Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Smc Infrastucures Private Limited vs Mahrashtra Jeevan Pradhikaran
2024 Latest Caselaw 1117 Bom

Citation : 2024 Latest Caselaw 1117 Bom
Judgement Date : 17 January, 2024

Bombay High Court

Smc Infrastucures Private Limited vs Mahrashtra Jeevan Pradhikaran on 17 January, 2024

Author: Neela Gokhale

Bench: Neela Gokhale

2024:BHC-AS:2377                                                           5-ASARP-118-2023.DOC




                                                                                                    Gitalaxmi



                         IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      CIVIL APPELLATE JURISDICTION
                                ARBITRATION PETITION NO. 118 OF 2023
                    SMC Infrastructures Private Limited                                   ...Petitioner
                         Versus
                    Maharashtra Jeevan Pradhikaran                                     ...Respondent


                    Mr. Shardul Singh, a/w Ms. Sayali Sawant & Mr. Anish
                         Shahapurkar, for the Petitioner.
                    Mr. Ajit Pitale, a/w Mr. Ameya Pitale & Mr. Siddharth Pitale, for
                         the Respondent.


                                                  CORAM        Dr. Neela Gokhale, J.
                                                  DATED:       17th January 2024
                    PC:-
                    1.      The Petitioner seeks appointment of an Arbitrator to
                    adjudicate the disputes that have arisen between the parties out of
                    the agreement dated 5th April 2013.

                    2.      The Petitioner is a company registered under the Companies
                    Act, 1956 and the Respondent is the undertaking of the Government
                    of Maharashtra established under the Maharashtra Jeevan Authority
                    Act, 1976.

                    3.      The Petitioner was a successful bidder in respect of a tender
                    floated by the Petitioner for the work of augmentation to Ambernath
                    Water       Supply       Scheme,        Taluka-Ambernath,         District-Thane,
                    construction of C.C. weir at Chikhloli Dam, designing, constructing




                                                         Page 1 of 7
                                                       th
                                                    17      January 2024


                   ::: Uploaded on - 18/01/2024                            ::: Downloaded on - 17/02/2024 01:31:28 :::
                                                      5-ASARP-118-2023.DOC




 and commissioning 7.20 ML capacity WTP at Chikhloli and other
 allied works as mentioned therein.

 4.      It is the Petitioner's case that the contract is concluded and
 the work was completed on 31st December 2018 itself. The dispute
 between the parties is in respect of certain outstanding bills as
 claimed by the Petitioner. The Petitioner has thus invoked the
 arbitration agreement. Clause 20(b) of the agreement reads thus,

                  "20. LAWS AND REGULATIONS

                          b.   Resolving the disputes :

                               In case of disputes, between a Contractor
                               decision of the Member Secretary, MJP,
                               shall be final and binding to both the
                               parties."

 5.      By notice dated 29th December 2022, the Petitioner invoked
 the arbitration agreement contained in Clause 20(b) of the contract.

 6.      The Respondent issued a reply denying all the claims of
 Petitioner and also objected to the arbitrability of the dispute.

 7.      Mr. Ajit Pitale, learned Counsel appearing for the Respondent
 states that Clause 20(b) of the agreement does not fulfill the criteria
 of an arbitration agreement since the word 'arbitration' does not
 appear in the clause. Mr. Singh, learned Counsel appearing for the
 Petitioner however contends that it is not necessary for the word
 'arbitration' to be specifically contained in the arbitration clause as
 long as the intention of the parties to refer to arbitration can be
 clearly ascertained from the clause. He has placed reliance on the
 following two decisions of the Supreme Court :



                                    Page 2 of 7
                                 th
                               17     January 2024


::: Uploaded on - 18/01/2024                         ::: Downloaded on - 17/02/2024 01:31:28 :::
                                                             5-ASARP-118-2023.DOC




                    1.      Bihar State Mineral Development Corporation
                    and Another v. Encon Builders (I) (P) Ltd.1 and

                    2.      State of Orissa and Others v. Bhagyadhar
                    Dash2.

 8.      In the matter of Bihar State Mineral Development Corporation
 (supra), there was a clause similar to the one in the present
 arbitration agreement of the matter. In this decision, the Supreme
 Court held as follows :
                 "12. The short question which arises for consideration in this
         appeal is as to whether the learned court below committed an illegality in
         refusing to refer the matter to arbitration.
                    13.     The essential elements of an arbitration agreement are as
         follows:
                    (1)    There must be a present or a future difference in
                    connection with some contemplated affair.

                    (2)     There must be the intention of the parties to settle such
                    difference by a private tribunal.

                    (3)     The parties must agree in writing to be bound by the
                    decision of such tribunal.

                    (4)     The parties must be ad idem.


                 14.     There is no dispute with regard to the proposition that for
         the purpose of construing an arbitration agreement, the term
         "arbitration" is not required to be specifically mentioned therein. The
         High Court, however, proceeded on the basis that having regard to the
         facts and circumstances of this case, the arbitration agreement could have
         been given effect to. We may, therefore, proceed on the basis that Clause
         60 of the Contract constitutes an arbitration agreement."




 1. (2003)7 Supreme Court Cases 418.
 2. (2011)7 Supreme Court Cases 406.


                                         Page 3 of 7
                                       th
                                    17      January 2024


::: Uploaded on - 18/01/2024                                ::: Downloaded on - 17/02/2024 01:31:28 :::
                                                            5-ASARP-118-2023.DOC




 9.      Even in the matter of State of Orissa (supra), the Supreme
 Court has interpreted same to be an arbitration clause and held as
 under :
         "17.    In Encon Builders (supra) this court proceeded on the assumption
         that the following clause was an arbitration agreement, as that issue was
         not disputed:
                  "60. In case of any dispute arising out of the agreement, the
                  matter shall be referred to the Managing Director, Bihar State
                  Mineral Development Corporation Limited, Ranchi, whose
                  decision shall be final and binding."
         The clause specifically provided for "disputes being referred to the
         Managing Director" and made the said authority's decision not only final,
         but also binding on the parties. Therefore it can be said that it answers the
         tests of an arbitration agreement. The issue considered therein was
         whether the High Court committed an error in refusing to refer the
         dispute to arbitration, even after finding the clause to be an arbitration
         agreement, by presuming bias in view of the fact that the named arbitrator
         was an employee of one of the parties to the dispute. This Court held that
         disputes were arbitrable in terms of the said clause. Be that as it may. A
         similar clause was also considered in Punjab State Vs. Dina Nath ((2007) 5
         SCC 28) and held to be arbitration agreement."


         Hence, Mr. Shardul Singh submits that even though the word
 'arbitration' is not contained in Clause 20(b) of the agreement, the
 parties very much intended to refer their disputes to arbitration.

 10.     Mr. Ajit Pitale draws my attention to paragraph no. 21 of the
 decision in the matter of Vishnu (Dead) by LRs. v. State of
 Maharashtra and Others3, which reads thus,
       "21.       In State of Orissa v. Damodar Das ((1996)2 SCC 216), the three
       Judge Bench interpreted Clause 21 of the contract entered into between the
       appellant and the respondent for construction of sump and pump chamber
       etc. for pipes W/S to Village Kentile. The respondent abandoned the work
       before completion of the project and accepted payment of the fourth
       running bill. Subsequently, he raised dispute and sent communication to the
       Chief Engineer, Public Health, Orissa for making a reference to an
       Arbitrator. The Subordinate Judge, Bhubaneswar allowed the application
       filed by the respondent under Section 8 of the 1940 Act and the order


 3. [2013]11 Supreme Court Reports 340.


                                       Page 4 of 7
                                     th
                                  17      January 2024


::: Uploaded on - 18/01/2024                               ::: Downloaded on - 17/02/2024 01:31:28 :::
                                                            5-ASARP-118-2023.DOC




       passed by him was upheld by the High Court. This Court referred to Clause
       25 of the agreement, relied upon the judgment in State of U.P. v. Tipper
       Chand ((1980)2 SCC 341) and held that the said clause cannot be
       interpreted as providing resolution of dispute by an Arbitrator. Paragraphs
       9 and 10 of the judgment, which contain discussion on the subject, are
       extracted below:
         "9.    The question, therefore, is whether there is any arbitration
         agreement for the resolution of the disputes. The agreement reads thus:

                  "25. Decision of Public Health Engineer to be final.-- Except
                  where otherwise specified in this contract, the decision of the
                  Public Health Engineer for the time being shall be final,
                  conclusive and binding on all parties to the contract upon all
                  questions relating to the meaning of the specifications; drawings
                  and instructions hereinbefore mentioned and as to the quality of
                  workmanship or materials used on the work, or as to any other
                  question, claim, right, matter or thing, whatsoever in any way
                  arising out of, or relating to, the contract, drawings,
                  specifications, estimates, instructions, orders or these
                  conditions, or otherwise concerning the works or the execution
                  or failure to execute the same, whether arising during the
                  progress of the work or after the completion or the sooner
                  determination thereof of the contract."


         10.      Section 2(a) of the Act defines "arbitration agreement" to mean
         "a written agreement to submit present or future differences to
         arbitration, whether an arbitrator is named therein or not". Indisputably,
         there is no recital in the above clause of the contract to refer any dispute
         or difference present or future to arbitration. The learned counsel for
         the respondent sought to contend from the marginal note, viz., "the
         decision of Public Health Engineer to be final" and any other the words
         "claim, right, matter or thing, whatsoever in any way arising out of the
         contract, drawings, specifications, estimates, instructions, orders or
         these conditions, or otherwise concerning the works or the execution or
         failure to execute the same, whether arising during the progress of the
         work or after the completion or the sooner determination thereof of the
         contract" and contended that this clause is wide enough to encompass
         within its ambit, any disputes or differences arising in the aforesaid
         execution of the contract or any question or claim or right arising under
         the contract during the progress of the work or after the completion or
         sooner determination thereof for reference to an arbitration. The High
         Court, therefore, was right in its conclusion that the aforesaid clause
         gives right to arbitration to the respondent for resolution of the
         dispute/claims raised by the respondent......."

                                                           (emphasis supplied).




                                       Page 5 of 7
                                     th
                                  17      January 2024


::: Uploaded on - 18/01/2024                               ::: Downloaded on - 17/02/2024 01:31:28 :::
                                                          5-ASARP-118-2023.DOC




 11.     I have gone through the decisions in all the matters and infact
 the decision in Vishnu (supra) supports the contention of Petitioner
 and it is of no assistance to the Respondent.

 12.     In view of the foregoing, I am of the view that Clause 20(b)
 clearly reveals the intention of the parties to refer their disputes to
 arbitration. The invocation of said agreement by the Petitioner by
 notice dated 29th December 2022 is thus valid. In the result, I pass
 the following order leaving all contentions of the parties open, to be
 agitated before the arbitrator :

                                          ORDER

a. Mr. M. G. Gaikwad, Former Judge, Bombay High Court is appointed as a Sole Arbitrator to enter reference and adjudicate the disputes between the parties out of the Agreement dated 5th April 2013. The seat of the arbitration shall be Thane as agreed by the parties in the Clause 20(b) of the agreement.

b. The learned Sole Arbitrator shall forward a statement of disclosure as per the requirement of Section 12(1) of Arbitration and Conciliation Act, 1996 to the Prothonotary and Senior Master of this Court to be placed on record of this petition with a copy forwarded to both the parties.

c. At the first instance the parties shall appear before the learned Arbitrator within a period of ten days from the

th 17 January 2024

5-ASARP-118-2023.DOC

date of uploading of this order or on such date that may be fixed by the Sole Arbitrator.

d. All contentions of the parties on merits of the disputes are expressly left open.

e. The fees payable to the Arbitral Tribunal shall be in accordance with the Bombay High Court (Fee payable to the Arbitrator) Rules, 2018 which shall be borne by the parties in equal proportion.

f. The petition is disposed of in the above terms. There will be no order as to costs.

g. Office to forward a copy of this order to the learned Sole Arbitrator on the following address :

104, Birya House, 1st Floor, 265 Perin Nariman Street, Near Apna Bazar, Fort, Mumbai-400 001. E-mail ID : [email protected] Phone : +91-9167461686.

(Dr. Neela Gokhale, J.) GITALAXMI KRISHNA KOTAWADEKAR

th 17 January 2024

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter