Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bharat Heavy Electricals Ltd. Nagpur ... vs Al-Bilal Group For General Contracts ...
2023 Latest Caselaw 11908 Bom

Citation : 2023 Latest Caselaw 11908 Bom
Judgement Date : 30 November, 2023

Bombay High Court

Bharat Heavy Electricals Ltd. Nagpur ... vs Al-Bilal Group For General Contracts ... on 30 November, 2023

Author: A.S. Chandurkar

Bench: A. S. Chandurkar

2023:BHC-NAG:16608-DB


                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
                                      NAGPUR BENCH, NAGPUR.

                                COMMERCIAL APPEAL NO. 11/2022
              Bharat Heavy Electricals Limited, Having its                 ]
              Registered Office at BHEL, PSWR, 345, Kingsway,              ]
              Nagpur - 440 001, Maharashtra, India, Through                ]
              Its Authorized Representative.                               ] APPELLANT
                               .....VERSUS.....
              Al-Bilal Group for General Contracts Ltd., A Company         ]
              Registered in Iraq having its Office at Fountain Plaza,      ]
              Gate(2), 2nd Floor, Abdel Rahim Haj Moh'd St.,               ]
              Sweifiyah, PO. Box 852085, Sweifiyah, Amman 11185,           ]
              Jordan, Through its Managing Director.                       ] RESPONDENT

              Shri Anand Jaiswal, Senior Advocate with Shri Surjendu Das, Yash
              Maheshwari, and Miss Annie Mittal, counsel for the appellant.
              Shri Vijay Sharma with Ms Swagoti Batches, Rashi Verma and Kushal Jain,
              counsel for the respondent.

              CORAM : A. S. CHANDURKAR AND MRS. VRUSHALI V. JOSHI, JJ.
              DATE ON WHICH ARGUMENTS WERE HEARD               : OCTOBER 13, 2023
              DATE ON WHICH JUDGMENT IS PRONOUNCED : NOVEMBER 30, 2023
                        [ PRONOUNCEMENT THROUGH VIDEO CONFERENCE ]


              JUDGMENT (PER : A.S. CHANDURKAR, J.)

ADMIT. Heard the learned counsel for the parties at length.

2. This appeal preferred under Section 37 of the Arbitration

and Conciliation Act, 1996 (for short, 'the Act of 1996') raises a

challenge to the judgment dated 05.05.2022 passed in Criminal

Miscellaneous Application No.501 of 2012 by which the application

preferred by the appellant herein under Section 34 of the Act of 1996

came to be partly allowed. The appellant is aggrieved by that part of

COMAP 11-22 1 Judgment the order by which its challenge to the majority award passed by the

Arbitral Tribunal has been rejected.

3. The facts relevant for considering the challenge as raised are

that the appellant is a public sector undertaking engaged in the work of

Power Generation, Transmission, Industry and Renewable Energy. On

10.03.2009 the appellant entered into a contract with the respondent, a

construction company that has been incorporated in the year 2003 and has

been registered in Iraq. As per Clause 2.2 of the General Conditions of

Contract, the contract was to be governed by the law for the time

being in force in the Republic of India. The Civil Court at Nagpur was to

have the exclusive jurisdiction in respect of all the claims under the

contract. Clause 2.14 incorporated the arbitration clause and the Rules

of arbitration framed by the International Commercial Council were to

be adhered.

4. On disputes arising between the parties the arbitration clause

came to be invoked by the respondent herein. It raised its claim under

various heads and sought payment of outstanding amounts. The appellant

raised its defence and denied the claim as made. It also raised a

counter claim against the respondent and sought monetary relief in

that regard. In terms of the arbitration clause, the Arbitral Tribunal

consisting of three Arbitrators, one Arbitrator each nominated by the

COMAP 11-22 2 Judgment parties with a third Arbitrator as Chairman conducted the said

proceedings. At the conclusion thereof, two arbitrators passed a

majority award and directed the appellant to pay the respondent a sum

of US $ 368539.40 ¢. The appellant was also required to pay costs to

the respondent of US $ 2,22,500. The minority award passed by the

third Arbitrator held the appellant entitled to US $ 22,50,5000. He

also held the respondent entitled to US $ 11,00,928. The parties were

accordingly governed by the majority award as passed on 25.06.2012.

The appellant being aggrieved the said majority award filed

application under Section 34 of the Act of 1996 raising a challenge to

the same on various counts. It sought the setting aside of the award

dated 25.06.2012 to the extent its counter claim was disallowed and

the claims of the respondent were allowed. The respondent filed its

reply to the aforesaid proceedings and supported the majority award.

After the pleadings were complete the parties placed on record written

submissions as well as written arguments for consideration. The

learned District Judge - 2, Nagpur considered the said proceedings. It

was held that the award dated 25.06.2012 could not be treated as a

foreign award. On the other challenges as raised by the appellant, the

learned Judge observed that in the proceedings under Section 34 of

the Act of 1996 it was not permissible to re-appreciate and re-evaluate

the evidence on record. He further held that the reasons assigned in

COMAP 11-22 3 Judgment the majority award were supported by sound reasons and hence it was

not permissible to interfere with the same. On that premise, the

learned Judge proceeded to hold that the challenge to the majority

award passed by the Arbitral Tribunal did not warrant interference.

The miscellaneous civil application was accordingly dismissed on

05.05.2022. Being aggrieved the appellant has challenged the

aforesaid order in the present appeal under Section 37 of the Act of

1996.

5. Shri Anand Jaiswal, learned Senior Advocate for the appellant

submitted that the learned Judge failed to take into consideration the

specific challenges raised by the appellant to the findings recorded in

the majority award and merely observed that the scope for interference

under Section 34 of the Act of 1996 was limited and refused to examine

such challenge. Inviting attention to the adverse findings recorded in the

majority award and the challenge raised to such findings in the written

notes that were placed on record, it was submitted that the same

required due consideration by the Court exercising jurisdiction under

Section 34 of the Act of 1996. If the challenge as raised was not

acceptable, reasons for the same ought to have been indicated in the

impugned judgment. He submitted that in paragraph 48 of the impugned

judgment a finding was recorded that the award dated 25.06.2012 was

not a foreign award. Thereafter the challenges on merit have only been

COMAP 11-22 4 Judgment briefly referred to in paragraphs 49 to 54 and without specifically

considering individual challenges, the majority award has been upheld.

Referring to the discussion in paragraph 52 of the impugned judgment

it was submitted that various factual incorrect observations had been

made thereunder. The majority award in paragraph 20.2.2 did not

apply its own formula in the matter of awarding liquidated damages.

Reference in paragraph 20.2.2 was only in the context of the respective

pleadings of the parties. Except for stating that what was discussed in

the impugned judgment was self-explanatory, an independent analysis

was not undertaken by the learned Judge. On the aspect of delay

caused by the respondent it was submitted that the majority award

incorrectly held that the losses suffered could be quantified at US $

4000 per day. This finding was contrary to the material placed before

the Arbitral Tribunal. He referred to various other Heads of claims that

were considered by the Arbitral Tribunal and submitted that for each

of the said Heads, the appellant had sought to demonstrate the

incorrectness in the said findings. The material evidence on the aspect

of delay on the part of the respondent had been ignored while holding

against the appellant. Similar was the contention on the aspect of

unjust enrichment and the finding recorded on the claim with regard

to the caravans. It was thus submitted that the learned Judge ought to

have specifically considered the grounds of challenge as raised in

COMAP 11-22 5 Judgment detail. However without doing so the challenge was brushed aside by

observing that the reasons contained in the award were sufficient and

that the scope for interference was limited. In support of his

submissions, the learned Senior Advocate placed reliance on the

decisions in Oil & Natural Gas Corporation Ltd. Versus Saw Pipes Ltd.

[(2003) 5 SCC 705], Rajasthan State Mines & Minerals Ltd. Versus

Eastern Engineering Enterprises & Another [(1999) 9 SCC 283],

Hindustan Zinc Ltd. Versus Friends Coal Carbonisation [(2006) 4 SCC

445], Delhi Development Authority Versus R.S. Sharma & Company,

New Delhi [(2008) 13 SCC 80], Arulvelu & Another Versus State

represented by the Public Prosecutor & Another [(2009) 10 SCC 206],

Sumitomo Heavy Industries Limited Versus Oil and Natural Gas

Corporation Limited [(2010) 11 SCC 296], Security Printing and

Minting Corporation of India Limited & Another Versus Gandhi

Industrial Corporation [(2007) 13 SCC 236], Oil and Natural Gas

Corporation Limited Versus Western Geco International Limited

[(2014) 9 SCC 263] Associate Builders Versus Delhi Development

Authority [(2015) 3 SCC 49], Ssangyong Engineering and

Construction Company Limited Versus National Highways Authority

of India (NHAI) [(2019) 15 SCC 131], Antrix Corporation Ltd. Versus

Devas Multimedia P. Ltd. [Arbitration Petition No. 20 of 2011] decided

on 10.05.2013, Antrix Corporation Ltd. Versus Devas Multimedia Private

COMAP 11-22 6 Judgment Limited [O.M.P. (Comm.) 11 of 2021] decided on 29.08.2022 at Delhi

High Court, Axios Navigation Co. Ltd. Versus Indian Oil Corporation

Ltd. [2012(3) Mh.L.J. 701], Oil and Natural Gas Corporation Ltd.

Versus Interocean Shipping (India) Pvt. Ltd. [2017(5) Bom.CR 8], Modi

Entertainment Pvt. Ltd. Versus Prasar Bharati [2017(163) DRJ 291],

General Manager, BSNL Versus Anil Kumar Tripathi [Arbitration Appeal

No.01/2012] decided on 22.04.2016, Krishna Lifestyle Technology Ltd.

Versus Cotton Corporation of India Ltd. [2021 SCC OnLine Bom 12963],

Bharat Immunologicals and Biologicals Corporation Ltd. Versus

Rameshwari Devi & Others [First Appeal No.127 of 1995] decided on

01.09.1997 at High Court of Allahabad, Central Bank of India Versus

State of Gujarat & Others [(1987) 4 SCC 407], Sihor Nagar Palika Bureau

Versus Bhabhlubhai Virabhai & Co. [(2005) 4 SCC 1] and Harbhajan Kaur

Bhatia Versus M/s Aadya Trading & Investment Pvt. Ltd. & Another

[(2017) 242 DLT 360]. It was thus submitted that the impugned order

passed under Section 34 of the Act of 1996 ought to be set aside.

6. Shri Vijay Sharma, learned counsel for the respondent

opposed the aforesaid submissions and supported the order passed

under Section 34 of the Act of 1996. According to him the

observations made by the learned Judge in paragraph 20 of the

impugned judgment were correct since the appellant had restricted

consideration of the challenge on the aspect of seat of arbitration and

COMAP 11-22 7 Judgment other points referred to therein. Despite the allegation that the

respondent was responsible for the delay, the appellant did not take

steps whatsoever to terminate the contract. According to the learned

counsel since the Arbitral Tribunal had passed a speaking award and

had assigned reasons for its conclusions it was not necessary for the

learned Judge to have dealt with the entire proceedings and passing a

detailed order. As the learned Judge accepted the findings of the

majority award it rightly did not interfere in the proceedings under

Section 34 of the Act of 1996. There were various claims raised by the

respondent which had not been granted by the Arbitral Tribunal in

which no further grievance was raised. It therefore could not be said

that the Arbitral Tribunal acted in a biased manner against the

appellant. It was rightly held that the scope for interference under

Section 34 of the Act of 1996 was limited. In absence of any perversity

or patent illegality on the face of record the majority award was rightly

not interfered with. The learned counsel referred to various findings

recorded in the majority award and submitted that the same were in

accordance with the various terms of the contract and the Arbitrators

did not travel beyond the contract. Since the majority award had been

upheld under Section 34 of the Act of 1996 there was no reason

whatsoever to interfere in a challenge to the said judgment. To

substantiate his contentions in that regard, the learned counsel

COMAP 11-22 8 Judgment referred to the decisions in Delhi Airport Metro Express Private Limited

Versus Delhi Metro Rail Corporation Limited [(2022) 1 SCC 131],

Punjab State Civil Supplies Corporation Ltd. & Another Versus

Ramesh Kumar and Company & Others [AIR 2021 SC 5758],

Maharashtra State Electricity Board Versus Sterlite Industries (India)

& Another [(2001) 8 SCC 482], Dyna Technologies Private Limited

Versus Crompton Greaves Limited [(2019) 20 SCC 1], UHL Power

Company Ltd. Versus State of Himachal Pradesh [(2022) 4 SCC 116],

Haryana Tourism Limited Versus Kandhari Beverages Limited [(2022)

3 SCC 237] and Welspun Specialty Solutions Limited (Formerly known

as Remi Metals Gujarat Limited) Versus Oil and Natural Gas

Corporation Limited [(2022) 2 SCC 382] and submitted that the

appeal was liable to be dismissed.

7. We have heard the learned counsel for the parties at length

and with their assistance we have also perused the relevant documents

that were placed on record in proceedings under section 34 of the Act

of 1996. At the outset it may be stated that insofar as the finding

recorded by the learned Judge that the award dated 25.06.2012 was

not a foreign award is concerned, that finding has been accepted by

both the parties and hence it is not necessary to go into the said aspect.

The challenge raised by the appellant to the judgment passed under

Section 34 of the Act of 1996 is based on the premise that specific

COMAP 11-22 9 Judgment challenges raised by the appellant to various Heads in the majority

award had not been considered by the learned Judge while dismissing

the proceedings. The contentions urged have not been dealt with. In

this regard we may observe that while it is true that the scope for

interference under Section 34 of the Act of 1996 is limited to

examining as to whether the contingencies stipulated in Section 34 of

the Act of 1996 have been satisfied or not, it would nevertheless be

necessary for the Court to examine the challenge as raised on such

permissible grounds. When a specific challenge is raised to the award

in the context as permissible under Section 34 of the Act of 1996, it

would be necessary for the Court to deal with such challenge. Merely

by stating that the scope for interference under Section 34 of the Act of

1996 is limited, the Court would not be justified in refusing to examine

specific challenges to the award. Though the Court while exercising

jurisdiction under Section 34 of the Act of 1996 cannot sit in appeal

over the award passed by the Arbitrator, it would have to refer to and

deal with objections raised to the award and assign some reasons for

either accepting such challenge or for turning down the same. The

order passed under Section 34 of the Act of 1996 therefore ought to

indicate consideration of the challenges raised on the touchstone of

Section 34 of the Act of 1996 and briefly indicate the reasons for either

accepting the same or negating such challenge. The impugned

COMAP 11-22 10 Judgment judgment is therefore required to be examined in the aforesaid

context.

8. Perusal of the impugned judgment dated 05.05.2022

indicates that after referring to the factual aspects and rival

contentions the judgment proceeds to hold in paragraph 48 that the

award dated 25.06.2012 is not a foreign award. The other challenges

on merit have been dealt with in the remaining six paragraphs of the said

judgment. As regards the aspect of liquidated damages is concerned the

contention has been referred to that the express terms and conditions

of awarding liquidated damages had not been followed by the majority

award and the same could not have exceeded 2.5% of the total

contract cost. The learned Judge in paragraph 52 has observed that

the majority award had applied its own formula in view of the

discussion in paragraph 20.2.2. It has then observed that the reasons

discussed in paragraph 42.4 to 42.15 in the majority award were self

explanatory and on that basis has concluded that since the said aspect

was supported by sound reasons the Court under Section 34 could not

interfere.

The appellant in its written submissions in paragraphs 12 to 18 has

raised a ground that the award passed by the majority ignores express

terms of the contract insofar as liquidated damages are concerned. It

COMAP 11-22 11 Judgment has sought to justify its entitlement to liquidated damages and has

urged that even if the respondent was responsible for the delay of only

75 days, the appellant would be entitled to maximum liquidated

damages for delay exceeding ten weeks. It has referred to the

contractual terms in that regard. It has also sought to rely upon the

dissenting opinion on the aspect of liquidated damages to contend that

the appellant was entitled to the counter claim on this basis. We find

that in paragraph 20.2.2 the majority award has not applied any

formula as observed by the learned Judge but it merely refers to the

contentions of the parties in that regard. In this context, reference can

also be made to the stand taken in paragraphs 42 to 58 of the

application filed under Section 34 of the Act of 1996 by the appellant.

We thus find that when a specific challenge was raised by the appellant

to the majority award while adjudicating the claim for liquidated

damages that it failed to take into consideration the terms of the

contract, this contention ought to have been dealt with by the learned

Judge in the backdrop of the terms of the contract. However, the

observations in paragraph 52 of the impugned judgment do not

indicate such consideration.

9. On the aspect of claims based on caravans a specific

challenge was raised by the appellant that the majority award has

recorded an adverse finding by ignoring material evidence on record.

COMAP 11-22 12 Judgment According to the appellant it was not liable to make any payment in

that regard since the breach in that regard was committed by the

respondent. The purchase price of the caravans was also not available

before the Arbitral Tribunal and the claim as awarded was therefore

without any supporting evidence. The aspect of depreciation in the

value of the caravans being used for a period of more than two years

had also not been considered. Such stand has been taken in

paragraphs 38 to 42 of the written submissions. The same has also

been countered by the respondent. Paragraphs 53 and 54 of the

impugned judgment however do not indicate any such consideration in

that regard. Same is the case on the aspect of loss of profit due to de-

scoping of works as well as the claim based on Invoice No.10 as well as

the aspect of interest. It is to be noted that in paragraph 20 of the

impugned judgment reference to these aspects having been argued on

behalf of the appellant has been made which observations even

according to the learned counsel for the respondent are correct. We

however find that the impugned judgment does not specifically deal

with these challenges except for observing that what was granted in

the majority award was based on facts and supported by reasons.

Without dealing with the specific challenges as raised it has merely

been observed that it was incumbent on the part of the appellant to

show that such findings were against or beyond the scope of the terms

COMAP 11-22 13 Judgment and conditions of the agreement. As stated above, the specific

challenges though raised have not been dealt with and the only

observation made is that the scope for interference under Section 34 of

the Act of 1996 was limited.

10. The right conferred on a party aggrieved by an award is

required to be exercised in the manner prescribed by Section 34 of the

Act of 1996. We therefore find that such challenge having been raised

by the appellant it ought to have been considered on the basis of the

material on record. Mere observation that the scope for interference

with the award would not be sufficient in the facts of the present case

since we find from the record that detailed written submissions as well

as written notes of arguments were placed on record by both the

parties. It may be stated that both the learned counsel sought to

substantiate their respective contentions in support of and against the

award by referring to the said material. We however find that such

consideration for the first time in proceedings under Section 37 of the

Act of 1996 without there being such consideration under Section 34

of the Act of 1996 would not be feasible. We are therefore inclined to

direct re-consideration of the proceedings under Section 34 of the Act

of 1996 afresh. For this reason we have not specifically referred to the

various decisions sought to be relied upon by the learned counsel for

the parties in support of such challenge. For supporting our

COMAP 11-22 14 Judgment conclusion, we may only refer to the judgment of the Delhi High Court

in Harbhajan Kaur Bhatia as well as the subsequent decision in Indian

Oil Corporation Limited (supra). The learned Judge while considering

a somewhat similar challenge has observed that dismissal of objections

raised under Section 34 of the Act of 1996 except by stating that the

award was not against public policy or that it did not violate the ratio

of the judgment in Oil and Natural Gas Company Limited (supra) was

not a satisfactory manner of disposing off Section 34 objections.

11. For aforesaid reasons, the following order is passed :-

(I) The judgment dated 05.05.2022 passed in

Commercial Miscellaneous Application No.

501 of 2012 is set aside. The proceedings are

remitted to the District Court for considering

the application filed under Section 34 of the

Act of 1996 afresh and in accordance with law.

(II) Since the said proceedings were filed in the

year 2012 the same are expedited. The

District Court shall take necessary steps to

ensure that the proceedings are decided by the

end of April-2024.

COMAP 11-22 15 Judgment (III) It is clarified that the observations in this

judgment have been made only for dealing

with the rival submissions of the parties and

the same do not indicate consideration of such

claims on merits.

(IV) All points are expressly kept open.

12. The Commercial Appeal is allowed in aforesaid terms

leaving the parties to bear their own costs.





                                      (MRS.VRUSHALI V. JOSHI, J.)          (A.S. CHANDURKAR, J.)




                            APTE




                            COMAP 11-22                        16                 Judgment



Signed by: Apte
Designation: PS To Honourable Judge
Date: 30/11/2023 18:50:45
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter