Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vardhaman Builders vs Narendra Balasaheb Ghatge
2023 Latest Caselaw 13015 Bom

Citation : 2023 Latest Caselaw 13015 Bom
Judgement Date : 19 December, 2023

Bombay High Court

Vardhaman Builders vs Narendra Balasaheb Ghatge on 19 December, 2023

         Digitally signed
         by LAXMIKANT
LAXMIKANT
   2023:BHC-OS:15019
         GOPAL
GOPAL    CHANDAN
CHANDAN  Date:
         2023.12.20
         10:00:28 +0530                                      1                   COMAP-92.23 .doc


                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      ORDINARY ORIGINAL CIVIL JURISDICTION
                                           IN ITS COMMERCIAL DIVISION

                                  COMMERCIAL APPEAL NO.92 OF 2023 (NOB)
                                                   IN
                              COMM. ARBITRATION PETITION (L) NO.12018 OF 2023

                        Vardhaman Builders                       : Appellant/Petitioner.
                             Vs.
                        Narendra Balasaheb Ghatge & ors.         : Respondents.

                                                         WITH
                                          INTERIM APPLICATION NO.3363 OF 2023
                                                          IN
                                            COMMERCIAL APPEAL NO.92 OF 2023

                        Vardhaman Builders                       : Applicant
                                                                 (Orig.Appellant/Petitioner)

                        In the matter between

                        Vardhaman Builders                       : Appellant/Petitioner.
                             Vs.
                        Narendra Balasaheb Ghatge & ors.         : Respondents.

                                                      -----
                        Mr. Kevic Setalvad, Senior Advocate a/w Mr. Jehan Lalkaka,
                        Ms.Rashna Khan, and Mr. Simon Mascarenhas i/by Mulla & Mulla
                        and Craigie Blunt and Caroe for the Appellant/Applicant.

                        Mr. Suneel Mogre a/w Mr. Chinmaya Acharya i/by Mr. Kevin
                        Pereira for Respondent Nos.1 and 2.

                        Mr. Mayur Khandeparkar a/w Mr.Rohan Savant, Mr.Viraj Jadhav,
                        Ms. Disha Jain, Adv. Jasvinder Choudhary and Mr. Gaurav Lele
                        i/by Mr. Ashwin Sawlani for Respondent No.3.
                                                      -----


                        LGC                                                              1 of 33




                              ::: Uploaded on - 20/12/2023         ::: Downloaded on - 21/12/2023 04:11:51 :::
                                       2                        COMAP-92.23 .doc



                    CORAM : DEVENDRA KUMAR UPADHYAYA, CJ. &
                            ARIF S. DOCTOR, J.

DATE : 19th DECEMBER, 2023

P.C. :

1 The captioned Commercial Appeal is not on board.

With the consent of the learned counsel for the parties, the

Appeal is taken on board and heard finally.

2 The Appeal impugns an order dated 11th July 2023 by

which the Commercial Arbitration Petition filed by the Appellant

under Section 9 of the Arbitration and Conciliation Act, 1996

("the Arbitration Act") came to be dismissed.

3 Before adverting to the rival contentions, it is useful

to set out the following facts which will give a context to the

challenge before us, viz.




          i.        The Appellant had initiated arbitration proceedings

                    against Respondent Nos. 1 and         2 (the Respondent



LGC                                                                    2 of 33





                                              3                           COMAP-92.23 .doc


Owners) and had sought specific performance qua a

Plot of land admeasuring about 1580.28 sq.mt. CTS

323, Borivali ("the said property") of which

Respondent No. 1 and 2 were the owners. By an

Award dated 22nd November 2011 the Arbitral Tribunal

was pleased to reject the Appellant's prayer for

specific performance as also the prayer for damages.

ii. The Arbitral Award was subsequently set aside by an

order dated 8th February 2017 passed in Arbitration

Petition No. 286 of 2012 filed by the Appellant under

Section 34 of the Arbitration Act. The Respondent

Owners filed Arbitration Appeal No. 257 of 2017

("Arbitration Appeal) under Section 37 of the

Arbitration Act impugning the order dated 8 th

February 2017. The Arbitration Appeal also came to

be dismissed by an order dated 24th November 2017.

iii. It was thus that the Appellant on 28th February 2018

filed an Application under Section 11 of the Arbitration

LGC 3 of 33

4 COMAP-92.23 .doc

Act for appointment of a new Arbitrator in view of the

dismissal of the Appeal (Commercial Arbitration

Application 78 of 2018).

iv. Thereafter by an order dated 6th April 2018, the

Hon'ble Supreme Court remanded the Appeal, (being

Arbitration Appeal No. 257 of 2017) back to this

Hon'ble Court for consideration on merits and also

expedited the hearing of the said Appeal. The

Appellant thereafter on 12th April 2018 withdrew

Arbitration Application No.78 of 2018.

v. On 25th June 2018 a Development Agreement came to

be executed between Respondent Owners on the one

hand and Respondent No.3 (Respondent Developer)

on the other in respect of the said property. It is the

Appellant's contention that the Appellant became

aware of this Development Agreement for the first

time only in April 2023 on noticing that the said

LGC 4 of 33

5 COMAP-92.23 .doc

property had been boarded up with large metal

construction sheets and the structures standing

thereon being demolished.

vi. It was thus that the Appellant on 17th April 2023, filed

Interim Application No.1686 of 2023 in the Arbitration

Appeal inter alia seeking injunctive relief against the

Respondent Owners from dealing with and/or

dispossessing the said property. It is the Appellant's

case that it was only on filing of the Affidavit in Reply

by Respondent Owners that they, for the first time,

became aware of the Development Agreement

entered into between the Respondent Owners and the

Respondent Developer.

vii. On 24th April 2023 a Division Bench of this Court

granted the Appellant leave to withdraw the Interim

Application and file a Petition under Section 9 of the

Arbitration Act before the Learned Single Judge. It

LGC 5 of 33

6 COMAP-92.23 .doc

was thus that the captioned Commercial Arbitration

Petition came to be filed by the Appellant on 27 th April

2023. The Appellant thereafter on 20 th June 2023

invoked arbitration against the Respondent Owners

and Respondent Developer. The Respondent Owners

and the Respondent Developer refused to participate

in the fresh arbitral proceedings inter alia on the

ground that the Arbitration Appeal was pending and

contended that pending determination thereof, the

Appellant was not entitled to invoke the arbitration

again.

viii. The Appellant thereafter on 5th July 2023 filed the

second Application (Commercial Arbitration

Application 165 of 2023) under Section 11 of the

Arbitration Act for Constitution of an Arbitral Tribunal.

The captioned Commercial Arbitration Petition was

heard on 11th July 2023 when the Impugned Order

dismissing the Interim relief was passed.

LGC                                                                         6 of 33





                                       7                        COMAP-92.23 .doc


Submissions of Mr. Setalvad, on behalf of the Appellant

4 At the outset, Mr. Setalvad, Learned Senior Counsel,

appearing on behalf of the Appellant submitted that by the

Impugned Order, not only had the Learned Single Judge

dismissed the Interim Application on factually and legally

untenable grounds, but had also effectively prevented the

Appellant from proceeding with the Section 11 Petition against

the Respondent Developer. He thus submitted that the Appellant

was rendered remediless.

5 Mr. Setalvad then in dealing with his first contention

i.e. that the Interim Application was dismissed on factually and

legally untenable grounds submitted that the Learned Single

Judge had gravely erred in placing reliance upon the judgement

of in the case of Dirk India Pvt. Ltd. vs. Maharashtra State

Electricity Generation Company1 to deny relief to the

Appellant on the basis that the Appellant was the unsuccessful

party in Arbitration. He pointed out that the Impugned Order

1 2013 7 Bom CR 493

LGC 7 of 33

8 COMAP-92.23 .doc

suffered from inherent contradictions as the Learned Single

Judge had on the one hand denied relief to the Appellant on the

ground that the Appellant was the unsuccessful party in

Arbitration and thus in terms of the law laid down in Dirk India

Pvt. Ltd. (supra) denied relief to the Appellant, while on the

other hand, the Learned Single Judge had specifically recorded

that the parties were at the pre arbitral stage. Basis this he

submitted that the Impugned Order was required to be set aside

and the matter to be remanded back for consideration of the

Interim Application afresh on merits.

6 Mr. Setalvad then invited our attention to paragraph

22 of the Impugned Order and pointed out that the Learned

Single Judge had factually erred by recording therein that the

Appellant had not invoked arbitration. He pointed out that it was

specifically brought to the knowledge of the Learned Single

Judge that the Appellant had invoked arbitration to which the

Respondents had even replied. He pointed out that it was in fact,

not even the case of either the Respondent Owners or the

LGC 8 of 33

9 COMAP-92.23 .doc

Respondent Developer that the Appellant had not invoked

arbitration. He submitted that the Learned Single Judge had thus

proceeded on a completely erroneous basis/assumption that the

Appellant had not invoked arbitration, and that the parties were

at the post award stage, basis which relief was denied to the

Appellant.

7 He then, highlighted the conduct of the Respondents

and pointed out that the Respondents had on the one hand

resisted arbitration on the ground that the Arbitration Appeal

was pending, while on the other hand they were rapidly

proceeding with development on the said property which would

effectively defeat the Appellant's claim. He pointed out that the

effect of denial of interim relief was that the Respondent

Developer would build upon the said property and thereby

effectively defeat the rights of the Appellant under the

Memorandum of Understandings entered into with the

Respondent Owners.

8 Mr. Setalvad then submitted that it was only in April

2023 i.e., when the Appellant first became aware of the

LGC 9 of 33

10 COMAP-92.23 .doc

Development Agreement entered into between the Respondent

Owners and the Respondent Developer that occasion to apply for

interim measures of protection first arose. He pointed out that

the Development Agreement had been entered into by the

Respondent Owners with the Respondent Developer without at

any time informing this Court of the same. Basis such conduct,

he submitted that it was imperative that the Appellant be

granted interim reliefs as prayed, failing which the Respondents

would succeed in making capital of their mala fide conduct.

9 Mr. Setalvad pointed out that the Learned Single

Judge had erred in holding that the Appellant was merely

seeking a restraint order against a third party (Respondent

Developer) under Section 9 of the Arbitration Act. He submitted

that it was well settled that under Section 9 interim measures of

protection could infact be granted against a third party i.e., non-

signatory to an arbitration agreement. In support of his

contention, he placed reliance upon the judgments of this

Hon'ble Court in the case of Girish Mulchand Mehta Vs.

LGC 10 of 33

11 COMAP-92.23 .doc

Mahesh Mehta2 and Housing Development and

Infrastructure Limited Vs. Mumbai International Airport

Pvt. Ltd.3

10 He then to buttress his contention that in the present

case the Appellant was entitled to interim measures of protection

against the Respondent Developer invited our attention to

clauses 1(d), 1(e), 3A, 6 and 18 of the Development Agreement

and pointed out therefrom that the rights of the Respondent

Developer were entirely dependent upon the outcome of the

Arbitration Appeal. It was thus he submitted that the finding of

the Learned Single Judge that the Appellant was merely seeking

a restraint order against a third party who had entered into an

Agreement with the Respondent Owners was plainly incorrect.

11 Mr. Setalvad then submitted that Court as

contemplated in Section 43(4) of the Arbitration Act must

necessarily mean the Court which finally decides the lis between

2 2010 2 Mh LJ 657 3 2013 SCC Online Bom 1513

LGC 11 of 33

12 COMAP-92.23 .doc

the Parties and not the Court passing orders under Section 34 of

the Arbitration Act. He submitted that if "the Court" under

Section 43(4) was not the Court which finally decides the matter

the same would lead to absurd consequences. He submitted that

this issue was now no longer res integra. In support of his

contention, he placed reliance upon a judgement of this Court in

the case of Siddhivinayak Realities Vs. V Hotels Limited 4

and a judgement of the Punjab and Haryana High Court in the

case of State of Uttar Pradesh Vs. Firm M/s Pearl Hosiery

Mills Ludhiana5 .

12 Mr. Setalvad then without prejudice to his aforesaid

contention, submitted that even on first principles, an Appeal is

merely a continuation of the original proceedings. He thus

submitted that it would be absurd to suggest that the exclusion

period under Section 43(4) would come to an end on the date

the competent Court passes an order under Section 34 of the

Arbitration Act and not the date on which any appeal/challenge

4 MANU/MH/1163/2021 5 ILR 1975 (2) PH 77

LGC 12 of 33

13 COMAP-92.23 .doc

from such order is finally disposed of. In support of his

contention he placed reliance upon the following judgments

Laxmi Narayan Guin Vs. Niranjan Modak6, Rafiquennessa

Vs. Lal Bahadur Chetri7, Amarjit Kaur Vs. Pritam

Singh8and Dayawati Vs. Inderjit9. Basis this, he submitted

that there was no delay on the part of the Appellant and present

arbitration proceedings were in no manner delayed, much less

beyond limitation since the Appellant became aware of the

Development Agreement only in April 2023 and the Arbitration

Appeal was still pending.

13 Mr. Setalvad then submitted that in light of the

observations made in the Impugned Order the Appellant could

not move the Section 11 Application since the observations

made by the Learned Single Judge in the Impugned Order that

the Respondent Developer cannot be brought within the purview

of the arbitration proceedings would come in the way of the

Appellant proceeding to arbitration. Placing reliance upon the 6 1985 1 SCC 270 7 1964 6 SCR 876 8 1974 2 SCC 363 9 1966 3 SCR 275

LGC 13 of 33

14 COMAP-92.23 .doc

judgement of the Hon'ble Supreme Court in the case of Arcelor

Mittal Nippon Steel India Ltd Vs. Essar Bulk Terminal

Ltd.10 he pointed out that once the Arbitral Tribunal is

constituted, the Court cannot grant interim relief under Section

9, and it is only for the Arbitrator to consider such interim relief

in an Application filed under Section 17 of the Arbitration Act. He

thus submitted that the Impugned Order had effectively

rendered the Appellant remediless since the Learned Single

Judge had on the one hand denied relief to the Appellant under

Section 9 of the Arbitration Act and on the other, held that the

Respondent Developer could not be brought within the purview

of arbitration. Thus, he submitted that the very arbitration

invoked by the Appellant had been defeated by the Impugned

Order as the same would equally bind the Arbitral Tribunal in any

application taken out under Section 17.

14 Mr. Setalvad then placed reliance upon the judgement

of the Hon'ble Supreme Court in the case of Cox and Kings Ltd

10 2022 1 SCC 712

LGC 14 of 33

15 COMAP-92.23 .doc

Vs. SAP India Pvt Ltd11 and pointed out that the same

specifically held that it was the Arbitral Tribunal that should

decide whether a non-signatory party is indeed a party to the

arbitration agreement and/or required to be joined as a party to

the arbitration. In the present case he pointed out that the

Respondent Developer was deemed to be a party to the

Agreement given the plain terms of the said Development

Agreement.

15 Mr. Setalvad, in the aforesaid backdrop of facts,

submitted that the balance of convenience was entirely in favour

of the Appellant. He submitted that commencement certificate

had been granted to the Respondent Developer on 8th December

2023 and that the Respondent Developer was taking active steps

to commence the re-development. He however pointed out that

at present, no excavation work had commenced. He therefore

submitted that if an injunction was not granted at this stage, the

Respondent Developer would proceed to construct a building and

thereafter create third party interest therein. He submitted that

11 2023 SCC Online SC 1634

LGC 15 of 33

16 COMAP-92.23 .doc

if an injunction was not granted and the Appellant ultimately

succeeded in the arbitration, the Appellant would have to take

steps to remove the flat purchasers and demolish the building.

He further submitted that the Respondent Owners and the

Respondent Developer had entered into the Development

Agreement with open eyes and made the same subject to the

pending Arbitration Appeal. He thus submitted that neither of

them could therefore claim any equity basis steps taken under

the Development Agreement. Insofar as the tenants of the

building, which was standing on the said property, he submitted

that they would also not in any manner be prejudiced by any

such order of injunction since under the Development

Agreement, the tenants were to be provided with either

alternate accommodation or paid monetary consideration in lieu

of their tenancy rights. He pointed out that the Development

Agreement did not contemplate re-housing the tenants in the

newly proposed building.

16 Basis the above, he submitted that the Appellant had

made out a strong prima facie case and balance of convenience

LGC 16 of 33

17 COMAP-92.23 .doc

was entirely in favour of the Appellant. He thus submitted that it

was just and equitable to allow the present Appeal and injunct

the Respondents from carrying out any construction work on the

property. In support of his contention, he placed reliance upon

the judgement of this Hon'ble Court in the case of Raigad CHS

Vs. Suman Eknath Gaike12.

Submissions of Mr. Khandeparkar, on behalf of Respondent-Developer.

17 Per contra, Mr. Khandeparkar, Learned Counsel

appearing on behalf of the Respondent Developer submitted that

the Appellant had clearly abandoned the arbitration. He pointed

out that the Appellant unconditionally withdrew the first

Application under Section 11 filed by it on 12 th April 2018

without seeking liberty to file a fresh. He then pointed out that

the second Application under Section 11 was filed on 5 th July,

2023 which was almost six years from the date on which the

Arbitral Award was set aside. He submitted that the Respondent

Owners had issued the termination notice dated 24 th July 2006

12 2021 SCC Online Bom 13958

LGC 17 of 33

18 COMAP-92.23 .doc

and invoked arbitration by a notice dated 2 nd September 2006

and the award was set aside on 8th February 2017. Mr.

Khandeparkar submitted that the Arbitration Application under

Section 11 (6) of the Arbitration Act ought to have been filed

within three years from the date of the Award being set aside. In

support of his contention that Article 137 of the Limitation Act,

1963 would also apply in the instant case, he placed reliance

upon the judgement of the Hon'ble Supreme Court in the case of

Bharat Sanchar Nigam Ltd. & Anr. Vs. M/s Nortel

Networks India Pvt Ltd.13. He then pointed out that once the

limitation period commences the same continues to run and

exclusion of time, if any, would only be as per Sections 12 to 24

of the Limitation Act or Section 43(4) of the Arbitration Act. In

the present case it was his contention that none of the grounds

for exclusion of time under Section 12 to 24 of the Limitation Act

were available to the Appellant.

18 Mr. Khandeparkar, then submitted that the Appellant

could not be permitted to hitch their wagon to the Arbitration

13 (2021) 5 SCC 738

LGC 18 of 33

19 COMAP-92.23 .doc

Appeal filed by the Respondent Owners since whatever the

outcome thereof, the Appellant would not be granted the relief of

specific performance in whatever the fate of those proceedings

were. It was thus, he submitted that the exclusion of time as per

Section 43(4) of the Arbitration Act could not be extended

beyond the date on which the Arbitral Award was set aside under

Section 34 unless there was a stay of such order. In this context,

he pointed out that the words used in Section 43 (4) of the

Arbitration Act were "Where the court orders that an arbitral

award be set aside" and not "where the proceedings for setting

aside the arbitral award concludes". Basis this, he submitted that

the intention of the legislature was clear and unambiguous that

the trigger point for limitation was date on which the award is

set aside. He submitted that the exclusion of time cannot be

kept in abeyance or suspension without an order of the Court.

He pointed out that the exclusion of time could only be claimed

when the Appeal filed under Section 37 of the Arbitration Act

was filed by an unsuccessful petitioner and where the award was

set aside in such Appeal for the first time. It was submitted that

LGC 19 of 33

20 COMAP-92.23 .doc

the exclusion of time contemplated under Section 43 (4) comes

into operation immediately when the award is set aside and the

same cannot be kept in abeyance absent a specific stay. He then

submitted that it was well settled that the law of limitation is a

harsh law, but equally had to be applied with all its rigour when

the statute so prescribes. He submitted that the Court has no

power to extend the period of limitation on equitable grounds

even though the statutory provision may sometimes cause

hardship or inconvenience to a particular party. He submitted

that the Court had no choice but to enforce it giving full effect to

the same. In support of his contention, he placed reliance upon

the judgment of the Hon'ble Supreme Court in the case of

F.Liansanga & Anr vs Union of India & Ors.14

19 Mr. Khandeparkar then submitted that the doctrine of

merger does not apply to Section 34 or Section 37 of the

Arbitration Act. He submitted that the proceedings under Section

34, after an Arbitral Award is passed, are not proceedings which

LGC 20 of 33

21 COMAP-92.23 .doc

are in continuation of the Arbitral Proceedings. He submitted

that unlike the Appeal, in a Petition under Section 34, the Court

can either set aside an Arbitral Award or part thereof or then

dismissed the Arbitration Petition. It cannot pass a decree or

allow a claim which has been rejected by the Arbitral Tribunal. In

support of his contention, he placed reliance upon a judgement

of the Hon'ble Supreme Court in the case of MMTC Limited Vs.

Vedanta Ltd.15. He thus submitted that considering the limited

scope of Section 34 Petition filed by the Respondent Owners, the

Appellant cannot be permitted to take advantage of the

pendency of such Appeal to assert that the filing/pendency of

the same has suspended the Appellant's right indefinitely. He

submitted that the concept of merger would also not apply in the

present case because execution proceedings under Arbitration

Act are always in the context of an Award. He submitted that the

order passed by a Court under Section 34 or Section 37 is never

executed. He submitted that it is the Award passed by the

Arbitral Tribunal which is executed under Sections 35 and 36 of

the Arbitration Act. He, therefore, submitted that the otherwise

15 (2019) 4 SCC 163

LGC 21 of 33

22 COMAP-92.23 .doc

applicable rule of merger in the context of Suits and Appeals

would not be applicable to arbitral proceedings.

20 Mr. Khandeparkar then submitted that the Appellant

had taken no effective steps to actually commence the Arbitral

Proceedings and thus had no present right to seek any injunctive

reliefs qua the said property. He pointed out that despite the fact

that the Respondent Owners had issued a notice of termination

dated 24th July 2006, the Appellant had at no point thereafter

taken any steps to stay the effect of such termination or to

restrain Respondent Owners from acting thereon. He submitted

that therefore there was absolutely no fetter on the Respondent

Owners in any manner dealing with the subject property for the

last approximately 18 years. He pointed out that the Respondent

Owners were constrained to execute the Development

Agreement with the Respondent Developer on account of the

fact that the building had outlived its life and had to be

demolished pursuant to the notice dated 21st October 2022

issued under Section 354 of the Mumbai Municipal Corporation

LGC 22 of 33

23 COMAP-92.23 .doc

Act, 1888. He pointed out that the Appellant, save and except

for deposit/payment of an amount of Rs.22,00,000/-, had taken

no steps whatsoever. He pointed out that the said amount of Rs.

22,00,000/- along with interest had been deposited with the

Prothonotary and Senior Master. He then submitted that it was

well settled that a mere Memorandum of Understanding creates

no interest in the property and further that there was no

registered document, basis which the Appellant could claim any

rights in the said property. He pointed out that the Appellant, if

at all, would always be entitled to claim compensation in terms

of money, but the Appellant was merely attempting to profiteer

from what was a purely commercial transaction in respect of

which the Appellant had failed to perform/discharge its

obligations.

21 Mr. Khandeparkar submitted that it was imperative for

the Appellant, who was seeking interim protection under Section

9 of the Arbitration Act, to satisfy the Court that the arbitral

proceedings were infact actually contemplated or manifestly

LGC 23 of 33

24 COMAP-92.23 .doc

intended, and that the Appellant was positively going to

commence the proceeding within a reasonable period of time. In

support of his contention, he placed reliance upon a judgement

of the Hon'ble Supreme Court in the case of Firm Ashok

Traders & Anr. Vs. Gurumukh Das Saluja & Ors.16. In the

present case, he reiterated that the Appellant had effectively

abandoned the proceedings having taken no steps whatsoever

since 2017 except for filing the first Arbitration Application in the

year 2018 and then subsequently withdrawing the same. He

submitted that the Appellant's conduct in the present case did

not even remotely reflect that the Appellant actually

contemplated or manifestly intended that the Appellant was

going to commence Arbitration Proceedings within a reasonable

time.

22 Mr. Khandeparkar, in dealing with the judgement of

the Hon'ble Supreme Court in the case of Cox and Kings Ltd.

(supra) relied upon by the Appellant, pointed out that the

Appellant's reliance thereon was entirely misplaced. He pointed

16 (2004) 3 SCC 155

LGC 24 of 33

25 COMAP-92.23 .doc

out that since the Respondent Developer was not a party to the

Memorandum of Understanding, the Respondent Developer could

not be regarded as a party as contemplated in Section 2(1)(h)

and Section 7 of the Arbitration Act. Equally he pointed out that

the Appellant was not a party to the Development Agreement,

which was admittedly executed only between the Respondent

Owners on the one hand and the Respondent Developer on the

other hand. It was thus, he submitted that the Appellant could

not implead the Respondent Developer in the Section 9 Petition

or seek to challenge a document executed by the Respondent

Developer in arbitration proceedings to which the Respondent

Developer had not consented to be a part of. He submitted that

the cause of action, if any, that the Appellant might have against

the Respondent Developer was entirely independent of the

arbitral proceedings between the Appellant and the Respondent

Owners. He, therefore, submitted that it was incumbent upon

the Appellant to have adopted an appropriate independent

remedy against the Respondent Developer as may be available

to the Appellant in law. He submitted that any cause of action

LGC 25 of 33

26 COMAP-92.23 .doc

that the Appellant might have against the Respondent Developer

was thus independent and distinct from the cause of action that

the Appellant had against Respondent Owners.

23 Mr. Khandeparkar then, in dealing with the judgement

of this Hon'ble Court in the case of Siddhivinayak Realties

Pvt. Ltd. (supra), submitted that the same was wholly

inapplicable to the facts of the present case, since in that case

the Plaintiff therein when withdrawing the Section 11 Petition

filed was infact granted liberty to file a Suit whereas in the

present case the Appellant had unconditionally withdrawn the

first Section 11 Application. .

24 Mr. Khandeparkar then placed reliance upon an order

passed by this Court in the case of Wadhwa Group Holdings

Pvt. Ltd. Vs. Homi Pheroze Ghandy & Anr.17 submitted that

this Court had taken the view that notwithstanding the pendency

of an Appeal under Section 37, a party can file and maintain an

Application under Section 11 for constituting the Arbitral Tribunal 17 Order dated 7th March 2022 in Commercial Arbitration Application No.414 of 2019.

LGC                                                                                         26 of 33





                                      27                       COMAP-92.23 .doc


after securing an order of setting aside an Arbitral Award. He

submitted that this was because there was no stay of the order

setting aside the order of the Arbitral Tribunal and also

considering the scheme of the Arbitration Act contemplates

expeditiousness. He submitted that the ratio in the case of

Siddhivinayak Realties Pvt. Ltd. (supra) would not be

applicable.

Submission of Mr. Mogre, on behalf of Respondent- Owners.

25 Mr. Mogre while adopting the submissions made by

Mr. Khandeparkar placed reliance on the judgment in the case of

Dirk India Pvt. Ltd. (supra) to submit that the same had been

properly construed by the Learned Single Judge. He pointed out

that if the Appellant had been granted relief in Section 9 Petition,

the same would result in interim specific performance of a

contract in the teeth of Arbitral Award which held to the

contrary. He pointed out that the interference of the Court at

this stage to grant what in essence, according to him, was a

mandatory order for interim specific performance would negate

LGC 27 of 33

28 COMAP-92.23 .doc

a sanctity and efficacy of the Arbitral process. He submitted this

because even if the Respondent Owners were to fail in the

Arbitration Appeal, the Appellant would still not be entitled to

specific performance in these proceedings. He, therefore,

submitted that what a litigating party could not possibly obtain

upon completion of the proceedings under Section 34, they could

not secure in a Petition under Section 9 as an interim measures

of protection. Basis this, he submitted that the question of

Appellant now in the present fact scenario seeking interim

measures of protection did not arise. He also then reiterated that

despite the Respondent Owners having issued a letter of

termination in the year 2006, no steps whatsoever were taken

by the Appellant to in any manner restrain the Respondent

Owners from dealing with the said property. He pointed out that

there has thus never been any fetter upon the Respondent

Owners from dealing with the said property. He, therefore,

submitted that the Respondent Owners were well and sufficiently

entitled to enter into the Development Agreement. He pointed

out that the amount paid by the Appellant had been deposited in

LGC 28 of 33

29 COMAP-92.23 .doc

this Court and would be returned to the Appellant along with

accrued interest, therefore, no prejudice whatsoever would be

caused to the Appellant. Basis this, he submitted that the

present Appeal be dismissed.

Reasons and Conclusion

26 As already noted by us above, the Appellant's

challenge in the present Appeal is twofold. Firstly, the Appellant

has contended that relief under Section 9 of the Arbitration Act

was denied to the Appellant on both factually as also legally

untenable basis and, secondly, that the Learned Single Judge

had effectively rendered the second Application under Section 11

qua Respondent Developer as infructuous. It was basis this that

both Mr. Setalvad appearing on behalf of the Appellant and Mr.

Khandeparkar appearing on behalf of the Respondent Developer,

advanced detailed arguments on the aspect of the

maintainability of the second Application under Section 11. We

must, however, note that what is before us is an Appeal from an

Order passed in a Petition filed under Section 9 of the Arbitration

Act and not either the section 11 Application or any challenge

LGC 29 of 33

30 COMAP-92.23 .doc

thereto. It is for this reason that it is not necessary for us to

enter into the realm of the controversy of the maintainability or

otherwise of the Section 11 Application which is presently

pending and shall no doubt be heard and decided on its own

merits. For this reason, we make it clear that the second

Application under Section 11 being Commercial Arbitration

Application No. 165 of 2023 shall be heard and disposed of on its

own merits uninfluenced by the observations made by the

Learned Single Judge in the Impugned Order.

27 Insofar as the Appellant's challenge to the failure to

grant interim measures of protection to the Appellant, what we

find is that the Learned Judge has essentially denied relief to the

Appellant by placing reliance upon the judgement of this Hon'ble

Court in the case of Dirk India (supra) on the basis that the

Appellant was the unsuccessful party in arbitration and was thus

not entitled to seek any relief under Section 9 of the Arbitration

Act. We find that this premise is palpably erroneous since infact

that Arbitral Award was set aside, and the Appellant had sought

LGC 30 of 33

31 COMAP-92.23 .doc

to have its claim adjudicated afresh. In these circumstances it

cannot be said that the Appellant was the unsuccessful party in

arbitration. We must also that the Learned Single Judge has

infact in the Impugned Order noted that the Parties were at a

pre arbitration stage which would mean that the judgement in

the case of Dirk India (supra) would infact not apply. Another

patent error in the Impugned Order is that the Learned Single

Judge has erred in recording that the Appellant had not invoked

arbitration and was merely seeking a restraint order against a

third-party/Developer, who had entered into an agreement with

the Respondent owners. Firstly, there is no dispute that the

Appellant had infact filed Commercial Arbitration Application No.

165 of 2023 i.e. the Second Arbitration Application in which both

the Respondent Owners and the Respondent Developer were

parties and against all of whom the appointment of an Arbitrator

was sought for and secondly, it is well settled that relief under

Section 9 can be granted against a third party. The objection as

to whether or not the Respondent Developer could be made a

party to the Arbitration proceedings was an issue to be decided

LGC 31 of 33

32 COMAP-92.23 .doc

by the Arbitral Tribunal as has been held by the Hon'ble

Supreme Court in the case of Cox and Kings (supra).

28 Given the above, we find force in the contention of

Mr. Setalvad learned senior counsel appearing on behalf of the

Appellant that by the Impugned Order, the Appellant has

effectively been rendered remediless. We must also note that

there has been not adjudication on merits by the Learned Judge

but the Appellant has been denied relief only on the aforesaid

grounds which we have found untenable. In view thereof, we

accordingly set aside the Impugned Order and remand the

matter back to the Learned Single Judge for consideration of the

same afresh. We make it clear that the observations made in

this order are only for the purposes of considering and disposing

of the present Appeal and shall not in any manner come in the

way of the Learned Single Judge when deciding Commercial

Arbitration Petition (L) No. 12018 of 2023. All the rights and

contentions of the parties are kept open.

LGC                                                                    32 of 33





                                      33                        COMAP-92.23 .doc


29                  For the reasons stated herein above, the captioned

Appeal is disposed of in aforesaid terms.

30 In view of the disposal of the Appeal, the captioned

Interim Application does not survive and the same is accordingly

disposed of.

(ARIF S. DOCTOR, J.)                                  (CHIEF JUSTICE)




LGC                                                                   33 of 33





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter