Citation : 2022 Latest Caselaw 9049 Bom
Judgement Date : 12 September, 2022
43.CARBPL.26420.22..doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ANJALI Digitally signed by
ANJALI TUSHAR
ORDINARY ORIGINAL CIVIL JURISDICTION
TUSHAR ASWALE
Date: 2022.09.12
ASWALE 19:01:13 +0530
IN ITS COMMERCIAL DIVISION
COMMERCIAL ARBITRATION PETITION(L) NO. 26420 OF 2022
Nina Percept Pvt Ltd
(formerly known as Nina
Waterproofing Systems Pvt Ltd) ..Petitioner
Vs.
Gammon Engineers and Contractors
Pvt Ltd & Anr ..Respondents
Mr.Karl K. Shroff a/w Ms.Sheetal Parkash i/b Jayesh Desai &
Associates, for the Petitioner.
CORAM:- B. P. COLABAWALLA,J.
DATE :- SEPTEMBER 12, 2022.
P. C.:
Taken out of turn due to urgency made out by the
Petitioner.
2 Mr. Shroff, the learned counsel appearing on behalf of the
Petitioner, has tendered a draft amendment which is taken on record
and marked "X" for identification. The Petitioner is allowed to amend
Aswale page 1 of 7
43.CARBPL.26420.22..doc
the Petition as per the draft handed in, within a period of one week from
today. Re-verification is dispensed with.
3 The above Section 9 Petition has been filed to injunct and
restrain Respondent No.1 and /or its officers, agents, servants, and/or
employees from invoking the Performance Bank Guarantee dated 6 th
February, 2018 (Exhibit-B to the Petition). In the event the bank
guarantee is already invoked, it is also prayed that Respondent No.2
(ICICI Bank Ltd), be restrained from paying Respondent No.1 any sums
under the Performance Bank Guarantee dated 6th February, 2018.
4 These aforesaid reliefs are sought in the factual background
which is this. Under a Letter of Intent dated 24 th January, 2018,
Respondent No.1 awarded a Water Proofing Contract to the Petitioner.
There were amendments to the scope of work for which the
amendments to the work order as also purchase order came to be issued
from time to time. Clause 28 of the Special Conditions and General
Conditions of the work order sets out the defect liability period and
Clause 33 relates to dispute resolution.
5 Mr. Shroff, the learned counsel appearing on behalf of the
Petitioner, submitted that under the contract, the Petitioner was to issue
Aswale page 2 of 7
43.CARBPL.26420.22..doc
two bank guarantees, one for cash retention and other being the
Performance Bank Guarantee. He submitted that in the present case,
the issue in the Petition is only with reference to the Performance Bank
Guarantee as the Cash Retention Bank Guarantee has already been
returned by the 1st Respondent to the Petitioner on 13th May, 2022.
6 Mr. Shroff submitted that though the entire contract is fully
completed and even the defect liability period has expired, the
Performance Bank Guarantee has not been returned to the Petitioner.
He brought to my attention that the 1st Respondent, by its
communication dated 1st July, 2021, had infact noted that the
Performance Bank Guarantee submitted by the Petitioner for the value
of Rs.1,70,80,000/- issued by ICICI Bank Ltd would be returned by the
1st Respondent to the Petitioner for cancellation at the earliest. He
submitted that despite this, the bank guarantee has not been returned.
7 Mr. Shroff submitted that this does not stop here. He
thereafter brought to my attention a communication dated 31 st August,
2021 issued by the 1st Respondent to the Petitioner wherein it is
confirmed that the Petitioner has successfully completed the Water
Proofing Contract. Mr. Shroff submitted that in these circumstances, it
would be highly unjust if the 1 st Respondent is not restrained from
Aswale page 3 of 7
43.CARBPL.26420.22..doc
invoking the bank guarantee. He submitted that admittedly no amounts
are due and payable by the Petitioner to the 1 st Respondent and even the
contract has been successfully performed and the defect liability period
has also expired. In these circumstances, if an injunction is not
granted, irretrievable injustice would be caused to the Petitioner, was
the submission. In support of this proposition, Mr. Shroff relied upon
an unreported decision of a learned Single Judge of this Court (S. J.
Vazifdar, J. as he then was) dated 13th September, 2011 passed in
Notice of Motion No.__ of 2011 in Suit (L)No. 2331 of 2011
[Man Industries (India) Ltd v/s Indusind Bank Ltd & Ors].
8 I have heard Mr. Shroff at some length. The matter has
been moved ex-parte without giving notice to the Respondents. From
the documents on record, it appears that the Petitioner gave two bank
guarantees to the 1st Respondent. First was a Cash Retention Bank
Guarantee in the sum of Rs.85,40,000/- and the second was the
Performance Bank Guarantee in the sum of Rs. 1,70,80,000/-. The
Cash Retention Bank Guarantee has infact been returned by the 1 st
Respondent. The dispute in the present case is only in relation to the
Performance Bank Guarantee in the sum of Rs.1,70,80,000/-. The
record clearly shows that the 1st Respondent, by its communication
dated 1st July, 2021 had informed the Petitioner that it would return
Aswale page 4 of 7
43.CARBPL.26420.22..doc
this Performance Bank Guarantee at the earliest. Over and above this,
the 1st Respondent has also issued a certificate (page 152 of the paper
book) confirming that the Petitioner has successfully completed the
Water Proofing Contract. In these facts, I am in agreement with Mr.
Shroff that if the injunction restraining the 1 st Respondent from
invoking or encashing the bank guarantee is not granted, irretrievable
injustice would be caused to the Petitioner. In the view that I take, I
find support in the decision of a learned Single Judge of this Court dated
13th September, 2011 in the case of Man Industries (India) Ltd v/s
Indusind Bank Ltd & Ors (supra). The facts in that case were
similar to the facts before me. The learned Single Judge, after relying
upon a decision of the Supreme Court in the case of Larsen & Toubro
v/s MSEB reported in AIR 1996 SC 334 in fact granted an
injunction from invoking/encashing the Bank Guarantee because even
in that case the contract was satisfactorily performed. The relevant
portion of this decision reads thus:-
"11.Mr. Tulzapurkar, on the other hand, relied upon the judgment of the Supreme Court in Larsen & Toubro v. MSEB, AIR 1996 SC 334. In that case, clause 70.4.01 of the contract provided that upon successful completion of all the performance tests at site, the owner shall issue to the contractor a taking over certificate as proof of the final acceptance of the equipment. A certificate was issued stating that the trials were generally satisfactory. All the commissioned equipments under the contract were take over for regular operation and maintenance as per the contract. The appellant, accordingly, addressed a letter stating that the plant was completed and so all the bank guarantees had served their contractual requirements. It must be noted that the certificate merely stated that the trials were generally satisfactory and that the
Aswale page 5 of 7
43.CARBPL.26420.22..doc
certificate was issued "after reasonable completion" of the plant works. The Supreme Court held as under :-
"11. ...................The appellant wrote to the first respondent on 21.2.1994 that the plant was completed and so all Bank Guarantees have served their contractual requirements. On a perusal of the relevant clauses in the contract executed between the appellant and the first respondent, and the communication of the first respondent dated 10-6-1994, it is fairly clear that the stipulations or conditions mentioned as per Clauses 70.2, 70.3 and 70.4 have been successfully fulfilled and the Plant was admittedly taken over by the first respondent. The Guarantee given by the Citi Bank, N.A. Dated 10 th of May, 1989 appearing in Volume II at pages 122 to 126 will enure only till successful completion of the trial operations and the plant is taken over. That event having ensued, the invocation of the Guarantee given by the Citi Bank dated 10-5-1985 in the sum of Rs. 2.72 crores is not encashable on its terms and in order to prevent irretrievable injustice, an injunction as prayed for, to respondents 1 and 4 deserves to be issued on that score. The Court below was in error in not doing so. We hereby restrain respondents 1 and 4 from invoking the Bank Guarantee aforesaid."
In the present case, the certificate dated 11th July, 2011, is more categorical regarding the plaintiff's compliance with the contractual provisions. The judgment, therefore, would apply with equal if not greater force to the present case.
9 In these circumstances, there shall be ad-interim relief in
terms of prayer clauses (A) and (B) which read thus:-
A) "That pending the disposal and final hearing of the present Arbitration Petition and the arbitral proceedings, this Hon'ble Court be pleased to injunct and restrain the Respondent No. 1 itself and/or its officers, agents, servants, employees from invoking the said Performance Bank Guarantee dated 6.2.2018 (Exhibit B hereto);
B) That pending the disposal and final hearing of the present Arbitration Petition and the arbitral proceedings, this Hon'ble Court be pleased to injunct and restrain the Respondent No. 2 itself and/or its officers, agents, servants, employees form paying Respondent No. 1 under the said Performance Bank Guarantee dated 6.2.2018."
10 It is needless to clarify that since this order is passed in the
absence of the 1st Respondent, the 1st Respondent shall be at liberty to
make an application to have the ad-interim order vacated. A copy of
this order shall be served on Respondent No.1 as well as Respondent
Aswale page 6 of 7
43.CARBPL.26420.22..doc
No.2 within a period of one week from today. Place the above matter
for hearing and final disposal as per its turn.
11 This order will be digitally signed by the Private
Secretary/Personal Assistant of this Court. All concerned will act on
production by fax or email of a digitally signed copy of this order.
( B. P. COLABAWALLA, J. )
Aswale page 7 of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!