Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Thermax Ltd vs Rashtriya Chemicals And Fertilizers ...
2025 Latest Caselaw 8282 Bom

Citation : 2025 Latest Caselaw 8282 Bom
Judgement Date : 9 December, 2025

[Cites 39, Cited by 0]

Bombay High Court

Thermax Ltd vs Rashtriya Chemicals And Fertilizers ... on 9 December, 2025

Author: R.I. Chagla
Bench: R.I. Chagla
2025:BHC-OS:24006



                                                                          RJ-CARBP 394.2023 with IAL-23263-23.doc


                  Kavita S.J. & Sharayu Khot




                                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        ORDINARY ORIGINAL CIVIL JURISDICTION


                                COMMERCIAL ARBITRATION PETITION NO.394 OF 2023

                        Thermax Limited                                         ...Petitioner

                                Versus

                        Rashtriya Chemicals & Fertilizers Ltd.,                 ...Respondent

                                                              WITH

                                   INTERIM APPLICATION (L) NO. 23263 OF 2023
                                                       IN
                                COMMERCIAL ARBITRATION PETITION NO.394 OF 2023
                                                    ----------
                        Mr. Janak Dwarkadas, Senior Counsel a/w Mr. Mustafa Doctor,
                        Senior Counsel a/w Mr. Aditya Thakkar, Mr. R. Sudhinder, Mr. Ranjit
                        Shetty, Mr. Rahul Dev & Ms. Monika Vyas i/b Argus Partner for the
                        Petitioner.
                        Mr. Shyam Mehta, Senior Counsel a/w Mr. Aditya Bapat, Mr. Mac. C.
                        Bodhanwala, Mr. Sheraj M. Bodhanwalla, Ms. Sayali Puri, Mr. Akash
                        Singh and Mr. Shreyas Thakur i/b M.S. Bodhanwala & Co., for the
                        Respondent.
                                                             ----------
         SHARAYU
         PANDURANG
         KHOT
                                                             CORAM : R.I. CHAGLA, J.
         Digitally
         signed by
         SHARAYU
         PANDURANG
                                                        RESERVED ON : 30th JUNE 2025.
         KHOT
         Date:
         2025.12.09
         17:53:03
         +0530

                                                      PRONOUNCED ON : 9th DECEMBER 2025.




                                                                 1




                       ::: Uploaded on - 09/12/2025                        ::: Downloaded on - 09/12/2025 20:55:45 :::
                                                  RJ-CARBP 394.2023 with IAL-23263-23.doc


JUDGMENT:

1. By this Commercial Arbitration Petition, the Petitioner

has challenged the Award dated 5 th June, 2023 ("the said/subject

Award") passed by the learned Sole Arbitrator, under Section 34 of

the Arbitration & Conciliation Act, 1996 ("the Arbitration Act").

2. The relevant facts are stated under:

(i) The Petitioner - Thermax Limited (referred to as

"Thermax") is an Indian industrial company offering

engineering, procurement and commissioning

services and sustainable solutions in Energy and

Environment domain. The Respondent - Rashtriya

Chemicals & Fertilizers Limited (referred to as

"RCF") is a commercial public sector undertaking

engaged in the manufacturing and marketing of

nitrogenous, phosphatic and potassic fertilizers as

well as a variety of industrial chemical products. For

the aforesaid manufacturing of fertilizers, among

others, electricity is one of the utility costs of RCF.

RJ-CARBP 394.2023 with IAL-23263-23.doc

(ii) RCF issued a Notice Inviting Tender ("NIT") on 19th

January, 2015 which invited eligible bidders to

submit bids for setting up of a 2X25 MW Gas

Turbine Generators ("GTGs") and 2X100 PH HRSG

along with all Balance of Plant, at RCF's factory at

Thal, Maharashtra as per detailed scope laid down

in the NIT on a Lump Sum Turnkey basis. Under

the NIT, Siemens was one of four approved vendors

(the other approved GT manufacturers being BHEL,

GE Power, Hitachi) specified by RCF. Thermax

decided to participate in the bid with Siemen's

manufactured GTGs.

(iii) Thermax was the successful bidder for the same and

RCF accordingly issued a Letter of Intent ("LOI") on

12th February and 25th February, 2016 in favour of

Thermax for award of contract for the said scope of

work.

(iv) A Statement of Agreed Variation was executed

between the parties on 26th February, 2016 whereby

RJ-CARBP 394.2023 with IAL-23263-23.doc

it was agreed that RCF would operate the plant only

after successful completion of the Performance

Guarantee Test ("PG Test").

(v) The Contract was executed between Thermax and

RCF on 3rd March, 2016 for a total Contract price of

Rs.3,53,08,99,313/- (Rupees three hundred and

fifty three crores eight lakhs ninety nine thousand

three hundred and thirteen only) out of which the

Contract price for supply of GTGs was

approximately Rs.106 Crores. The contract which

was executed between the parties stipulated inter

alia that RCF upon compliance of several conditions

by Thermax would issue a Preliminary Acceptance

Certificate ("PAC") (Clause 3(50) of GCC); 'Taking

over' shall mean RCF taking possession and use of

the Plant following issuance of PAC (Clause 3(63) of

GCC); PAC would be followed by a Defect Liability

Period of one year (Clause 17 of SCC) and post the

Defect Liability Period a Final Acceptance Certificate

would then be issued by RCF (Clause 19.1 of SCC)

RJ-CARBP 394.2023 with IAL-23263-23.doc

and Payments by RCF and Warranties by Thermax

were linked to these periods under the Contract.

(vi) As per the baseline schedule, it was RCF's obligation

to complete the Main steam line by 31 st August,

2017 and Thermax had to complete the PG Tests by

02nd December, 2017. It is pertinent to note that

RCF could not complete the main steam line by the

original timeline of 31st August, 2017, which, in

turn, delayed the PG Tests.

(vii) Thermax imported the GTGs from Siemens and

supplied the same to RCF. The executives of

Siemens were also directly involved in the erection,

installation and commissioning of the Plant.

(viii) On 28th February 2018 and 27th March 2018 the

sustained load throw off tests in respect of both

GTGs were conducted. It is pertinent to note that

from March 2018 onwards, the primary source of

power for the manufacturing activity at RCF's plant

were the 2 GTGs.

RJ-CARBP 394.2023 with IAL-23263-23.doc

(ix) RCF deducted Mutually Agreed Damages ("MAD")

amounting to Rs.19,56,85,716/- vide its Debit Note

No. LD130080123 on 30th March, 2018.

(x) The PG Tests were successfully completed for GTG-1

and GTG-2 on 24th April, 2018 and 10th May, 2018

respectively. RCF vide its email dated 10 th May,

2018 congratulated Thermax for successful

completion of the PG Test in respect of GTG-2.

(xi) Thermax informed RCF that it will de-mobilize its

manpower at the site after 11 th May 2018 vide

Email dated 10th May, 2018.

(xii) After the successful completion of PG Tests in

respect of GTG-2 and all guarantees being met, on

14th May, 2018 to 23rd May, 2018, RCF demanded

that the PG Test be re-conducted. Though according

to Thermax there was no requirement to conduct

another PG Test on the basis of the issues raised by

RCF, Thermax ultimately agreed to do a re-test.

RJ-CARBP 394.2023 with IAL-23263-23.doc

(xiii) It is Thermax's case that from the correspondences

available on record i.e. from May to September

2018, the GTGs were under unilateral control of

RCF.

(xiv) Thermax though maintaining that no fresh PG Test

was required for GTG 2, successfully conducted the

re-test for GTG 2 in October, 2018.

(xv) During the period 22nd February, 2019 to 8th March,

2019 there were multiple alarms in the control

systems of both GTGs which had been ignored by

RCF. It is Thermax's case that RCF did not inform

either Thermax or Siemens about the same.



           (xvi)     Since RCF was complaining about the efficiency of

                     GTGs      having   dropped,   Siemens        i.e.    Original

Equipment Manufacturer ("OEM") was contacted

and Siemens advised RCF to immediately stop the

units and carry out internal washing of the

compressor since major amount of dirt had entered

the compressor and accumulated on the blades.

RJ-CARBP 394.2023 with IAL-23263-23.doc

(xvii) In view of RCF not immediately carrying out

Siemens instructions, Siemens sent an official letter

under cover of email dated 22 nd February, 2019

calling upon RCF to shutdown GTGs immediately

and carryout immediate internal washing of the

compressor and also after inspecting the filters to

share pictures of the same with Siemens.

(xviii) Siemens, by its e-mail dated 11th March 2019,

enquired with Thermax whether any air intake

filters had been changed by RCF.

(xix) RCF vide email dated 12th March, 2019 conveyed to

Siemens that they had not changed any air intake

filters till date.

(xx) The PAC was issued by RCF on 15th March, 2019

with effect from 7th March, 2019.

(xxi) After being operational for 11 months, GTG-2 broke

down on 20th March, 2019.

(xxii) Siemens vide email dated 21st March, 2019 at 13:27

RJ-CARBP 394.2023 with IAL-23263-23.doc

hours informed Thermax and RCF to stop the unit

(GTG 1) immediately and internally wash the

compressor of GTG-1. It is an admitted position that

RCF did not comply with these directions of

Siemens. After being operational for 11 months,

GTG - 1 broke down on 22nd March, 2019.

(xxiii) It is the contention of RCF that the breakdown had

occurred on account of the GTGs being defective

and that since the PAC had been issued only on 15 th

March, 2019, in terms of the contract, Thermax was

liable to repair the machines. RCF sought to invoke

the 'defect liability' clause under the Contract

claiming that failure of GTGs was covered by

supplier's warranty undertaking. Thermax disputed

that it was responsible for the breakdown of GTGs,

inter alia since RCF had been commercially

operating the GTGs since March 2018. This was

recorded in the emails dated 13 th May, 2019 and

18th May, 2019 exchanged between RCF and

Thermax.

RJ-CARBP 394.2023 with IAL-23263-23.doc

(xxiv) Between May and June 2019 discussions ensued

between the Parties to determine the exact quantum

and value of repair and the time period required for

the repair and restoration. Thermax vide email

dated 24th May, 2019 submitted a proposal to

Siemens setting a way forward for repair and

restoration of the GTGs under which liability for

cost of repairs was contemplated to be apportioned

between the parties based upon the findings of the

Final Root Cause Analysis Report which was to be

conducted by Siemens.

(xxv) Siemens submitted the Final Root Cause Analysis

Report ("Final RCA") on 24th June, 2019 inter alia

stating that the root cause of the compressor

damage was the fouling of the compressors i.e. dirt

was accumulated on the blades of the compressor.

As per Final RCA, the filters let a significant amount

of dirt enter the compressors causing the

compressor to become significantly dirty. The reason

was that the filters were not replaced on time. It

RJ-CARBP 394.2023 with IAL-23263-23.doc

was also observed that if a compressor wash had

been performed, it was likely that the compressor

damage would have never occurred.

(xxvi) An agreement titled 'Notice to Proceed' was entered

into between Thermax and RCF on 2nd July, 2019.

This Agreement specified, inter alia, the manner in

which the repairs would be conducted and also

provided that the Notice to Proceed was the final

expression and a complete understanding between

the parties with respect to the warranty claim of

repair and restoration of GTGs.

(xxvii) RCF ordered a new Gas Generator (GG) from

Siemens directly on 6th July, 2019, in order to

restart GTG-2. The GTG-2 was thus made

operational from August 2019.

(xxviii) RCF invoked arbitration on 5 th November, 2019

claiming inter alia, that - the GTGs that had been

supplied were defective and hence, Thermax was

liable to repair the machines at its cost. RCF has

RJ-CARBP 394.2023 with IAL-23263-23.doc

claimed damages under several heads including a

claim of Rs.173.72 Crores for loss allegedly suffered

on account of additional expenditure on power for

the period 1st April 2019 to 30th November 2020 on

account of non-availability of the GTGs. This was on

the premise that since the PAC was issued on 15 th

March, 2019 with effect from 7 th March 2019, all

defaults prior thereto would be at the sole

responsibility of Thermax.

(xxix) In the arbitration proceedings, Thermax preferred a

Counter Claim for refund of MAD deducted by RCF

to the tune of Rs.19,56,85,716/-; for charges on

delayed release of bank guarantee (bank charges

amounting to Rs.7,06,000/-) furnished by Thermax;

for compensation and additional costs amounting to

Rs.2.15 crores incurred for the period during which

RCF was operating the plant without "Taking Over"

the plant as per the Contract; for refund of 2%

retention money withheld by RCF which was

payable at the time of final bill; and for release of

RJ-CARBP 394.2023 with IAL-23263-23.doc

fresh bank guarantee furnished by Thermax

amounting to 5% of the contract value.

(xxx) The learned Arbitrator framed a total of 16 issues.

The challenge to the impugned Award is on Issue

Nos. 1, 2 and 3 which deal with the issue of defect

in the GTGs supplied and who is responsible for

repairs and rectification of GTGs after breakdown;

Issue No.4 which deals with the issue of additional

expenditure on power awarded as damages; and

Issue No.10 which deals with the refund of MAD.

3. Mr. Janak Dwarkadas, learned Senior Counsel

appearing for the Petitioner has submitted that there was no defect in

the GTGs which had been supplied by Thermax to RCF. He has

submitted that the reason for breakdown of the GTGs was on account

of faulty handling of the GTGs by RCF. He has submitted that

Thermax has placed on record several correspondence exchanged

between Siemens, Thermax and RCF between February 2019 till the

ultimate breakdown of the GTGs i.e. 20 th March 2019 and 22nd March

2019 respectively.

RJ-CARBP 394.2023 with IAL-23263-23.doc

4. Mr. Dwarkadas has submitted that the Final RCA

Report prepared by Siemens has opined that the cause for the

breakdown of GTGs was faulty operation and failure on the part of

RCF to comply with the O&M Manual, inter alia as it had ignored

the air intake filter alarms which numbered 269 for GTG 1 and 52 for

GTG-2. The Final RCA Report has also found that there was a failure

on the part of RCF to inspect air intake for combustion air on a

monthly basis, failed to evaluate the performance of the

compressor on a weekly basis, failed to adhere to the express

instructions of Siemens etc.

5. Mr. Dwarkadas has submitted that RCF in its Reply to

Thermax's Counter Claim had for the first time referred to the

Report dated 1st September 2019 of Shakti (as an expert) to

contend that the cause for breakdown of the GTGs was the

Rubbing Theory. As per Rubbing Theory, there were heavy rubs on

the compressor metal blades and casings which would have induced

high fatigue in the metal blades thereby causing cracks in some of

the blades. Over a period, these cracks propagated causing the metal

blades to fail and break. The Shakti Report has sought to rely upon a

Report of Metallurgical Report namely TCR Advanced Engineering

RJ-CARBP 394.2023 with IAL-23263-23.doc

Private Limited, Vadodara considering that this was metal blades. He

has submitted that though the author of the Shakti Report was

produced for cross examination, RCF failed to produce the author of

the Metallurgical Report for cross examination. He has submitted

that in view thereof, the Shakti Report is based on hearsay evidence

and remained 'not proved'. He has submitted that this being the

only evidence that RCF produced in order to discharge the burden of

proving Issue No. 1 viz. Whether the GTGs supplied to the Claimant

were defective in nature, which evidence could not be tested by cross

examination, it becomes entirely worthless.

6. Mr. Dwarkadas has submitted that Thermax at the

stage of oral as well as written submissions, objected to the evidence

of one Mr. Sudhakar Jammula (CW-3), Director of Shakti, who was

a co-author of Shakti Report being taken into consideration on the

ground that the Report is based almost entirely on a Metallurgical

Report prepared by some other agency, the author of which never

entered the box for cross examination. He has submitted that on this

objection being raised in the course of oral arguments, the Counsel on

behalf of RCF abandoned relying upon the Shakti Report. He has

placed reliance upon Paragraphs 5.8 to 5.12 of Synopsis of Written

RJ-CARBP 394.2023 with IAL-23263-23.doc

Submission filed on behalf of Thermax.

7. Mr. Dwarkadas has submitted that the learned

Arbitrator has not rendered any finding on whether the Shakti Report

has been proved by RCF. He has submitted that it is trite law that

principles of the Evidence Act apply to arbitral proceedings. Further, it

is a trite law that no materials can be relied upon to establish a

contested fact which are not spoken to by persons who are competent

to speak about them and are subjected to cross-examination by the

party against whom they are sought to be used. The learned

Arbitrator, without giving any ruling/finding on the proof and veracity

of Shakti Report has proceeded on a completely alternate basis by

observing in Paragraph 49 that "Even if we proceed entirely on the

basis of the RCAs of Siemens and RINA report, there were defects in

GTGs installed by the Respondent and supplied by Siemens..."

8. Mr. Dwarkadas has submitted that the learned

Arbitrator in so finding failed to take into account the contrary

evidence led in by Thermax in the form of Final RCA and RINA Report

wherein the experts had categorically stated there is no evidence in

support of the conclusion that rubbing between the blades and the

RJ-CARBP 394.2023 with IAL-23263-23.doc

casing caused initiation of cracks.

9. Mr. Dwarkadas has referred to the evidence of Michael

Wood (RW-3) who has commented on the Shakti Report and disputed

its contents and opined it as unreliable. He has submitted that RW-3

was extensively cross examined by RCF with regard to aforesaid

conclusion reached by him and this conclusion remains unshaken.

10. Mr. Dwarkadas has submitted that Issue No.1 ought to

have been decided against RCF, as it had failed to prove the Expert's

Report and / or abandoned the same. He has submitted that if Issue

No. 1 were to be decided against RCF, Issue Nos. 2 and 3 would also

have to be decided in the negative. Issue No.2 being "Whether the

breakdown of the GTGs is covered under the defect liability and

warranty clauses of the contract?" and Issue No.3 "Whether the

Claimant is entitled to a declaration that the entire cost of repair and

rectification of the GTGs is to be borne by the Respondent?".

11. Mr. Dwarkadas has submitted that the learned

Arbitrator has relied upon an admission in the Final RCA by Siemens

that the Compressor Malfunction Alarm was 'configured incorrectly'

and therefore it did not raise the required alarm. The learned

RJ-CARBP 394.2023 with IAL-23263-23.doc

Arbitrator has further held that in view of the incorrect configuration

of the Compressor Malfunction Alarm, the recommendation made in

the Final RCA for more frequent washing of the dirt from the

compressor blades to prevent the breakdown of GTGs could not be

accepted.

12. Mr. Dwarkadas has submitted that the learned

Arbitrator has in rendering the above findings, overlooked and not

considered the most material admitted facts and evidence available

on the record. He has submitted that the admitted/uncontroverted

evidence on record was that air intake filters were the first line of

defence to protect the compressor from any dirt; the function or

purpose of the filters was to prevent the dirt to pass through and

settle on the compressor blades; the Filter Operation and

Maintenance manual (O&M) requires a periodic checking of the

filters; there were separate and independent alarms system called the

'Deviation Air Intake Filter Differential Pressure' and 'DP Air Intake

Filter' ("Filter Alarms"); and the O&M manual provided for a fault

procedure for the actions to be taken inter alia in the event of the

Filter Alarms going off, which has also been extracted in the Final

RCA.

RJ-CARBP 394.2023 with IAL-23263-23.doc

13. Mr. Dwarkadas has submitted that admittedly, between

20th February, 2019 to 22nd March, 2019, when the GTGs broke down,

there were 269 Filter Alarms triggered for GTG -1 and 52 Filter

Alarms triggered for GTG 2. He has placed reliance upon Appendix 1

and 2 of Siemens Final RCA in this context. He has submitted that

the correspondence shows that though Siemens had specifically

requested RCF to inspect the filters and send photos of the same, RCF

never provided any pictures to Thermax/Siemens.

14. Mr. Dwarkadas has submitted that RCF had admitted

that they had not changed any air intake filters till date. Despite

numerous repeated warnings from the Filter Alarms which were

admittedly noticed by RCF, RCF did not either report this to

Thermax/Siemens nor took any action as per the O&M manual to

change the filters and merely gave a perfunctory explanation for not

changing the filters as per the O&M manual.

15. Mr. Dwarkadas has submitted that it is evident from

the Final RCA that real cause for accumulation of dirt on blades of

compressor was that the filters were not changed in time. The

conclusion from the Final RCA is that breakdown could have been

RJ-CARBP 394.2023 with IAL-23263-23.doc

avoided by washing the dirt on the compressor blades in time.

16. Mr. Dwarkadas has submitted that the finding of the

learned Arbitrator, in Paragraph 39 of the Impugned Award, to the

effect that the compressor malfunction alarm being configured

incorrectly did not put RCF to notice of the accumulation of the dirt

on the compressor blades is only a secondary fact in as much as it

completely fails to consider and overlooks the fact that air intake filter

alarms are the primary alert mechanism to indicate the problem in

filtration and the condition of the filters. These alarms admittedly

were triggered on multiple occasions.

17. Mr. Dwarkadas has placed reliance upon the evidence

of Roger Ahlin (RW-2), Product Owner of SGT-700 at Siemens Energy

AB, Sweden who had the overall responsibility for the GTGs during

their entire lifecycle. He was also a member of the review team for the

RCA which finally approved the Final RCA.

18. Mr. Dwarkadas has submitted that the evidence of

Roger Ahlin (RW-2) remains unimpeached/unchallenged. The learned

Arbitrator has not even adverted to the said evidence, although, it has

been the case of Thermax, that the Filter Alarms being the primary

RJ-CARBP 394.2023 with IAL-23263-23.doc

alert mechanism to indicate the problem in filtration and the

condition of the filters, RCF had not taken requisite steps, either for

preventive maintenance or remedial action.

19. Mr. Dwarkadas has submitted that RW-2 has given

evidence that under the O&M manual, RCF was required to

periodically inspect the filters as well as monitor the compressor

efficiency. According to RW-2, the reason for the breakdown of the

GTGs was the failure on part of RCF to abide by the requirements of

O&M manual.

20. Mr. Dwarkadas has submitted that it is apparent from

the evidence on record that RCF's case is that the frequency with

which the air intake filter alarms went off were for short durations

and was activated only for a few seconds after which it got

normalized, no action was warranted. This is evident from the extract

of the Evidence Affidavit of R.P. Jawale (CW-1). Accordingly, the

learned Arbitrator was required to evaluate the evidence led by

witnesses of RCF as well as Thermax and come to a conclusion that

which of the two was believable/acceptable with reasons thereof. He

has submitted that what the learned Arbitrator has done instead is to

RJ-CARBP 394.2023 with IAL-23263-23.doc

jettison the evidence led by RCF's witness as well as evidence led by

the expert witness of Thermax and arrive at a perverse conclusion

that on a reading of Clause 14.1 of the Contract, it was the duty of

Thermax to have inspected the atmospheric conditions at the site

prior to supply of GTGs.

21. Mr. Dwarkadas has submitted that it was incumbent

upon the learned Arbitrator to have examined/evaluated the evidence

on the Filter Alarms and the conduct of RCF and give a finding

thereon before deciding on the aspect of Compressor Malfunction

Alarm.

22. Mr. Dwarkadas has submitted that although Thermax

had placed the above facts in its Written Submissions (filed prior to

final hearing) as well as Synopsis of Submissions (filed after final

hearing) before the learned Arbitrator, the Learned Arbitrator has not

considered the submissions and rendered no finding in respect

thereof.

23. Mr. Dwarkadas has submitted that the findings of the

learned Arbitrator on (i) filters of requisite capacity were not installed

- which defect had a direct connection with breakdown of the

RJ-CARBP 394.2023 with IAL-23263-23.doc

compressor and, (ii) compressor malfunction alarm was configured

incorrectly and hence, RCF cannot be blamed for not washing the

compressor; are perverse and patently illegal.

24. Mr. Dwarkadas has submitted that instead of holding

that the evidence on record could lead to one and only one conclusion

namely, that the breakdown occurred on account of RCF's failure to

maintain and operate the GTGs as required by the O&M manual, the

learned Arbitrator has held Thermax liable for the breakdown on a

simplistic finding based on a provision in the contract, i.e. definition

of 'Taking over' under Clause 3(63) of General Conditions of Contract

("GCC") by holding that since the PAC was issued on 15 th March,

2019 w.e.f 7th March 2019, Thermax was responsible for all acts prior

thereto. He has submitted that the entire record before the learned

Arbitrator has been ignored/overlooked.

25. Mr. Dwarkadas has submitted that Thermax, relying on

the evidence on record, had contended before the learned Arbitrator

that the Contract as understood and as performed by parties led to

only one interpretation viz. RCF had taken over the plant and was

responsible for the breakdown. It was submitted before the learned

RJ-CARBP 394.2023 with IAL-23263-23.doc

Arbitrator that RCF by its conduct did not wait for PAC for taking over

the Plant and rendered the provision qua issuance of a PAC

completely irrelevant, otiose and redundant. He has relied upon

Paragraph 4.10 to 4.16 of the Synopsis of Submissions in this context.

26. Mr. Dwarkadas has submitted that the learned

Arbitrator without considering the effect of these

contentions/arguments and the incontrovertible evidence on record,

negates their relevance by merely relying on the Contract and holding

in Paragraph 34 of the Award that " it is not necessary to go into the

details of the emails exchanged between the parties when the terms

of the contract are clear and responsibility of the Respondent

continues till the issuance of PAC (Preliminary Acceptance Certificate)

...".

27. Mr. Dwarkadas has submitted that this finding of the

learned Arbitrator is completely circuitous, perverse and patently

illegal in as much as the learned Arbitrator had completely

disregarded the entire evidence on record regarding the actual facts

and commercial realities in the performance of the Contract.

RJ-CARBP 394.2023 with IAL-23263-23.doc

28. Mr. Dwarkadas has placed reliance upon the relevant

clauses of the GCC. He has relied upon Clause 8 of the GCC which

provides that commercial use shall mean that use of the Plant, which

the contract contemplates or of which it is commercially capable. He

has placed reliance upon Clause 21 of the GCC which provides that

such matter shall not be a defect if it is caused by inter alia a failure

by the Purchaser to operate and maintain the Plant in accordance

with any operating and maintenance manuals provided by the

Contractor and/or with good engineering practice. He has placed

reliance upon Clause 22 of the GCC which is Defect Liability Period

and which shall mean a period of 12 months commencing from the

date of Preliminary Acceptance. He has placed reliance upon

"Preliminary Acceptance" and "Preliminary Acceptance Certificate"

under Clause 50 and 51 of the GCC. He has also relied upon Clause

63 of the GCC which is 'Take Over' 'Taking Over' and 'Taken Over'

which shall mean owner taking possession of and use of the Plant

following issue of the PAC.

29. Mr. Dwarkadas has also placed reliance upon Clause 17

of the Special Conditions of Contract ("SCC") which provides for

Liability for Defects.

RJ-CARBP 394.2023 with IAL-23263-23.doc

30. Mr. Dwarkadas has submitted that since RCF had

started operating the Plant and was commercially using the GTGs, the

issue of inadequate maintenance leading to breakdown would be the

responsibility of RCF. He has submitted that in light of the factual

position including the admitted and uncontroverted fact that RCF had

put the GTGs to commercial use for over a year, the Contract would

have to be interpreted in a manner so as to make the Contract

commercially efficacious. To put it differently, a party who had used

and operated the GTGs as its primary source of power and gained

commercial benefit therefrom could not be allowed to take advantage

of its own wrong in not issuing a PAC and thereby contend that

responsibility until PAC is with Thermax. He has submitted that

alternatively, RCF wrongly delayed the issuance of PAC. The fact that

RCF took over operational control of the Plant post commissioning

and started using it for commercial purposes from March/April 2018

makes the requirement of issuing PAC under the Contract as

redundant/otiose.

31. Mr. Dwarkadas has submitted that the admitted

documents and correspondence between the parties establish that

RCF was in full control and operating the GTGs (atleast) from April

RJ-CARBP 394.2023 with IAL-23263-23.doc

2018 onwards. He has placed reliance upon the e-mails exchanged

between parties from 12th April, 2018 till 24th February, 2019 in this

context.

32. Mr. Dwarkadas has submitted that the correspondence

shows that RCF had made a warranty claim in December, 2018

indicating that it had taken over the GTGs. By Letters dated 30 th

November 2018, 15th February, 2019 and 7th March 2019, Thermax

repeatedly called upon RCF to issue PAC. He has also placed reliance

upon the pre-arbitration correspondence between the parties

including the letter dated 18th May, 2019 of RCF stating that they had

followed instructions of Siemens and the Operating and Maintenance

manual thereby admitting that RCF was solely operating the GTGs in

the month of February 2019, i.e. prior to issuance of PAC. Thermax in

its Letter dated 18th May, 2019 informed RCF that the GTGs were in

commercial operation since February/March 2018 and had clocked

7644 and 7827 operating hours prior to breakdown during which the

units were solely operated by RCF. Further, in its annual report for

the financial year 2018-19, RCF had made a categorical statement

that the GTGs have been commissioned and had resulted in energy

savings to RCF. RCF had also claimed depreciation in respect of GTGs

RJ-CARBP 394.2023 with IAL-23263-23.doc

for the financial year 2018-19 commencing on 1st April 2018.

33. Mr. Dwarkadas has submitted that for the first time in

the Reply to Counter Claim, RCF contended that till the issuance of

PAC, the GTGs were under the control and supervision of Thermax.

He has submitted that however, in the Rejoinder Note of Written

Submission, RCF admitted that "it was not disputing the position that

it had put the plant to commercial use with effect from March/April

2018". He has submitted that RCF, at the stage of Rejoinder

arguments changed its tune and abandoned its case that it was not

using the plant for commercial operations from March/April 2018 and

suddenly purported to contend that "...the question whether and

when RCF took over the plant from Thermax will have to be

determined on the basis of the terms and conditions of the

contract..."

34. Mr. Dwarkadas has submitted that Thermax in its

Statement of Defence ("SoD") and the Evidence in Chief established

the fact that RCF was in physical control of the Plant since

March/April 2018. RCF had in the Statement of Claim at Paragraphs

34 and 39 of SoC, positively asserted that the machines were operated

RJ-CARBP 394.2023 with IAL-23263-23.doc

by trained personnel of RCF after taking thorough training from

Siemens in accordance with the operation and maintenance ("O&M")

manual provided by Thermax and also in line with good engineering

practice.

35. Mr. Dwarkadas has submitted that the learned

Arbitrator has disregarded the evidence led by Thermax i.e. of Mr.

Sunil Raina (RW-1), Head - Strategic Business Unit (Power Division)

to establish that RCF, in fact, had taken over operations of the GTGs in

March/April 2018 by deploying their own O&M crew and was

thereafter using the same for its commercial operations. RW-1 has

deposed that even after using the GTGs for more than 7000 hours,

RCF grossly delayed in issuance of PAC by raising minor punch points

which were irrelevant to the issuance of PAC.

36. Mr. Dwarkadas has submitted that upon reading of the

cross examination of RW-1, it would be apparent that RCF has been

unable to establish that operations and control of the plant was with

Thermax till issuance of PAC. He has in this context relied upon Q&A

Nos.1, 2, 42, 46, 50, 76, 108.

RJ-CARBP 394.2023 with IAL-23263-23.doc

37. Mr. Dwarkadas has submitted that it is an admitted fact

that commissioning of GTG 1 was completed on 28th February 2018

and commissioning of GTG 2 was completed 27 th March 2018. RCF

had put the plant to commercial use immediately after commissioning

with effect from March/April 2018. Under the Statement of Agreed

Variations of Contract, RCF was not allowed to start commercially

operating the GTGs prior to PG Test, however, RCF admittedly did

start using the GTGs immediately post commissioning of plant.

Manufacturing activity of the plant for the period March 2018 to

March 2019 was primarily done from the power generated by the two

GTGs. Both GTGs were operated for more than 7000 hours till the

date of breakdown and generated a total 3,27,152 MWH of power i.e.

90% of the power requirement.

38. Mr. Dwarkadas has submitted that on its own showing,

RCF derived huge commercial benefit by the use of the GTGs in terms

of cost of power saving from use of GTGs and Urea Policy incentive

received from the Government of India, as is evident on a simple

calculation from the documents produced by RCF itself.

RJ-CARBP 394.2023 with IAL-23263-23.doc

39. Mr. Dwarkadas has submitted that RCF by its actions in

taking over and using the Plant prior to issue of the PAC has clearly

chosen to give a go by to the Clause 3(63) read with Clause 3(50) of

GCC relating to 'Take Over' and 'PAC' and they became completely

irrelevant, redundant and otiose. He has submitted that RCF cannot

take advantage of its own wrong by breaching terms of the Contract

at the first place by using the Plant for its commercial purposes and

then hold Thermax strictly to the contractual provisions.

40. Mr. Dwarkadas has submitted that RCF had claimed a

loss aggregating to an amount of Rs.173.72 Crores on account of

additional expenditure incurred towards the cost of power due to non

- availability of GTGs for the period 1st April, 2019 to 30th November,

2020. It is claimed by RCF that total cost of the power incurred during

the said period, i.e. by (i) importing power through the State MSEB

grid; (ii) generation of power from Turbo Generators and (iii) cost of

power generated from one of the GTGs (which became operational on

or about 12th August, 2019) after RCF directly purchased a Gas

Generator from Siemens. From this aggregate amount, RCF has

reduced the notional cost of power that it would have incurred on the

basis that the GTGs continued to remain operational and supplied

RJ-CARBP 394.2023 with IAL-23263-23.doc

100% of RCF's power requirements for its plant at Thal for the period

1st April, 2019 to 30th November, 2020.

41. Mr. Dwarkadas has submitted that the impugned

Award, has awarded damages amounting to Rs.173.72 Crores in

relation to alleged additional expenditure incurred by RCF by

importing power from MSEB and from Turbo Generator for the period

1st April, 2019 to 30th November, 2020.

42. Mr. Dwarkadas has submitted that the claim for

damages could not have been granted as the claim was beyond the

contract and contrary to the contractual bargain; the claim was

beyond the scope of agreement titled as "Notice to Proceed" dated 2 nd

July, 2019 entered into between Thermax and RCF in relation to

repairs and reinstatement of GTGs; and RCF failed to lead adequate

evidence to prove the claim for damages.

43. Mr. Dwarkadas has submitted that RCF's claim for

damages is a claim for consequential loss. Being a claim for

consequential loss - award of damages to that extent is patently

illegal. He has relied upon Clause 32 of the GCC and in particular

Clause 32.2 thereof which provides "Notwithstanding anything

RJ-CARBP 394.2023 with IAL-23263-23.doc

contained elsewhere in CONTRACT or implied to the contrary:

(a) CONTRACTOR shall, in no circumstances, be liable

in respect of any indirect or consequential loss or

loss of profit suffered by OWNER in connection with

or arising out of performance of WORK under

CONTRACT.

(b) OWNER shall, in no circumstances, be liable in

respect of any indirect or consequential loss or loss

of profit suffered by CONTRACTOR in connection

with or arising out of performance of WORK by

CONTRACTOR under the CONTRACT."

44. Mr. Dwarkadas has submitted that the contract

specifically excludes any liability for consequential loss and Clause

32.0 states that the Contractor shall not be liable for any indirect loss

or loss of profits suffered by the Owner. He has placed reliance upon

Thermax's contention in Paragraph 84(a)(iv) of its Statement of

Defence to this effect.

45. Mr. Dwarkadas has submitted that it is RCF's

RJ-CARBP 394.2023 with IAL-23263-23.doc

contention that the claims are direct losses arising from the breaches

committed by Thermax of the terms of said contract and therefore the

provisions of Clause 32(a) does not apply to these losses suffered by

the RCF. This is evident from Paragraph 6 of Reply to Statement of

Defence / Counter Claim.

46. Mr. Dwarkadas has submitted that it was the

submission of Thermax in its Written Submissions before the learned

Arbitrator that from the provision of Clause 32(2)(a), it was clear that

the claims in question being barred by the terms of the contract would

fall outside and beyond the scope of the jurisdiction of the Hon'ble

Tribunal and therefore are ex-facie liable to be rejected. He has

submitted that RCF did not deal with the aforesaid submission made

by Thermax in its written submissions. However, during the course of

arguments, it was argued that the claim for damages was on account

of a direct loss incurred by RCF and hence, beyond the scope of

exclusion under Clause 32.2(a) of the GCC.

47. Mr. Dwarkadas has referred to Paragraphs 64, 65, 70

and 75 (last four lines) and 76 of the impugned Award. He has

submitted that the learned Arbitrator has accepted the claim of the

RJ-CARBP 394.2023 with IAL-23263-23.doc

Claimant for loss amounting to Rs.173.72 Crores by holding that the

loss is neither indirect nor consequential but a direct loss and hence,

Clause 32.2(a) has no application.

48. Mr. Dwarkadas has submitted that the learned

Arbitrator in considering whether the claim for consequential loss

made by RCF came within the exclusion clause set out in Clause

32.2(a) of the GCC was required to apply her mind firstly to the

provisions of Section 73 of the Contract Act; secondly to what is

excluded from being claimed as compensation for loss or damage

claimed from the provisions of Section 73 of the Contract Act; and

thirdly, in the light of the interpretation of Section 73 of the Contract

Act consider the width and ambit of the exclusionary Clause 32.2(a)

of the GCC. He has submitted that from the plain reading of Section

73 of the Contract Act, what is apparent is - that when a contract is

broken, a party who suffers by the breach is entitled to receive

"compensation for any loss or damage caused to him, which naturally

arose during the usual course of things from such breach, or which

the parties knew, when they made the contract, was likely to result

from the breach of it." Section 73 of the Contract Act, however,

provides that compensation cannot be given for any remote or

RJ-CARBP 394.2023 with IAL-23263-23.doc

indirect loss or damage sustained by reason of the breach.

49. Mr. Dwarkadas has submitted that the learned

Arbitrator had not reached the conclusion that the exclusion Clause

32.2(a) of GCC falls within the realm of 'remoteness' and 'indirect

loss' or 'damage' provided for by second part of Section 73 of the

Contract Act. In other words, the learned Arbitrator has not held the

exclusion clause to be void or as being unenforceable being contrary

to the second part of Section 73 of the Contract Act. This was also

not the case of RCF.

50. Mr. Dwarkadas has submitted that the learned

Arbitrator therefore proceeded on the assumption that Clause 32.2(a)

of GCC is a valid and enforceable exclusion clause. He has submitted

that the question therefore immediately arises is and which ought to

have been answered by the learned Arbitrator is what is it that the

parties agreed to exclude by virtue of Clause 32.2(a) of GCC.

51. Mr. Dwarkadas has submitted that the word "damage"

is defined in the Collins New English Dictionary to mean: " any injury

or harm to person, property or reputation....legal compensation paid

to injured party". He has submitted that the word "loss" is defined in

RJ-CARBP 394.2023 with IAL-23263-23.doc

Collins New English Dictionary to mean: "the act of losing". By

definition, the words 'loss' and 'damage' are not synonyms and/or do

not have the same meaning. It is for this reason that Section 73 of the

Contract Act provides for right of a party who suffers by breach from

party who has broken the contract "compensation for loss or damage"

caused.

52. Mr. Dwarkadas has submitted that Section 73 permits

for claims for compensation which could fall either within the normal

measure of damages as also from consequential losses so long as it is

established that they normally arise in the usual course of things or

which parties knew was likely result from breach of it.

53. Mr. Dwarkadas has submitted that Clause 32.2(a) of

GCC when it provides that the Contractor (Thermax) shall, in no

circumstances, be liable in respect of any 'indirect' or 'consequential

loss' or 'loss of profit' was meant to exclude the claim for

consequential loss, which would otherwise be claimable under

Section 73 of the Contract Act. The word 'indirect' appearing in

Clause 32.2(a) does not mean the same as 'remote' and 'indirect'

appearing in the latter part of Section 73 of the Contract Act. In any

RJ-CARBP 394.2023 with IAL-23263-23.doc

event, the word 'indirect' appearing in Clause 32.2(a) of GCC is

distinct from the words 'consequential loss' appearing in Clause

32.2(a).

54. Mr. Dwarkadas has submitted that it is trite law that

Indian Courts have repeatedly enforced exclusion clauses under a

contract. He has placed reliance upon following Judgments:

(i) Seth Thawardas Pherumal v. Union of India, AIR 1955 SC 468

(ii) Oil and Natural Gas Corporation v. WIG Brothers Builders and Engineers Private Limited (2010) 13 SCC 377 at Paragraphs 6 and 7

(iii) Ramnath International Construction (P) Ltd. v.

Union of India (2007) 2 SCC 453

(iv) Steel Authority of India v. J.C. Budharaja Government and Mining Company (1999) 8 SCC

55. Mr. Dwarkadas has also placed reliance upon the

Judgment of the Supreme Court in Superintendent Company of India

v. Krishan Murgai 1 at Paragraphs 25 and 26. He has submitted that

the question therefore which the learned Arbitrator was required to

1 (1981) 2 SCC 246

RJ-CARBP 394.2023 with IAL-23263-23.doc

decide was the question as to what the normal measure of damages

is as contrasted with any indirect or consequential loss or loss of

profits suffered by RCF.

56. Mr. Dwarkadas has submitted that it is too well settled

a proposition of law is what can be claimed under the heading

normal measure is either the diminution in the value of the goods or

the reasonable cost of repair which may arise on account of any

breach. He has placed reliance upon Pages 1143-1144 of Mcgregor

on Law of Damages (21st Edition). He has also submitted that the

expression consequential loss has been judicially interpreted to mean

and include expenses which may be incurred by a claimant as a result

of a breach which will constitute a recoverable loss. He has referred

Pages 1143-1144 of Mcgregor on Law of Damages (21 st Edition). He

has submitted that given this distinction which exists in the eyes of

law, the parties consciously incorporated Clause 32.2(a) in the

Contract by which RCF clearly waived its right to hold Thermax liable

in respect of any 'indirect' or 'consequential loss' suffered by RCF in

connection with or arising out of performance of work under the

contract.

RJ-CARBP 394.2023 with IAL-23263-23.doc

57. Mr. Dwarkadas has submitted that the reliance placed

by the learned Arbitrator on Saint Line Limited v. Richordson

Westgarth & Co. Ltd.2 is completely misplaced in as much as this

decision deals with different set of facts and in any event cannot be

applied in the context of statutory provisions contained in Section 73

of the Contract Act. This Judgment is a Judgment under the heading

loss of user profits which comes under the topic of consequential loss

and not under the normal measure of damages. The ratio of the

decision is that what the clause sought to exclude in that case was

something which by the provisions of Section 73 of the Contract Act

already stands excluded under the Indian law.

58. Mr. Dwarkadas has submitted that the claim for

damages was beyond the scope of agreement titled as "Notice to

Proceed" dated 2nd July, 2019 ("NTP") entered into between the

parties. The NTP was prior to the repairs of the GTGs being

undertaken and prior to an investigation by Siemens with respect to

the cause of the breakdown of the GTGs.

59. Mr. Dwarkadas has submitted that the learned

Arbitrator has in the teeth of Clause 5 of the NTP which provides that

2 [1940] 2 K.B. 99

RJ-CARBP 394.2023 with IAL-23263-23.doc

it is intended to be a complete understanding of the parties with

respect to the warranty claim and repair and restoration of GTGs, has

held that NTP has no connection with claims not connected with

repairs and recommissioning of the GTGs which RCF may have for

breach of any terms of the original contract. The learned Arbitrator

rejected Thermax's claim that RCF's claim for damages was therefore

barred by the terms of NTP. He has submitted that it is clear from the

findings in this regard in the impugned Award that the same are ex

facie contrary to the plain language of NTP and are based on an

impossible interpretation thereof. He has in this context referred to

the relevant findings in the Award on this aspect at Paragraphs 59 to

63 of the impugned Award.

60. Mr. Dwarkadas has submitted that the learned

Arbitrator has failed to consider the implications of Force Majeure

event (COVID 19) from March 2020 and two Force Majeure Letters

dated 23rd March, 2020 and 11th July, 2020 and wrongfully granted

damages for the period April 2019 to November 2020. The learned

Arbitrator has not even referred to let alone give any findings on the

impact of the force majeure event on the ability of Thermax to carry

out the repairs of the GTGs within the period prescribed under the

RJ-CARBP 394.2023 with IAL-23263-23.doc

NTP. He has submitted that given the fact that the parties had agreed

upon a reasonable period for completing the repairs and given the

facts and circumstances in which the delay occurred on account of

Force Majeure events, Thermax could not have been made liable for

any damages in this regard. The learned Arbitrator has completely

failed to deal with this submission in its entirety.

61. Mr. Dwarkadas has submitted that RCF has failed to

lead adequate evidence to prove the claim for damages. RCF has

relied upon Chartered Accountant's Certificate dated 20 th February,

2020 in support of its claim which is annexed at Annexure-23 to its

original (unamended) Statement of Claim. This Chartered

Accountant's Certificate was not produced on the evidence by RCF.

62. Mr. Dwarkadas has submitted that though the original

claim for loss aggregated to an amount of Rs.113.70 Crores upto 31 st

December 2019, this was revised cumulatively to Rs.173.72 crores to

claim loss towards additional expenditure of power for additional

period from 1st January, 2020 to 30th November, 2020. In the

amended Statement of Claim, RCF has relied upon the Certificate

dated 28th February, 2020 of the Chartered Accountant Parekh Sule &

RJ-CARBP 394.2023 with IAL-23263-23.doc

Associates for the dues sought by the Claimant as on 31 st December,

2019 set towards the additional expenditure on power and for loss of

income on account of lower energy savings and which is set out in

the particulars of claim.

63. Mr. Dwarkadas has submitted that alongwith the

amended Statement of Claim, RCF produced a table of particulars of

claim as Annexure 25 and which table inter alia contained unproved

figures relating to loss caused due to additional expenditure incurred

on power for the period (i) 1 st April 2019 to 31st December 2019 (ii)

1st January 2020 to 31st March 2020 and (iii) 1st April 2020 to 30th

November 2020.

64. Mr. Dwarkadas has relied upon the Statement of

Defence of Thermax dated March 2021 and in particular Paragraph

84(a) and (f) thereof. Thermax has expressly disagreed with the

computation of the extra cost as alleged by the RCF as the Chartered

Accountant's Certificate dated 20th February, 2020 is extremely

restrictive and only based on limited records.

65. Mr. Dwarkadas has submitted that RCF in support of

its claim for damages of Rs.173.72 Crores has led the evidence of Mr.

RJ-CARBP 394.2023 with IAL-23263-23.doc

Shivkumar Subramaniam (CW-2) the Deputy General Manager -

Corporate Finance of RCF. Mr. Shivkumar Subramaniam (CW-2) has

filed three Affidavits in lieu of Examination in Chief dated 29 th

March, 2021, 30th June, 2021 and 20th July, 2021. He has submitted

that RCF alongwith the Evidence Affidavit dated 29 th March 2021 of

CW - 2, for the first time produced two new CA Certificates both

dated 11th January, 2020 authored by the same Chartered

Accountants who had certified the earlier Certificate annexed as

Annexure 23 of the Statement of Claim. Thermax has by its letter

dated 12th July, 2021 to Advocates of RCF expressly denied the

existence and contents of the CA Certificates.

66. Mr. Dwarkadas has submitted that CW-2 during the

course of his examination-in-chief, firstly - abandoned and/or not

even relied upon Annexure 23 which was produced alongwith the

Statement of Claim; and secondly - abandoned and/or not relied on

the table of Particulars of Claim produced as Annexure 25 of the

Statement of Claim. Instead, CW - 2 attempted to rely upon the two

new CA Certificates, the existence and contents of which were

expressly denied by Thermax. These two new CA Certificates were

nevertheless marked as Exhibit CW-2/C-1(Colly).

RJ-CARBP 394.2023 with IAL-23263-23.doc

67. Mr. Dwarkadas has submitted that even though the

two purported CA Certificates were marked in evidence, the author

of the documents viz. the Chartered Accountant was never examined

to prove the existence and correctness of the contents of the said

purported Certificates. He has submitted that the unproved

Certificates were themselves premised on alleged underlying

documents allegedly seen by the Chartered Accountants, which

documents were never produced nor proved.

68. Mr. Dwarkadas has referred to the two Affidavits in

lieu of Examination-in-Chief of CW-2. He has submitted that there

are no underlying documents whatsoever which were produced other

than the CA Certificates dated 11th January 2020 through CW-2.

69. Mr. Dwarkadas has submitted that in Paragraph 4 of

the Evidence Affidavit dated 20 th July, 2021, CW-2 has stated that all

information is derived from SAP Enterprise Resource Planning (ERP)

System, the primary document would be the print out or an

electronically retrieved data from such SAP ERP System. He has

submitted that this has not been produced. The reason for non-

production is apparent. This is because such electronic records can

RJ-CARBP 394.2023 with IAL-23263-23.doc

only be proved and could be regarded as admissible only if it is

proved in accordance with Section 65-B of the Evidence Act, 1872.

This has admittedly not even been attempted in the present case.

70. Mr. Dwarkadas has submitted that the only manner in

which the contents of the purported data stored on the SAP ERP

System could have been proved was by way of producing the primary

document i.e. the data retrieved directly from SAP ERP System with

the underlying documents thereof.

71. Mr. Dwarkadas has relied upon Paragraphs 5.6 to 5.14

of the Written Submissions of Thermax prior to final hearing of the

arbitration, where Thermax dealt with the issue of alleged loss

caused to RCF on account of additional expenditure of power. It has

been expressly submitted that Thermax was deprived of the

opportunity of questioning the Chartered Accountant as to the

Methodology used by him and/or in preparing the statement and / or

the underlying based on which the Chartered Accountant prepared

the same. In this view of the matter, RCF is not entitled to rely upon

the Chartered Accountant's statement and the same must be rejected

in toto by the Hon'ble Tribunal. Thermax has also relied upon

RJ-CARBP 394.2023 with IAL-23263-23.doc

authorities in this context.

72. Mr. Dwarkadas has submitted that the learned

Arbitrator in Paragraphs 70 to 75 of the Award, dealt with Issue No. 4

in relation to the alleged loss caused to RCF due to additional

expenditure incurred on power on account of breakdown of GTGs.

The finding in Paragraph 75 is that " the Respondent has contended

that in his affidavits Mr. Shivakumar has relied upon certificate of

Chartered Accountant but evidence of chartered accountant has not

been led. Hence, his evidence should not be accepted. This

contention cannot be accepted because Mr. Shivakumar who has

deposed to these figures has done so on his personal knowledge as

also on the basis of the records of the Claimant company as

maintained in the ordinary course of business. His evidence is not

shaken in cross- examination."

73. Mr. Dwarkadas has submitted that RCF has failed to

discharge its burden of proving its claim for damages. It has been

overlooked by the learned Arbitrator that RCF, without producing the

best evidence and primary evidence and in violation of the mandate

of Sections 59 and 65 of the Evidence Act, 1872 led parole/secondary

RJ-CARBP 394.2023 with IAL-23263-23.doc

evidence of Mr. Shivkumar Subramaniam (CW-2) on the alleged

contents of the documents which would have shown the alleged

expenses incurred, if any. He has submitted that failure to produce

the primary evidence and the best evidence ought to have invited

adverse inference to the effect that had these documents been

produced they would not have borne out the allegations of RCF.

Thus, CW -2 has failed to discharge its burden of proof by producing

the best evidence and primary evidence being the documents

themselves in his examination in chief.

74. Mr. Dwarkadas has submitted that finding of the

learned Arbitrator that the evidence of Mr. Shivkumar Subramaniam

(CW-2) is not shaken in cross examination, is entirely unreasoned. He

has relied upon the Questions and Answers (Q&A), in cross

examination of CW-2 where 25 questions relating to the

computations made in his evidence with respect to the claim made by

RCF of Rs.173.72 Crores were asked. It became apparent during the

cross examination of CW - 2 that he had merely relied on the CA

Certificates for computation of the claim.

75. Mr. Dwarkadas has submitted that the CA Certificates

RJ-CARBP 394.2023 with IAL-23263-23.doc

were not produced by leading evidence of the Authors thereof being

the Chartered Accountants themselves and the said unproved

Certificates were premised on alleged documents, which documents

were never produced nor proved.

76. Mr. Dwarkadas has submitted that the learned

Arbitrator rendered a completely unreasoned, perverse and patently

illegal finding in Paragraph 75 of the Award. He has submitted that

the conclusions reached by the learned Arbitrator that the CW - 2

had deposed to the figures "on his personal knowledge" and also on

the basis of the records of RCF as maintained "in the usual course of

business" are patently illegal and perverse. He has submitted that this

is because CW - 2, during the course of his cross examination,

admitted that the information contained in the records was

maintained by a separate department namely the accounts

department and officials working in that department. Additionally,

the CW-2 has stated that since the information contained in the

records was certified by Chartered Accountant, he had relied on the

said Certificates issued by the Chartered Accountant. Therefore, CW-

2 could never be said to have any personal knowledge of the

information contained either in the records or in the Certificates of

RJ-CARBP 394.2023 with IAL-23263-23.doc

the Chartered Accountant. At best, his evidence could be considered

as hearsay which is clearly not admissible in law.

77. Mr. Dwarkadas has submitted that the claim for

damages remained not proved and ought to have been rejected. The

learned Arbitrator rendered no reasons and finding qua the

quantification of the claim for additional expenditure and more

particularly the proof thereof. This is in contravention to Section

31(3) of the Arbitration Act. He has submitted that the award for

claim of damages to the tune of Rs.173.72 Crores is unreasoned,

perverse, patently illegal and against the most basic notions of justice

and is accordingly liable to be set aside.

78. Mr. Dwarkadas has submitted that one of the

conditions of Thermax was that the claim for damages due to

additional expenditure incurred on account of sourcing power from

other sources was either an indirect or consequential claim expressly

waived by the parties and hence, the learned Arbitrator, being a

creature of contract, was barred from awarding the same in terms of

the contract between the parties. However, the learned Arbitrator has

held that the damages claimed are a "direct loss" . He has referred to

RJ-CARBP 394.2023 with IAL-23263-23.doc

Paragraphs 70 and 75 of the Award in the context.

79. Mr. Dwarkadas has submitted that the issue which the

learned Arbitrator was thus called upon to determine considering the

contractual bar on grant of "indirect loss" or "consequential loss" was

to determine firstly, what would be the normal measure of damages

in a case like the present case and secondly, if something was beyond

the normal measure of damages then would the same not be

"indirect" or "consequential" and hence, contractually barred.

80. Mr. Dwarkadas has placed reliance upon the Judgment

of the Delhi High Court in Shwetadri Speciality Papers Pvt. Ltd. v.

National Research Development Corp.3 at Paragraph 19. He has also

placed reliance upon Judgment of the Supreme Court in Trojan and

Company vs R.M. Nagappa Chettiar 4 at Paragraph 22. He has placed

reliance upon Judgment of this Court in Chief Commercial

Superintendent of Railways vs. Anand Kumar 5. These Judgments

have considered Section 73(1) of the Contract Act in the context of

the loss or damages being "indirect" or "consequential" as against

3 2019 SCC OnLine Del 9345 4 (1953) 1 SCC 456 5 1996 SCC OnLine Bom 412

RJ-CARBP 394.2023 with IAL-23263-23.doc

direct approximate damages.

81. Mr. Dwarkadas has submitted that the learned

Arbitrator has in Paragraph 68 of the Award has observed, inter alia,

that the claim for loss of income on account of allegedly being unable

to obtain government subsidies is barred by Clause 32.2(a). This

finding shows that the Arbitrator found the claim for loss of income

as not being within the notional Section 73(1) i.e. not being

proximate nor direct but being indirect and remote. The learned

Arbitrator then holds that the claim for indirect and remote loss is

barred by Clause 32.2(a) thereby rendering Clause 32.2(a) a dead

letter, since it is held to exclude indirect and remote loss which is

already excluded by the statute itself.

82. Mr. Dwarkadas has submitted that the normal measure

of damages is what it would have cost the party to get out of the

situation. Applying the said principle, the only damages which could

be said to be the normal measure of damages would have been the

cost of repairs. The claim for additional expenditure on account of

power sourced from other sources cannot and would not fall within

the normal measure of damages nor has there been any consideration

RJ-CARBP 394.2023 with IAL-23263-23.doc

nor finding on this aspect by the learned Arbitrator.

83. Mr. Dwarkadas has submitted that applying the said

principles laid down by the Supreme Court and followed by the

Division Bench of this Court, the claim for additional expenditure

incurred on account of power sourced from other sources is only an

"indirect" or "consequential" loss and hence, expressly barred by the

Contract and beyond the jurisdiction of the learned Arbitrator.

Accordingly, the impugned Award in so far as it grants a claim for

Rs.173.72 crores towards additional expenditure allegedly incurred

by RCF is perverse and a patent illegality.

84. Mr. Dwarkadas has submitted that Thermax had

preferred a Counter Claim, inter alia, for refund of MAD which had

been unilaterally deducted by RCF ostensibly under Clause 3(73)

read with Clause 31.0 and Clause 31.1.3 of the GCC to the tune of

Rs.19,56,85,716/-.

85. Mr. Dwarkadas has submitted that it was Thermax's

contention that while as per the "Baseline Schedule" the RCF was

required to provide the main steam line by 30th August 2017, the

same was not made available by RCF till 8 th February 2018. Thus,

RJ-CARBP 394.2023 with IAL-23263-23.doc

there was a delay of approximately 162 days on the part of RCF in

providing the said main steam line which led to consequential delays

in project completion. It was Thermax's case that the non-availability

of steam line had an overriding effect on project completion. He has

referred to Paragraph 20(s) and 23 of Counter Claim of Thermax in

this context.

86. Mr. Dwarkadas has submitted that RCF in its Reply to

Counter Claim, alleged that PAC was issued on 7 th March 2019 after a

delay of 444 days and RCF had incurred huge losses due to delayed

performance of contract by Thermax. He has relied upon the emails

exchanged between the parties which show that RCF itself admitted

that the communication qua the main steam line being ready was

made only in February, 2018. As per the Baseline Schedule, RCF was

required to provide the main steam line by 30 th August 2017,

however, as is evident, the same was made available by RCF only in

February, 2018. Thus, there was a delay of approximately 162 days

on the part of RCF in providing the said main steam line.

87. Mr. Dwarkadas has submitted that Thermax placed

reliance upon the evidence of Mr. Sunil Raina (RW-1) in support of

RJ-CARBP 394.2023 with IAL-23263-23.doc

its Counter Claim. Thermax in particular placed reliance upon the

Affidavit of Evidence of RW-1 dated 10 th June 2021 at Paragraphs 21,

25 to 27 and 30. In contrast, RCF led the evidence of Mr. R.P. Jawale

(CW-1). He has submitted that in the evidence led by CW-1 there is

neither any deposition nor documentary material produced to even

allege, let alone establish that RCF incurred or suffered any loss on

account of the alleged delay by Thermax.

88. Mr. Dwarkadas has submitted that Thermax during the

course of oral arguments and in its written submissions, inter alia,

contended that the levy of MAD was illegal, in as much as, it was

RCF which delayed the handing over of steam line and that RCF had

not suffered any loss on account of the purported delays.

89. Mr. Dwarkadas has submitted that the learned

Arbitrator in Paragraph 81 to 92 of the said Award held that RCF was

entitled to levy MAD, as defined under the contract, for the delay

which comes to 444 days.

90. Mr. Dwarkadas has submitted that it is trite law as

held by the Supreme Court in the case of Kailash Nath v Delhi

RJ-CARBP 394.2023 with IAL-23263-23.doc

Development Authority6 at Paragraph 43.3 that even in case of levy

of liquidated damages, proof of actual loss or damage is a sine qua

non. He has submitted that there is no averment qua actual loss or

damage nor evidence led but the record shows to the contrary that

the admitted commercial use of RCF from March/April, 2018 was to

its immense benefit. The learned Arbitrator has not even considered

nor addressed the aspect of loss or damage suffered whilst permitting

RCF to deduct monies as liquidated damages despite there being no

established loss nor damage. He has submitted that the impugned

Award is thus, perverse and patently illegal in as much as it upholds

the levy of liquidated damages completely contrary to the express

provisions of Section 74 of the Indian Contract Act and the law laid

down by the Supreme Court in several decisions regarding the

requirement to prove actual loss or damage before any liquidated

damages can be imposed.

91. Mr. Dwarkadas has submitted that the learned

Arbitrator has not even addressed the aforementioned lack of proof

and the settled law.

92. Mr. Dwarkadas has submitted that the learned

6 (2015) 4 SCC 136

RJ-CARBP 394.2023 with IAL-23263-23.doc

Arbitrator has failed to appreciate and address the submission of

Thermax in so far as the levy of MAD by RCF for the alleged delay is

concerned. He has submitted that since RCF was in breach of its

contractual obligations and delayed the completion of main steam

line by 162 days, it cannot complain of any delay by Thermax. RCF

cannot take advantage of its own wrong. He has accordingly

submitted that the counter claim of Thermax ought not to have been

rejected by the learned Arbitrator.

93. Mr. Dwarkadas has relied upon Judgments which can

be broadly classified as under:

(i) On Principles of Evidence Act applying to arbitral

proceedings, he has placed reliance upon

Pradyuman Kumar Sharma V. Jaysagar M. Sancheti 7

at Paragraph 18 and 33.

(ii) On mere production and marking of documents not

amounting to proof of its contents, he has placed

reliance upon Bareilly Electricity Supply Co.Ltd. Vs.

7 (2013) 5 MhLJ 86

RJ-CARBP 394.2023 with IAL-23263-23.doc

The Workmen & Ors.,8 at Paragraph 14 & Sudhir

Engg. Company Vs. Nitco Roadways Limited 9 at

Paragraph 6 and 8.

(iii) On failure to produce party for cross examination

leads to a presumption that case set up is not

correct, he has placed reliance upon Vidhyadhar V.

Manikrao10 at Paragraph 17; Maharashtra State

Board of Secondary and Higher Education Vs. K.S.

Ganshu & Ors.,11 at Paragraph 11; Man Kaur (Dead)

by Irs. V. Hartar Singh Sangha12 at Paragraph 14 &

17; and Seethakathi Trust Madras Vs. Krisnaveni 13

at Paragraph 12.

(iv) On allowing claims for damages without any

evidence is liable to be set aside under Section 34

he has relied upon Essar Procurement Vs.

8 (1971) 2 SCC 617 9 1995 (34) DRJ 86 10 (1999) 3 SCC 573 11 (1991) 2 SCC 716 12 (2010) 10 SCC 512 13 (2022) 3 SCC 150

RJ-CARBP 394.2023 with IAL-23263-23.doc

Paramount Constructions14 at Paragraph 100 to 114;

Unibros Vs. All India Radio15 at Paragraph 19-20;

Jaiprakash Hyundai Consortium Satluj Jal Vidyut

Nigam Ltd.16 at Paragraphs 10, 14, 20-24, 38-49.

(v) On Arbitrator requiring to give reasons for rejecting

the submissions of a party; finding based on no

evidence is liable to be set aside and grounds for

setting aside under Section 34, he has relied upon

Bhanumati Jaisukhbhai Bhuta Vs. Ivory Properties &

Hotels Private Limited17 at Paragraphs 172, 173 and

175 & 176; Ssangyong Engineering and

Construction Company Limited Vs. National

Highways Authority of India (NHAI)18 at Paragraphs

37, 39, 41; Associate Builders Vs. Delhi

Development Authority19 at Paragraphs 29, 31, 32,

42.2, 43.

14 2016 SCC Online Bom 9697 15 2023 SCC Online SC 1366 16 2024 SCC Online Del 1237 17 2020 SCC Online Bom 157 18 (2019) 15 SCC 131 19 (2015) 3 SCC 49

RJ-CARBP 394.2023 with IAL-23263-23.doc

(vi) On rule of best evidence, he has relied upon J.

Yashoda Vs. K. Shobha Rani20 at Paragraphs 7-10;

Neeraj Dutta Vs. State (NCT of Delhi)21 at Paragraph

60; Vijay Vs. Union of India22 at Paragraph 34.

(vii) On admissions are best proof of facts, he has relied

upon Nagindas Ramdas Vs. Dalpatram Iccharam &

Ors.23 at Paragraph 27.

94. Mr. Dwarkadas has accordingly submitted that the

impugned Award requires to be set aside on ground of it being bereft

of reasons, overlooking material evidence, being perverse and

suffering from patent illegality.

95. Mr. Shyam Mehta, the learned Senior Counsel

appearing for the Respondent-RCF has submitted that it is the RCF's

case before the Arbitral Tribunal that the Plant was under the control

and supervision of Thermax and that the same was being operated by

Thermax with support of RCF and further that till issuance of the

20 (2007) 5 SCC 730 21 (2023) 4 SCC 731 22 2023 SCC Online SC 1585 23 AIR 1974 SC 471

RJ-CARBP 394.2023 with IAL-23263-23.doc

PAC, Thermax was responsible for the plant.

96. Mr. Mehta has submitted that Thermax's contention

that RCF had not pleaded that it was operating the plant under the

supervision of Thermax is totally incorrect. He has submitted that it is

clear that both Thermax and RCF agreed that till the issuance of the

PAC, Thermax was responsible for the plant and that the same was

being operated at the risk and cost of Thermax.

97. Mr. Mehta has referred to the contractual provisions,

viz. Clauses 1.1.1, 1.1.2, 1.2.19.1, 1.2.19.2, 4, 6, 30.1 and 30.2 in

support of his submission that these contractual provisions establish

beyond a shadow of doubt that Thermax was in charge and control of

the plant until the issuance of the PAC. Thermax also remained liable

and responsible for the plant in all respects until the issuance of the

PAC. He has submitted that this has also been admitted by Thermax

in its Counterclaim. It was the obligation of Thermax to handover the

fully operational plant to RCF inasmuch as the contract was a Lump

Sum Turnkey Contract.

98. Mr. Mehta has submitted that it is Thermax's

contention that the provisions of the Contract relating to PAC viz.

RJ-CARBP 394.2023 with IAL-23263-23.doc

Clauses 3(50) and 3(63) were irrelevant, redundant and otiose and

had been given a go-by to by RCF. It is not their case that any of the

aforementioned provisions of the contract viz. Clauses 1.1.1, 1.1.2,

1.2.19.1, 1.2.19.2, 4, 6 and 30.1 and 30.2 were irrelevant,

redundant and otiose and had been given a go-by to by RCF. He has

submitted that Thermax has accepted that these provisions were

always binding and applied in full force to the parties at all times. He

has submitted that this being so, it is absolutely clear that Thermax

was in charge and control of the plant and liable and responsible for

the same until the issuance of the PAC.

99. Mr. Mehta has submitted that as regards the contention

that Clauses 3(50) and 3(63) were irrelevant, redundant and otiose

and had been given a go-by to by RCF, no such contention was raised

by Thermax in its pleadings. He has submitted that in the absence of

a plea to this effect, Thermax was not entitled to raise the contention

in the course of arguments. He has submitted that since there was no

such pleadings raised by Thermax, there was no occasion for RCF to

deal with the same. Further no issue was framed by the Arbitral

Tribunal in that regard. He has submitted that there was also no

evidence whatsoever led by Thermax to prove the said contractual

RJ-CARBP 394.2023 with IAL-23263-23.doc

provisions were irrelevant, redundant and otiose and given a go-by to

by RCF.

100. Mr. Mehta has referred to the pleadings of Thermax

viz. Statement of Defence at paragraphs 34 and 35 where Thermax

had relied upon Clause 6 of the SCC; at paragraph 37 where Thermax

has referred to Clause 3(63) of the GCC; and at paragraphs 40 and 41

where Thermax has relied upon Clause 3(50) of the GCC. He has also

referred to paragraph 39 of the Counterclaim where Thermax has

relied upon Clauses 30.1 and 30.2 of the GCC as well as Clause 3(63)

of the GCC. These provisions have been relied upon by Thermax in

support of their case. Whilst relying upon the aforementioned

contractual provisions, Thermax has not averred that the same were

being relied upon without prejudice to its rights and contention that

they were irrelevant, redundant and otiose and given a go-by to by

RCF.

101. Mr. Mehta has submitted that it is well settled that an

Arbitrator is a creature of contract and is bound by terms and if the

Arbitrator travels beyond or outside the contract, the Award is liable to

be set aside. He has placed reliance upon Section 28(3) of the

RJ-CARBP 394.2023 with IAL-23263-23.doc

Arbitration Act and the judgment of the Supreme Court in Union of

India Vs. Bharat Enterprise24 in this context.

102. Mr. Mehta has submitted that as regards the contention

of Thermax that RCF wrongly delayed the issuance of the PAC, it is

important to note that in the course of arguments before the Arbitral

Tribunal, Thermax accepted the position that both GTGs had failed

during the defect liability period. Thermax did not question the

correctness of the PAC being issued w.e.f. 7th March 2019. There were

no arguments advanced by Thermax on this aspect.

103. Mr. Mehta has submitted that in view of above, it must

be accepted as an undisputed position that the PAC was rightly issued

w.e.f. 7th March 2019 and the defect liability period commenced from

7th March 2019.

104. Mr. Mehta has submitted that though Thermax has

argued to the contrary before this Court in these proceedings, by

denying that the PAC had been rightly issued with effect from 7th

March 2019 and which stand is also taken in Note 4 of the Written

Submission filed before this Court, the proven facts establish beyond

24 2023 SCC OnLine SC 369

RJ-CARBP 394.2023 with IAL-23263-23.doc

doubt that the RCF had rightly issued the PAC with effect from 7th

March 2019.

105. Mr. Mehta has submitted that in the proposal submitted

by Thermax to RCF on 2nd July 2019 for the purpose of issuing the

Notice to Proceed, Thermax expressly admitted that the effective date

of the PAC was 7th March 2019 and the defect liability period started

from this date.

106. Mr. Mehta has submitted that the PAC was liable to be

issued only upon Thermax fulfilling all the conditions stipulated in

Clause 3(50) of the GCC. From Thermax's letter dated 7th March

2019, requesting RCF to issue the PAC, itself it is absolutely clear that

even as on 7th March 2019, Thermax had not fulfilled all the

conditions stipulated in the said Clause 3(50). Thermax stated that it

was working on these pending issues and sought time till 30th June

2019 to complete the same. Thermax even suggested withholding Rs.

20 lakhs until the pending works were completed. It was pursuant to

this letter that RCF issued the PAC dated 15th March 2019 with effect

from 7th March 2019. He has submitted that thus, it is clear that

Thermax was not entitled to the PAC prior to 7th March 2019.

RJ-CARBP 394.2023 with IAL-23263-23.doc

107. Mr. Mehta has submitted that as per Clause 3(50), 12

milestones had to be achieved by Thermax before it was entitled to the

PAC. He has relied upon the evidence on record which shows that all 12

milestones were not achievable by the stipulated dates, and were

achievable only by 27th September 2019. He has submitted that this is

not being disputed by Thermax before the Arbitral Tribunal, because in

fact, no arguments were advanced by Thermax in this regard.

108. Mr. Mehta has submitted that though it is the case of

Thermax that the GTGs were put to commercial use in March / April

2018, it meant that RCF had taken over the plant and was in charge of

the same notwithstanding that the PAC was not issued with effect

from March / April 2018, Thermax had at no stage objected to RCF

using the plant for commercial production and/or asked RCF to stop

doing it. It was only when Thermax applied for the PAC vide its letter

dated 30th November 2018 that Thermax sought the PAC with effect

from 27th March 2018 on the basis that commercial production for

both GTGs had commenced by this date. However, subsequently, after

correspondence and meetings in this regard with RCF, in its letter

dated 7th March 2019 seeking the PAC, Thermax did not request for

the PAC to be issued with effect from 27th March 2018. It is therefore,

RJ-CARBP 394.2023 with IAL-23263-23.doc

clear that Thermax had itself given up its contentions regarding

commercial use / production with reference to the issuance of the PAC

and had accepted the fact that it had to fulfill the conditions stipulated

in the contract for the purpose of securing the PAC from RCF.

109. Mr. Mehta has submitted that both RCF and Thermax

are bound by the Contract and consequently, take over can be effected

only in accordance with the Contract and not otherwise. Under the

contract commissioning is a stage prior to production (Clause 3(7) of

the GCC). Since commercial production started sometime in March /

April 2018, commissioning occurred sometime before that.

Accordingly, it was stated in the Annual Report that the plant was

commissioned in April 2018. Thermax in its submissions has sought

equating commissioning with the take over of the plant after issuance

of PAC. He has submitted that it is clear from the contract that

commissioning and take over are two different and distinct stages

during the manufacture and installation of the plant and the two

cannot be equated.

110. Mr. Mehta has submitted that though Thermax has

relied upon Annual Report for FY 2018-19 where RCF had made a

RJ-CARBP 394.2023 with IAL-23263-23.doc

categorical statement that the GTGs were commissioned and had

resulted in energy savings for RCF and had claimed depreciation in

favour of the GTGs during FY 2018-19, neither of these two acts of

RCF show that RCF had taken over the plant under the Contract or

otherwise.

111. Mr. Mehta has submitted that depreciation was claimed

in accordance with law and has no bearing on the takeover of the

plaint by RCF under the Contract and does not and cannot even

remotely suggest that RCF had taken over the plant. In any event, RCF

did take over the plant in FY 2018-19 and as such its claim for

depreciation was consistent with the take over of the plant in FY

2018-19.

112. Mr. Mehta has submitted that though it was contended

that RCF derived a commercial benefit of Rs. 500 crores by using the

GTGs from March / April 2018, no such contention was raised before

the Arbitral Tribunal. The computation of Rs. 500 crores has been

arrived at by Thermax in Annexure A to Note 2 submitted before this

Court. He has submitted that this computation cannot be and ought

not to be considered at this stage. It is a factual issue and a matter of

RJ-CARBP 394.2023 with IAL-23263-23.doc

evidence and was required to be pleaded and proved before the

Arbitral Tribunal. He has submitted that even on the face of it, it is

speculative and based on assumptions and surmises.

113. Mr. Mehta has submitted that it is the contention of

Thermax that the Arbitral Tribunal did not consider extensive

evidence, which purportedly shows that RCF had taken over the plant

in March / April 2018. He has submitted that the Arbitral Tribunal

considered the relevant and material facts while arriving at its

conclusion that Thermax was in charge and control of the plant until

7th March 2019. The Arbitral Tribunal has considered the contractual

provisions, the counterclaim of Thermax, Thermax's submissions with

regard to the statements made by RCF in its Annual Report, RCF's

claim for depreciation and various other relevant facts while arriving

at its conclusion and the same cannot be faulted.

114. Mr. Mehta has submitted that it is the case of RCF in its

pleadings on the issue of the defective nature of the GTGs that the

filters installed by Thermax/Siemens were not as per the specifications

provided in the contract. They did not have the minimum operating

life of two years and on the contrary had an operating life of only six

RJ-CARBP 394.2023 with IAL-23263-23.doc

months and were required to be replaced every six months. It was also

the case of RCF in its pleadings that Thermax/Siemens were required

to inform themselves of the local conditions before supplying and

installing the plant, which they failed to do. Thermax/Siemens had

not configured the Compressor Malfunctioning Alarm in the control

system of the GTGs.

115. Mr. Mehta has referred to the evidence led by RCF in

the first additional Affidavit dated 31st March 2021 of CW-1, Mr.

Jawale, where he has deposed regarding the defective filters and the

non-configuration of the Compressor Malfunctioning Alarm. He has in

particular relied upon paragraphs 23 and 25 of the Affidavit of

Evidence of CW-1 in this context. He has submitted that it is clear that

both in the pleadings and in its evidence that RCF had consistently

made out a case of defective filters and the failure on the part of

Thermax/Siemens to configure the Compressor Malfunctioning Alarm.

116. Mr. Mehta has submitted that the Arbitral Tribunal in

the impugned Award although has not accepted RCF's case based on

the rubbing theory, accepted its case with regard to the defective filters

and non-configuration of the Compressor Malfunctioning Alarm.

RJ-CARBP 394.2023 with IAL-23263-23.doc

117. Mr. Mehta has submitted that as regards the alleged

non-compliance by RCF with the O & M Manual, the Arbitral Tribunal

accepted the case of RCF that Thermax was in charge and responsible

and liable for the plant in all respects until the issuance of the PAC and

consequently until then, if there was any non-compliance with the O &

M Manual, the fault lay at the door of Thermax and RCF could not be

blamed for the same.

118. Mr. Mehta has submitted that Thermax's case regarding

the 269 air intake filter alarms for GTG 1 and 52 air intake filter

alarms for GTG 2 observed in their respective control systems during

the period from 22nd February 2019 to 8th March 2019 and the

allegation that RCF being aware of these alarms did not bring the

same to the notice or attention of Thermax/Siemens, was not a case

which was sought to be made out before the Arbitral Tribunal at any

time. This factual contention had been raised for the first time in the

course of arguments in this Petition, which is clearly impermissible.

119. Mr. Mehta has submitted that Thermax / Siemens were

fully aware and apprised of the situation at the site and the issues

being faced in the GTGs. He has submitted that in not a single email

RJ-CARBP 394.2023 with IAL-23263-23.doc

have either Thermax or Siemens raised any grievance with regard to

the non-availability of the data relating to the alarms and that they

were not aware of the same and alleged that RCF had not provided

the same. This is because their engineers were at the site and therefore

aware of all the alarms and signals observed in the control systems of

the GTGs.

120. Mr. Mehta has submitted that the 269 air intake filter

alarms and 52 air intake filter alarms observed in GTG 1 and GTG 2

respectively, were all the FP915 signal / alarm. In the Fault Procedure

forming part of the O & M Manual, the action suggested when this

alarm is observed is to "Check the trend curve. Change filter stage No.

1 and or stage 2 depending on the trend curve. ". He has submitted

that it is pertinent to note that the data regarding the trend curves was

always available with Thermax / Siemens and the same even finds

place in the Siemens RCA. This has also been admitted by Mr. Roger

Ahlin (RW-2) during his cross-examination that the trend curve data

was available with Siemens at the time of making the Siemens RCA.

He has submitted that neither in its pleadings nor in the evidence has

Thermax sought to make out a case that the trend curves observed

with regard to the filters pursuant to the FP915 signals / alarms, were

RJ-CARBP 394.2023 with IAL-23263-23.doc

of such a nature that they indicated that the filters required to be

changed.

121. Mr. Mehta has submitted that the FP915 signal / alarm

did not relate to the compressor and did not suggest any fault in the

compressor or action to be taken with regard to the compressor. The

only signal / alarm relating to the compressor was the FQ910

Compressor Malfunctioning Alarm. The action suggested when this

signal / alarm was observed, was to shut down the GTG and wash the

compressor. He has submitted that admittedly, this signal / alarm was

never observed in the control system of either of the GTGs. He has

submitted that in the absence of the Compressor Malfunctioning

Alarm being observed in the control system, it was safe for parties to

assume that there was nothing wrong in the compressor, including

that the compressor was not severely fouled.

122. Mr. Mehta has submitted that the contention of

Thermax that the primary alert mechanism were the air intake filter

alarms is completely misconceived and baseless. He has submitted that

it is only the Compressor Malfunctioning Alarm which indicates a

problem in the compressor. This alarm is therefore the primary alert

RJ-CARBP 394.2023 with IAL-23263-23.doc

mechanism in relation to the compressor. He has submitted that the

failure on the part of Thermax / Siemens to configure this alarm was

therefore a very serious defect in the GTGs and this led to the

breakdown of the GTGs inasmuch as there was no indication at any

point of time that there was any problem or issue with the

compressors or that they were severely fouled.

123. Mr. Mehta has referred to Siemens RCA in support of his

submission that this establishes that the GTGs were defective. He has

submitted that in view of high saline or salt content in the air at the

site of the plant, the Siemens RCF recommended the adjustment of the

replacement interval of the filters based on time. It was also

recommended to evaluate whether the existing maintenance plan for

the air intake filters required to be modified. It is further stated in the

Siemens RCA that if F9 filters had been installed instead of F8 filters,

the events that had occurred would have occurred at a slightly later

stage, meaning thereby that the GTGs would not have failed in March

2019. It was further found that the Compressor Malfunctioning Alarm

of both GTGs was incorrectly programmed in the control system as a

result of which this alarm did not appear in February and March 2019,

when it should have appeared in the control system. The RCA

RJ-CARBP 394.2023 with IAL-23263-23.doc

recommended that this alarm be rectified in both GTGs.

124. Mr. Mehta has submitted that the Siemens RCA does not

arrive at any conclusive finding with regard to the cause of the failure

of the GTGs, but merely provides "likely" and "possible" causes for the

failure. He has submitted that therefore, it is evident that Siemens is

not clear about the cause of the failure of the GTGs. In any event, it is

not possible to blame RCF for the failure of the GTGs on the basis of

such a speculative RCA.

125. Mr. Mehta has submitted that the testimony of Mr.

Roger Ahlin (RW-2) and Mr. Michael Wood (RW-3), inter alia, also

corroborates the findings of the Siemens RCA on the above aspects. He

has referred to their evidence in this context.

126. Mr. Mehta has submitted that it is clear from the

Siemens RCA itself that GTGs were defective and that if in fact any

party had failed to follow the O & M Manual or the instructions of

Siemens, it was Thermax and not RCF.

127. Mr. Mehta has submitted that though the material on

record shows that the normal operating life of the filters was a

RJ-CARBP 394.2023 with IAL-23263-23.doc

minimum of two years, the filter lifetime did not even last a year. He

has relied upon the documentary evidence on record, which includes

O & M Manual, which provides that the filter expiry date is required

to be checked after two years of operation, suggesting that the filter

operating life is at least two years.

128. Mr. Mehta has submitted that the plant was inherently

defective and neither designed nor installed properly by Thermax /

Siemens and which is apparent from the fact that at the very

beginning, the plant was displaying all kinds of defects. Repeatedly

signals/alarms/trips as provided in the Fault Procedure were

observed. On 27th February 2019, an abnormal sound was heard in

GTG-1 and the air compressor suction duct clamps of GTG-2 had

become detached from their original position and that there was a gap

between the suction duct, lower and upper halves, from where air was

being released. Although this was to be brought to the attention of

Thermax, in view of plant being under control and supervision of

Thermax, these issues ought to have been investigated thoroughly by

Thermax / Siemens, possibly by opening the compressor and

examining it.

RJ-CARBP 394.2023 with IAL-23263-23.doc

129. Mr. Mehta has submitted that on 28th February 2019,

there was an increase in vibrations in GTG-1, thereafter the vibrations

remained more or less constant at the increased level. He has

submitted that Mr. Wood has considered this aspect in paragraph 6.4.1

of the RINA Report. Mr. Wood states that sudden changes in vibrations

normally indicated that there has been a mechanical change in the

compressor or turbine. He has referred to the cross-examination of Mr.

Michael Wood (RW-3) (Q&A 52 and 53) where he was asked what is

meant by mechanical change in the compressor or turbine. Mr.

Michael Wood (RW-3) stated that if there were changes in the

vibration behaviour, then one of the possible reasons was that pieces

of the rotating equipment had broken away e.g. a piece of the blade.

He has admitted that vibrations in GTG-1 had continued to remain at

the higher level after 28th February 2019 until its failure i.e. changed

permanently.

130. Mr. Mehta has submitted that in view of RINA Report

and the deposition of Mr. Michael Wood (RW-3), it is clear that on

28th February 2019 itself, one or more pieces of the rotor blades of

GTG-1 had broken away which resulted in the permanent increase in

vibrations.

RJ-CARBP 394.2023 with IAL-23263-23.doc

131. Mr. Mehta has submitted that Mr. Roger Ahlin (RW-2)

was cross-examined (Q&A 78 - 80) with regard to the abnormal

sound heard on 27th February 2019. He has virtually admitted that no

independent investigation was carried out and that Siemens therefore

did not know the cause of the sound.

132. Mr. Mehta has submitted that it is clear from Mr. Roger

Ahlin's answers that Thermax / Siemens did not investigate the matter

further with a view to determine the reason for the sound. They ought

to have opened the compressor and examined it. Instead, all that they

did and recommended was to keep washing the compressor.

133. Mr. Mehta has submitted that though it is alleged by

Thermax that RCF did not shut down GTG-1 immediately on receiving

instructions from Siemens on 21st March 2019 at 13:27 p.m. to do so,

RCF did immediately commence the process of shutting down GTG-1.

He has submitted that in a similar situation in February 2019, when

instructed by Siemens to urgently shut down and wash the

compressor, Thermax/RCF had not done so within 24 to 48 hours after

receiving the instructions and Siemens had not found any fault with

the same. He has submitted that moreover, the Compressor

RJ-CARBP 394.2023 with IAL-23263-23.doc

Malfunctioning Alarm was not seen in the control system and hence,

there was no cause for RCF to be concerned about the compressor

being damaged. He has submitted that RCF cannot be blamed for not

instantaneously shutting down GTG-1 by risking its downstream plant

but instead taking all the proper steps to shut down GTG-1 after

taking precautions to safeguard the downstream plant and GTG-1 in

the same manner as it had done in the past, e.g. February 2019, under

the supervision of Thermax.

134. Mr. Mehta has relied upon the findings of the Arbitral

Tribunal on the above aspects i.e. paragraphs 19, 35 to 54, 63, 85 to

87 and 95 of the impugned Award. He has submitted that these

findings clearly show that there was no confusion whatsoever in the

mind of the Tribunal nor is there any confusion in the findings

rendered in the impugned Award.

135. Mr. Mehta has submitted that out of the claims of RCF

for damages / compensation from Thermax, the Arbitral Tribunal has

only awarded claim of Rs. 173.72 Crores towards loss suffered by RCF

due to additional expenditure on power. All the other claims of RCF

were rejected by the Arbitral Tribunal. He has referred to the findings

RJ-CARBP 394.2023 with IAL-23263-23.doc

of the Arbitral Tribunal where the claim of Rs. 173.72 Crores has been

dealt with i.e. paragraphs 56 to 62, 64 to 76 and 96 of the impugned

Award.

136. Mr. Mehta has submitted that RCF's claim for damages /

compensation of Rs. 173.72 Crores was based on the loss caused to it

on account of the increased expenditure incurred by RCF to secure

power from other sources due to the breakdown of the 2 GTGs. After

the GTGs broke down, RCF was required to secure power from the

State Grid i.e. MSEB as well as to generate power from steam turbo

generators. The cost of procuring power through these sources was

higher than the cost of power procured through the GTGs. The

increased cost of power procured by RCF during the period from 1st

April 2019 to 30th November 2020 was Rs. 173.72 Crores.

137. Mr. Mehta has submitted that the said loss suffered by

RCF naturally arose in the usual course of things and parties obviously

knew that such a loss would arise in the event of the breakdown of

the GTGs. The immediate effect of the breakdown of the GTGs would

be the procuring of power from other sources and this was the natural

consequence of the breakdown of the GTGs. Such a loss was obviously

RJ-CARBP 394.2023 with IAL-23263-23.doc

in clear contemplation of the Parties. There is no question of such a

loss being remote or indirect. This loss is therefore covered by the

first paragraph of Section 73.

138. Mr. Mehta has submitted that Thermax has accepted the

position that such a loss on account of the increased expenditure arose

out of the breakdown of the GTGs is covered by the first paragraph of

Section 73. However, it seems to be the case of Thermax that this loss

is a "consequential loss", which though covered by the first

paragraph of Section 73, is excluded by virtue of Clause 32.2(a) of

the GCC. It is Thermax's case that the consequential loss is not the

same as remote or indirect loss. Thus, it fell for consideration before

Arbitral Tribunal, as to what is the meaning of consequential loss.

139. Mr. Mehta has submitted that the consequential loss is

the same as indirect loss and is not a loss naturally arising in the usual

course of things or which parties knew would arise. It is therefore, a

loss covered by the second paragraph of Section 73 and not the first

paragraph. He has placed reliance upon Saint Line Limited Vs.

Richardsons, Westgarth & Co., Limited (supra); McDermott

International Inc. Vs. Burn Standard Co. Ltd. and others 25, Black's

25 (2006) 11 SCC 181 at paras 116 to 120

RJ-CARBP 394.2023 with IAL-23263-23.doc

Law Dictionary and P. Ramanatha Aiyar Dictionary.

140. Mr. Mehta has submitted that in the decision relied

upon by Thermax on the issue of consequential loss, namely Seth

Thawardas Pherumal (supra), the parties had contemplated the

remote loss and expressly excluded it contractually. This was not a

decision on consequential loss. Further, the decision of Shwetadri

Speciality Papers Pvt. Ltd. (supra) and Trojan And Company (supra)

relied upon by Thermax are not cases of consequential damages. They

are cases relating to the sale of shares (i.e. goods) and, as such, the

principle relied upon therein by Thermax is not applicable in the

present case, in as much as the present case is not a case of sale of

goods. He has submitted that Chief Commercial Superintendent of

Rail ways, Secunderabad Vs. Anand Kumar (supra) relied upon by

Thermax was a case where the claim in question was held to be

remote and hence, barred under Section 78(d) of the Indian Railways

Act, 1890. He has referred to Section 78(d), which treats indirect

and consequential damages as being of the same kind i.e. remote. He

has submitted that even the Legislature has treated consequential

damages as damages which do not naturally arise in the usual course

of things from a breach of contract.

RJ-CARBP 394.2023 with IAL-23263-23.doc

141. Mr. Mehta has submitted that the extracts from

McGregor on Law of Damages relied upon by Thermax relate to

damages under the law of torts and that too, on damage to goods. It is

inapplicable in the present case. He has submitted that it is well

settled that the plant and machinery fixed to the ground are not

goods, but are immovable property. The GTGs manufactured and

installed by Thermax constitute plant and machinery and are fixed to

the ground and hence, are not goods. Consequently, the principles

applicable to goods will not apply to the GTGs.

142. Mr. Mehta has submitted that Section 73 is based on the

principles of English Law as enunciated in the classic case of Hadley

Vs. Baxendale. This being so, there is no question of Thermax

contending that English Law ought not to be considered while

deciding what is consequential loss in the context of Section 73.

143. Mr. Mehta has submitted that the consequential loss is

also an indirect or remote loss and is not a loss that arises naturally in

the usual course of things from a breach of contract. Accordingly,

Clause 32.2(a) did not exclude losses naturally arising from the usual

course of things from a breach of contract. He has submitted that

RJ-CARBP 394.2023 with IAL-23263-23.doc

RCF's claim for damages/compensation of Rs. 173.72 Crores is not

excluded by Clause 32.2(a) of the GCC.

144. Mr. Mehta has dealt with the contention of Thermax viz.

that the claim of RCF to damages / compensation was beyond the scope

of Agreement titled as "Notice to proceed" dated 2nd July 2019 entered

into between Thermax and RCF in relation to repairs and reinstatement

from GTGS. He has submitted that this contention is misconceived.

Notice to Proceed is a clear and unambiguous document and therefore,

required to be construed on the basis of the terms contained therein. He

has submitted that it is clear from the terms of the Notice To Proceed

that it was only concerned with the repairs and restoration of the GTGs

and was issued by RCF in view of the provisions of Clause 17 of the

SCC and pursuant to an arrangement agreed to between RCF and

Thermax with regard to the repairs and restoration of the GTGs. The

Notice To Proceed had no bearing on the right of RCF to claim damages

from Thermax for the loss suffered by RCF on account of the failure of

the GTGs.

145. Mr. Mehta has submitted that the contention of Thermax

with regard to force majeure, i.e. Covid-19 pandemic, which broke out

RJ-CARBP 394.2023 with IAL-23263-23.doc

in March, 2020 being a force majeure event due to which RCF's claim

for damages of Rs. 173.72 Crores is liable to be rejected is

misconceived. He has submitted that there is no question of the Covid-

19 pandemic being a force majeure event for a claim commencing from

1st April 2019, when there was no such pandemic in existence.

Moreover, the two GTGs were required to be repaired and restored

within 33 and 35 weeks respectively, which period was virtually over by

March, 2020. He has submitted that it is obvious that Thermax was

merely using the Covid-19 pandemic as an excuse for the delay on its

part in repairing and restoring the GTGs.

146. Mr. Mehta has submitted that Thermax neither produced

any material whatsoever in terms of Clause 35 of the GCC nor evidence

was led to show how the Covid-19 pandemic prevented or delayed the

completion of the repairs and restoration of the GTGs. The damaged

GTGs had already shipped to Sweden much before the Covid-19

pandemic. Thermax has neither explained nor proved what prevented

or delayed the carrying out of the repairs and restoration of the GTGs in

Sweden, when they were already at the factory of Siemens prior to the

outbreak of the Covid-19 pandemic.

RJ-CARBP 394.2023 with IAL-23263-23.doc

147. Mr. Mehta has submitted regarding the contention of

Thermax that the issue of force majeure due to the Covid-19 pandemic

was not considered by the Arbitral Tribunal, the admitted facts

established beyond a shadow of doubt that there is no substance

whatsoever in this contention and that the Arbitral Tribunal was not

required to consider every such frivolous and trivial issue raised by

Thermax.

148. Mr. Mehta has submitted that insofar as the contention of

Thermax that the Chartered Accountant, who had prepared the

Certificates which have been relied upon in the Affidavit of Evidence of

Mr. Shivkumar Subramanian (CW-2), the Deputy General Manager-

Corporate Finance of RCF, at the relevant time, having neither been

examined nor produced for cross-examination, made it impossible for

Thermax to ascertain the basis on which, the said Certificates were

prepared or the details of the relevant records relied upon, nor was it

possible the controvert the said Certificates, is misconceived. He has

submitted that the claim of Rs. 173.72 Crores was proven by the

evidence of Mr. Shivkumar Subramanian (CW-2), who had personal

knowledge of the facts and figures deposed in the Affidavit of

Evidence. He has referred to the Affidavit of Evidence dated 29th

RJ-CARBP 394.2023 with IAL-23263-23.doc

March 2021 as well as cross-examination of CW-2 in this context. He

has submitted that CW-2 has in support of the computation of

damages i.e. additional expenditure incurred by RCF towards the cost

of power, submitted two financial statements, one for the period from

1st April 2019 to 31st March, 2020 and the second for the period from

1st April 2020 to 30th November 2020, which have been annexed to

the Affidavit of Evidence. Thus, the Financial Claim Statements were

part of the Certificates of the Chartered Accountants dated 11th

January 2020, which were produced by CW-2. These Financial

Statements contained the break up and particulars of the various

expenses incurred by RCF for the purpose of generating power from

the GTGs, Turbo generators and MSEB.

149. Mr. Mehta has also referred to the further Affidavit of

Evidence dated 20th July 2021, in which the CW-2 has deposed to the

correctness of the amounts and figures in the Financial Claim

Statements. He has also relied upon the readings in the SAP ERP

System as regards the cost of power secured through the turbo

generators and GTGs. CW-2 has deposed that he has personally

verified the figures and data in the SAP ERP System and that the

computation of the expenditure incurred towards the consumption of

RJ-CARBP 394.2023 with IAL-23263-23.doc

power as provided by CW-2 in his Affidavit of Evidence dated 29th

March 2021, which was based on these figures and data and was

correct.

150. Mr. Mehta has submitted that the CW-2 in his cross-

examination when asked as to who had prepared these Financial

Claim Statements, CW-2 answered that the same were prepared by his

costing team under his supervision. He has submitted that both the

Certificates of the Chartered Accountant state the Financial Claim

Statements annexed thereto were prepared by the Management of

RCF and that the contents thereof had been verified by the Chartered

Accountants from the Books of Accounts and from the other relevant

records of RCF. He has submitted that CW-2 being part of the

Management of RCF as the Deputy General Manager, Corporate

Finance was having personal knowledge of the matter and was in the

best position to prove the claim. In fact, CW-2 was in a better position

than the Chartered Accountants. Consequently, the evidence of Mr.

Shivkumar Subramanian (CW-2) was the best evidence and there was

no requirement to lead the evidence of the Chartered Accountants.

151. Mr. Mehta has submitted that the contention of

RJ-CARBP 394.2023 with IAL-23263-23.doc

Thermax that the alleged underlying documents were not produced is

based inter alia on the incorrect assumption that the data and figures

relied upon by Mr. Shivkumar Subramanian (CW-2) can be derived

only from underlying documents.

152. Mr. Mehta has submitted that the contention of Thermax

that RCF ought to have produced a printout of the SAP-ERP System to

prove its claim and that in the absence thereof, the evidence of Mr.

Shivkumar Subramanian (CW-2) was secondary evidence is also

misconceived. He has submitted that as explained by CW-2, the SAP-

ERP System is a system in which entries are made. It is not a

document in the sense of an email, contract etc. CW-2's deposition was

that he verified the various inputs and figures available in the SAP-ERP

System with his own records and the records of RCF. In these

circumstances, the evidence of CW-2 was not secondary evidence, but

primary evidence adduced on the basis of his records and records of

RCF and his personal knowledge.

153. Mr. Mehta has submitted that it is well settled that

while considering an application under Section 34 of the Arbitration

Act, the Court does not act as a Court of Appeal and errors of fact

RJ-CARBP 394.2023 with IAL-23263-23.doc

cannot be corrected. A possible view by the Arbitrator on facts has

necessarily to pass muster as the Arbitrator is the ultimate master of

the quantity and quality of evidence to be relied upon, when he

delivers his award. Once it is found that the Arbitrator's approach is

not arbitrary or capricious, then he is the last word on facts. He has

placed reliance on the decision of the Supreme Court in Associate

Builders Vs. Delhi Development Authority (supra) in this context.

154. Mr. Mehta has submitted that the counterclaim of

Thermax with regard to MAD by which Thermax sought an Award

against RCF for the amount of Rs. 23,09,09,100/- recovered by RCF as

MAD has been rightly rejected by the Arbitral Tribunal.

155. Mr. Mehta has submitted that Clause 3(73) and Clause

31.1.3 of the GCC provided for MAD. He has submitted that it is clear

from the above provisions of the GCC that the time for completion of

the works was the essence of the Contract and of utmost importance

and in the event of Thermax failing to achieve the Preliminary

Acceptance within the contractual completion period from the

effective date, then Thermax was liable to pay to RCF, MAD at the

rate of 0.77% of the total contract price for every week or part thereof,

RJ-CARBP 394.2023 with IAL-23263-23.doc

subject to a maximum of 5% of the contract price. He has submitted

that the Preliminary Acceptance was to be achieved within 22 months

from effective date i.e. by 11th December 2017. Thermax achieved

Preliminary Acceptance only on 7th March 2019 after a delay of 444

days. Consequently, RCF was entitled to recover MAD from Thermax

for the period of delay. RCF recovered only 5% of the contract price as

MAD in view of the ceiling of 5% stipulated by Clause 31.1.3 of the

GCC.

156. Mr. Mehta has submitted that it is well settled that if

the terms of a contract stipulate the liquidated damages to be

recovered in the case of breach of contract, the same can be recovered

from the party who has committed the breach of contract unless it is

established by such party that the said liquidated damages /

compensation was unreasonable or by way of a penalty. He has placed

reliance on the decision of the Supreme Court in Oil and Natural Gas

Corporation Ltd. Vs. SAW Pipes26. He has submitted that it is not the

case of Thermax in its Counterclaim that the liquidated damages

stipulated by Clause 31.1.3 were either unreasonable or in the nature

of a penalty. It is the case of Thermax in its pleadings that RCF had

26 2003(5)SCC 705

RJ-CARBP 394.2023 with IAL-23263-23.doc

not shown that the delay in achieving Preliminary Acceptance was on

account of Thermax. He has submitted that the question whether the

stipulation of liquidated damages was unreasonable or in the nature of

a penalty cannot be raised unless it is pleaded. Accordingly, it must be

assumed that the liquidated damages agreed by parties vide Clause

31.1.3 were a reasonable estimate of the loss that would be caused to

RCF on account of the delay on the part of Thermax in achieving

Preliminary Acceptance and there was no necessity for RCF to prove

any loss.

157. Mr. Mehta has submitted that the contention of

Thermax that RCF did not establish that the delay in achieving

Preliminary Acceptance was on account of Thermax is misconceived.

The Arbitral Tribunal after considering all the evidence and material

on record has rejected the contention of Thermax. RCF had produced

voluminous documents in answer to Thermax's contentions and

proved that Thermax alone was guilty of the delay in achieving

Preliminary Acceptance. This was accepted by the Arbitral Tribunal.

He has placed reliance upon the evidence of RCF's witness, Mr.

Ravindra Jawale, CW-1, who has deposed regarding delay on the

part of Thermax in paragraph 4 of further Affidavit of Evidence dated

RJ-CARBP 394.2023 with IAL-23263-23.doc

31st March 2021. Thermax's Witness, Mr. Sunil Raina, RW-1 was also

cross-examined in detail on this aspect. The Arbitral Tribunal, after

considering and appreciating the evidence led by both sides, dealt with

the various issues raised by Thermax in detail in paragraph 91 of the

impugned Award. He has submitted that these are all findings of fact

and they cannot be interfered with through proceedings under Section

34 of the Arbitration Act.

158. Mr. Mehta has submitted that the learned Arbitrator has

considered the submissions of Thermax as well as the evidence on

record while arriving the findings on the matters relating to PAC. He

has relied upon the various findings on the submissions of Thermax.

159. Mr. Mehta has submitted that Thermax has contended

that the impugned Award is liable to be set aside, if it falls within the

three categories enunciated in the decision of the Supreme Court in the

case of OPG Power Generation Pvt. Ltd. Vs. Enexio Power Cooling

Solutions India Pvt. Ltd. & Anr.27. He has submitted that according to

Thermax, the impugned Award is devoid of reasons or in any event, the

reasons furnished are inadequate. He has submitted that in fact the

learned Arbitrator has given reasons in support of her findings and

27 (2025) 2 SCC 417

RJ-CARBP 394.2023 with IAL-23263-23.doc

which have been relied upon. He has submitted that Thermax has

completely misconstrued the judgment of the Supreme Court in OPG

Power Generation Pvt. Ltd. (supra). In paragraph 80, the Supreme

Court in the first sentence itself expressed its absolute agreement with

the view taken by the Supreme Court in paragraphs 34 and 35 of its

decision in the case of Dyna Technologies (supra). The ratio of the

Supreme Court in Dyna Technologies (supra) has thus been reaffirmed

by the Supreme Court in OPG Power Generation Pvt. Ltd. (supra). The

Supreme Court has merely added that in appropriate cases, the

documents referred to in the award may also be examined to decide

whether the reasons in the award are unintelligible or inadequate.

Accordingly, it is open for the Court considering an application under

Section 34 to examine documents produced before the Arbitral Tribunal

for the purpose of deciding whether the reasons in the award are

adequate and intelligible. He has submitted that the contention of

Thermax that RCF has sought to cover up the absence of reasons by

relying upon the documents and material not referred to in the Award

is misconceived.

160. Mr. Mehta has submitted that the reasons in the

impugned Award are in fact intelligible and adequate. The learned

RJ-CARBP 394.2023 with IAL-23263-23.doc

Arbitrator may not have referred to every email or correspondence in

the impugned Award. He has submitted that all relevant facts and

materials have duly been considered by the learned Arbitrator. It is well

settled that an Arbitrator is not required to consider or deal with each

and every submission and piece of evidence while adjudicating upon

the various issues and it is sufficient for the Arbitrator to consider the

relevant submissions and material on record, which in the instant case,

the learned Arbitrator has done.

161. Mr. Mehta has submitted that RCF has not attempted to

call upon this Court to reappreciate the entire evidence or to reinterpret

the terms of the Contract as contended by Thermax. On the contrary,

this is exactly what Thermax has invited this Court to do so.

162. Mr. Mehta has accordingly, submitted that there is no

valid ground raised by the Petitioner under Section 34 of the

Arbitration Act and the above Commercial Arbitration Petition requires

to be dismissed.

163. Having considered the submissions, from a reading of

the impugned Award, it is evident that the findings arrived at by the

learned Arbitrator are inter alia based on no evidence at all or by

RJ-CARBP 394.2023 with IAL-23263-23.doc

disregarding vital evidence. It is well settled law that a Court under

Section 34 of the Arbitration Act can only look beyond and outside the

Award for the limited purpose of considering whether the evidence on

record has been ignored and/or disregarded by the Arbitral Tribunal.

Further several findings of the learned Arbitrator in the impugned

Award are bereft of reasons.

164. The Supreme Court in its recent decision in OPG Power

Generation Pvt. Ltd. (supra) has laid down three categories for setting

aside an Arbitral Award in paragraph 80, which read thus :-

"80. We find ourselves in agreement with the view

taken in Dyna Technologies (supra), as extracted

above. Therefore, in our view, for the purposes of

addressing an application to set aside an arbitral

award on the ground of improper or inadequate

reasons, or lack of reasons, awards can broadly be

placed in three categories:

(1) where no reasons are recorded, or the

reasons recorded are unintelligible;

RJ-CARBP 394.2023 with IAL-23263-23.doc

(2) where reasons are improper, that is, they

reveal a flaw in the decision- making process; and

(3) where reasons appear inadequate."

165. After setting out the three categories, the Supreme

Court has in paragraphs 81 to 83 held as under:

"81. Awards falling in category (1) are vulnerable as

they would be in conflict with the provisions of

Section 31(3) of the 1996 Act. Therefore, such

awards are liable to be set aside under Section

34, unless (a) the parties have agreed that no

reasons are to be given, or (b) the award is an

arbitral award on agreed terms under Section 30.

82. Awards falling in category (2) are amenable to a

challenge on ground of impropriety or perversity,

strictly in accordance with the grounds set out in

Section 34 of the 1996 Act.

83. Awards falling in category (3) require to be dealt

with care. In a challenge to such award, before

RJ-CARBP 394.2023 with IAL-23263-23.doc

taking a decision the Court must take into

consideration the nature of the issues arising

between the parties in the arbitral proceedings and

the degree of reasoning required to address them.

The Court must thereafter carefully peruse the

award, and the documents referred to therein. If

reasons are intelligible and adequate on a fair-

reading of the award and, in appropriate cases,

implicit in the documents referred to therein, the

award is not to be set aside for inadequacy of

reasons. However, if gaps are such that they render

the reasoning in support of the award

unintelligible, or lacking, the Court exercising

power under Section 34 may set aside the award."

(emphasis supplied)

166. Having perused the impugned Award, it falls within all

the three categories as enunciated by the Supreme Court in OPG Power

Generation Pvt. Ltd. (supra), which render the impugned Award liable

to be set aside.

RJ-CARBP 394.2023 with IAL-23263-23.doc

167. The learned Arbitrator has side-stepped one of the

principal issues that arose for consideration, viz. the fact that RCF had

taken over the plant from Thermax and was using the plant for

commercial purposes for approximately eleven months from April 2018

to March 2019 prior to issuing the PAC. It was the contention of

Thermax that RCF had benefited by the use of the plant by substantially

saving on energy costs as well as other benefits. Thermax had led

extensive evidence before the learned Arbitrator to show that RCF was

in complete control of the plant from April 2018 onwards, i.e. well

before it issued the PAC and was using the plant for its commercial

production. In the impugned Award, this entire evidence has been

completely disregarded.

168. The learned Arbitrator has omitted to consider the

documents on record as well as the evidence which established that

RCF was using the GTGs as its primary source of power from April 2018

by using the same i.e. for 7644 hours for GTG-1 and 7827 hours for

GTG-2 and generating a total of 3,27,152 MWH of power between April

2018 and March 2019. The material on record which includes

correspondence between Siemens and RCF relied upon by Thermax

before the learned Arbitrator in relation to the operation of the GTGs,

RJ-CARBP 394.2023 with IAL-23263-23.doc

shows that it was RCF who had sent emails to Siemens on the

difficulties faced by it while commercially operating / running the plant.

It is the established fact that RCF was independently operating the plant

(without any supervision) long before the PAC was issued by them. The

learned Arbitrator has completely failed to consider and/or deal with

this aspect of the matter in the Award.

169. The learned Arbitrator has solely based her findings on

the aforementioned fundamental issue by taking shelter behind a

contractual provisions of PAC and the term "Taking over". This is

apparent from paragraph 34 of the impugned Award. This approach by

the learned Arbitrator is ex facie perverse. There is not even a

smattering of reason given by the learned Arbitrator for ignoring the

extensive evidence produced by Thermax in this regard.

170. In view of aforementioned issue being a fundamental

issue it was required to be determined not only on the contractual

provisions, but also on the evidence as well as the material documents

placed on record. The learned Arbitrator could not simply ignore

and/or disregard the same. It is evident from the material on record

that RCF had taken possession of and started using the plant as far back

RJ-CARBP 394.2023 with IAL-23263-23.doc

as April 2018 prior to the issuance of PAC on 15th March 2019. There is

merit in the submission of Thermax that Clauses 3(63) read with 3(50)

of GCC relating to 'take over', 'taking over' and 'taken over' and defining

'Preliminary Acceptance' were rendered completely irrelevant and

otiose. RCF having chosen to take over the plant and start using the

same for commercial purposes prior to the issuance of a PAC was no

longer entitled to contend that the date of taking over was the date of

the PAC. RCF had admittedly claimed depreciation on the plant for

the entire year, which makes it evident that RCF had itself chosen to

take over the plant without issuing a PAC as contemplated under the

Contract.

171. I do not find any merit in the submission of RCF that

Thermax had not raised the argument before the learned Arbitrator

that Clauses 3(63) read with 3(50) of GCC had been rendered

completely irrelevant and otiose. This is contrary to material on

record as well as evidence placed by Thermax before the learned

Arbitrator in support of this contention of Thermax.

172. RCF has with an attempt to support the impugned

Award called upon this Court to re-appreciate the evidence without

RJ-CARBP 394.2023 with IAL-23263-23.doc

dealing with the submissions made by Thermax in relation to

deficiencies in the Award.

173. It is Thermax's case that the reason for breakdown of

the GTGs was on account of faulty handling of the GTGs by RCF and

failure to comply with the O & M Manual. RCF had ignored several

numerous repeated warnings from the air intake filter alarms, i.e.

269 Filter Alarms in GTG-1 and 52 Filter Alarms in GTG-2, though

admittedly noticed by RCF and this was neither reported to

Thermax / Siemens nor did RCF take any action as per O & M

Manual to change the filters. The Final RCA opines that the real

cause for accumulation of dirt on blades of compressor was that the

filters were not changed on time. The Final RCA in its conclusion

stated that breakdown could have been avoided by washing the dirt

on the compressor blades in time. The learned Arbitrator inspite of

the material on record, has failed to consider and overlooked the fact

that air intake filter alarms was the primary alert mechanism to

indicate the problem in filtration and the condition of the filters. The

learned Arbitrator has in side-stepping the issue, placed reliance on

the fact that the compressor malfunction alarm had been incorrectly

configured.

RJ-CARBP 394.2023 with IAL-23263-23.doc

174. The learned Arbitrator by failing to deal with and/or

disregarding the evidence of Thermax in particular, the testimony of

RW-2 regarding the repeated warnings from air intake filter alarms,

makes the impugned Award vulnerable to being set aside under

Section 34 of the Arbitration Act on this ground.

175. RCF had not answered Thermax's arguments on failure

of RCF to take appropriate action upon noticing these filter alarms.

RCF has attempted to justify the same on the ground that this issue

had not been raised before the learned Arbitrator and was being

raised before this Court for the first time.

176. The material on record also establishes that at the

relevant time of breakdown of GTG-1, this could have been avoided,

if the plant had been shutdown immediately by RCF on instructions

of Siemens. It has been admitted by RCF's witness (CW-1) during his

cross-examination that it is possible to shutdown the plant within

half an hour. The only reason given by RCF for failure to immediately

shut down GTG-1, which would have prevented its breakdown, was

that on previous occasions also RCF had taken 24 - 48 hours to

shutdown the plant. This overlooks the fact that Siemens by its email

RJ-CARBP 394.2023 with IAL-23263-23.doc

on 21st March 2019 at 13:27 hours, had categorically instructed RCF

to "stop the unit immediately and wash it" . The argument that RCF

had stopped the plant within 24-48 hours of the Instructions of

Siemens on prior occasions could not be applied to a situation where

RCF was categorically informed to stop the unit "immediately" to

"prevent same events as that of GTG-2" . The learned Arbitrator has

not considered this aspect of the matter in the Award.

177. The learned Arbitrator has in the impugned Award

selectively relied upon the findings in the Final RCA to hold that the

GTGs were defective in nature. This overlooks the conclusion of the

Final RCA, viz. that dirt and most likely liquids entered into the

compressor causing the compressor to become so dirty that the blades

cracked due to high cycle fatigue causing the debris to damage other

parts of the compressor. The dirt on the blades was caused on account

of the filters not filtering the dirt and allowing dirt and salts to wash

through the filters and settle on the blades. Had the filters been

inspected and maintained periodically and replaced in time, the

breakdown of the GTGs could have been prevented.

178. The case of RCF before the Arbitral Tribunal was that

RJ-CARBP 394.2023 with IAL-23263-23.doc

the GTGs supplied to them were inherently defective in nature. RCF in

order to prove this defect, had produced the Shakti Report and had led

evidence of Mr. Jamula Sudhakar (CW-3), Director of Shakti, who was

co-Author of the Shakti Report. This was in order to establish that

the defect in the GTGs was on account of rubbing theory. However,

RCF abandoned and/or failed to prove the Shakti Report. In view

thereof, the learned Arbitrator should have held that RCF had failed

to establish that the GTGs supplied to them were inherently

defective.

179. The learned Arbitrator has mixed up the issues of

defect in GTGs with the breakdown in the GTGs. It was for the

learned Arbitrator to consider that RCF had by taking over the plant

from Thermax and putting it to use for commercial purpose for

approximately eleven months from April 2018 to March 2019 i.e. prior

to the issuance of the PAC, was incharge in control of the plant and by

its neglect in taking action on the filter alarms as per O & M Manual,

the breakdown of the GTGs is to their account.

180. The RCF has sought to supplement the inadequacy of

reasons of the learned Arbitrator. RCF has contended that Thermax had

RJ-CARBP 394.2023 with IAL-23263-23.doc

not investigated into the ambient air conditions at Thal site. This by

relying upon Clauses 14.4 and 14.5 of the Instructions to Bidders and

Clauses 4.1 and 6.1.2 of Technical Specifications. The Award makes no

mention and/or reference to these Clauses and/or considers the same.

Further, RCF has relied upon events that purportedly transpired on

27th February 2019, 28th February 2019 and 1st March 2019 and the

evidence of Mr. Michael Wood (RW-3) to contend that

Thermax/Siemens had not responded to RCF in respect of certain

problems faced by it while operating the plant. It is pertinent to note

that the Award does not make any reference to these dates/events and

thus, RCF is relying on material/evidence which does not form part of

the Award.

181. RCF also sought to refute the contention of Thermax that

Thermax had moved out from RCF's plant on 11th May 2018 barring

one site engineer by referring to the Counterclaim of Thermax for

overstay of personnel at site. The learned Arbitrator in the Award has

not arrived at any findings on this issue. There is no discussions /

findings in the Award on the issue of costs incurred by Thermax for

extended stay of manpower. This submission of RCF clearly travels

beyond the Award.

RJ-CARBP 394.2023 with IAL-23263-23.doc

182. The learned Arbitrator has not dealt with the 'Statement

of Agreed Variation' under which RCF was not allowed to start

commercial operation of the GTGs prior to the PG Test. The learned

Arbitrator has thus ignored vital evidence in the form of 'Statement of

Agreed Variation' .

183. RCF has sought to justify the categorical statement made

in their Annual Report for FY 2018-19 that GTGs were commissioned in

April 2018 and depreciation had been claimed for FY 2018-19 by

claiming that commissioning of the GTGs was at the stage prior to

commercial production and hence, the Annual Report for FY 2018-19

correctly mentioned that GTGs were commissioned in April 2018. This

justification / reasoning is conspicuously absent from the Award.

184. This Court under Section 34 of the Arbitration Act

cannot re-appreaciate the evidence placed before the learned Arbitrator

by a party. Under the provisions of Section 34 of the Arbitration Act

while deciding whether or not to set aside an award, the Court is only

concerned with the question with respect to whether the Arbitral

Tribunal has considered all relevant evidence, dealt with the same by

providing reasons in the award and/or whether the Arbitral Tribunal

RJ-CARBP 394.2023 with IAL-23263-23.doc

has disregarded/ignored certain vital evidence resulting in perversity in

the Award which amounts to a patent illegality. It is clear from a

reading of the impugned Award that the learned Arbitrator has

completely ignored and/or disregarded the submissions, and oral and

documentary vital evidence in support of these submissions. This results

in perversity in the Award which amounts to patent illegality. The

impugned Award is accordingly, liable to be set aside on this ground.

185. The learned Arbitrator has granted RCF damages to the

tune of Rs. 173.72 Crores. The learned Arbitrator has in paragraph 75

of the said Award given a finding to the effect that Mr. Shivkumar

Subramanian ('Shivkumar') / CW-2 had personal knowledge of the

figures that he had deposed. Shivkumar / CW-2 has relied upon the CA

Certificates to establish the claim regarding the cost of power, which

formed the basis of RCF's claim for damages. However, the evidence of

the Chartered Accountant was neither led nor the Chartered Accountant

produced for cross-examination.

186. RCF during the arguments before this Court purported to

contend that it did not rely upon the CA Certificates at all to prove its

claim. The learned Arbitrator has not recorded any such submission on

RJ-CARBP 394.2023 with IAL-23263-23.doc

the part of the RCF and the only finding recorded by the learned

Arbitrator as aforementioned is in paragraph 75 of the impugned

Award. The finding being that Shivkumar / CW-2 had deposed to these

figures on his personal knowledge as also on the basis of records of the

Claimant Company as maintained in the ordinary course of business

and his evidence is not shaken in cross-examination.

187. The learned Arbitrator has overlooked the fact that

Shivkumar / CW-2 has himself at multiple places in his evidence, and

even during the course of his cross - examination relied upon the CA

Certificates. RCF's entire case relating to adequacy of evidence to

support its claim for damages is now based on its contention that

Shivkumar / CW-2 had personal knowledge, which was adequate to

prove RCF's claim of Rs. 173.73 Crores. However, the claim made by

RCF and evidence led by its witness Shivkumar / CW-2 is on the

fundamental premise that the actual power requirement during 1st

April 2019 to 31st March 2020 was 3,50,669.64 MWH and that the

actual power requirement during 1st April 2020 to 30th November

2020 was 2,25,418.88 MWH. Except for the bare word of the witness

Shivkumar / CW-2, there is no evidence to corroborate these figures.

RJ-CARBP 394.2023 with IAL-23263-23.doc

188. Shivkumar / CW-2 claims that the figures have been

extrapolated from the SAP/ERP System maintained by RCF with

which he is "familiar". However, no supporting data from the

SAP/ERP System is produced to justify these claims. The learned

Arbitrator was thus expected to decide this claim only on the bare

statement of Shivkumar / CW-2 to the effect that the SAP/ERP System

contains the data that the witness claims to have seen. Further,

Shivkumar / CW-2 has relied upon what he calls "a certified copy of

Financial Claim Statement". The alleged certification of these financial

claim statements is based on the two Chartered Accountant

Certificates annexed to the Affidavit of Evidence dated 29th March

2021, of which RCF has now claimed that it does not wish to rely

upon.

189. In view of the submission now made by RCF that it does

not wish to rely on the CA Certificates, the references to the CA

Certificates in evidence is required to be disregarded. If this exercise is

undertaken, it will become all the more apparent that Shivkumar /

CW-2 had no personal knowledge that he claims to have and that his

evidence is completely insufficient to prove his claim. There is a failure

to provide the underlying documents evidencing the claim and this

RJ-CARBP 394.2023 with IAL-23263-23.doc

cannot be cured by leading the oral evidence of Shivkumar / CW-2.

Section 34 of the Evidence Act provides that entries in Books of

Accounts including those maintained in electronic form are not

sufficient to charge any person with liability. In this case the entries

have also not been produced.

190. The finding of the learned Arbitrator in paragraph 75 of

the impugned Award that Shivkumar's evidence "is not shaken in

cross-examination" is rendered without any supporting reasons and is

contrary to the answers given by Shivkumar / CW-2 during his cross

examination, which ex-facie shows that he has admitted his lack of

knowledge in relation to the claim. Thus, the learned Arbitrator by

accepting the evidence of Shivkumar / CW-2, has acted in an arbitrary

or perverse manner.

191. It is Thermax's contention that the claim for damages

on account of additional expenditure incurred on account of sourcing

power from alternate sources was either an "indirect" or a

"consequential" claim, which was expressly waived by the parties and

hence, the learned Arbitrator, being a creature of contract, was barred

from awarding the same. There is merit in this submission, considering

RJ-CARBP 394.2023 with IAL-23263-23.doc

Clause 32.2(a) of the GCC, which provides that a "Contractor shall, in

no circumstances, be liable in respect of any indirect or consequential

loss or loss of profit suffered by owner in connection with or arising

out of performance of Work under Contract.".

192. The cost incurred for purchasing of power in the

absence of power from the GTGs is consequential to the failure of the

GTGs. Under normal circumstances, applying Section 73 of Contract

Act, RCF could have claimed the said cost. Section 73 of the Contract

Act, 1872 reads as under :-

"73. Compensation for loss or damage caused by

breach of contract.-

1) When a contract has been broken, the party who

suffers by such breach is entitled to receive, from

the party who has broken the contract,

compensation for any loss or damage caused to

him thereby,

(a) which naturally arose in the usual course of

things from such breach, or

RJ-CARBP 394.2023 with IAL-23263-23.doc

(b) which the parties knew, when they made the

contract, to be likely to result from the breach

of it.

2) Such compensation is not to be given for any

remote and indirect loss or damage sustained by

reason of the breach."

193. Thermax and RCF had under Clause 32.2(a) of the GCC

expressly agreed for exclusion of certain categories of loss/damages,

from the ambit of Section 73(1). The "indirect loss" or "consequential

loss" in Clause 32.2(a) have been judicially interpreted to mean other

than and distinct/ different from "remote and indirect losses or

damages" , which are in any event, statutorily excluded under the

Indian codified law. The learned Arbitrator was called upon to

determine whether the contractual bar under Clause 32(2)(a) to grant

"indirect loss" or "consequential loss" was attracted. The learned

Arbitrator would firstly have to determine what would be the normal

measure of damages in a case like the present case; and secondly,

whether the claim for damages of RCF was beyond the normal

measure of damages and would therefore constitute an "indirect loss"

RJ-CARBP 394.2023 with IAL-23263-23.doc

or "consequential loss". The learned Arbitrator without determining

these issues, came to the conclusion that the claim of RCF fell within

Section 73(1) without examining the effect of parties excluding

"consequential" losses within the ambit of Section 73(1) by

incorporating Clause 32.2(a). I find much merit in the submission of

Thermax that Clause 32(2)(a) could never have been intended to

exclude what was anyways statutorily barred under Section 73(2).

194. The RCF by relying upon the decision of the King's

Bench Division in Saint Line Limited (supra) in support of their

contention that if the loss is direct, then it is not indirect or

consequential, has overlooked that whereas the law in India is codified

in Section 73 of the Indian Contract Act, 1872, the law being

considered in the Saint Line Limited (supra) case was based on

English common law dealing with a claim for damages.

195. Further, RCF's reliance on McDermott (supra) is also

misplaced since the Supreme Court did not consider the effect of an

exclusion clause, which excludes certain damages, which would

otherwise fall within Section 73(1). This judgment relied upon by RCF

is clearly distinguishable on facts.

RJ-CARBP 394.2023 with IAL-23263-23.doc

196. It has been held by the Supreme Court in Trojan

(supra), relied upon by Thermax, that damages due either for breach

of contract or for tort are damages which, so far as money can

compensate, will give the injured party reparation for the wrongful act

and for all the natural and direct consequences of the wrongful act.

Damages can only be the difference between the price which he paid

and the price which he would have received, if he had resold the

goods in the market forthwith after the purchase, provided of course

that there was a fair market then. In other words, the mode of dealing

with damages in such a case is to see what it would have cost him to

get out of the situation i.e. how much worse off was his estate owing

to the bargain in which he entered into.

197. The learned Arbitrator ought to have applied the

principle as laid down in Trojan (supra) that a party is entitled to

receive the normal measure of damages and which could have only

been the cost of repairs. The claim for additional expenditure on

account of power sourced from other sources cannot and would not

fall within the normal measure of damages. There has neither been

any consideration nor finding on this aspect by the learned Arbitrator.

RJ-CARBP 394.2023 with IAL-23263-23.doc

198. The attempt made by RCF to distinguish this judgment

is misconceived. The impugned Award insofar as it awards the claim

for Rs. 173.72 towards the additional expenditure allegedly incurred

by RCF, although falling within the exclusion clause is perverse and

patently illegal.

199. The Counterclaim of Thermax for refund of MAD, which

had unilaterally been deducted by RCF ostensibly under Clause 3(73)

read with Clause 31.1.3 of the GCC has been rejected by the learned

Arbitrator.

200. The findings of the learned Arbitrator overlooks the

emails and correspondence, wherein RCF itself had admitted that the

main steam line was made available only in February, 2018. As per the

baseline schedule, RCF was required to be provide the main steam line

by 31st August 2017. Thus, there was a delay of approximately 162

days on the part of RCF providing the main steam line.

201. The learned Arbitrator has failed to appreciate and

address the submissions of Thermax insofar as levy of MAD by RCF for

the alleged delay. It was Thermax's case that there was no delay on

the part of Thermax in completing the PG Test and MAD was

RJ-CARBP 394.2023 with IAL-23263-23.doc

accordingly, not leviable. These submissions and material documents

relied upon by Thermax in support thereof have not even been dealt

with by the learned Arbitrator. Given the fact that there was delay on

the part of RCF in provision of the main steam line, RCF cannot take

advantage of its own wrong and complain of delay by Thermax.

Accordingly, the finding of the learned Arbitrator that there was delay

of 444 days on the part of Thermax is perverse.

202. Thermax has accordingly, raised valid grounds of

challenge to the impugned Award under Section 34 of the Arbitration

Act. The failure on the part of the Arbitrator to give reasons for

rejecting the submissions of Thermax; the findings of the learned

Arbitrator based on no evidence; are all grounds for which the

impugned order is liable to be set aside. This is as per the settled law

laid down by this Court in Bhanumati Jaisukhbhai Bhuta (supra); the

Supreme Court in Ssangyong Engineering and Construction Company

Limited (supra) and Associate Builders (supra).

203. In view thereof, the Commercial Arbitration Petition is

allowed and the impugned Award dated 5th June 2023 is set aside.

204. RCF is directed to comply with the order of stay dated

RJ-CARBP 394.2023 with IAL-23263-23.doc

4th October 2023, in particular paragraph 7 of the said order and

refund the entire amount of Rs. 218,45,88,493/- deposited by the

Petitioner along with interest at the rate of 6% per annum within a

period of ten days from uploading of this Judgment and Order.

205. Commercial Arbitration Petition is accordingly, disposed

of. There shall be no order as to costs.

206. In view of disposal of the Commercial Arbitration

Petition, Interim Application (L) No. 23263 of 2023 does not survive

and is disposed of.

[R.I. CHAGLA, J.]

207. After this judgment and order has been pronounced, the

learned Counsel for the Respondent-RCF has sought for a stay of the

judgment and order in order for them to avail of their appellate

remedy.

208. Considering the application of Respondent-RCF, for a

period of four weeks, the undertaking given by RCF recorded in the

order of stay dated 4th October 2023 will not be given effect to.

[R.I. CHAGLA, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter