Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Surya Construction vs Steel Authority Of India Ltd
2025 Latest Caselaw 4654 Bom

Citation : 2025 Latest Caselaw 4654 Bom
Judgement Date : 9 April, 2025

Bombay High Court

Surya Construction vs Steel Authority Of India Ltd on 9 April, 2025

Author: M. S. Karnik
Bench: M. S. Karnik
   2025:BHC-OS:6329


                                                                                      15-Appeal-127-2024.doc



                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                 ORDINARY ORIGINAL CIVIL JURISDICTION

                                       APPEAL NO. 127 OF 2024
                                                 IN
                                 ARBITRATION PETITION NO. 46 OF 2017

                       M/S. Surya construction                    )
          Digitally
          signed by
          MANGALTAI
MANGALTAI JAYWANT
          JADHAV
                       (Through its POA Shri. Akhilesh J.
JAYWANT
JADHAV    Date:
          2025.04.15
          19:16:54
          +0530
                       Singh)                                     )
                       Having office at Surya House,              )
                       Plot Nos. CM- 23, 101, 102, 103,
                       194, N.H 18GIDC, Vapi- 396 195             )
                       Dist. Valsad, Gujarat                      )         ...Appellant/
                                                                            Original Claimant
                            Versus
                       Steel Authority of India Ltd.     )
                       Through its Asst. General Manager )
                       (M-WH) & Ware House Manager,      )
                       Kalamboli Warehouse,              )
                       Navi Mumbai, dist:Raigad          )                  .... Respondent

                                                ****
                       Mr. Abhijeet A. Desai a/w Ms. Mohini Rehpade a/w
                       Mr. Digvijay Kachare a/w Mr. Ajit M. Savagave, for the
                       Appellant.
                       Mr. Sarosh Bharucha a/w Mr. Anant Upadhyay a/w
                       Ms. Payal Upadhyay i/b ANP Chambers, for the
                       Respondent.

                                                           ****

                                               CORAM : ALOK ARADHE, CJ &
                                                       M. S. KARNIK, J.

                                                  DATE : 9th APRIL, 2025


                       JUDGMENT (PER M. S. KARNIK, J.) :

-

1. This appeal filed under Section 37 of Arbitration

15-Appeal-127-2024.doc

Conciliation Act, 1996 (for short "the Act") arises from

order dated 10th July, 2017 passed by the learned Single

Judge in an arbitration petition filed under Section 34 of

the 1996 Act.

2. The learned Judge by the impugned order did not

find any merit in the arbitration petition. The arbitration

petition was against the Award dated 19 th June, 2016

passed by the Arbitral Tribunal to the extent that the

Arbitral Tribunal rejected the claim of the appellant as

more particularly set out in Exhibit A-1 to the Petition. The

claims that were rejected by the Arbitral Tribunal were

under two heads. The first head was for claim of less

supply (calculated at 80% of Estimated Quantity in 33

months) for an amount of Rs.80,88,015/-. In the

alternative, a claim was made for reimbursement /

recovery of unrecovered expenses / costs in the amount

of Rs.99,04,779/-.

3. It is apposite to set out the facts in brief. The

appellant / original claimant is a proprietary firm engaged

15-Appeal-127-2024.doc

in the business of Civil Construction. The respondent,

steel authority of India Ltd., is a Government of India

undertaking engaged in the production, distribution and

marketing of steel throughout India.

4. On 12th November, 2007, the respondent published a

Notice for operating a Consignment Agency Yard at

Silvassa, Dadra and Nagar Haveli. The appellant was the

Sole Bidder, for bids by the respondent which were held in

September, 2007 and subsequently on 12th November

2007.

5. The respondent called the appellant for negotiation

to Mumbai where a meeting took place between the

representatives of both the parties. The officers of the

respondent informed the appellant that, the estimated

quantity had been mentioned in the tender document

since they were opening a yard for the first time at

Silvassa and expected fluctuation in the market. However

respondent assured the appellant that they are expecting

good business. It was on this assurance of respondent the

15-Appeal-127-2024.doc

appellant felt the need to have infrastructure sufficient to

handle the estimated quantity, considering 20%

fluctuation in the estimated quantity. The parties agreed

to the rate of Rs.550 per metric ton.

6. The respondent issued letter of intent on 30 th January

2001 with rate based on estimated quantity of 10,800

metric ton to be handover per year. Respondent issued

work order on 3rd November, 2008 and parties signed the

agreement on the same day and the appellant was

appointed as the Consignment Agent for a period of 2 and

half years.

7. The appellant made huge investment of

Rs.29,96,170/- up to 2nd May, 2008 (or 3rd November,

2008) and availed of cash credit facility from State bank

of Indore. The appellant also incurred monthly expenses

of Rs.3,00,145/- to employ staff. Due to supply of stock

being much below the quantity that had been assured

during the negotiation, the appellant repeatedly

approached the officers of the respondent regarding the

15-Appeal-127-2024.doc

same but did not receive any response.

8. According to the appellant, the supply of the

estimated quantity of 10,800 MTs/year was mandatory

precondition of establishment of the infrastructure

involving huge finance. The respondent is liable to

indemnify the appellant against any losses and bound to

reimburse costs incurred bona fide under the contract. It

is submitted that assuming 20% to be reasonable

variation in supply, the respondent ought to have routed

8,640 MTs/year and thus respondent is liable to pay a sum

quantified at Rs.80,88,015/- with interest.

9. The respondent had asked the appellant to arrange

infrastructure to handle 10,800 MTs/year while respondent

could deliver only 10,216 MTs i.e. 65% less quantity

during the entire contract period of 33 months. That the

appellant was only paid Rs.52,71,081/- as against the

expected amount (after considering 20% fluctuation) of

Rs.1,33,59,016/- for entire period of contract.

15-Appeal-127-2024.doc

10. The appellant earned a profit of 15% on the total

amount paid to the appellant during the contract period

i.e. Rs.56,40,741/-. Consequently, the respondent is liable

to compensate the appellant an amount of Rs.99,04,779/-

for the cost together with interest @ 13% p.a. till

payment.

11. It is the case of the appellant that the rate of

Rs.550/MT was agreed to be the rate for the first year and

the same was subject to escalation thereafter. That, the

respondent finally resolved the escalation rate and paid

extra amount of Rs.1,29,666/- as the balance on 31 st

January, 2012. The appellant claims interest on the

delayed payment queue the escalation rate at 13%

interest p.a.

12. Appellant took the initiative by introducing various

clients to the respondent with a view to generate supply

and recoup losses. Despite this there was no increase in

supply by the respondents. Appellant states that, the

respondent also proceeded to deal directly with the

15-Appeal-127-2024.doc

clients introduced by the appellant and those clients

introduced by the appellant consumed at least 2000 MTs

of steel during relevant period. Hence respondent acted in

a manner detrimental to interest of the appellant.

13. The appellant sent a legal notice to the respondent

on 5th April, 2011 not to extend the said contract period

due to inability of the respondent to explore the market.

However, respondent pointed out that it had the right to

extend the contract and threatened to invoke the bank

guarantee and extended the contract for further period of

3 months. However, while extending the contract, the

respondent assured it would increase the quantity of

dispatch. However, again there was no improvement in

the supply to appellant and due to which the appellant

suffered loss of Rs.5,22,284/-.

14. During the end of extended period, the respondent

claimed that an amount of Rs.4,99,385/- was due and

payable by the appellant due to shortage in clearance

during the contract period but there was no shortage that

15-Appeal-127-2024.doc

had been reported by the respondent during the contract

period. Hence, the appellant is also claiming a sum of

Rs.4,99,385/- together with the interest @ 13% p.a. from

1st September, 2011 till the date of payment.

15. Appellant further states that through an RTI they got

to know that the respondent had directly dealt with the

third party / retailer and had supplied 5133.17 MT of

steel, thereby causing a loss of profit Rs.4,23,486/- i.e. at

the rate of 550/MT.

16. The contract between the parties had been

concluded on 1st August, 2011. The appellant issued a

notice through his advocate on 12 th December, 2011

claiming the amount of Rs.1,27,35,362.42. The

respondent disputed the amount claimed by the appellant

through their advocates vide letter dated 14 th February,

2012.

17. The dispute was referred to the arbitration. The

statement of claim was duly filed. The Sole Arbitrator

15-Appeal-127-2024.doc

made impugned award dated 19 th September, 2016

rejecting the claim. The arbitration petition filed under

Section 34 of the Act is dismissed. Hence, this Appeal.

18. Mr. Desai, learned counsel for the appellant

submitted that the learned Single Judge as well as the

arbitrator had committed manifest error in assigning a

very narrow interpretation to clause 3.5 and clause 5.12

of the agreement in question as the said clauses are

nothing but negative cognates drawn at the instance of

the respondent Authority having higher bargaining

powers. According to him, the said clauses are nothing

but defeating the entire nature and scope of the contract

in question and were completely misconceived. It is

submitted that clauses 3.5 and 2.12 are completely

against Public Policy and therefore voidable. Mr. Desai

was at pains to point out that on the representation made

by the respondent assuring minimum supply, the

appellant made huge investment. The appellant had to

face losses because the respondent failed to honour the

commitment of minimum supply of 10,800 metric tons of

15-Appeal-127-2024.doc

steel per year. It is submitted that the learned Single

Judge erred in holding that the agreement nowhere says

that the respondent is under obligation to supply

minimum quantity of 10,800 MT steel. It is further

submitted that the entire infrastructure was set up by the

appellant which was used by the respondent without

fulfilling its obligations. Learned counsel submitted that it

is the appellant who had referred some customers to the

respondent and even though the infrastructure set up was

used by the respondent, the benefit was not passed to

the appellant. He further submitted that the relevant

clauses of the contract are not properly interpreted which

has caused immense prejudice to the appellant. It is

further submitted that the award made and the order

passed by the learned Single Judge is contrary to the

evidence on record.

19. Mr. Desai, relied upon the decision of the Supreme

Court in MAHANAGAR TELEPHONE NIGAM LIMITED VS.

CANARA BANK AND OTHERS1 and THE UNION OF INDIA

1 (2020) 12 SCC 767

15-Appeal-127-2024.doc

VS. M/S. D. N. REVRI AND CO. AND OTHERS 2 in support of

his submissions.

20. Learned counsel for the respondent on the other

hand argued in support of the findings of the arbitral

tribunal and the learned Single Judge.

21. Before we proceed to consider the submissions of

learned counsel, it would be profitable to refer to decision

of this Court in URBAN INFRASTRUCTURE REAL ESTATE

FUND VS. NEELKANTH REALTY PRIVATE LIMITED AND

OTHERS3 as regards the scope of Section 34 and 37 of

1996 Act. The relevant observations read thus:-

"SCOPE OF SECTION 34 OF THE 1996 ACT

15. The scope and ambit of Section 34 is well delineated by decisions of Supreme Court. In SSANGYONG ENGINEERING & CONSTRUCTION CO. LTD. VS. NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) (SUPRA), while dealing with powers of the Court deciding the application under Section 34 of the 1996 Act, the Supreme Court took note of the amendments brought about to Section 34 of the Act by Amendment Act 2015 and explained the ratio of the decision of the Supreme Court in ONGC VS.

WESTERN GECO INTERNATIONAL LTD.4, and laid down the following principles which are mentioned in para 2 (1976) SCC 147

4 (2014) 9 SCC 263

15-Appeal-127-2024.doc

34 to 41 of the judgment which are extracted for the facility of reference:

"(i) The interference by the court with an award on the ground that arbitrator has not adopted a judicial approach would tantamount to interference with merits of the award which cannot be permitted, post amendment of Section 34 of the Act.

(ii) The ground for interference insofar as it concerns 'interests of India' has been deleted, therefore, it is no longer permissible to interfere with the award on the said ground.

(iii) Similarly, the ground for interference in the award on the basis that the same is in conflict with justice and morality, has to be understood as conflict with 'most basic notions of morality or justice.

(iv) The expression 'public policy of India' is now restricted to mean that a domestic award is contrary to fundamental policy of Indian law and the ground for interference that such an award is against basic notions of justice or morality is done away with.

(v) The exercise of re-appreciation of evidence, which the appellate court can undertake is not permitted on the ground of patent illegality in the award.

(vi) Mere contravention of substantive law of India by itself is no longer a ground available to set aside an arbitral award.

(vii) The change made in Section 28(3) by the Amendment Act follows that construction of terms of a contract is primarily for an arbitrator to decide unless the arbitrator construes the contract in a manner that no fair minded or

15-Appeal-127-2024.doc

reasonable person would, in short that arbitrators' view is not even a possible view to take. If the arbitrator wanders outside the contract and deals with the matter not allotted to him he commits an error of jurisdiction and this ground of challenge is covered under Section 34(2-A) of the Act.

(viii) A decision of the arbitral tribunal, which is perverse is though no longer a ground of challenge under public policy of India', would certainly amount to a patent illegality appearing on the face of the award.

(ix) Thus a finding recorded by an arbitrator which is based on no evidence at all or an award which invokes vital evidence in arriving at its decision would be perverse and is liable to be set aside on the ground of patent illegality."

(F) SCOPE OF SECTION 37 OF THE 1996 ACT:

16. An appeal is a continuation of an original proceeding. It is equally well settled in law that in absence of any statutory provision to the contrary, the power of appellate Court is co-terminus with the power of a subordinate court. [See : JUTE CORPN. OF INDIA LTD. VS. CIT5]. Thus, an appellate Court exercising the power under Section 37 of the 1996 Act would interfere only if a ground under Section 34 of the Act is made out. [See : STATE OF CHHATISGARH AND ANOTHER VS. SAL UDYOG PRIVATE LIMITED6].

SCOPE AND AMBIT OF PHRASE 'PUBLIC POLICY OF INDIA'

17. In ONGC LTD. VS. SAW PIPES7, the Supreme Court dealt with the scope and ambit of expression 'public policy of India'. It was held that if award is contrary to 'fundamental policy of Indian law', or interest of justice or morality or patently illegal, the same would be contrary to 'public policy of India'. A three Judge Bench of Supreme Court in ONGC VS. WESTERN GECO INTERNATIONAL LTD. (SUPRA) however, noted

5 1991 Supp 2 SCC 744 6 (2020) 21 SCC OnLine 1027 7 (2003) 5 SCC 705

15-Appeal-127-2024.doc

that the expression 'fundamental policy of Indian law' was not elaborated upon in ONGC LTD. VS. SAW PIPES (SUPRA). It was held that the expression 'fundamental policy of Indian law' would include three distinct and fundamental juristic principles which must be understood as part and parcel of Indian law, which are as under:

(i) In every determination, a Court or other authority that affects rights of a citizen or leads to any civil consequences the Court or authority is bound to adopt a judicial approach. The duty to adopt such an approach arises from the very nature of power exercised by the court and authority.

(ii) The Court or a quasi-judicial authority, while determining the rights and obligation of the parties must follow principles of natural justice.

(iii) A decision which is perverse or so irrational that no reasonable person would have arrived at the same will not be sustained in a court of law.

It was further held that the expression 'fundamental policy of law' cannot be put in the straight jacket of a definition.

18. The Parliament, after the aforesaid decision of the Supreme Court, amended Section 34 of the 1996 Act by Amendment Act of 2015 w.e.f. 23 rd October 2015 and incorporated the clarification to ensure that the phrase 'fundamental policy of Indian law' is narrowly construed so as not to entail a review on merits of a dispute."

22. Keeping these principles in mind, we have examined

the impugned order of the learned Single Judge as well as

the award of the Arbitral Tribunal in light of the

submissions made by learned counsel.

15-Appeal-127-2024.doc

23. Clauses 3.5 and 5.12 of the tender document on

which much emphasis is placed by learned counsel for the

appellant reads thus:

"3.5:- To enable the tenderer to assess the quantum of work, the estimated quantities expected to be delivered during the first year of operation is indicated below:

Steel: 10,800 MT Pig Iron: NIL Note: The above quantities are only indicative for enabling the tenderer to asses the probable/expected quantum to be handled. The company doesn't guarantee any minimum quantity of handling during the entire period of contract.

5.12: No. guarantee whatsoever is given as to any definite tonnage, which would be entrusted the Consignment Agent for transportation, handling and storage at any given period of time during the entire tenure of contract."

24. The main contention which we have to deal with is

whether there is any binding obligation on the respondent

to supply 10,800 MT of steel per year as is the case of the

appellant. The bare reading of clause 3.5 makes it amply

clear that the quantity of 10,800 MT of steel is only

indicative for enabling the tenderer to asses the

probable / expected quantum to be handled. The

respondent did not guarantee any minimum quantity of

15-Appeal-127-2024.doc

handing during the entire period of contract. Moreover,

clause 5.12 clearly states that no guarantee whatsoever

is given as to any definite tonnage, which would be

entrusted to the Consignment Agent for transportation,

handling and storage at any given period of time during

the entire tenure of the contract.

25. We find that the appellant knowing fully well the

terms and conditions of the tender proceeded to set up

the infrastructure. We cannot find any term in the tender

document compelling us to form an opinion that there

was any binding obligation on the respondent to supply

minimum quantity of 10,800 MT of steel per year.

26. Having gone through the impugned order, we are

satisfied that there is no reason for us to take a view

different from the one taken by the learned Single Judge

and the Arbitral Tribunal having regard to the scope of

this Appeal under Section 37 of the Act. The argument of

learned counsel for the appellant that the appellant had a

lessor bargaining power as he was in a weaker position

15-Appeal-127-2024.doc

while entering into the contract is without merit. The

terms of the agreement clearly stipulated that the

appellant was free to store materials of any other person

over and above the supply from the respondent. There

was no embargo on the rates, which the appellant was to

quote to the third parties. The scope of the appeal under

Section 37 of the Act of 1996 challenging the decision of

the learned Single Judge is well settled. We are satisfied

with the order of the learned Single Judge and the award

of Arbitral Tribunal as the same are well considered based

on the materials on record.

27. In the decision relied upon by Mr. Desai in

MAHANAGAR TELEPHONE NIGAM LIMITED VS. CANARA

BANK AND OTHERS (SUPRA), we fail to comprehend as to

how any of the principles laid down by Their Lordships is

breached in the facts of the present case so to find favour

with the arguments advanced by learned counsel for the

appellant.

28. The next decision relied upon by Mr. Desai is in THE

UNION OF INDIA VS. M/S. D. N. REVRI AND CO. AND

15-Appeal-127-2024.doc

OTHERS (Supra). Their Lordships in paragraph No. 7

observed 'that it must be remembered that a contract is a

commercial document between the parties and it must be

interpreted in such a manner as to give efficacy to the

contract rather than to invalidate it. It would not be right

while interpreting a contract, entered into between two

lay parties, to apply strict rules of construction which are

ordinarily applicable to a conveyance and other formal

documents. The meaning of such a contract must be

gathered by adopting a common sense approach and it

must not be allowed to be thwarted by a narrow, pedantic

and legalistic interpretation.'

29. In the present case, the appellant cannot be

said to be a lay person as rightly observed by

the learned Single Judge. In fact on a reading

of the entire contract as a whole, the finding by the

learned Single Judge as well as the Arbitral Tribunal that

the same does not support the appellant's case is

correct. There is absolutely no scope for interference

with the findings of the learned Single Judge and the

15-Appeal-127-2024.doc

Arbitral Tribunal.

30. The Appeal is dismissed. No costs.

(M. S. KARNIK, J.)                   (CHIEF JUSTICE)







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter