Citation : 2024 Latest Caselaw 2674 Bom
Judgement Date : 30 January, 2024
2024:BHC-OS:1672-DB 501-OSWPL-3212-2024.DOC
Ashwini
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION (L) NO. 3212 OF 2024
Roadway Solutions India Infra Ltd & Anr ...Petitioners
Versus
Brihanmumbai Municipal Corporation ...Respondent
Mr Janak Dwarkadas, Senior Advocate, with Chirag Mody, Parag
Khandhar, Prachi Garg & Tapan Radkar, i/b DSK Legal, for the
Petitioner.
Mr Anil C Singh, Senior Advocate, with Rupali Adhate, i/b Sunil
Sonawane, for the Respondent-MCGM.
Mr Ankush Jagdale, Executive Engineer, (Road Department), is
present.
Mr Rohan Niparte, Executive Engineer, (Road Department), is
present.
CORAM G.S. Patel &
Kamal Khata, JJ.
Digitally DATED: 30th January 2024 signed by ASHWINI ASHWINI GAJAKOSH PC:-
GAJAKOSH Date:
2024.01.31 12:42:45 +0530
1. Heard. This is Round Two of the Mumbai road concreting battles. Round One ended with our order of 17th January 2024. The Petitioner had what is described as a mega tender or a mega contract to concrete several hundred roads in Mumbai. That Petition was strenuously opposed inter alia on the ground that since the time of the tender in January 2023 the Petitioner, knowing full well the
30th January 2024
501-OSWPL-3212-2024.DOC
terms of the tender and the potential difficulties, had done nothing to progress the work. Our order of 17th January 2024 centred on one limited aspect of the matter and that was a question of public law, viz., the demand of the Petitioner for a hearing. Paragraphs 8, 9 and 11 of our order read as follows:
"8. The e-tender in question was of 21st November 2022 and the letter of acceptance/work order is of 18th January 2023. This tells us that everything that has happened is in a fairly compressed time frame. The show cause notice in question (and we are fast forwarding through the list of dates) is of 9th October 2023. The reply to the show cause notice is of 16th October 2023. The notice of intent to terminate to work order is of 1st November 2023 and it is this notice that says that the Petitioners reply to the show cause notice is not necessary.
9. But in that reply the Petitioners had sought an opportunity of a personal hearing and -- this is now critical
-- on 2nd November 2023, the MCGM conceded to this request. It wrote to the Petitioners asking them to attend a meeting in the chamber of the Chief Engineer (Roads and Traffic) on 3rd November 2023 at 3:00 pm. The Petitioners sought an adjournment to 8th or 9th November saying that they were attending matters before the GST Authorities in Vapi on the hearing date. The assertion was that the Director of the Petitioners who was handling this contract was already in Vapi at that time. This request was not accepted. On 9th November 2023 came the termination notice from the MCGM to the Petitioners terminating the work order or the contract.
11. It is in these peculiar facts and circumstances that we do find that the MCGM's refusal to accommodate the Petitioners by a few days and to afford it a hearing despite first offering it to the Petitioners (irrespective of what the
30th January 2024
501-OSWPL-3212-2024.DOC
contract may or may not expressly say) is unjustified. We dare say that if we applied this standard to MCGM Advocates before us, there would be a great deal of protest."
2. It is for this reason that we required the Municipal Commissioner to nominate an officer at a sufficiently high level to hear the Petitioners. We reproduce paragraphs 12, 14, 15, 17 and 18.
"12. Consequently, we require the Municipal Commissioner to nominate an officer of sufficiently high rank to hear the Petitioners on the show cause notice, the notice of intent to terminate and the termination notice itself on merits. It is for the Commissioner or his nominated officer to decide when that hearing is to take place but, in any view of the matter, we expect it to be done before 31st January 2024. From the Petitioners we accept an undertaking that they will not seek an adjournment for any reason whatsoever.
14. As to the decision itself, we make it clear that we are not expecting, as indeed we cannot expect, a judgment properly so called. But we note that there are many defences taken by the Petitioners including that on certain matters in respect of which there is an alleged default by the Petitioners there is on the contrary compliance or demonstrable compliance. They also may have a case that if there is a default, the MCGM either extended time for performance or dispensed with strict compliance with any particular condition. The record before us indicates that the previous decision was a simple one-line finding that the Petitioners' response to the show cause notice was unsatisfactory. That will not do. The show cause notice lists individual items. The notice of termination mentions specifics. The Petitioners replied to these individual items. We expect at least some form of a proper decision
30th January 2024
501-OSWPL-3212-2024.DOC
displaying application of mind to the various matters in controversy.
15. To be perfectly clear, it is not a requirement of our order or even on law that the MCGM must find against the Petitioners on every single item in the show cause notice. It may well be that a single default by the Petitioners, if so found by the officer concerned on any one issue, might well be sufficient to justify the termination of the entire contract. That is for the officer to decide in the first instance. We are only highlighting this lest it be argued that unless the MCGM finds against the Petitioners on every count in the show cause notice it is somehow stopped from terminating the contract. That is not the position in law.
17. The present injunction in regard to the show cause notice, the notice of intention to terminate and the termination notice will continue until the three are decided by the nominated officer or 31st January 2024, whichever is later. It goes without saying that once a date and venue is fixed and the officer is nominated, the Petitioners Advocates will be given 48 hours' notice.
18. At Mr Thorat's request, we clarify that our order requiring a hearing is not based on an interpretation of the contract at all but simply because the MCGM had itself accepted the Petitioners' request for a hearing and had called the Petitioners to a hearing which ultimately never took place."
3. The Municipal Corporation of Greater Mumbai ("MCGM") accepted this order in the sense that it did not carry it higher. That order was not by consent of the MCGM. The Additional Municipal Commissioner (City), Dr Ashwini Joshi, called a hearing on 23rd January 2024. The Petitioners were given notice and there is no complaint about insufficiency of notice.
30th January 2024
501-OSWPL-3212-2024.DOC
4. Mr Dwarkadas's submission is that although the impugned order that followed on 25th January 2024 purports to record the rival submissions over six or seven pages, the reasoning is entirely perfunctory and insufficient. He says the hearing was a farce. The Petitioners were heard not more than 30 minutes.
5. The length of the hearing is not material and indeed we might ourselves be tempted to adopt that standard in hearings before this Court. Mr Dwarkadas would be well advised not to tempt fate, at least in that regard. Sufficiency of reasons is not dependent on length.
6. Our order also said clearly that we did not expect a judgment or, as we said in paragraph 15, that a finding should be returned on every single item in the Show Cause Notice.
7. Mr Dwarkadas assails the reasoning in the order from pages 118 to 120. Our intention was to afford the Petitioner an opportunity of being heard. It was most emphatically not to create another window of opportunity to assail a resultant order after a hearing on merits. Remedies in that regard lie elsewhere and we note that the contract in question has in Clause 13(e) of the General Conditions of Contract, a comprehensive arbitration provision. Mr Dwarkadas himself accepts that there is also a contractual provision for the appointment of an Emergency Arbitrator.
8. What is now being argued is on merits that a particular factual aspect namely that the MCGM had on 31st October 2023 asked the
30th January 2024
501-OSWPL-3212-2024.DOC
Petitioners to carry on work, was not considered. But that is surely an implication arising out of facts because evidence will be required as to the circumstances in which that particular direction was issued and, more importantly, what is it that the Petitioners did even thereafter. Mr Dwarkadas complains that new issues were introduced such as the matter of duct designs. He claims that the Petitioners were taken unawares. That cannot possibly have been so because the Petitioners were fully aware of their obligations throughout the term of the contract until termination. Their answer was that there were only oral discussions in regard to the demands relating to the duct designs. An important finding at page 119 is that the Petitioners accepted the tender being fully aware about the conditions prevalent in Mumbai, the conditions in the tender and therefore accepted the tender on this basis. They can hardly be heard to say that they were taken unawares by this city or by the tender itself. A specific finding also returned is that the Petitioners took no efforts to comply with the tender conditions and to complete the tasks before the monsoon. Now the Petitioners may have many answers as to why they did not or could not but that is surely a matter for dispute resolution following the arbitration process. It does not lend itself to a judicial review in Article 226 of the Constitution of India nor it can be said that the order in question is vitiated on any of the well-settled principles that would justify the invocation of our writ jurisdiction.
9. A study of the record to the extent necessary satisfied the Additional Municipal Commissioner that the contractor had neither the ability nor the interest in carrying on the works. There is a finding that this is an essential infrastructure project for the city and
30th January 2024
501-OSWPL-3212-2024.DOC
that there are Public Interest Litigations before the First Court regarding the poor condition of roads. That may not have a bearing on our decision on the merits of this matter but it certainly indicates that the MCGM and its Additional Municipal Commissioner are fully alive to the various concerns that the MCGM must take into account. The AMC was of the view that rather than coordinate with the MCGM, its officers and the police, all that the contractor chose to do was to build up a record in correspondence. The finding is emphatic: that any further continuation would not only be against the spirit of the contract but would be detrimental to the city and the MCGM. There is also a finding in regard to the lack of due diligence by the Petitioners.
10. We are not to be misunderstood as having expressed any opinion on these findings. We are simply not satisfied that the case of the Petitioners lends itself to judicial review or that our writ jurisdiction can be invoked simply because the order is by the MCGM. The Petitioners have sufficient remedies under the contract itself. They are at liberty to pursue those.
11. Paragraph 17 of our order of 17th January 2024 said that the present injunction would continue until the decision of 31st January 2024 whichever was later. This means that the injunction in any case continues until tomorrow, 31st January 2024.
12. We reject Mr Dwarkadas's submission that this injunction should be continued for a short time further to enable the Petitioner to do something. In another manner of speaking, on a contract of
30th January 2024
501-OSWPL-3212-2024.DOC
this magnitude and that has been going on for so long, enough is enough.
13. The Petition is rejected.
14. The Petition is to be finally numbered for statistical purposes by Friday, 2nd February 2024.
(Kamal Khata, J) (G. S. Patel, J)
30th January 2024
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!