Citation : 2023 Latest Caselaw 2904 Bom
Judgement Date : 24 March, 2023
2023:BHC-AS:9099
1 of 9 17-wp-2972-22
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
CIVIL WRIT PETITION NO. 2972 OF 2022
Kondaji Hari Kale ..Petitioner
Versus
Ramkrushna Arjun Gaikar & Ors. ..Respondents
__________
Mr. Sugandh Deshmukh a/w. Irvin D'Souza for Petitioner.
Mr. Shailesh Kharat for Respondent Nos.1 to 6.
__________
CORAM : SARANG V. KOTWAL, J.
DATE : 24 MARCH 2023 PC :
1. By this petition, the Petitioner is seeking quashing of the
order dated 09/10/2021 passed in Miscellaneous Civil Appeal
No.12 of 2018 by learned District Judge, Nashik, thereby
confirming the order passed by 2nd Jt. C.J.J.D., Nashik Road,
Nashik below Exhibit-5 in Regular Civil Suit No.104 of 2017, dated
19/12/2017.
2. Heard Shri. Sugandh Deshmukh, learned counsel for the
Petitioner and Shri. Shailesh Kharat, learned counsel for the
Respondent Nos.1 to 6.
Gokhale
2 of 9 17-wp-2972-22
3. The Petitioner is the original Defendant No.1 in
R.C.S.No.104 of 2017. The Respondent Nos.1 to 6 herein are the
original Plaintiffs. For the sake of convenience the parties are
described by their status in the suit wherever necessary.
4. The Petitioner had initially approached the Tahsildar
under the Mamlatdars' Courts Act 1906 for access to his field at
Gat No.65/1+2 at Lahvit, Taluka and District Nashik. During those
proceedings, a panchanama was conducted by the Talathi on
23/04/2017. It was mentioned in the panchanama that the
Petitioner did not have any access road to approach his
agricultural field and that he was using the land Gat No.64 for that
purpose. The panchanama further mentions that, if the owners of
the Gat No.65/4 and Gat No.65/3 permit him, then he could use
the road which was in existence between Gat No.65/3 and 65/4.
The owners of the Gat No.65/4 and 65/3 are the plaintiffs in the
suit.
5. The Tahsildar vide his order dated 31/07/2017 allowed
the Petitioner's application and issued directions that the Petitioner
3 of 9 17-wp-2972-22
was entitled for removal of the obstruction on the road leading to
his land between Gat No.65/4 and 65/3. The said order was
confirmed by the S.D.O. on 20/04/2018 passed in Revision No.300
of 2017. The order of the Tahsildar was confirmed. In between,
the Plaintiffs i.e. the Respondent Nos.1 to 6 herein filed the above
mentioned suit for declaration that the Petitioner herein i.e. the
Defendant No.1 does not have any right to access his land except a
common bandh between two gat numbers mentioned earlier. The
other prayer was for perpetual injunction against using that
particular road.
6. The Plaintiffs had also filed an application for interim
relief vide Exhibit-5 in the said suit, which was allowed in their
favour vide order dated 19/12/2017 passed by the trial Court. It
was observed in that order that, if the relief was granted to the
plaintiffs, no hardship would be caused to the Defendants, as they
were already using the common access way to their property and,
therefore, the balance of convenience was in favour of the
Plaintiffs. The said order was confirmed by the learned District
Judge, Nashik in M.C.A.No.12 of 2018 vide order dated
4 of 9 17-wp-2972-22
08/10/2021. The suit was expedited.
7. Learned counsel for the Petitioner submitted that the
Petitioner did have a prima facie case at least for grant of interim
injunction because there was an order passed by the Tahsildar in
his favour; which was confirmed by the S.D.O. He had adopted
legal remedies before the competent authority and the order was
passed in his favour. Those two orders were completely ignored by
the learned Trial Judge, as well as, by the Appellate Judge. He
submitted that, though the stay is operating against him, since the
year 2017, every passing year is causing irreparable loss to him. He
submitted that, since the monsoon is approaching very fast, he
needs to cultivate his land, so that, he can have sufficient crop
during monsoon season. He, therefore, submitted that, in this
situation, he is pressing for interim protection in his favour by
setting aside both the impugned orders. He submitted that the
Tahsildar's order clearly shows that, there was no way available to
him except one through the land at Gat No.64, but that land is also
used by it's owner for taking crop in the monsoon season and,
therefore, it will not be possible for him to access his land at all.
5 of 9 17-wp-2972-22
8. Learned counsel for the original Plaintiffs submitted that
the impugned orders need not be interfered with. Stay is operating
since 2017 and, therefore, it is not necessary to vacate that stay. He
relied on the observations of the Hon'ble Supreme Court in the
case of Bachhaj Nahar Versus Nilima Mandal and another 1. He
relied on paragraph-19 of the said Judgment wherein it was
observed that, a dominant owner seeking any declaratory or
injunctive relief relating to an easementary right shall have to
plead and prove the nature of easement, manner of acquisition of
the easementary right, and the manner of disturbance or
obstruction to the easementary right. Learned counsel for the
Plaintiffs submitted that, there are no such pleadings by the
present Petitioners. Therefore, they have no case. He further
submitted that, the action brought out by the Petitioners before the
Mamlatdars' Court was barred by limitation and, therefore, that
order was not binding. He further submitted that, in any case, that
order is under challenge in the civil suit.
9. I have considered these submissions. It is made clear
1 (2008) 17 Supreme Court Cases 491
6 of 9 17-wp-2972-22
that, today I am only considering the question of interim relief. All
the questions raised by both the sides will obviously be dealt with
and decided by the civil court at the final stage of the suit. The suit
is at the stage of recording of evidence on behalf of the Plaintiffs.
All these questions, will have to be finally decided when both
parties lead their evidence and both of them are given sufficient
opportunity for the same. Today I am only considering whether the
Petitioner's claim is frivolous or whether they deserve some
protection till the decision of the suit.
10. The Trial Court while deciding the interim application
has observed in paragraph-8 that the Petitioner i.e. Defendant No.1
in the suit want to have access to his property through the
property of the Plaintiffs by using common way situated on the
property of the Plaintiffs. It was observed that the Defendants were
claiming way for certain area where there was no way seen and as
such, it required creation of way for the defendants through
Survey No.65/3. Learned counsel for the plaintiff relied on this
particular observation.
7 of 9 17-wp-2972-22
11. Learned counsel for the Petitioner, on the other hand,
referred to the observation made in paragraph-10 wherein, it was
observed that, from the factual aspect of the case it appeared that
the Defendant (present Petitioner) wanted to create way to their
property which may deprive the Plaintiff of the portion of their
property because that portion of the property which may be used
as access way could not be brought under cultivation.
12. Learned counsel for the Petitioner submitted that, this
particular observation is erroneous. At no stage the Petitioner had
claimed creation of a new way. There was no question of the
plaintiffs suffering from any loss by creation of way depriving them
of their land from cultivation.
13. In this context, it is necessary to refer to the operative
part of the Tahsildar's order, wherein, it was mentioned that the
obstructions which were placed in the way were to be removed. It
nowhere states that, a new way was to be created. To that extent,
submissions of learned counsel for the original Plaintiffs is not
acceptable. The Appellate Court has merely confirmed the
8 of 9 17-wp-2972-22
observation of the Trial Court.
14. Considering all these aspects, it does appear that the
Defendant No.1 i.e. the present Petitioner did have an order of the
Tahsildar in his favour. It is obvious that, ultimately, all the issues
will have to be decided by the Trial Court, but at this stage, order
of the Tahsildar cannot be totally ignored. Both the learned
Judges, in the Trial Court, as well as, in the Appellate Court have
not given due consideration to the order passed by the Tahsildar,
which was confirmed by the S.D.O., in arriving at their conclusion
in the interim application and the Appeal respectively. In this view
of the matter, I am of the opinion that, till the suit is decided,
operation of the Tahsildar's order can continue.
15. Hence, the following order:
ORDER
i) The order passed by the District Judge, Nashik in
M.C.A.No.12 of 2018 on 09/10/2021 confirming
the order passed by 2nd Jt. C.J.J.D., Nashik Road,
Nashik below Exhibit-5 in Regular Civil Suit
9 of 9 17-wp-2972-22
No.104 of 2017, dated 19/12/2017, is set aside.
ii) The hearing of the suit is expedited. The Trial
Court is directed to conclude and decide the suit
within two months from today. Both the parties
shall co-operate with early disposal of the suit.
iii)Till then, the order passed by the Tahsildar on
31/07/2017 in case No.7 of 2016 on his file shall
continue to operate.
iv) With these observations the petition is disposed
of.
v) The Trial Court shall not be influenced by any of
the observations made in this order while
deciding the suit.
(SARANG V. KOTWAL, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!