Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S V.N. Reddy Through Proprietor ... vs The Superintending Engineer, ...
2022 Latest Caselaw 2955 Bom

Citation : 2022 Latest Caselaw 2955 Bom
Judgement Date : 25 March, 2022

Bombay High Court
M/S V.N. Reddy Through Proprietor ... vs The Superintending Engineer, ... on 25 March, 2022
Bench: A.S. Chandurkar, G. A. Sanap
                  WP1787.2021(J)                                                                                   1/17

                                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                              NAGPUR BENCH, NAGPUR.


                                                  WRIT PETITION NO.1787/2021

                        M/s. V.N.Reddy,
                        Through its Proprietor -
                        Shri V. Narsimha Reddy S/o Obula Reddy,
                        Aged about 50 years, Occ: Govt. Contractor,
                        R/o. House No.777, Bhaisare Layout,
                        Karla Bypass, Wardha.
                                                                                      ....... PETITIONER

                                               ...V E R S U S...

                 1]     The Superintending Engineer,
                        Vidarbha Irrigation Development Corporation,
                        Office at Water Resources Department,
                        Civil Lines, Nagpur.

                 2]     The Executive Engineer,
                        Lower Wardha Project Division,
                        Wardha.

Amended as       3]   Shri Mahesh Reddy,
per Court's           M/s. Om Gurusai Construction Company
order dated
                      through its Managing Director,
07.01.2022
                      C/o. Shri Shankarrao Maraskolhe,
Sd/-Counsel           Sir Plot No.34, Vrundavan Nagar, Sindhi (Meghe)
for petitioner        Wardha-442 001.
dt.12.01.2022                                                                       ....... RESPONDENTS
               ---------------------------------------------------------------------------------------------------------------
               Shri S.D.Chopde, Advocate for petitioner.
               S/Shri S.G.Jagtap with Shri H.D.Marathe, Advocates for respondent nos. 1 & 2.
               Shri Tushar Tathod, Advocate for respondent no.3.
               --------------------------------------------------------------------------------------------------------------

                 CORAM : A.S.CHANDURKAR and G.A.SANAP, JJ.
                 ARGUMENTS WERE CLOSED ON : 25th FEBRUARY, 2022.
                 JUDGMENT IS PRONOUNCED ON : 25th MARCH, 2022
                 AS PER CHAPTER XI RULE 1 OF THE BOMBAY HIGH COURT APPELLATE SIDE RULES,
                 1960).


                          ::: Uploaded on - 25/03/2022                                 ::: Downloaded on - 26/03/2022 09:53:06 :::
 WP1787.2021(J)                                                                  2/17


JUDGMENT (Per A.S.CHANDURKAR, J.)

1. Rule. Rule made returnable forthwith and heard the learned

counsel for the parties.

2. The challenge raised in this writ petition is to the issuance of work

order dated 07.05.2021 by the Executive Engineer, Lower Wardha Project,

Division Wardha- second respondent in favour of the third respondent.

3. The facts relevant for considering the challenge to the issuance of

the work order are that the second respondent on 18.01.2021 issued a tender

notice calling upon interested bidders to submit their bid documents with

regard to three works. The work at serial no.1 which is "construction of land

development works (Part-I) of Gadegaon main minor offtaking @ R.D. 4995 M

on Nandgaon Dy" is the subject matter of the writ petition. Pursuant to the

tender notice three bidders submitted their bids. The technical bids were

opened on 08.02.2021 and the bids submitted by the petitioner and the third

respondent were found to be eligible. On opening of the financial bid on

12.03.2021 it was found that the financial bid of the third respondent was

lowest and therefore as required by Clause 2.22.0 the third respondent was

required to furnish additional performance security within a period of two

working days. According to the petitioner, the third respondent furnished such

additional performance security on the third working day and hence the third

respondent ought to be debarred from the tender process for failure to submit the

WP1787.2021(J) 3/17

additional performance security within the prescribed time. Ancillary grounds

also raised pertain to certain shortcomings in the documents submitted by the

third respondent. In the aforesaid factual backdrop, the petitioner has

challenged the issuance of work order to the third respondent as having been

issued disregarding the mandatory tender conditions.

4. Shri S.D.Chopde, learned counsel for the petitioner has invited

attention to various tender conditions and especially Clause 2.22.0. According

to him, as per sub-clause (ix) thereof the lowest bidder was required to submit

the additional performance security in the form of Demand Draft/Bank

Guarantee or Fixed Deposit Receipt within two working days of opening of the

financial bid. This period of two working days was not liable to be relaxed

under any circumstances and therefore since the third respondent furnished

such additional performance security beyond the period of two working days,

the second respondent was not justified in issuing the work order to the third

respondent. It was submitted that the financial bid was opened on 12.03.2021.

13.03.2021 was a Saturday and 14.03.2021 was a Sunday. The next two

working days were 15.03.2021 and 16.03.2021. The third respondent

submitted the additional performance security in the form of a Fixed Deposit

Receipt on 17.03.2021 which was beyond the period of two working days. The

learned counsel submitted that with regard to other works that were the

subject matter of the same tender notice wherein the bids were to be submitted

as per similar schedule, the bidders for other two works had furnished

WP1787.2021(J) 4/17

additional performance security within a period of two working days. Inviting

attention to the Government Resolution dated 23.06.2020 which was also

referred to in Clause 2.22.0 it was submitted that reading of paragraph 18

thereof indicated that the mandatory period of two days was not liable to be

extended for any reason whatsoever. The third respondent had sought to rely

upon a communication dated 11.05.2021 that was issued by the Branch

Manager of the Bank of Maharashtra that on 15.03.2021 and 16.03.2021 there

was a strike of bank employees due to which there were no banking

transactions. Since the third respondent had approached the bank on

17.03.2021, the Fixed Deposit Receipt was issued on that date. On the

aforesaid basis, it was submitted that the Executive Engineer had no authority

to accept the additional performance security beyond the period of two

working days. If the bid of the third respondent was liable to be rejected for

this reason the petitioner would be entitled to seek the work order since his bid

was the next lowest bid. The learned counsel also invited attention to the

communication dated 12.04.2021 issued by the Assistant Superintending

Engineer to the second respondent to submit his report in the light of the

grievance made by the petitioner in that regard on 30.03.2021. The second

respondent had come up with the stand that on account of strike of the bank on

15.03.2021 and 16.03.2021, the request for extension of time to submit the

additional performance security came to be accepted. Referring to the

provisions of Section 25 of the Negotiable Instruments Act, 1881 (for short, the

WP1787.2021(J) 5/17

Act of 1881), it was submitted that only a "public holiday" was liable to be

excluded while construing Clause 2.22.0. As 15.03.2021 and 16.03.2021 were

not declared as public holidays, those days could not be excluded from

consideration. Reference was made to the provisions of Section 42(2A) of the

Reserve Bank of India Act, 1934 in that regard. Thus when other bidders could

submit the additional performance security either on 15.03.2021 or on

16.03.2021, there was no reason for the second respondent to have extended

the time to furnish the additional performance security by a period of one day

to enable the third respondent to furnish the same when the same was not

permissible under Clause 2.22.0 of the tender document.

It was also submitted by the learned counsel for the petitioner that

various documents as required by Clause 2.23.0 and especially income tax

returns for the last five years as per sub-clause (v), scanned copy of the deed of

partnership as per sub-clause (vii) and scanned copy of the power of attorney

duly registered/notarised as per sub-clause (xii) had not been validly submitted

by the third respondent. Though one of the two partners of the partnership

firm of the third respondent had expired on 05.05.2020, the said deed of

partnership was submitted which amounted submitting false and misleading

information. If the income tax returns as submitted indicated 'nil' income of

the third respondent, the same reflected its financial capacity. Referring to the

communication dated 04.02.2022 that was issued by the third respondent for

seeking extension of time for a period of one year for completing the work in

WP1787.2021(J) 6/17

question, it was submitted that as per the tender notice the work awarded to

the third respondent was required to be completed within a period of six

months as per commencement order dated 24.05.2021 issued to the third

respondent. This period of six months had expired in November 2021 and

further extension sought was for a period of one year which was even beyond

the period prescribed in the tender notice. On this count it was submitted that

the work order issued to the third respondent was liable to be revoked and the

work order ought to be issued to the petitioner. In support of aforesaid

contentions, the learned counsel placed reliance on the decisions in Ramana

Dayaram Shetty vs. The International Airport Authority of India and others

AIR 1979 SC 1628 and Jagdish Mandal vs. State of Orissa and others (2007) 14

SCC 517. It was thus prayed that the petitioner was entitled to the reliefs as

prayed for.

5. Shri S.G.Jagtap, learned counsel for the first and second respondent-

Tender Issuing Authority submitted that the work order was issued to the

third respondent in accordance with the tender notice itself. Referring to

paragraph 2 of the additional affidavit filed on behalf of the first and second

respondent, it was submitted that the third respondent on 15.03.2021 had

informed the second respondent that on account of strike of the bank, it would

not be possible to furnish the additional performance security. That request

was accepted and the Fixed Deposit Receipt in that regard was accepted on

17.03.2021. It was further submitted that the objection raised by the petitioner

WP1787.2021(J) 7/17

on 17.03.2021 was only with regard to the extension of time that was granted

to the third respondent to furnish the additional performance security. No

other objection with regard to the documents submitted by the third

respondent was raised by the petitioner at that point of time. After verifying

the documents submitted by the third respondent, it was found that the same

were in order. Since the third respondent was the lowest bidder, the work

order was issued to it. There were no mala fides on the part of the first and

second respondent in granting the work order to the third respondent.

Shri Tushar Tathod, learned counsel for the third respondent

opposed the submissions as urged on behalf of the petitioner. It was submitted

that since the banks were closed on 15.03.2021 and 16.03.2021, it was not

possible for the third respondent to furnish the additional performance security

as required. The same was furnished immediately on re-opening of the bank

on 17.03.2021. The request made by the third respondent having been duly

accepted by the second respondent, there was no reason to doubt the grant of

such permission by the second respondent. In absence of any arbitrariness or a

plea of mala fides there was no reason to interfere with the decision of the

second respondent of granting time to the third respondent to furnish the

additional performance security. The learned counsel placed reliance on the

decision Galaxy Transport Agencies, Contractors, Traders, Transports and

Suppliers vs. New J. K. Roadways, Fleet Owners and Transport Contractors

and others 2020 SCC Online SC 1035 in that regard. It was further submitted

WP1787.2021(J) 8/17

that on 23.10.2020 the partnership firm of the third respondent that was

re-constituted was duly registered. After acceptance of the additional

performance security, the work order in question was duly issued to the third

respondent and the work in question had commenced. It was thus submitted

that there was no reason to interfere with the action of the second respondent

in accepting the additional performance security as furnished by the third

respondent. The writ petition was therefore liable to be rejected.

6. We have heard the learned counsel for the parties at length and with

their assistance, we have also perused the tender conditions and other

documentary material relied upon by the parties. The principal challenge

raised by the petitioner to the acceptance of the financial bid of the third

respondent is that the additional performance security that was required to be

submitted within two working days of opening of the financial bid and which

period was not liable to be relaxed/extended was accepted by extending the

period of one day which was not permissible.

It is not in dispute that the financial bids of the bidders were opened

on 12.03.2021. 13.03.2021 was a Saturday and 14.03.2021 was a Sunday. As

per Clause 2.22.0(ix) read with Government Resolution dated 23.06.2020 two

working days within which the additional performance security was required to

be submitted were 15.03.2021 which was Monday and 16.03.2021 which was

Tuesday. The third respondent sought to submit the Fixed Deposit Receipt

dated 17.03.2021 for amount of additional performance security along with his

WP1787.2021(J) 9/17

covering letter dated 17.03.2021. The said letter bears 'Inward No.1009 and

date 19.03.2021". In effect, the additional performance security has been

submitted after two working days as contemplated by Government Resolution

dated 23.06.2020. The questions therefore to be considered are (a) whether it

was open for the Tender Issuing Authority to have accepted the additional

performance security from the third respondent on 17.03.2021 which was the

third working day ? and (b) if it is held that the Tender Issuing Authority had

no power to relax the time stipulated by Clause 2.22.0(ix), whether it would be

in public interest to interfere in exercise of writ jurisdiction under Article 226

of the Constitution of India ?

7. To consider the aforesaid questions it would be necessary to first

refer to Clause 2.22.0 and sub-clause (ix) thereof :

"2.22.0 Additional Performance Security in case of offer below the cost put to tender as per Government of Maharashtra WRD Government Resolution No. Tender 0417/C.No.247/17/M.P.-1 Mantralaya Mumbai Date 30/11/2018 and PWD Government Resolutions Act 2017, on Dated 7/3/2019 & WRD Government Resolution No.0417/(subj.247/17/MP/1) on dated 23/06/2020.

(ix) L-I shall submit the demand draft/BG or FDR additional performance security in the office of the Executive Engineer, Lower Wardha Project Division, Wardha within 2 days of opening of envelope-2. This duration of 2 days will not be relaxed under any circumstances. Failure to do so will result in forfeiture of EMD and the contractor/ Joint Venture (jointly or individually) shall be debarred from participating in any bid of Water Resources Department / VIDC, Nagpur for two years from date of opening of

WP1787.2021(J) 10/17

envelope-2, if L-1 fails to submit to additional performance security within prescribed time period then Executive Engineer ask L-2 in writing and if L-2 bidder agree to do work at the rate quoted by L-1 then L-2 bidder shall be considered for acceptance". (emphasis supplied)

The aforesaid Clause refers to Government Resolutions dated 30.11.2018,

07.03.2019 and 23.06.2020. A perusal of the Government Resolution dated

23.06.2020 indicates reference to the earlier Government Resolutions dated

30.1.2018, 12.12.2018 and 13.09.2019. It has been stated in the Government

Resolution dated 23.06.2020 that as per the earlier Government Resolutions a

period of eight days had been provided for submitting the additional

performance security deposit. It was noticed by the Government that granting

such period of eight days resulted in causing delay in issuing the work order for

commencement of the work. In that view of the matter, it was resolved

to reduce the earlier period of eight days and it was decided that period of two

days would be granted to furnish the additional performance security deposit

to the Executive Engineer. It was further stated that this period of two days

would not be relaxed for any reason whatsoever. Failure to submit the

additional performance security deposit would result in forfeiture of the

earnest money of the bidder and such bidder would stand disqualified for a

period of two years from participating in future tenders of the Department. It

was stated that in such contingency without calling for fresh bids, the second

lowest bidder should be called upon to carry out the work in question at the

rates quoted by the lowest bidder. If the second lowest bidder was willing

WP1787.2021(J) 11/17

to carry out the work on the same terms and conditions, the bid of the second

lowest bidder could be accepted.

Thus from the contents of the Government Resolution dated

23.06.2020 which finds specific reference in Clause 2.22.0 of the tender notice,

it is clear that the earlier period of eight days was reduced to two days with a

further condition that this period of two days would not be relaxed/extended

under any circumstances whatsoever. The consequence of failure to comply

with the aforesaid conditions to result in forfeiture of earnest money deposit

and debarment in participating in any bid for a period of two years from the

opening of the financial bid. Thus, the condition imposed by sub-clause (ix) of

Clause 2.22.0 is clearly of a mandatory nature considering the background in

which the period of eight days was reduced to two days. The consequence of

non-compliance also having been prescribed, there is no doubt whatsoever that

submission of the additional performance security deposit within a period of

two days of opening of the financial bid is a mandatory and essential condition

prescribed by the notice inviting tenders.

8. Once it becomes clear that Clause 2.22.0(ix) was a mandatory

condition prescribed by the tender notice, it follows that the Tender Issuing

Authority was prevented from extending the duration of two working days

under any circumstances whatsoever. In this regard, reference can be made to

the decision of the Hon'ble Supreme Court in B.S.N.Joshi & Sons Ltd. vs. Nair

Coal Services Ltd. and others, (2006) 11 SCC 548 and especially paragraph 66

WP1787.2021(J) 12/17

thereof wherein it has been held as under :

"66. We are also not shutting our eyes towards the new principles of judicial review which are being developed; but the law as it stands now having regard to the principles laid down in the aforementioned decisions may be summarised as under :

(i) If there are essential conditions, the same must be adhered to;

(ii) if there is no power of general relaxation, ordinarily the same shall not be exercised and the principle of strict compliance would be applied wherein it is possible for all the parties to comply with all such conditions fully;

(iii) if, however, a deviation is made in relation to all the parties in regard to any of such conditions, ordinarily again a power of relaxation may be held to be existing;

(iv) the parties who have taken the benefit of such relaxation should not ordinarily be allowed to take a different stand in relation to compliance with another part of tender contract, particularly when he was also not in a position to comply with all the conditions of tender fully, unless the Court otherwise finds relaxation of a condition which being essential in nature could not be relaxed and thus the same was wholly illegal and without jurisdiction;

(v) when a decision is taken by the appropriate authority upon due consideration of the tender document submitted by all the tenderers on their own merits and if it is ultimately found that successful bidders had in fact substantially complied with the purport and object for which essential conditions were laid down, the same may not ordinarily be interfered with;

(vi) the contractors cannot form a cartel. If despite the same, their bids are considered and they are given an offer to match with the rates quoted by the lowest tenderer, public interest would be given priority;

(vii) where a decision has been taken purely on public interest, the Court ordinarily should exercise judicial restraint." (emphasis supplied)

WP1787.2021(J) 13/17

9. In Tata Cellular Ltd. vs. Union of India (1994) 6 SCC 651 it has

been held by the Hon'ble Supreme Court that in contractual matters the Court

ought to confine itself to the question of legality and one of the concerns should

be whether the decision making authority has exceeded its powers. It is in that

context that the decision of the Tender Issuing Authority to relax the time

stipulated by Clause 2.22.0(ix) would have to be examined. In that regard, the

power of relaxation/extension of time must be stipulated in the tender

document itself and in absence thereof the principle of strict compliance is

required to be adhered to. In this context, the petitioner has sought to rely

upon the submission of additional performance security deposit by another

bidder who had submitted his bid in another work under the same tender

notice. M/s. Sai-Aniruddha Construction had on 15.03.2021 itself furnished

the additional performance security deposit vide demand draft dated

15.03.2021. In other words, it was possible for a bidder under the same tender

notice to furnish the additional performance security deposit on 15.03.2021 as

per Clause 2.22.0.

The Principal (Tender Issuing Authority) no doubt has sought to rely

upon the communication dated 11.05.2021 issued by the Branch Manager,

Bank of Maharashtra, Gandhinagar Branch, Wardha. It was stated that on

15.03.2021 and 16.03.2021 there was a strike of bank employees due to which

there were no banking transactions. However, in the light of the clear

stipulation in Clause 2.22.0 read with Government Resolution dated

WP1787.2021(J) 14/17

23.06.2020 there was no scope for the Executive Engineer to extend the period

of two working days and hence the consequence provided in Clause 2.22.0(ix)

of the tender condition would have to operate.

10. Thus having been found that the period of two days as prescribed by

Government Resolution dated 23.06.2020 as well as Clause 2.22.0(ix) was not

liable to be relaxed under any circumstance with further stipulation that failure

to comply with the time prescribed would result in forfeiture of the earnest

money deposit as well as the debarment from further participation, Question

(a) is answered by holding that it was not open for the Tender Issuing

Authority to have accepted the additional performance security from the third

respondent on 17.03.2021 which was the third working day from opening of

the financial bid.

11. Having found that there was no power with the Tender Issuing

Authority to relax the time stipulated by Clause 2.22.0(ix), that by itself would

not entitle the petitioner to relief. It would be necessary to consider whether it

would be in public interest to exercise writ jurisdiction under Article 226 of the

Constitution of India on that ground. In Bharat Coking Coal Limited and others

vs. AMR Dev Prabha and others (2020) 16 SCC 759 the Hon'ble Supreme Court

has held that in such contractual disputes the power of judicial review should

not be permitted to be invoked to protect private interest at the cost of public

interest or to decide contractual disputes. In addition to the grounds of

WP1787.2021(J) 15/17

arbitrariness, illegality or discrimination, involvement of public interest is also

required to be demonstrated before the remedy is sought. It has been further

observed that although the threshold for the public interest to exist need not be

high nevertheless it is essential to prevent bypassing of civil Courts and use of

constitutional avenues for enforcement of contractual obligations. Reference

was made to the decision in Shobikaa Impex (P) Ltd. vs. Central Medical

Services Society (2016) 16 SCC 233 that even when some defect is found in

decision making process, the Court must exercise its discretionary powers

under Article 226 of the Constitution with caution and should exercise it only

in furtherance of public interest and not merely on the making out of a legal

point. Keeping this aspect in mind, the question as to whether discretion

should be exercised will have to be considered.

12. The work order in question was issued to the third respondent and

on 24.05.2021 the Tender Issuing Authority issued the work commencement

order. It was stated therein that the duration for completion of the work in

question was six months and the period for rectification of deficiencies therein

was twenty-four months. It is thus clear that the work allotted to the third

respondent was to be completed within a period of six months. That work

therefore was to be completed by the end of 2021. It is however pertinent to

note that on 04.02.2022 the third respondent issued a communication to the

second respondent stating therein that it could not complete the work as

allotted and it sought extension of time to complete the same till 31.03.2023.

WP1787.2021(J) 16/17

In other words, the work order having been issued on 24.05.2021 with the

stipulation that the work was required to be completed within a period of six

months, the same was not so completed and a further extension of almost 18

months was sought by the third respondent. The work in question is for

construction of land development works and the Tender Issuing Authority

therefore required the same to be completed within a period of six months.

From the communication dated 04.02.2022 issued by the third respondent

itself it becomes clear that the third respondent has not been able to meet the

time limit prescribed in the work order and has sought further extension of

almost eighteen months. This would naturally result in cost escalation in

normal course. In our view therefore the third respondent by its own conduct

has indicated that it is not in a position to adhere to the time framed as per the

work order and in fact has sought extension much beyond the original period

permitted under the work order. It would therefore definitely be a reason to

interfere in public interest since the extension of time for completion of the

work much beyond what was prescribed would naturally result in an increase

in the amount of expenditure. We are therefore satisfied that there is an

element of public interest involved thus making out a case for interference

under Article 226 of the Constitution of India. Question (b) is answered

accordingly.

13. For the aforesaid reasons, we find that the Tender Issuing Authority

could not have extended the period of two days for furnishing the additional

WP1787.2021(J) 17/17

performance security under Clause 2.22.0(ix). The consequences for not

furnishing the additional performance security within a period of two days

having been provided in that Clause itself, the Tender Issuing Authority would

be required to act accordingly.

14. Accordingly, the following order is passed :

(I) The work order dated 07.05.2021 issued to the third respondent by

the second respondent is quashed and set aside. Consequentially, the work

commencement order dated 24.05.2021 would not survive.

(ii) The second respondent is free to take further steps in accordance

with Clause 2.22.0(ix) and proceed further.

Rule is made absolute in aforesaid terms with no order as to costs.

In the facts of the case, this judgment shall operate after a period of

four weeks from today.

       (G.A.SANAP, J.)                 (A.S.CHANDURKAR, J.)



Andurkar...





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter