Citation : 2023 Latest Caselaw 3615 Bom
Judgement Date : 12 April, 2023
2023:BHC-OS:2913
NMS-1361-13+IA-293-22.DOC
Sayali Upasani
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
NOTICE OF MOTION NO.1361 OF 2013
WITH
INTERIM APPLICATION NO-293 OF 2022
Mr. Kantilal Khimji Haria and Ors ...Applicants
Mr. Kantilal Khimji Haria and Ors ...Plaintiffs
Vs.
Sanyam Realtors Private Limited and Ors ...Defendants
Mr. Rajiv Narula with Adv. Shwetaa H Doshile i/b Jhangiani
and Ms. Mehak Chaudhary, Narula and Associates, for
Applicants/Plaintiffs.
Mr. Dinyar D. Madon, Senior Counsel, with Mr. Aditya
Shiralkar, Mr. Vivek Shiralkar, Yashoda Desai and Vijay
Poojari i/b Shiralkar and Co., for Defendant No. 1.
CORAM:- N. J. JAMADAR, J.
RESERVED ON:- 24th NOVEMBER, 2022 PRONOUNCED ON:- 12th APRIL, 2023 JUDGMENT:-
1) The plaintiffs-applicants have preferred these Notice of
Motion and Interim Application, seeking injunctive reliefs
against the defendants.
2) The background facts can be summarized as under:-
NMS-1361-13+IA-293-22.DOC
(a) Plaintiff Nos. 1 to 8 are the members of an Association
of Persons carrying on business, inter alia, of acquiring and
developing properties under the name and style of, "Sheetal
Realtors". M/s. Sanyam Realtors Private Limited (M/s. Sanyam),
defendant No. 1 is a Private Limited Company. M/s. EDMD
Infracon Private Limited (M/s. EDMD Infracon), the defendant
No. 2, who came to be impleaded by way of amendment, is also
a Private Limited Company.
(b) The defendant No. 1 purchased a property bearing CTS
No. 128, 128/1 to 8 admeasuring 2477 sq. meters situated at
Ghatkopar (suit property), under a Deed of Conveyance dated
31st December, 2002. There were sitting tenants on the suit
property, who had cattle stables thereon, and engaged in milk
business. Defendant No. 1 could neither develop the suit
property nor sale it as there were sitting tenants.
(c) Under an agreement described as "Terms Agreed",
between the plaintiffs and defendant No. 1, the defendant No. 1
agreed to sale the suit property to the plaintiffs. The defendant
No. 1 had, however, undertaken to evict the tenants/occupants
of the suit property. To this end under the terms of the
agreement (MOU), a part of consideration i.e. Rs.3 Crores was to
NMS-1361-13+IA-293-22.DOC
be paid to the defendant No. 1 to utilize the said corpus to get
all the tenants, (a list of which was enclosed), evicted from the
suit property within two months thereof. In the event the
defendant No. 1 was required to expend more amount to evict
the tenants, the defendant No. 1 would incur the same. In the
event the tenants did not vacate the respective portions of the
suit property, the defendant No. 1 was to ensure that the work
did not suffer.
3) The MOU further provided for obtaining Commencement
Certificate of original plot area of 2477 sq. meters and incurring
costs for the same by the defendant No. 1. The plaintiffs were to
incur the expenses for purchase and sanction of T.D.R. within
three months of obtaining the Commencement Certificate.
4) Apart from the lump sum consideration of Rs.3 Crores,
the defendant No. 1 was to get 10,000 sq. feet constructed area
with 35% to 40% loading on the carpet area; 5,000 sq. feet in
the construction with One F.S.I. and 5,000 sq. feet in
construction post purchase of T.D.R. The plaintiffs claim, they
paid the entire amount of lump sum consideration, during the
period 20th December, 2005 to 7th August, 2007. According to
the plaintiffs, further Supplemental Agreement was executed
NMS-1361-13+IA-293-22.DOC
between the plaintiffs and defendant No. 1 under which a
further sum of Rs.39 Lakhs was paid to the defendant No. 1. It
is further averred in accordance with the terms of Clause 20 of
the MOU, 50% equity share capital of defendant No. 1 came to
be transferred to the plaintiffs and their nominees by defendant
No. 1.
5) The plaintiffs further averred that the defendant No. 1 did
obtain IOD, as agreed. However, the defendant No. 1 could
obtain approval for plan of 2088 sq. meters only out of the total
area of 2477 sq. meters. C.C up to stilt for phase -1 was
obtained by defendant No. 1. However, the defendant No. 1
obtained Commencement Certificate for only part plinth of
phase- 1 programme as per modified approved plan dated 28 th
February, 2007, for 326 meters only out of 2477 sq. meters.
6) The plaintiffs commenced construction of part plinth as
per the sanctioned modified approved plan dated 28 th February,
2007. Construction of part plinth was completed in the month of
November, 2007. The defendant No. 1 obtained further
Commencement Certificate of phase-2 up to the extent of 900
sq. meters only and up to 3rd floor, on 27th December, 2007. The
plaintiffs could not carry out construction beyond plinth due to
NMS-1361-13+IA-293-22.DOC
multifarious reasons including various Suits filed against the
defendant No. 1 and injunctions obtained by the plaintiffs in
those Suits.
7) While the things thus stood, on 14th January, 2011, the
defendant No. 1 obtained amended plans for the suit property.
However, as the defendant No. 1 could not get all the
tenants/occupants evicted from the suit property
Commencement Certificate for amended plans could not be
obtained. The project Architect opined that the eviction of the
tenants/occupants was indispensable for consumption of F.S.I.
of plus One and the construction work could not proceed on
account of restraint orders passed by the Court and the then
pending Revision of Development Plan. All these factors were,
according to the plaintiffs, beyond the control of the plaintiffs
and attributable to omissions and inactions on the part of
defendant No. 1 in performance of its obligations under the
Memorandum of Understanding.
8) The plaintiffs averred, instead of evicting the
tenants/occupants in discharge of its obligations under the
MOU and obtaining full sanction and Commencement
Certificate, the defendant No. 1, vide letter dated 17th January,
NMS-1361-13+IA-293-22.DOC
2012, professed to terminate the MOU between the plaintiffs and
defendant No. 1. The said termination was premised on false
and frivolous grounds. In response to the reply addressed on
behalf of the plaintiffs to the illegal termination notice, the
defendant No. 1 for the first time sought to contest the MOU on
a patently contradictory ground that there was no contract
between the parties, and the amounts parted with by the
plaintiffs were in the nature of unsecured loans.
9) In the month of June, 2012, the defendant No. 1 destroyed
the plinth constructed by the plaintiffs. Thus, the plaintiffs were
constrained to institute the Suit for Specific Performance of the
agreement contained in MOU along with the Supplemental
Agreement and for a declaration that the contract contained
therein was valid, subsisting and binding on the defendant No.
1 and that the termination thereof by letter dated 17 th January,
2012, was illegal. The instant Notice of Motion was taken out for
ad-interim and interim reliefs.
10) When the Notice of Motion was listed before the Court on
31st October, 2012, the Court did not entertain the prayer for ad-
interim reliefs, as a statement was made on behalf of the
defendant No. 1 that it had entered into another Development
NMS-1361-13+IA-293-22.DOC
Agreement dated 27th September, 2012, with defendant No. 2.
Availing the liberty, the plaintiffs amended the plaint and
defendant No. 2 came to be impleaded as a party defendant.
11) After the Notice of Motion was heard, by an order dated
20th May, 2013, the Court thought it appropriate to frame a
preliminary issue as to whether the suit was barred by law of
limitation. When the Notice of Motion came up for hearing
before the Court on 28th August, 2015, in view of the contention
of defendant No. 1 that AOP was in fact a partnership and the
suit by unregistered firm was barred, the Court was persuaded
to frame an issue whether the suit is maintainable in view of the
bar contained in the Section 69 (2) of the partnership Act,
1932 .
12) In the said order, the Court also recorded that the ad-
interim reliefs have been refused on merits. It is the plaintiffs
claim that the said observation was against the weight of the
material on record and the Court never refused ad-interim
reliefs on merits.
13) Eventually, by an order dated 30th October, 2015, the
Court held that the Suit was not barred under Section 69(2) of
the Indian Partnership Act, 1932. The defendant No. 1
NMS-1361-13+IA-293-22.DOC
challenged the said order in Commercial Appeal No. 8 of 2016.
By an order dated 7th June, 2016, in Notice of Motion No. 1192 of
2016, the Appeal Bench ordered stay of the further proceedings
in the Suit keeping open the liberty to seek modification of the
order dated 21st August, 2015 to the extent it recorded that ad-
interim reliefs have been refused on merits.
14) In Commercial Appeal No. 8 of 2016 passed on 14 th
November, 2019, the Appeal Court with the consent of the
parties disposed of the Appeal recording that the order dated
30th October, 2015, passed by the learned Single Judge be
treated as a prima facie view taken by the Court requiring
substantive issue to be settled warranting a trial.
15) Narrating all these facts and developments, the plaintiffs
have taken out Interim Application No. 293 of 2022, seeking
appointment of Court Receiver and injunctive reliefs. The
plaintiffs assert that the defendant No. 1 has registered the
development project of the suit property, with RERA under the
name of "Ashok Odyssey" and has proposed 3 wings namely, "A"
wing comprising of 11 floors, "B" Wing of 12 floors and "C" Wing
of 11 floors. The construction in "B" and "C" Wing has reached
upto the stage of 6th floor. For "A" wing only plinth has been
NMS-1361-13+IA-293-22.DOC
constructed. The defendant No. 1 and 2 taking undue advantage
of the developments in the proceedings and absence of restraint
orders have carried out the construction post haste and started
selling the flats therein, to the prejudice of the rights of the
plaintiffs.
16) Hence, the instant application to appoint a Court Receiver
in respect of the suit property, restrain the defendant No. 1 from
carrying out further construction of wings "A", "B" and "C",
restrain the defendant No. 1 from selling unsold flats in wings
"A", "B" and "C" and, in the alternative, direct the defendant No.
1 to deposit in this Court the entire sale proceeds, which have
already been received by respondent No. 1 consequent to sale of
the various flats in the wings "A", "B" and "C" and the future
sale proceeds.
17) The prayers in Notice of Motion were resisted by defendant
No.1. At the outset, the defendant No.1 contented that there was
no privity of contract between the plaintiff Nos. 2 to 8 and
defendant No.1 as no agreement was executed inter partes.
18) Consequently, the tenability of the Suit was also assailed
on the ground that an Association of Persons which the
NMS-1361-13+IA-293-22.DOC
plaintiffs claim to have formed not a being a juristic entity, was
incompetent to institute the Suit.
19) Thirdly, on merits, the defendant No. 1 contended that the
MOU dated 15th December, 2005, was neither an agreement nor
a joint venture agreement. It was void for vagueness. At best,
the purported MOU was an inchoate instrument and the rights
and obligations of the parties thereto were not crystallised. It
merely reflected intent on the part of the parties to further
negotiate and arrive at a definite and binding agreement.
20) The defendant No. 1 further contended that the eviction of
the tenants from the suit property was dependent upon the
volition of the tenants. On account of refusal of the tenants to
vacate the portions of the suit property and the injunction
orders passed against the defendant No. 1 restraining it from
evicting the tenants, it became impossible for the defendant No.
1 to perform its part of the contract.
21) It was further alleged that the plaintiffs did not make any
earnest endeavor to negotiate and deal with the tenants.
22) According to the defendant No. 1, the plaintiffs had in fact
abandoned the project. The plaintiff No. 1 had not taken any
steps to purchase and acquire T.D.R.. There was default on the
NMS-1361-13+IA-293-22.DOC
part of the plaintiff No. 1 to pay premium for the purchase of
acquiring cattle F.S.I., which was then available under
Regulation 33 (17) of the Development Control Regulations. In
any event, the defendant No. 1 terminated the purported MOU
by letter dated 17th January, 2012, and offered to refund the
money which was paid by the plaintiffs. The said amounts in
the absence of any concluded contract between the parties were
only in the nature of unsecured loans, which the defendant No.
1 offered to pay. Lastly, as the suit came to be instituted after
more than 10 months of the said termination, the plaintiffs were
not entitled to any interim reliefs.
23) In affidavit-in-reply to the Interim Application, the
defendant No. 1 contended that the Interim Application not only
suffered from gross delay and laches, but also constituted an
abuse of the process of law as an application for interim reliefs
in the form of Notice of Notion No. 1361 of 2013, was awaiting
adjudication. According to the defendant No. 1, there was no
change in circumstances which warranted filing of a fresh
application for interim reliefs. The defendant No. 1 has narrated
the sequence of events leading to the passing of the order by
Appeal Bench dated 14th November, 2019 in Commercial Appeal
NMS-1361-13+IA-293-22.DOC
No. 8 of 2016, and asserted that from the conduct of the
plaintiffs, it becomes abundantly clear that the plaintiffs had
given up the prayers for interim relief. The plaintiffs, therefore,
can not be permitted to re-agitate the prayers for interim reliefs.
24) With reference to the Development Agreement executed
with defendant No. 2, the defendant No. 1 contends that the
defendant No. 1 and 2 mutually decided to cancel the
development agreements dated 27th September, 2012 and 10th
February, 2016 by executing a registered Deed of Cancellation
dated 9th June, 2017. The defendant No. 1 post the cancellation
of development agreement, took over the entire responsibility to
discharge the obligations undertaken by defendant No. 2 and
develop the suit property on its own. The defendant No.1 has
registered the project with RERA. Substantial construction of
"B" and "C" wings was also completed and plinth of "A" wing
was completed and further work was in progress. The defendant
No. 1 has also created third party rights as it has executed a
registered Deed of Mortgage dated 30th May, 2019, whereby and
whereunder the entire suit property and unsold inventory have
been mortgaged in favour of SBI for securing loan of 8 Crores. In
view of the aforesaid developments, at this juncture, the
NMS-1361-13+IA-293-22.DOC
plaintiffs are not entitled to any injunctive reliefs. Any restraint
order, as sought by the plaintiffs, would cause irreparable loss
not only to defendant No. 1 but also to the persons who have
already purchased the flats and the prospective purchasers.
25) In the backdrop of the aforesaid pleadings, I have heard
Mr. Narula, the learned Counsel for the plaintiffs and Mr.
Madon, the learned Counsel for the defendant No. 1 at some
length. The learned Counsel took me through the material on
record especially the MOU, the correspondence exchanged
between the parties and the orders passed by the Courts.
26) To start with the MOU, which according to the plaintiffs
incorporates the contract between the parties. Evidently, there
is no controversy about the execution of the said MOU dated
12th December, 2005, though the parties are at issue as to
whether the said MOU was executed by plaintiff No. 1- Mr.
Kantilal Haria for and on behalf of the Association of Persons
and whether rests of the plaintiffs are entitled to claim any
rights thereunder.
27) The material terms of the said MOU titled, "Terms Agreed
Between" read as under:-
"1. Area of the plot is 2477 sq. mtrs. Bearing C.T.S. Nos. 128, 128/1 to 8 of Village Ghatkopar, situated at off
NMS-1361-13+IA-293-22.DOC
L.B.S. Marg, Ghatkopar (West) Taluka and Registration Sub-District: Kurla, District and Registration District: Mumbai Suburban.
2. Rs.3,00,00,000/- (Rupees Three Cores Only) lump sum consideration to be used to vacate all the tenants; list enclosed, within two months. If extra amount is required to vacate, the owners will bear and pay. If it is less the benefits will be of the owners. If any tenant does not vacate then in that case it is the responsibility of the owners and the owners will see that due to the tenants the work does not suffer. The Developers can carry the work on the balance vacant plot, however if work suffers the Developers may at their option vacate the remaining tenants at the costs and risk of the owners, such amount to be reimbursed by the owners forthwith failing which shall be a charge on owner's share of built-up area, to be recovered with interest @ 18% p.a.
3. T.D.R. will be purchased by the Developers.
4. Total construction cost with good amenities by the Developers.
5. Sanction up to C.C. of original plot area i.e. 2477 square meters the cost of that like Architect, deposits, out of pocket expenses will be of Owners.
6. The sanction of the T.D.R. the total cost of that like premium, deposits, Architect fees out of pocket expenses will be of the Developers.
7. The Developers will purchase the T.D.R. within three months of obtaining C.C.
.............
10. 10,000 square feet duly constructed will be of Owners with 35% to 40% loading on the carpet area, 5000 square feet in the construction of one F.S.I. and 5000 square feet in the T.D.R. construction. ................
12. The Developers will complete the total project in all the respect between 18 to 24 months after obtaining full C.C.
NMS-1361-13+IA-293-22.DOC
12(a). In the event completion is delayed beyond 24 months and proposed construction has not reached 50% due to finance in that case, the owners shall complete the balance work at the cost of developers, such amount to be reimbursed by the developers forthwith, failing which shall be a charge on Developer's share of built-up area, to be recovered with interest @ 18% p.a. ..............
15. C.C. will be obtained by the owner within 2 months with an extension of 1 month from the date of M.O.U.
16. Since there are no other dealings in the company the Developers may opt for proportionate share holding with full and sole right to operate Bank accounts of the company or the Developers may opt for outright purchase of property then the stamp duty if any will be borne by the Developers. Shri. Rakesh Jain shall continue as director entitled to operate bank account with other directors till consideration mentioned in Clause 2 above is fully paid. Shri. Rakesh Jain shall continue being the director only till the compliance of the Clause 10 above referred.
..............
19. On execution the subject property is and shall be in proportionate possession of the Develpers and owners.
20. Since Developer will take over existing company, there shall be proportionate issue of shares with joint management. Sole and exclusive right of management to Developers shall be on payment of amount mentioned at clause 2 above. Even the Developers/nominees shall be appointed as directors and existing directors will resign forthwith. All past liabilities of the Company shall be borne and paid by past management."
28) In the light of the aforesaid nature of the MOU and the
terms thereof, the submissions on behalf of the parties as
regards the legal character of the MOU deserve consideration.
NMS-1361-13+IA-293-22.DOC
29) Mr. Narula would urge that the MOU incorporated all the
essential terms and conditions of the contract between the
parties. Mr. Narula further submitted that not only the parties
understood the MOU as a binding contract but acted upon the
material terms of the contract in as much as the plaintiffs
constructed plinth at the suit property. Thus, the submission
on behalf of the defendant No. 1 that the contract contained in
the MOU is not capable of specific performance or for that
matter, MOU was in the nature of an expression of intent to be
formalized by executing further documents is unsustainable.
30) Mr. Madon would urge that the MOU can not be said to
incorporate concluded contract between the parties. It was
urged that the intent of the parties to have a three tranche
consideration. Payment of a sum of Rs.3 Crores and allotment
of 10,000 sq. ft. of built up area represented two tranches. The
parties did not name and agreed upon the third tranche of
consideration. Therefore, the MOU can not be said to be a
concluded contract. Inviting attention of the Court to Clause
'16', Mr. Madon would urge that the consideration at which the
plaintiffs were to purchase the suit property was not agreed
NMS-1361-13+IA-293-22.DOC
upon. Secondly, Mr. Madon would urge that there was no clarity
as to the identity of the purchasers.
31) A conjoint reading of the afore extracted Clauses of the
MOU would indicate that there was a contract between the
defendant No. 1 and plaintiff No. 1, in the least, in so far as the
development of the suit property. The material terms of the
contract including the consideration, the mutual obligations,
the period within which the contract was to be executed and the
consequences of default were all provided in the aforeextracted
Clauses.
32) Undoubtedly, in Clauses '16' and '20', the parties had
agreed that eventually the plaintiffs may take over the defendant
No. 1 company or opt for outright purchase of the suit property
as the defendant No. 1 was a single property/project company.
This option to acquire the defendant No. 1-company, however,
does not detract materially from the agreement arrived at
between the parties for development of the suit property.
33) The submission on behalf of the defendant No. 1 that
MOU was an inchoate and non binding instrument runs
counter to the professed stand of the defendant No. 1
manifested in the letter dated 17th January, 2012, which was the
NMS-1361-13+IA-293-22.DOC
trigger for the disputes. This purported letter of termination
acknowledges the execution of the MOU and the agreement
incorporated therein. It attributes acts, defaults and omissions
to the plaintiffs qua the obligations under the MOU, which the
defendant No. 1 professed to terminate.
34) Paragraph Nos. 8 and 9 of the said termination letter
dated 17th January, 2022, read as under:-
"8. In view of the aforesaid facts and circumstances and looking to out clients past relationship out clients had humbly requested you as stated herein below.
a) Either you choose to become the owner of the said property by paying us the market value of the said complete property
or
b) You may take in return the money advanced by you in the said property. This offer was made to you without prejudice to the rights and contentions of our clients.
9. In view thereof our clients hereby terminate the agreement of the terms mentioned in the documents executed on 15th December, 2005 executed between you and our clients. "
35) It is imperative to note that one of the offer made by the
defendant No. 1 to the plaintiffs was to become the owner of the
suit property by payment of the market value thereof. This offer
clearly emanated from Clause 16 of the MOU (extracted above).
Moreover, the defendant No. 1 professed to terminate the "Terms
Agreed" between the parties on 15 th December, 2005. In the face
NMS-1361-13+IA-293-22.DOC
of the said stand of the defendant No. 1, whereby defendant No.
1 professed to terminate the agreement, it would be
impermissible to urge that there was no contract as such
between the parties.
36) Mr. Narula was justified in placing reliance on a judgment
of the Supreme Court in the case of Julien Educational Trust
Vs. Sourendra Kumar Roy and Others 1, wherein it was observed
that where the prima facie case of existence of the agreement for
sale was made out, the issue has to go to trial and whether
there was a concluded contract or not between the parties was
a matter of evidence and can only be gone into during the trial
of the suit.
37) Though the learned Counsel for the parties advanced
considerable submissions on the point as to whether ad-interim
reliefs were refused on merits, I do not deem it necessary to
delve into that aspect. Since the pleadings are complete in both
Notice of Motion and Interim Application and the parties were
heard at length. I deem it appropriate decide the Notice of
Motion and Interim Application on the touchstone of well
recognized principles.
1 (2010) 1 SCC 379
NMS-1361-13+IA-293-22.DOC
38) The parameters for grant of temporary injunction are well
settled. In the case of Seema Arshad Zaheer and Others Vs.
Municipal Corporation of Greater Mumbai and Others 2, the
essential requirements to be satisfied by the plaintiff for grant of
temporary injunction were postulated by the Supreme Court as
under:-
"(i) Existence of a prima facie case as pleaded, necessitating protection of plaintiff's rights by issue of a temporary injunction;
(ii) When the need for protection of plaintiff's rights is compared with or weighed against the need for protection of defendant's right or likely infringement of defendant's right, the balance of convenience tilting in favour of plaintiff; and
(iii) Clear possibility of irreparable injury being caused to plaintiff if the temporary injunction is not granted. In addition, temporary injunction being an equitable relief, the discretion to grant such relief will be exercised only when the plaintiff's conduct is free from blame and he approached the court with clean hands."
39) Once a prima facie finding is reached that there is a
contract, the next question that comes to the fore is whether the
contract is enforceable. Essential nature of the contract
contained in the MOU assumes significance. If the contract is
construed as a contract to build simplicitor, such a contract is
not enforceable. On the contrary, if the contract envisages
2 (2006) 5 SCC 282
NMS-1361-13+IA-293-22.DOC
creation of interest in the property to be developed, the Court
would be justified in passing a decree for Specific Performance,
if certain conditions are fulfilled.
40) A profitable reference, in this context, can be made to a
judgment of the Supreme Court in the case of Sushil Kumar
Agarwal Vs. Meenakshi Sadhu and Others 3 , wherein the
Supreme Court considered the question as to whether the
Section 14(3) (c) of the Specific Relief Act, 1963, constitutes a
bar to a suit by a developer for specific performance of a
development agreement between the developer and the owner of
the property. After adverting to the provisions contained in
Section 14 of the Act, 1963 and the judgments which bear upon
the enforceability of a development agreement, the Supreme
Court expounded the various facets of development agreement,
the conditions in which the development agreement may become
enforceable and the principles which govern the exercise of
discretion in granting the specific performance of development
agreement as under:
18. When a pure construction contact is entered into, the contractor has no interest in either the land or the construction which is carried out. But in various other categories of development agreements, the developer may have
3 (2019) 2 SCC 241
NMS-1361-13+IA-293-22.DOC
acquired a valuable right either in the property or in the constructed area. The terms of the agreement are crucial in determining whether any interest has been created in the land or in respect of rights in the land in favour of the developer and if so, the nature and extent of the rights.
.............
24. Various High Courts have interpreted the requirements under Section 14(3)(c) of the Act and opined on the maintainability of a suit by the developer for specific performance against the owner of the property for a breach in the conditions of the development agreement. A common thread that runs through the analysis in decided cases is the following:
24.1. The courts do not normally order specific performance of a contract to build or repair. But this rule is subject to important exceptions, and a decree for specific performance of a contract to build will be made only upon meeting the requirements under law;
24.2. The discretion to grant specific performance is not arbitrary or capricious but judicious; it is to be exercised on settled principles; the conduct of the plaintiff, such as delay, acquiescence, breach or some other circumstances outside the contract, may render it inequitable to enforce it;
24.3. In order to determine the exact nature of the agreement signed between the parties, the intent of the parties has to be construed by reading the agreement as a whole in order to determine whether it is an agreement simpliciter for construction or an agreement that also creates an interest for the builder in the property. Where under a development agreement, the developer has an interest in land, it would be difficult to hold that such an agreement is not capable of being specifically enforced; and
24.4. A decree for specific performance of a contract to build will be made if the following conditions are fulfilled:
24.4.1. the work of construction should be described in the contract in a sufficiently precise manner in order for the court to determine the exact nature of the building or work;
NMS-1361-13+IA-293-22.DOC
24.4.2. the plaintiff must have a substantial interest in the performance of the contract and the interest should be of such a nature that compensation in money for non- performance of the contract is not an adequate relief; and
24.4.3. the defendant should have, by virtue of the agreement, obtained possession of the whole or any part of the land on which the building is to be constructed or other work is to be executed.......... "
(emphasis supplied)
41) In light of the aforesaid enunciation of law, the primary
question that crops up for consideration is whether, in the facts
of the case, the developer has acquired valuable rights either in
the property or in the constructed area. Upon a conjoint reading
of the aforextracted clauses of the MOU, at this stage, prima
facie an inference becomes sustainable that the MOU in
question is not merely an agreement for constructing a building
for monetary consideration. The MOU inter alia provided for
capital investment by the plaintiffs not only for erecting the
building but also for getting the land vacated of the tenants and
for acquiring developments right by purchase of TDR. The MOU
provided for consideration to the owner in the nature of 10,000
sq.fts constructed area out of the developed property, implying
thereby that rest of the developed property was to fall to the
share of the developer.
NMS-1361-13+IA-293-22.DOC
42) Clause '19' expressly provided that on execution of the
MOU the suit property would be in proportionate possession of
the plaintiffs and defendant No. 1. In addition, the MOU made a
provision for acquisition of the entire suit property by the
plaintiffs. All these clauses, if cumulatively construed, lead to
an inference that plaintiffs were given additional rights than
mere building work. MOU thus prima facie appears to be
capable of specific performance.
43) This leads me to the pivotal question of existence of a
prima facie case to seek the specific performance of contract
and assail the termination of the contract by defendant No. 1
as bad and illegal. The MOU was executed on 15 th December,
2005. It came to be terminated vide letter dated 17 th January,
2012. The learned Counsel for the plaintiffs and the defendant
No. 1 made an endeavor to draw home the point that it was the
other party to the contract who committed defaults in the
performance of its obligations under the MOU.
44) Mr. Narula would urge that contrary to the terms of the
MOU, the defendant No. 1 could not get the entire suit property
vacated of the tenants. Secondly, the defendant No. 1 did not
obtain C.C. for total area of 2477 sq.mtrs. Commencement
NMS-1361-13+IA-293-22.DOC
Certificate could be obtained only for part plinth of phase-1.
Thirdly, restraint orders were passed by the Courts in the suit
instituted by the tenants. In view of these principal defaults on
the part of the defendant No. 1, Mr. Narula would urge, the
plaintiffs were not required to perform their reciprocal
obligations and thus the termination of the agreement by
attributing defaults to the plaintiffs was legally untenable.
45) Per contra, Mr. Madon would urge that the plaintiffs were
guilty of the breach of the contract in as much as the plaintiffs
made no efforts to purchase the T.D.R. despite grant of the
Commencement Certificate. Secondly, the plaintiffs were under
an obligation to pay cattle premium to get additional F.S.I.
Plaintiffs did not pay the cattle premium, though the additional
F.S.I. was approved by the Municipal Corporation. Mr. Madon
would urge that, in fact, inaction on the part of the plaintiffs
bordered on abandonment of the project. The defendant No. 1
was thus justified in terminating the contract.
46) Mr. Narula countered by submitting that obligation to
purchase T.D.R. would have arisen only upon the defendant No.
1 obtaining full C.C. Mr. Narula would urge Clause 5 and 15 of
the MOU (extracted above) are required to be read in
NMS-1361-13+IA-293-22.DOC
juxtaposition and thus read would indicate that plaintiffs
obligation to purchase the T.D.R. never arose.
47) To bolster up the submissions that sequence in which the
obligations are to be performed deserves to be taken into
account, Mr. Narula placed reliance on the judgment of the
Supreme Court in the case of Nathulal Vs. Phoolchand4. In the
said case, the Supreme Court enunciated that in considering
whether a person is willing to perform his part of the contract,
the sequence in which the obligations under a contract are to be
performed must be taken into account. By virtue of Section 4 of
the Transfer of Property Act, 1882, the Chapters and Sections of
the Transfer of Property Act, 1882 which relate to contracts are
to be taken as part of the Indian contract Act, 1872. If,
therefore, under the terms of the contract the obligations of the
parties are to be performed in a certain sequence, one of the
parties to the contract can not require compliance with the
obligations by the other party without in the first instance
performing his own part of the contract which in the sequence
of obligations is performable by him earlier.
48) It is trite the instrument is required to be read as whole.
Whilst there was an obligation on the defendant No. 1 to obtain 4 (1969) 3 SCC 120.
NMS-1361-13+IA-293-22.DOC
the Commencement Certificate within the stipulated period, the
plaintiffs were under an obligation to purchase T.D.R.
Indisputably part C.C. was obtained and the plaintiffs did erect
plinth in a portion of the suit property.
49) This situation is required to be appreciated in the light of
the fact that performance of the mutual obligations was further
contingent upon the suit property being vacated of all the
tenants. Indisputably, few of the tenants approached the Court
and obtained restraint orders. The extent of the property
covered by the restraint orders was sought to be debated.
However, the fact remained that few of the tenants could not be
evicted and continued to stay over the suit property.
50) When the performance of the reciprocal promises depends
upon an event, over which the parties had no control, especially
in a situation where the contingency is of eviction of the
tenants, who have statutory protection, the very enforceability of
the contract enters the arena of uncertainty. In such a situation
failure to perform such contingent obligation can not be readily
inferred. Thus, the failure of the defendant No. 1 to get all the
tenants evicted, in the face of the restraint orders passed by the
NMS-1361-13+IA-293-22.DOC
Courts, saves it of the element of deliberate non performance.
51) From this standpoint, the stand of the plaintiffs that the
plaintiffs were not obligated to purchase the TDR or pay cattle
premium to acquire additional F.S.I prima facie does not seem to
be in furtherence of the intent of the parties under the MOU.
The parties had not agreed that development was to commence
only after entire plot was got vacated of the tenants. Clause 2
clearly provided that the Developer can carry the work on
balance vacant land. The Developer had the option to vacate the
tenants who stayed over at the costs and risk of the owners.
Prima facie, there is no material to show that the plaintiffs
initiated measures to either evict the remaining tenants or erect
further construction beyond part plinth.
52) Non payment of the cattle premium can not be explained
away by contending that liability to pay did not arise. Additional
FSI came to be sanctioned by MCGM on 16th August, 2007,
much before the controversy arose. The grant of additional FSI
in lieu of shifting/removal of existing cattle sheds was subject to
payment of requisite premium. Non payment of premium
entailed the consequence of lapse of benefit. Likewise, the
NMS-1361-13+IA-293-22.DOC
purchase of TDR, as such, was not contingent upon grant of full
C.C. Purchase of TDR would have been a factor underscoring
the willingness of plaintiffs. Moreover, the things did not move
for almost Six years.
53) The situation which thus emerges is that the termination
of the agreement by the defendant No. 1 can not be said to be
prima facie, wholly unsustainable. That impinges upon the case
sought to be put-forth by the plaintiffs for grant of temporary
injunction.
54) The aforesaid aspects are required to be appreciated in the
light of the time lag and subsequent developments. They bear
upon the prima facie case, which the plaintiffs had at the
commencement of the dispute, to dilute its strength. They also
influence the determination of balance of convenience and
irreparable loss.
55) In the intervening period, there have been significant
developments. Indisputably, the plinth which the plaintiffs had
constructed was demolished. The defendant No.1 entered into
the development agreement with defendant No. 2. The defendant
No. 1 contends the said agreement with defendant No. 2 also
came to be terminated under a Deed of Cancellation dated 7 th
NMS-1361-13+IA-293-22.DOC
July, 2017. The defendant No. 1, post cancellation of
development agreement, took over the entire responsibility to
develop the project. Out of three Wings, construction of "B" and
"C" Wings was almost complete and the plinth of "A" wing was
also erected. Defendant No. 1 claims to have created security
interest in the suit property by executing a registered Deed of
Mortgage dated 13th May, 2019, in favour of SBI for securing a
loan of Rs.8 Crores. Third party rights in the nature of allotment
of the flats to the purchasers have been created.
56) Banking heavily upon the aforesaid developments, Mr.
Madon would urge that at this stage the balance of convenience
heavily tilts in favour of defendant No. 1. In the event any order,
either of appointing a receiver or restraint of whatsoever nature,
is passed, the defendant No. 1 and the third parties would
suffer irreparable loss. On the contrary the interest of the
plaintiffs has been adequately protected by order dated 27 th
April, 2022 by which the defendant No. 1 had been directed to
deposit a sum of Rs.3.39,00,000/-, which was parted with by
the plaintiffs.
57) Mr. Madon placed strong reliance on a judgment of this
Court in the case of Ambalal Maganlal Patel and Another Vs.
NMS-1361-13+IA-293-22.DOC
Indumati Narayan Mohile and Others 5, wherein a learned Single
Judge of this Court in the facts of the said case observed as
under:-
".... Interim reliefs such as those claimed in the present motion by the plaintiffs are basically in the discretion of the Court. Though discretion is expected to be exercised fairly and reasonably, this, in my judgment, is not a case for exercising the same in favour of the plaintiffs. Even assuming that the plaintiffs had initially, when the suit was filed, made out a case for interim relief, the same stood virtually destroyed by their utter silence all these long years. Third party rights have intervened. The old building has been demolished. A new construction has come up to third floor level....."
58) Mr. Narula, stoutly submitted that the mere fact that
during the pendency of the suit, the defendant No. 1 has erected
the structures would not dis-entitle the plaintiffs from enforcing
their rights. Mr. Narula would urge that it is not the case that
the plaintiffs had not been diligently prosecuting their remedies.
On the contrary, the material on record would show that the
defendant No. 1 resorted to litigative stratagem to delay and
defeat the legitimate rights of the plaintiffs. The defendant No. 1
took all sorts of technical objections and carried the matter in
Appeal to obviate an effective hearing on Notice of Motion and in
the intervening period carried out the development. Defendant
5 AIR 1990 Bombay 187
NMS-1361-13+IA-293-22.DOC
No. 1, therefore, can not be permitted to take advantage of its
own unscrupulous conduct, urged Mr. Narula.
59) To buttress the aforesaid submissions, Mr. Narula placed
strong reliance on the judgments of the Supreme Court in the
cases of Gangubai Bablya Chaudhary and Others Vs. Sitaram
Bhalchandra Sukhtankar and Others6, Bina Murlidhar Hemdev
and Others Vs. Kanhaiyalal Lokram Hemdev and Others 7, a
judgment of Karnataka High Court in the case of Anthony
Reddy and Others Vs. The State of Karnataka and Others 8 and
a judgment of Calcutta High Court in the case of Rayees Alam
Vs. Ganges Garden Realtors Pvt. Ltd. and Others9.
60) In the case of Gangubai Bablya Chaudhary (supra), the
Supreme Court, in the facts of the said case, held that if the
defendants were allowed to put up construction by the use of
the F.S.I. for whole of the land including the land involved in
dispute, the situation may become irreversible by the time the
dispute is decided and would preclude fair and just decision of
the matter.
6 (1983) 4 SCC 31 7 (1999) (5) SCC 222 8 MANU/KA/7740/2019 9 2021 (3) ICC 105
NMS-1361-13+IA-293-22.DOC
61) In the case of Bina Murlidhar Hemdev (Supra), the
Supreme Court enunciated that it is true that normally a
plaintiff who stands by when another is making construction on
his property could not seek injunction to stop construction.
However, in the facts of the said case, the Supreme Court held
that it was not inclined to deny temporary injunction to the
plaintiffs notwithstanding the investments made by the builder.
The builder had never shown any anxiety before the Court to
come to terms and avoid an injunction by offering certain terms
to plaintiffs.
62) In Anthony Reddy (supra) a learned Single Judge of the
Karnataka High Court held that if the parties were exercising
their legal rights, the passage of time can not be arrayed against
them to deny the relief.
63) In Rayees Alam (supra) the Calcutta High Court held that
delay in filing the suit is not material where an injunction is
sought in aid of a legal right, and mere lapse of time will not be
a bar to the grant of an injunction before the trial.
64) Evidently, the aforesaid propositions have been enunciated
in the facts of the given cases. One can not loose sight of the
fact that grant of injunction or appointment of a receiver is a
NMS-1361-13+IA-293-22.DOC
discretionary relief. It has to be exercised keeping in view the
fact situation of the matter. In the case at hand, the passage of
time has brought in its strain many factors which are of critical
salience. The suit property has been developed in a proportion
which far exceeds the terms of the MOU. Security interest of
significant bearing has been created. A multitude of third party
rights have been created. In fact, the physical character of the
suit property has been substantially altered. The contention
that the defendant No. 1 carried the development by resorting to
letigative stratagem is required to be appreciated in the light of
the fact that there has been no restraint order against the
defendant No. 1. In the circumstances, at this stage, the balance
of convenience clearly tilts in favour of defendant No. 1.
65) Irreparable loss, in the circumstances of the case, in the
event of grant of injunction would be suffered not only by the
defendant No. 1 but the parties in whose favour rights have
been created.
66) At this juncture, it would be contextually relevant to note
that Mr. Madon, the learned Counsel for the defendant No. 1, on
instructions, made a statement that the defendant No. 1 has no
objection to the plaintiffs withdrawing the amount of
NMS-1361-13+IA-293-22.DOC
Rs.3,39,00,000/- deposited in this Court by the defendant No. 1
pursuant to order dated 27th April, 2022.
67) Granting such permission to withdraw the amount subject
to final adjudication would be a measure in mitigation.
68) For the forgoing reasons, I am impelled to hold that Notice
of Motion as well as the Interim Application deserve to be
dismissed. At the same time, I am inclined to allow the plaintiffs
to withdraw the sum of Rs.3,39,00,000/-, along with interest
accrued thereon without prejudice to the rights and contentions
of the parties and subject to the determination of the suit.
69) Hence, the following order.
:ORDER:
(i) Notice of Motion No. 1361 of 2013 and Interim
Application No. 293 of 2022, stand dismissed.
(ii) The plaintiffs are permitted to withdraw a sum of
Rs.3,39,00,000/-, along with interest accrued thereon
without prejudice to the rights and contentions of the
parties and subject to the final decision of the suit.
Costs in cause.
[N. J. JAMADAR, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!