performance.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

10. This suit had initially been filed against Abhijeet, D'Silva and

also CIDCO and two of its officers. Meanwhile, even while Suit 44 was

pending, Abhijeet and D'Silva are said to have assigned the Allotted

Land and entitlements in favour of Villa Realcon. Therefore, Villa

Realcon was made Defendant No.6 in Suit 44.

11. Thereafter, Villa Realcon, Chandresh, Abhijeet and D'Silva

engaged in negotiations and arrived at a settlement, which was reduced

to writing in Consent Terms between the parties. The Consent Terms

were approved by the Learned Civil Judge, Senior Division, Panvel in

the form of a Consent Decree dated June 21, 2018 (" Consent Decree").

12. In terms of the Consent Decree, Chandresh was to be allotted

total constructed area admeasuring 20,586 square feet of developed

area ("Developed Area"), all of which was to be constructed on the

Allotted Land. It is pleaded in Suit 130 that in addition, D'Silva also

agreed to pay an aggregate consideration of Rs. 15 Crores to Chandresh.

Since the potential allotment of 34,500 square meters had been agreed

to be transferred and assigned to Chandresh in the 2013 MoU,

considering that the Allotted Land was only 8,323.55 square meters,

Abhijeet and Chandresh were acknowledged as being entitled to a share

even in any balance allotment that may be made by CIDCO.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

13. Towards this end, it was agreed that Chandresh would be

allotted 50% of the balance entitlement subject to Chandresh paying a

lumpsum consideration to Abhijeet at the rate of Rs.20,000/- per

square meter. D'Silva also agreed to share 50% of the balance

entitlement with Chandresh, and Villa Realcon agreed to acquire such

50% in the additional area and in lieu of the same, hand over additional

constructed area admeasuring 25,015 square feet (" Additional

Developed Area") in the buildings proposed to be constructed on the

Allotted Land.

14. It is clear from Chandresh's pleadings that his entitlement to

the Additional Developed Area was not contingent on any additional

land actually being allotted by CIDCO. The Additional Developed Area

was to be constructed on the Allotted Land, regardless of any additional

land being allotted by CIDCO. Villa Realcon is said to have agreed to

pay @ Rs.20,000/- per square meter to Abhijeet for and on behalf of

Chandresh. Therefore, the total developed area agreed to be given by

Villa Realcon to Chandresh was of the Developed Area (20,586 square

feet) and the Additional Developed Area (25,015 square feet).

15. While the Consent Decree resolved Suit 44, thereafter, Villa

Realcon and Villa Modern, its affiliate entered into another

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

Memorandum of Understanding dated February 21, 2019 (" 2019 MoU")

with Chandresh to deal with the additional allotment of land that would

potentially be made by CIDCO in favour of Abhijeet, of which,

Chandresh was entitled to 50%. The 2019 MoU contains a short and all-

encompassing arbitration clause.

16. According to Chandresh, the Consent Decree and the 2019

MoU are interconnected and Chandresh would have never given up his

rights even in respect of the Allotted Land but for the promise of his

share in the balance entitlement that would potentially come from

CIDCO. The 2019 MoU recorded that Chandresh would be entitled to

approximately 26,175 square meters in terms of the balance entitlement

and Chandresh would transfer and assign his share out of it to Villa

Realcon and Villa Modern on an as-is-where-is and as-is-what-is basis.

In return for his relinquishment of entitlement in favour of Villa

Realcon and Villa Modern, they were to allot to Chandresh free of cost,

the Additional Developed Area. Since Villa Realcon and Villa Modern

agreed to pay the amounts owed by Chandresh to Abhijeet and D'Silva,

Chandresh was absolved and exonerated of such liability to pay the

aforesaid sum.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

17. Chandresh pleaded that various approvals for the building

plan and requisite compliances were meant to be sought and obtained

by Villa Realcon and Villa Modern on their own. The consensus and

confirmations from Abhijeet and D'Silva in this regard, were also meant

to be the responsibility of Villa Realcon and Villa Modern.

18. Disputes and differences broke out between the parties in

connection with the Consent Decree read with the 2019 MoU.

Chandresh would specifically plead in Suit 130 that the 2019 MoU

explicitly recorded that even if no additional land was allotted by CIDCO

to Abhijeet, the allotment of the Additional Developed Area, as

contracted in the 2019 MoU, which was to be developed on the Allotted

Land, would need to be complied with by Villa Realcon and Villa

Modern. It is stated by Chandresh that Suit 44 had been disposed of in

terms of the Consent Decree while the 2019 MoU was executed only

seven months later on February 21, 2019. However, it is claimed, since

the understanding set out in the 2019 MoU had already been reached

even at the time of the Consent Decree, building plans had already been

approved by the local authorities on February 22, 2019, which,

coincidently, fell just one day after the execution of the 2019 MoU.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

19. Chandresh has pleaded that Abhijeet filed Writ Petition No.

5146 of 2019 in this Court seeking a direction that the balance

entitlement claimed by him be allotted. An order was passed on August

27, 2019 noting that the State of Maharashtra would hear his

representation afresh and pass a fresh order. Eventually, the State of

Maharashtra directed CIDCO to maintain status quo on the

development of even the Allotted Land. The PMC stayed the sanction

that had been given to the building proposal and therefore no

construction activity was taken up even on the Allotted Land.

20. Chandresh called upon the Villa Realcon and Villa Modern to

abide by the commitments under the Consent Decree and the 2019 MoU

and it is pleaded by Chandresh that these parties did not deny their

obligations. However, they stated that since development had not even

started and development activity on even the Allotted Land had been

put on hold, the time for making such allotment of any developed area

had not arrived. Therefore, as and when the ability to discharge the

obligations would come about, they would comply with all their

obligations.

21. Eventually, the State of Maharashtra lifted the status quo

order on the construction and development of the Allotted Land and

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

confirmed the allotment already made in favour of Abhijeet. However,

it was held that Abhijeet had no further entitlement to land. Chandresh

claims to be unaware of whether the rejection of the balance entitlement

forms subject matter of any challenge in any court by Abhijeet.

22. The decision of the State Government to lift the status quo

order on development of the Allotted Land and the decision that there

was no entitlement to any additional land, was conveyed by a letter

dated January 15, 2024 ("January 2024 Order"). Chandresh has

pleaded that while the January 2024 Order affects the rights perceived

to be enjoyed by all the parties, it has paved the way for development

and construction on the Allotted Land. Work on the Allotted Land had

commenced, and Chandresh demanded that he must be allotted free of

cost the Additional Developed Area as contracted in the 2019 MoU.

23. According to Chandresh, Villa Realcon and Villa Modern

turned hostile and took the position that they would abide by the

allotment of the Developed Area as provided in the Consent Terms but

would not allot the Additional Developed Area as mentioned in the 2019

MoU. Chandresh has pleaded that the right to the Additional

Developed Area is a clean and clear obligation under the 2019 MoU,

regardless of whether any additional land was to be allotted by CIDCO.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

This contention is said to have been rebuffed by Villa Realcon and Villa

Modern. This led to issuance of a legal notice by Chandresh on June

20, 2024, after which Suit 130 was filed.

24. The prayers in the suit primarily seek declaration that the

2019 MoU is a legal, valid, subsisting and an enforceable agreement

contracted in its terms, for provision of the Additional Developed Area

of 25,015 square feet area to Chandresh in any eventuality whatsoever.

Chandresh sought a restraint on constructed area admeasuring 25015

square feet out of the building proposed to be constructed. Interim

reliefs in terms of prohibition on creating any third-party interests on

the properties being developed were also sought.

25. In addition, prayer clause (d) sought a direction to CIDCO and

its officers who are arrayed as Defendant Nos. 3 to 8, to recall the

January 2024 Order and to allot the balance entitlement of land and to

conduct a fresh hearing and give an opportunity of hearing to

Chandresh as well ("CIDCO-related Prayer").

26. Finally, a prayer is also made against Abhijeet and D'Silva

seeking a restraint on them providing any further approval of any

development proposal that may be made by Villa Realcon and Villa

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

Modern, without taking cognizance of Chandresh's grievances in the

matter.

27. Villa Realcon filed an application under Section 8 of the Act

pointing out that since the 2019 MoU contained an arbitration

agreement, Suit 130 could not have been filed, and the disputes and

differences ought to have been referred to arbitration. The Impugned

Order rejected the Section 8 Application.

Impugned Order:

28. The Impugned Order records that the 2019 MoU indeed

contains an arbitration clause. However, on the premise that CIDCO

and its officials were made parties to Suit 130, and that they are not

signatories to the 2019 MoU, the Impugned Order holds that such

parties not being signatories, and the cause of action arising from a

combination of the Consent Decree and the 2019 MoU, the cause of

action pursued in Suit 130 could not be segregated to refer only a part of

the cause of action to arbitration.

29. The Impugned Order notes that the suit involves " complex

and interlinked issues involving both the parties to the MOU as well as

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

non signatories and therefore the matter is not fit for reference to

arbitration".

Analysis and Findings:

30. I have heard at length, Mr. Vineet Naik, Learned Senior

Advocate for Villa Realcon and Dr. Virendra Tulzapurkar, Learned

Senior Advocate for Chandresh. With their assistance, I have examined

the material on record including the Consent Terms, the 2019 MoU and

the Plaint in Suit 130.

31. Going purely by the case disclosed and pleaded in the Plaint

and the two underlying instruments namely the Consent Decree and the

2019 MoU, it is apparent that the subject matter of the disputes between

the parties relates to the allotment of the Additional Developed Area

contracted under the 2019 MoU to be provided by Villa Realcon and

Villa Modern to Chandresh. It is also common ground that the alleged

non-compliance with the Consent Decree forms subject matter of

execution proceedings.

32. The core subject matter of Suit 130 involves interpretation of

the terms of the 2019 MoU under which the parties are said to have

contracted that the Additional Developed Area is said to be handed over

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

to Chandresh by Villa Realcon and Villa Modern. It is Chandresh's own

case that such obligation under the 2019 MoU is to be discharged

regardless of whether CIDCO allots any further land under the 12.5%

Scheme. Therefore, it is writ large on the face of the Plaint that the core

cause of action pursued is for enforcement of the 2019 MoU.

33. It is also clear from Chandresh's own pleadings that he cannot

be called upon to ensure or procure that any additional land is actually

allotted by CIDCO to Abhijeet under the 12.5% Scheme in addition to

the Allotted Land, for such land to thereby be made available to Villa

Realcon and Villa Modern. Chandresh had also confirmed that subject

to Chandresh complying with all the respective obligations under the

Consent Terms and the 2019 MoU, there would be no claim whatsoever

in respect of the land in the event D'Silva committed a breach of his

obligations under the Consent Terms. Yet, Chandresh has also reserved

the right to litigate against D'Silva in the event of any breach by D'Silva

with respect to the Consent Decree. Under the 2019 MoU, prima facie,

it is clear that Chandresh has claimed to have assigned all entitlements

in respect of the land forming part of the Allotted Land as well as the

land expected to be allotted.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

34. On the face of it, the subject matter of the disputes and

differences between Chandresh on the one hand and Villa Realcon and

Villa Modern on the other squarely fall within the ambit of the 2019

MoU. The 2019 MoU builds further upon the Consent Decree and

entails allotment of the Additional Developed Area, all of which is to be

developed and constructed on the Allotted Land. The Consent Decree is

the subject matter of execution proceedings. The Additional Developed

Area is covered by the 2019 MoU, which admittedly and without doubt

contains an arbitration clause. In these circumstances, it would follow

that all disputes and differences between Chandresh on the one hand

and Villa Realcon and Villa Modern on the other, would form subject

matter of the arbitration agreement between the parties.

35. This brings one to the issue of the cause of action against

CIDCO. Indeed, Chandresh as dominus litus is entitled to fashion the

manner of prosecution of his claim. However, there is no connection

between Chandresh's purported claim against CIDCO and his claims

against Villa Realcon and Villa Modern. On the contrary, it is

Chandresh's own case that regardless of what CIDCO does with allotting

any additional land, Chandresh's entitlement to the Additional

Developed Area is crystallised and binding. Therefore, the entitlement

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

claimed against Villa Realcon and Villa Modern has nothing to do with

the purported claim against CIDCO.

36. It is in this light that the relief purportedly sought against

CIDCO is to be considered. The prayer is to direct CIDCO to recall the

January 2024 Order, which is not even an order of CIDCO. This letter is

not part of the record because it is an annexure to the Plaint and has not

been attached to the Appeal, but on a request from the Court, the parties

handed a copy across the bar. The January 2024 Order is a letter from

the Government of Maharashtra to CIDCO and not a letter by CIDCO

for it to be recalled by CIDCO. What is apparent is that the Plaint is

therefore a product of clever drafting of plugging in CIDCO and making

a purported prayer against CIDCO, which only serves to suggest that a

non-signatory to the arbitration agreement is also a party to Suit 130,

and thereby sidestep the arbitration agreement.

37. The core ground raised by Dr. Tulzapurkar to resist this

Appeal is that when a reference of a proceedings filed before the Section

8 Court is made to arbitration, the proceedings as filed in that Court

ought to be capable of being referred to arbitration. If it is found that the

Plaint as it stands cannot be referred to arbitration but only a part of

what is pursued in the Suit, howsoever material a part of the suit it may

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

be, the reference must not be made. Therefore, he would submit, the

Impugned Order does not call for interference.

38. I am afraid this is another means of indicating that the cause

of action purported to be covered by the suit cannot be "fragmented"

when considering an application under Section 8 of the Act. This is

precisely the law that had been declared in Sukanya Holdings1, which

has been overcome by the amendment effected to Section 8 of the Act in

2015, explicitly with a non-obstante provision that consideration of the

reference would be notwithstanding any judgement of the Supreme

Court or any other Court. It is now declared in multiple judgements of

multiple courts that the very objective of the amendments effected in

2015 was to overcome the position obtaining in Sukanya Holdings as is

also seen in the Law Commission report whose recommendation for the

amendment led to Section 8 being amended.

39. In Lindsay International2 , a Learned Single Judge of the

Calcutta High Court has discussed the issue threadbare under Section

(paragraphs 24 to 35) to hold that without doubt, Sukanya Holdings is

no longer a relevant factor for the Section 8 Court. It was held that the

Section 8 Court is not even mandated to adjudicate on the " bifurcability

Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya & Anr. - (2003) 5 SCC 531

Lindsay International Private Ltd. & Ors. Vs. Laxmi Niwas Mittal & Ors. - 2022 SCC OnLine Cal 171

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

of the causes of action of the presence of parties who are necessary

parties to the action but not to the arbitration ". It was explicitly held

that Sukanya Holdings would not be good law for any suit filed after

October 23, 2015, when the amended Section 8 took effect.

40. Dr. Tulzapurkar would press into service the decision of the

Supreme Court in Vinod Kumar Sachdeva3 to point to how the Supreme

Court reversed a reference to arbitration by taking note of the fact that

the cause of action pursued in one of the two underlying plaints involved

reliefs being sought against a bank not to disburse any financial

assistance, with the bank not having been party to the arbitration

agreement. The first suit was evidently filed before 2015 while the

second suit is identified as one filed in 2015 but the orders do not

indicate the date on which it was filed. That apart, on facts, the reliefs

sought in those proceedings against the third party bank was an integral

and interwoven element in the disputes between the parties.

41. In sharp contrast, in the instant case, there is no interlinkage

of the cause of action pursued by Chandresh against Villa Realcon and

Villa Modern with the purported cause of action against CIDCO. On the

contrary, Chandresh's own pleading indicates that regardless of what

Vinod Kumar Sachdeva (Dead) Through Legal Representatives Vs. Ashok Kumar Sachdeva & Ors. - (2023) 20 SCC 190

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

CIDCO does, there is a clear and segregated cause of action under the

2019 MoU to which CIDCO is not a party. The law on segregation of

elements of a suit has been dealt with in a seminal discussion by a

Learned Single Judge of this Court in the case of Taru Meghani4 to hold

that the litigant has the right to legitimately join more than one cause of

action in the same proceedings invoking Order II, Rule 3 of the Code of

Civil Procedure, 1908 ("CPC"), but the Court has the power to separate

causes of action invoking Order II, Rule 6 of the CPC, when the joinder

of multiple causes of action in one suit may embarrass or delay the trial

or make it inconvenient. To take the benefit of the detailed discussion

already made in Taru Meghani, the following portions are extracted

below:

17. In the aforesaid backdrop, the crucial question which wrenches to the fore is, whether the effect and force of the aforesaid arbitration clause gets diluted on account of inclusion in the suit, of a claim in re-

spect of a dispute which is not governed the arbitration clause......

18. The question posed by the facts of the instant case, however, is required to be considered from the perspective of the legislative object contained in section 8 of the Act. It is trite that the language of section 8 is peremptory in nature. In the cases where there is an arbitration clause in the agreement, the Court is enjoined to refer the dispute to arbitration in terms of the arbitration agreement and the Court would

Taru Meghani, Through his Constituted Attorney Ms. Shraddha Khandhadia and Others vs. Shree Tirupati Greenfield (Shree Tirupati Greenfield Developers) and Others - 2020 SCC OnLine Bom 110

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

have no jurisdiction to adjudicate the dispute after such an application seeking a reference under section 8 of the Act. Can this salutary object of the Act be defeated by adding a claim over and above the claim in respect of the matter which is squarely covered by arbitration agree- ment?

19. In the facts of the case, the question which crops up for consid- eration is whether there would be splitting of cause of action in the event the arbitration agreement in the MOU is given effect to. There appears a fine distinction between splitting of a single cause of action into parts, each being made a subject matter of a distinct proceedings and the separation of causes of caution which are joined together, al- beit in conformity with the provisions of the Code of Civil Procedure, 1908('the Code').

20. The plaintiffs are within their rights in joining multiple causes of action against the defendants. In fact, the provisions contained in the Code envisage such joining of several causes of action by the plaintiffs against the defendants.......

21. A conjoint reading of the aforesaid provisions would indicate that Rule 3 provides for joinder of causes of action and permits the plaintiffs to unite in the same suit, several causes of action against the same defendants. The remedy for any possible embarrassment, delay or inconvenience on account of the joinder of causes of action in one suit is provided in Rule 6. It authorizes the Court to order separate tri- als or make other order as may be expedient in the interest of justice, where the joinder of causes of action in one suit, though permissible under Rule (3)(1), would result in embarrassment, inconvenience or delay.

22. ........ If a Court is empowered to order separate trial when it finds that the joinder of causes of action would embarrass or delay the

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

trial or it is otherwise inconvenient, a fortiori a Court cannot be said to be divested of the authority to direct separation of causes of action when the joinder of causes of action, in pursuance of an enabling pro- vision like Rule 3 has the effect of defeating the provisions of a special law, like section 8 of the Act.

23. The aforesaid legal position is required to be considered coupled with the approach which is expected of the Court where an application seeking reference of the dispute to arbitration on the strength of an arbitration clause is preferred. Such an application, in substance, constitutes a plea of statutory exclusion of the jurisdiction of the court....... A useful reference in this context can be made to the judgment of the Supreme Court in the case of Sundaram Finance Limited v. T. Thankam, wherein the Supreme Court delineated the approach expected of the Civil Court in dealing with an application under section 8 of the Act, in Paragraph 13:

"13. Once an application in due compliance of Section 8 of the Arbitration Act is filed, the approach of the civil court should be not to see whether the court has jurisdiction. It should be to see whether its jurisdiction has been ousted. There is a lot of difference between the two approaches. Once it is brought to the notice of the court that its jurisdiction has been taken away in terms of the procedure prescribed under a spe- cial statue, the civil court should first see whether there is ouster of jurisdiction in terms or compliance of the procedure under the special statute. The general law should yield to the special law - generalia specialibus non derogant. In such a situation, the approach shall not be to see whether there is still jurisdiction in the civil court under the general law. Such ap- proaches would only delay the resolution of disputes and com-

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

plicate the redressal of grievance and of course unnecessarily increase the pendency in the court."

24. In the light of the aforesaid exposition of the legal position, I am of the considered view that the broad submission on behalf of the plaintiffs that the reference of the dispute to arbitration as regards the first transaction, would entail the bifurcation of the subject matter of the suit and, thus, it is impermissible in law, cannot accepted in an un- qualified manner. The submission is fraught with the danger of defeat- ing an arbitration agreement by simply adding a cause of action the plaintiff may have against the defendants, which is not covered by the arbitration agreement. If such a course is readily accepted, it has the propensity to give a long leash to the plaintiff to circumvent the arbit- ration agreement by uniting a cause of action which is beyond the pur- view of the arbitration agreement. It would have the effect of denuding section 8 of the Act of its force and vigour. Such an interpretation would also derogate from the object which the Arbitration and Con- ciliation Act, 1996 is intended to achieve; of minimum judicial inter- vention where parties have agreed to arbitrate the dispute.

25. In the peculiar facts of the case, in my view, the Court would be justified in referring the dispute to arbitration in respect of first transaction, as it is squarely covered by the arbitration clause and all the conditions of section 8 of the Act are fulfilled, and exercising its power under Order II Rule 6 of the Code to direct the plaintiffs to in- stitute a separate suit in respect of the second tranch of Rs. 19 lakhs.

[Emphasis Supplied]

42. One cannot declare the law in clearer conceptual terms. The

analysis extracted above squarely applies to the facts of the instant case,

and I am in respectful agreement with the same. One need not even go

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

into whether Chandresh indeed has a cause of action against CIDCO

when the Plaint itself pleads that Abhijeet may have the right to pursue

action against CIDCO as he had by filing a Writ Petition earlier.

43. The scope of jurisdiction of the Section 8 Court involves

examining the existence of an arbitration agreement (this has been

confirmed in the Impugned Order); comparing the subject matter of the

arbitration agreement and the subject matter of the suit; taking a view

as to whether the arbitration agreement covers the subject matter of the

suit; and refusing to refer the dispute to arbitration only if there is a

prima facie view that the arbitration agreement does not exist.

44. From a reading the pleadings in the Plaint and the cause of

action as disclosed in the plaint, the substratum of the suit evidently

entails adjudication of disputes and differences relating to the 2019

MoU. The MoU indeed contains an arbitration clause. In these

circumstances, I am unable to agree with the finding in the Impugned

Order that the case involves any complicated interlinkages between the

action sought against Villa Realcon and Villa Modern, and the action

purportedly pursued against CIDCO. In fact, Chandresh who had

received his rights from D'Silva who in turn had received his rights from

Abhijeet, has explicitly reserved the right to pursue against D'Silva.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

Indeed, Chandresh is not left remediless and has considered the

existence of avenues available to him. The joining of the causes of

action is a material inconvenience and has the effect of exercise of the

right to join separable causes of action to defeat the legislative objectives

of Section 8 of the Act.

45. In these circumstances, the Appeal deserves to be allowed,

referring the disputes and differences between Chandresh and Villa

Realcon and Villa Modern to arbitration. If the parties are unable to

agree on an arbitrator, an appropriate application may be made under

Section 11 of the Act.

Directions and Order:

46. In the result the following order is passed:-

a) The Impugned Order is quashed and set aside and

Suit 130 is directed to be returned to Chandresh, with refund

of Court fees in accordance with the rules;

b) Disputes and differences between Chandresh and

Villa Realcon and Villa Modern are declared as being covered

by the arbitration agreement contained in the 2019 MoU;

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

c) Chandresh is at liberty to pursue such action against

CIDCO as he may perceive to be his entitlement, in whichever

forum he is advised to pursue it;

d) The aspect of costs for this round of litigation is left

open for the parties to agitate in the arbitration proceedings

for the Arbitral Tribunal to consider.

47. The Appeal finally disposed of in the aforesaid terms. Interim

Applications, if any, shall also stand disposed of in these terms.

48. After the judgment was pronounced, the parties have

expressed their willingness to proceed to arbitration to avoid one more

round under Section 11 of the Arbitration Act. In these circumstances,

taking the consent of the parties on board, an Arbitral Tribunal is also

appointed in the following terms :-

A] Justice Jai Narayan Patel (Retired), former judge of this

Court, is hereby appointed as the Sole Arbitrator to adjudicate

upon the disputes and differences between the parties arising out

of and in connection with the Agreement referred to above. The

contact particulars of the arbitrator are set out below :

Office Address:- Raheja Chambers, 2nd floor, Near Tulsiani, Nariman Point, Mumbai - 400 021.

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

B] A copy of this Order will be communicated to the Learned

Sole Arbitrator by the Advocates for the Appellant within a

period of one week from the date on which this order is uploaded

on the website of this Court. The Appellant shall provide the

contact and communication particulars of the parties to the Arbi-

tral Tribunal along with a copy of this Order;

C] The Learned Sole Arbitrator is requested to forward the

statutory Statement of Disclosure under Section 11(8) read with

Section 12(1) of the Arbitration Act to the parties within a period

of two weeks from receipt of a copy of this Order;

D] The parties shall appear before the Learned Sole Arbitrator

on such date and at such place as indicated, to obtain appropriate

directions with regard to conduct of the arbitration including fix-

ing a schedule for pleadings, examination of witnesses, if any,

schedule of hearings etc. At such meeting, the parties shall pro-

vide a valid and functional email address along with mobile and

landline numbers of the respective Advocates of the parties to the

Arbitral Tribunal. Communications to such email addresses shall

constitute valid service of correspondence in connection with the

arbitration;

December 3, 2025 Purti Parab/Shraddha

ARAST-30899-2025 - F-.docx

E] All arbitral costs and fees of the Arbitral Tribunal shall be

borne by the parties equally in the first instance, and shall be

subject to any final Award that may be passed by the Arbitral Tri-

bunal in relation to costs.

49. Needless to say, nothing contained in this order is an

expression of an opinion on merits of the matter or the relative strength

of the parties. All issues on merits are expressly kept open to be agitated

before the Arbitral Tribunal appointed hereby.

50. The parties shall approach the Learned Arbitrator within a

period of one week from the upload of this order on the website of this

Court and seek directions including any interlocutory arrangements that

may desire.

51. All actions required to be taken pursuant to this order shall be

taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

December 3, 2025 Purti Parab/Shraddha

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter