IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.7193 OF 2003
M/s. Jaysynth Dyechem Ltd. and Anr. ... Petitioners
versus
Dyes and Chemical Workers Union ... Respondent
WITH
INTERIM APPLICATION NO.2468 OF 2020
Mr. A.K.Jalisatgi for Petitioners.
Mr. P.M.Patel for Respondent.
Mr. Kamlesh Singh, Manager of Petitioner No.1 present.
Mr. S.L.Gawde, General Secretary of Respondent present.
CORAM: N.J.JAMADAR, J.
DATE : 3 APRIL 2023
P.C.
1. Heard the learned Counsel for the parties.
2. The learned Counsel make a joint statement that the parties have
amicably resolved the dispute and Memorandums of Settlement dated 2 September
2022 have been executed. The learned Counsel seek leave to tender Consent Minutes
of Order. Copies of Memorandums of Settlement are annexed to the Consent Minutes
of Order.
3. Leave granted.
4. Consent Minutes of Order are taken on record.
5. Mr. Kamlesh Singh, Manager (Operations) of the Petitioner No.1 and
Mr. S.L.Gawde, General Secretary of the Respondent Union are present in Court.
SSP 1/2
4 wp 7193 of 2003.doc
6. They admit the contents of the Consent Minutes of Order and the
execution thereof.
7. It seems that the parties have executed Memorandums of Settlement
and the dispute is resolved voluntarily and there is no coercion or duress.
8. Hence, the Petition stands disposed in accordance with the Consent
Minutes of Order 'X', reproduced below :
CONSENT MINUTES OF ORDER "1.By consent of the parties the order and judgment dated 30 September 2003 passed by the Industrial Court, Thane in Complaint (ULP) No.196 of 2000 is quashed and set aside.
2. The parties have entered into settlements dated 2 nd September 2022. A copy of the each of the two settlements is annexed hereto and marked as Exhibit 1 and 2. The parties shall abide by the terms and conditions of the said settlement.
3. The Petitioner has already paid the entire amount arising out of the settlements mentioned in para (2) hereinabove to the workmen.
4. The Petitioner has deposited a sum of Rs.25,00,000/- (Rupees Twenty Five Lakh only) in the High Court as per the order dated 3 rd February 2004 passed in the above numbered Writ Petition. The workmen concerned have already withdrawn 50% of the said amount. Now the Respondent is allowed to withdraw the balance amount and disburse the same amongst the workmen concerned.
5. The Petition is disposed of in above terms with no order as to cost."
9. Interim Application No.2468 of 2020 also stands disposed.
( N.J.JAMADAR, J. )
SSP 2/2
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!