Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Premal Shankarlal Mehta vs The Additional Director Central ...
2023 Latest Caselaw 3476 Bom

Citation : 2023 Latest Caselaw 3476 Bom
Judgement Date : 10 April, 2023

Bombay High Court
Premal Shankarlal Mehta vs The Additional Director Central ... on 10 April, 2023
Bench: Sandeep V. Marne
2023:BHC-OS:2723-DB

                                                                 18.9328.23-wpl.docx

                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                 ORDINARY ORIGINAL CIVIL JURISDICTION

                                       WRIT PETITION (L) NO. 9328 OF 2023


                       Premal Shankarlal Mehta                      ..... Petitioner

                               Vs.

                       The Additional Director General,
                       Government Health Scheme, Mumbai             ..... Respondents


                       Mr. Saleel Borwandkar for the Petitioner
                       Dr. Uday Warunjikar with Jenish Jain for the Union of India


                                        CORAM:    S.V. GANGAPURWALA, ACJ &
                                                  SANDEEP V. MARNE,J.

DATED : APRIL 10, 2023

P.C.

1. Respondent No.1 had floated tender on 1st

February 2023 for supply of medicines and drugs to Central

Government Health Schemes. The technical and financial

bids were opened. The Petitioner was L1.

2. The learned Counsel for the Petitioner submits

that there was no need to cancel the tender process. The

Petitioner was declared as L1. The entire process of

technical evaluation was carried out by verifying the

documents and also on the field. The learned Counsel

Basavraj 1/5

18.9328.23-wpl.docx

submits that as per the General Financial Rules 2017 the

rejection of the bid is justified only when effective

competition is lacking or all bids and proposals are not

substantially responsive to the requirements of the

procurement documents, or the bids / proposals prices are

substantially higher than the updated cost estimate or

available budget or none of the technical proposals meet the

minimum technical qualifying score. According to the

learned Counsel, none of these reasons are available for

cancelling the tender process. The tender process has been

cancelled in arbitrary manner. It is further submitted that

21 days are available for processing the tender from the

date of advertisement. The said date can also be extended.

The Respondents, without waiting for the same, have

abruptly issued the fresh tender. According to the learned

Counsel, as per clause 7.5.11 of the Manual for Procurement

of Goods, in case where responsive bids are available the

aim should be to finalise the tender by taking mitigating

measures. According to the learned Counsel, the tender

process cannot be cancelled in arbitrary manner and

retender cannot be resorted to as a matter of course. The

retender would be prejudicial to the interest of the

Basavraj 2/5

18.9328.23-wpl.docx

Petitioner. The financial bids were opened. The rates were

disclosed. According to the learned Counsel, as the process

was completed, the said tender process ought not to have

been cancelled.

3. We have heard Dr.Warunjikar, the learned

Counsel for the Union of India.

4. The cancellation of the earlier tender process

was challenged by bidders who were L4 and L5 in the earlier

tender process by filing Writ Petition (L) No.8894 of 2023.

The present Petitioner was Respondent No.3 in the said

matter and was represented. This Court, under order dated

31st March 2023 dismissed the said Writ Petition.

5. We had observed that now pre-bid meetings have

been held on 24th March 2023 and 27th March 2023. It has

been clarified that as per the previous tender documents,

MSE certificate in the form of UAM alone was considered,

which resulted in many eligible MSE bidders being

considered as non MSE by the evaluation committee. It was

informed in the said meeting that the clarification regarding

correction of MSE status was sought from GEM Category

Manager, as there was no option on the GEM portal to

Basavraj 3/5

18.9328.23-wpl.docx

accord the MSE status after the opening of 2/26 schedules

for financial evaluation. To provide a fair opportunity to all

the bidders and as per the instructions from GeM, the bid

was cancelled and tendering was done again. All the

schedules of the previous tender stands cancelled. The

queries which were raised in the pre bid meeting were

clarified, which are as under:

Clarification was asked by the It was clarified that MSE bidders whether only MSE certificate in the form of certificate in the form of UAM shall Udhyam registration shall be accepted as they are not able to also be considered as valid generate UAM now. for obtaining benefits of MSE.

Whether the rates are separate for The discount is not generic and branded drugs? separate for generic or branded drugs and is the same for both Whether it is mandatory to supply The medicines which are medicines in the same brand only? prescribed in brand name shall be supplied in the same brand only and shall not be substituted. Penalty shall be imposed for each instance of substitution.

6. In the said judgment and order, we have also

observed that no rights have been crystalized in favour of

the Petitioner who was Respondent No.3 in the said Writ

Petition. No work order was ever issued nor any one was

declared as a successful bidder.

7. Act of Respondent Nos.1 and 2 does not smack

Basavraj 4/5

18.9328.23-wpl.docx

of mala fide or arbitrariness. The reasons are given for

cancellation of the tender process. Fresh tender process

has been initiated.

8. The Petitioner has also participated in the fresh

tender process by filling in his bid on 3 rd April 2023. After

submitting his bid in the new tender process, the Petitioner

is assailing the cancellation of old tender process.

9. It appears that to provide fair opportunity to all

the bidders and as per the instructions from GeM, the bid

was cacnelled and fresh tender was issued again. In the

earlier tender process, there was no option on the GEM

portal to accord the MSME status after opening of 2/26

schedules for financial evaluation and because of that some

MSMEs could not have participated in the said tender

process.

10. In light of the above, no case for interference is

made out. The Writ Petition, as such, is disposed of. No

costs.




       (SANDEEP V. MARNE, J.)                (ACTING CHIEF JUSTICE)



       Basavraj                                                                       5/5





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter