Citation : 2022 Latest Caselaw 13119 Bom
Judgement Date : 16 December, 2022
973.wp.9620.22.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 9620 OF 2022
Yash Construction Company
A partnership firm "Padmini
Niwas", H.No.9/529, Opp. Municipal
Council, Prashant Nagar, Ambajogai,
Tq. Ambajogai, Dist. Beed - 413 512
through its partner
Pradeep s/o Madhukarrao Thombre
Age : 42 years, Occ : Business,
R/o : "Padmini Niwas", H.No.9/529,
Opp. Municipal Council, Prashant
Nagar, Ambajogai, Tq. Ambajogai,
Dist. Beed - 413 512 ... PETITIONER
VERSUS
1. The Secretary
Ministry of Road Transport and
Highways (MoRT & H), Room
No.509, Ministry of Road Transport
and Highways Transport Bhavan, 1,
Parliament Street, New Delhi - 110 001.
2. The Chief Engineer and Regional
Office, (Maharashtra and Goa) Room
No.508 & 509, Konkan Bhavan, 5th
Floor, Sector-6, C.B.D., Belapur,
Navi Mumbai - 400 614.
3. The Chief Engineer,
Public Works Department,
National Highways, Government
of Maharashtra Room No.526,
5th Floor, Kokan Bhavan, Sector-10,
CBD, Belapur, Navi Mumbai - 400 614
4. The Superintendent Engineer,
National Highway (P.W.) Circle,
"Bandhakam Bhawan, Sneh Nagar,
Adalat Road, Aurangabad - 431 005.
1/18
::: Uploaded on - 16/12/2022 ::: Downloaded on - 17/12/2022 19:42:54 :::
973.wp.9620.22.odt
5. The Executive Engineer,
National Highways Division,
Barure Complex, Opp. S.T. Workshop,
Ambajogai Road, Latur - 413 512. ... RESPONDENTS
...
Mr. R.N. Dhorde, Senior advocate i/b.
Mr. V.R. Dhorde, advocate for petitioner
Mr. A.G. Talhar, DSGI for respondents No.1
Mr. D.R. Kale - Government Pleader for the respondent Nos. 2 to 5
...
WRIT PETITION NO.11026 OF 2022
1. M/s. Saket - RPS JV
A joint venture between one Saket
Infraprojects Private Limited and RPS
Infraprojects Private Limited having its
office at L-3, 308, the Summit Business
Bay, near Service Road, Off Western Express
Highway, Vile Parle (E), Mumbai - 400 057
2. Saket Infraprojects Private Limited
[CIN: U45201MH2006PTC163441]
A private limited company, governed
by the provisions of the Companies Act, 2013
having its registered address at L-3, 308,
the Summit Business Bay, near Service Road,
Off Western Express Highway, Vile Parle (E),
Mumbai - 400 057.
3. RPS Infra Project Private Limited
[CIN: U45201MH2006PTC163522]
A private limited company, governed
by the provisions of the Companies Act, 2013
having its registered address at C-113, 1st Floor,
Shyam Kamal, Agarwal Market, Vile Parle (E),
Mumbai - 400 057.
4. Vishal Wadhawan
Age : 42 years, adult, Indian Inhabitant,
Director and Shareholder/Member of
the petitioner No.2 Company, having his office
address at L-3, 308, the Summit Business Bay,
near Service Road, Off Western Express Highway,
Vile Parle (E), Mumbai - 400 057. ... PETITIONERS
2/18
::: Uploaded on - 16/12/2022 ::: Downloaded on - 17/12/2022 19:42:54 :::
973.wp.9620.22.odt
VERSUS
1. Union of India,
through the Ministry of Road
Transport and Highways Transport
Bhawan, 1, Parliament Street,
New Delhi - 110001.
also at : Regional Office, Maharashtra
and Goa, Room No.508 and 509, Konkan
Bhavan, 5th Floor, Sector-6, C.B.D., Belapur,
Navi Mumbai - 400 614.
2. State of Maharashtra
through the Chief Engineer (NH),
Public Works Department, Room No.526,
5th Floor, Konkan Bhavan, Sector-10,
CBD Belapur, Navi Mumbai - 400 614.
3. The Superintending Engineer,
National Highway (P.W.) Circle,
"Bandhakam Bhawan, Sneh Nagar,
Adalat Road, Aurangabad - 431005.
4. The Executive Engineer,
National Highways Division,
Latur Barure Complex, Opp.
S.T. Workshop, Ambajogai Road,
Latur, Maharashtra - 413512. ... RESPONDENTS
...
Mr. R.N. Dhorde, Senior advocate i/b.
Mr. V.R. Dhorde, advocate for petitioner
Mr. A.G. Talhar, DSGI for respondents No.1
Mr. D.R. Kale - Government Pleader for the respondent Nos. 2 to 4
...
CORAM : MANGESH S. PATIL &
Y.G. KHOBRAGADE, JJ.
Reserved on : 07.12.2022
Pronounced on : 16.12.2022
JUDGMENT (MANGESH S. PATIL, J.) :
In these two separate writ petitions, the respective petitioners
are challenging the action of the respondents impliedly not accepting their
respective bids for rehabilitation and upgradation of two different stretches
973.wp.9620.22.odt
of the same NH361F by deciding to and going ahead with the fresh tender
processes. Though the petitioners are different the respondents are the
same, the facts also being exactly the same and even the learned advocates
representing the parties being same we are disposing of these two writ
petitions by this common judgment in order to avoid rigmarole.
2. Heard. Rule in both the writ petitions. Rule is made returnable
forthwith. The learned DSGI waives service for respondent No.1 in both the
writ petitions and the learned Government Pleader waives service for
respondents Nos.2 to 5 in writ petition No.9620/2022 and for respondents
Nos.2 to 4 in writ petition No.11026/2022. At the request of the parties the
matters are being disposed of finally at the stage of admission.
3. The sum and substance of the relevant facts leading to the filing of
these writ petitions can be summarized as under :-
a) Rehabilitation and upgradation of NH361F, a project of the
Ministry of Road, Transport and Highways of the Central
Government (R1) and (R2), is being executed by the Public
Works Department of the State headed by the Chief Engineer
(R3), Superintendent Engineer (R4) and Executive Engineer
(R5). The Chief Engineer (R3) published the tenders on the
instructions of respondent Nos.1 and 2 for two stretchs of
widening and upgradation of 16.2 and 18.5 Kms into two lanes
with paved shoulder carriageway and also 5.5. Kms and 6 Kms
stretches of four lane carriageway.
973.wp.9620.22.odt
b) The work was to be completed within 24 months. Pre-bid
meetings were held on 14.01.2022. Apart from the petitioners
several entities submitted their bids. The estimated cost of the
stretch of road for which the petitioner in Writ Petition
No.9620/2022 had applied was 229 crores whereas in the other
matter it was 212.7 crores. The respective petitioners' bids were
29.99% and 24.83% less than the estimated cost. After financial
bids, technical bides were opened the petitioners were declared
as L1. They furnished requisite bank guarantees. The
respondent Nos.3 and 4 recommended the petitioners' offers to
the respondent Nos.1 and 2 in August 2022.
c) The respondent No.5 in Writ Petition No.9620/2022 called upon
the petitioners therein to furnish justification for completing the
work at less than 29.99% of the estimated cost. The petitioner
furnished the details of his ability to perform the work at that
cost. The explanation was accepted, the report was submitted to
the Superintendent Engineer (R4) who also accorded approval
and it was forwarded to the Chief Engineer (R3) who also
approved it and submitted it to the respondent No.2.
d) By two separate communications dated 29.08.2022 in Writ
Petition No.9620/2022 and dated 30.08.2022 in Writ Petition
No.11026/2022 respondent No.2 informed the respondent No.3
that the stipulation in the tender advertisement regarding
973.wp.9620.22.odt
completion of work in 24 months was incorrect and it ought to
have been 18 months and directed to invite fresh bids for the
same works.
e) Both the petitioners conveyed their readiness and willingness to
complete the work even within 18 months with the same cost.
However, in September 2022 the process was cancelled and
fresh tender notices were published on 07.09.2022 for the same
work.
4. The learned senior advocate Mr. Dhorde for the petitioners at the
outset submitted that in spite of the petitioners having found to be the
lowest bidders, the respondents have aborted the process for an
unsustainable reason. In fact no specific order was communicated to the
petitioners quoting the reasons for cancellation. The respondents being
public authorities it was imperative for them to have communicated the
precise reason for not going ahead with the process to conclude the
contracts. He would refer to the decisions in the following matters :
i. Poddar Steel Corporation Vs. Ganesh Engineering Works and Ors.;
(1991) 3 SCC 273
ii. Jailaxmi Constructions Vs. State of Maharashtra;
2012 SCC OnLine Bom 1127
iii. Rashmi Metaliks Limited Vs. Kolkata Metropolitan Development Authority and Ors.; (2013) 10 SCC 95
iv. Royal Power Turnkey Implements Pvt. Ltd. Vs. Maharashtra Industrial Development Corporation; 2014 SCC OnLine Bom 2884
v. Pankaj Kesara Vs. Andaman and Nicobar Administration ;
2014 SCC OnLine Cal 22708
973.wp.9620.22.odt
vi. Shree Ganesh Construction Vs. State of Orissa;
2016 SCC OnLine Ori 288
vii. Gangadhar Jena Vs. State of Odisha;
2017 SCC OnLine Ori 611
viii. United Contractors Association Vs. State of Orissa ;
2018 SCC OnLine Ori 44
ix. Maharashtra Chess Association Vs. Union of India and Ors.;
(2020) 13 SCC 285
x. Insituform Pipeline Rehabilitation Private Limited V/s New Delhi Municipal Council ; 2021 SCC OnLine Del 3210
xi. BOC India Limited and Ors. Vs. Kolkata Metropolitan Development Authority and Ors.; (WP No.5292/2010 dated 07.05.2010 Calcutta High Court)
5. Mr. Dhorde would submit that contrary to the well settled principles
laid down in the matter of Mohinder Singh Gill and Anr. Vs. The Chief
Election Commissioner New Delhi and Ors.; (1978) 1 SCC 405 the reasons
are now being quoted by the respondents in their affidavit-in-reply which is
impermissible. He would then submit that even according to the guidelines
applicable to the Central P.W.D. projects and the general terms of bidding,
there is no precise clarity as to the period of completion of the work
particularly when the projects involve rehabilitation and upgradation of
mixed stretch of roads where some portion is two lane road where the work
is to be completed within 18 months and a four lane road for which the
period is 24 months. Admittedly, in both the matters, the projects involved
mixed work (16.2 Kms of two lane + 5.5 Kms of four lane in Writ Petition
No.9620/2022 and 18.5 Kms of two lane and 6 Kms of four lane in Writ
Petition No.11026/2022). Mr. Dhorde would, therefore submit that in view
973.wp.9620.22.odt
of such peculiar state of facts, the ground being furnished for cancelling the
tender process on this sole count is too technical.
6. Mr. Dhorde would submit that even both the petitioners even
before cancellation, had communicated their readiness to complete the
project even within 18 months without any escalation in the cost. He would
submit that though it is trite that no post bid negotiations are permissible,
since these are the projects for constructions of roads and when petitioners
are admittedly the lowest bidders, that analogy would not be applicable,
even if they have after initial offer expressed their willingness to complete
the project within 18 months. In the peculiar facts and circumstances when
the work was a mixed work where admittedly a portion of the work even
according to the respondents could be completed within 24 months, this
difference of interpretation would make the condition not a material
condition or essential terms. In support of his submission he would refer to
the judgment in the matter of Rashmi Metaliks Ltd.(supra). Mr. Dhorde
would also refer to the CVC circular which enables negotiations in
exceptional circumstances with L1 lowest tenderer in the work/supply
orders where the Government has to make the payment. He would also
emphasize on the fact that the bid capacity of the petitioners to complete the
work even within 18 months is much more.
7. As an appendage to these submissions Mr. Dhorde would also
emphasize the fact that when the petitioners bids would cut even the
estimated cost by around 25% to 30%, it would be in the public interest
973.wp.9620.22.odt
inasmuch as the Government would spend much less than the estimated
cost. As against this, he would submit, when this process had begun almost
10 to 11 months back, any fresh invitation to offer in all probability would
escalate the cost of construction, increasing the burden on the public
exchequer. Besides the petitioners would lose edge inasmuch as the process
has been aborted at the fag end making everybody aware about their offer
to complete the projects at such a lesser cost which would cause a serious
prejudice to the petitioners. He would, therefore, submit that the
respondents have not acted in fair manner and have decided to go ahead
with the fresh tender process undermining the public interest that too on an
untenable ground.
8. Learned DSGI Mr. Talhar would at the outset begun with the
argument that there is no concluded contract. It was merely an invitation to
offer and it would be the prerogative of the respondents to accept or refuse
the offer. The petitioners would have a right only in the case there was a
concluded contract. That being not the state of affairs. The respondents are
not under any contractual obligation. Mr. Talhar would then raise the issue
regarding clause 6.1 of the tender document restricting the jurisdiction to
decide any dispute to the Delhi High Court. He would submit that the
petitions in this Court are not maintainable in view of such a stipulation. He
would submit that it is the prerogative of the respondents expressly
stipulated in clause 2.16.1 to annul the bidding process. He would further
submit that contrary to the guidelines issued by the Ministry the period for
973.wp.9620.22.odt
construction of the project was stipulated as 24 months instead of 18
months. Realizing the mistake a fresh tender has been floated. A change
post negotiation altering the condition to complete the project would
constitute a material alteration. There is no discrimination. It was always
open for the petitioners to participate even in the fresh tender process. No
mala fides have been attributed. The decision is based on technical reasons.
The stipulation as to the period is strictly based on the technical note of the
Ministry and this Court cannot embark upon and decide the correctness or
reasonableness of the stipulation. Since it is a matter touching completion
of a public work involving some special knowledge, this Court cannot sit in
appeal to scrutinize the decision of the technical expert committee. He
would rely upon the following decisions to buttress his arguments :
i. Rajasthan Co-Operative Dairy Federation Vs. Maha Laxmi Mingrate Marketing Service Private Limited ; 1966 DGLS (SC) 1429
ii. Laxmikant and Ors. Vs. Satyawan and Ors.; (1996) 4 SCC 208
iii. South Delhi Municipal Corporation Vs. Ravinder Kumar and Anr.;
2015 DGLS (SC) 961
iv. State of Jharkhand and Ors. Vs. CWE Soma Consortium ;
2016 DGLS (SC) 706
v. Bharat Coking Coal Limited and Ors. Vs. AMR Dev Prabha and Ors.;
2020 DGLS (SC) 318
vi. Agmatel India Private Limited Vs. Resoursys Telecom and Ors.;
(2022) 5 Supreme 362
vii. N.G. Projects Limited Vs. Vinod Kumar Jain and Ors.;
2022 DGLS (SC) 324.
viii. Omassery Labour Contract Co-operative Society Omassery P.O. Vs. Mukkam Municipality Mukkam ; (WP (C) No.3228/2022)
973.wp.9620.22.odt
9. The learned Government Pleader would submit that the respondents
Nos.3 to 5 are merely implementing the project of the respondents Nos.1
and 2. The ultimate decision to accept the offers or to go for a fresh tender
fully rests with them. The scope for judicial review in such matter is very
limited. The circumstances do not warrant any interference in the on going
process.
10. The rival submissions now fall for our consideration.
11. At the cost of repetition we begin with the observation that so
far as the facts are concerned there is not much of a dispute. In the
invitation to offer the period for completion of work was stipulated as 24
months pursuant to which the offers were received. The petitioners were
the lowest bidders and had quoted almost 30% and 25% less than the
estimated cost, respectively. No dispute has been raised either in their
capacity to complete the work at this less cost and the sole reason being
relied upon by the respondents for going for a fresh tender is the stipulation
as to the period of completion of work. For that matter even there is no
dispute that the respondents are implementing a project where as per the
technical note of the Ministry dated 05.03.2019 there is stipulation as to the
period for completion of work for construction of highways depending upon
the width and the length of the road. Admittedly, it was a project of the
Central P.W.D. and the work was to be completed in accordance with the
permission granted by the respondent No.2 with the approval of the
competent authority. The State PWD was supposed to implement the project
973.wp.9620.22.odt
strictly in accordance with the communication vide letter No.1275 dated
31.01.2022 and the bids were supposed to be invited based on standard RFP
and EPC documents of the Ministry dated 05.03.2019.
12. Normally this Court cannot interfere with the view taken by the
tender inviting authority or indulge in the process of interpretation of the
terms which essentially has to be left for the author of the tender document
as has been laid down in the matter of Agmatel India Pvt. Ltd. (supra)
wherein with respect the principles have been succinctly laid down while
considering the scope of judicial review in tender matters.
13. This Court has its inherent limitations in going into the
technical aspect and it would not be proper to scientifically scrutinize
justification for the period for implementation of the work, whether it
should be 18 months or 24 months. However, going by the guidelines, for a
road up to the length of 50 Kms stretch for laying two lanes with paved
shoulder carriageway the period stipulated for completion of work is 18
months whereas for the roads comprising of four lanes the period is 24
months. However in the peculiar matters in hand, admittedly, each work
comprises of two different stretches a part of the portion may be major of
around 60% to 65% is a two lane road and the rest is a four lane road. It is
perhaps because of this peculiar state of affairs, even there seems to be a
difference of opinion in the respondent Nos.1 and 2 on the one hand and the
respondent Nos.3 to 5 on the other.
14. It can be seen from the papers that the respondent Nos.1 to 3
973.wp.9620.22.odt
had scrutinized the aspect and even attempted to justify their interpretation
and the stand of stipulating 24 months in the bid document as the period for
completion of work. For that matter, irrespective of the stand being taken in
the affidavits-in-reply filed on behalf of respondents, even during pendency
of the petitions Mr. Dhorde tendered across the bar a communication inter
se between the respondents demonstrating that even now some of the
respondents are of the view that the projects can be completed within 24
months even by following the guidelines of the Ministry. It is not that such
an attempt has been made belatedly. Even before filing of the petitions
there has been a communication inter se between the respondents, wherein,
some of them tried to justify the period for completion of project as 24
months. It is in view of such a peculiar state of affairs, we have been called
upon to consider the petitions questioning the decision of the respondents to
go for a fresh tender.
15. As has been observed earlier we have inherent limitations in
entering into this debate. The fact remains that as per the guidelines of the
Ministry there is a stipulation as to the period of completion of work but
conspicuously, we are concerned that the guidelines do not contemplate a
situation where it is a mixed work, where a portion of the road is to be
constructed within 24 months whereas the remainder of it is expected to be
completed in 18 months. Be that as it may, there is every room to believe
that it is a subjective satisfaction of the authorities to go ahead and decide
the issue more so involving construction of a public project and it can be
973.wp.9620.22.odt
said that the reason for abortion of the project is too technical for this Court
to step in and scrutinize the action of the respondents.
16. Admittedly, the petitioners were never expressly communicated
with the reasons cancelling the tender process. It appears that they only
learnt about the aforementioned being the ground for the respondents to go
for a fresh bidding process. However, irrespective of this aspect, admittedly,
both the petitioners had expressly stated and informed the respondents their
willingness to go ahead and complete the project as per their interpretation
within 18 months without escalation of the cost. This certainly cannot be
said to be a post tender negotiation inasmuch as, the government was to
spend for the project and was not to earn something. The petitioners are
the lowest bidders who though had initially offered to complete the work
within the period of 24 months stipulated in the tender document but in
view of the supervening events have expressed their willingness to complete
the same work within 18 months, and more importantly the respondents
have not formed any opinion by resorting to any inquiry regarding
petitioners inability to complete the work within 18 months. The decision of
the respondents to refuse to concede to the petitioners' fresh offer to
complete the work even in 18 months is clearly an arbitrary decision which
potentially would have the tendency to burden the public exchequer.
Already 8 to 10 months have lapsed. Factoring the inflation, in all
probability, going for a fresh tender merely because of this technical defect
which can be easily cured by accepting the petitioners' fresh offer to
973.wp.9620.22.odt
complete the project even in 18 months at the same cost offered by them is
nothing but an arbitrary and capricious decision and would lead to a loss to
the public exchequer. Besides, as mentioned herein above, as it is the offer
of the petitioners is less than the estimated costs by 30% to 25% which
would save another 70 to 80 crores for each project.
17. The submission of the learned DSGI and the decision cited by
him regarding the rule being to desist from any post-bid negotiation would
not came into play when the Government is to pay the money for the work
to be performed when the negotiation is with the lowest bidder. Such
negotiations are not justifiable when the Government is to receive the
money. It is in this sense that the decisions quoted herein above by the
learned DSGI will have to be appreciated. The negotiation in the facts and
circumstances is only for performing the work in a lesser period and not for
increasing the period of performance which would have been impermissible.
18. In the peculiar facts and circumstances of the matters in hand
we are merely pointing out that even the respondents inter se have a
different opinion as to what should have been the period for completion of
the work. We have pointed out that the guidelines do not take into
consideration a peculiar circumstance where a part of the project is to be
completed in 18 months and the remainder to be completed in 24 months.
The situation is certainly susceptible to a difference of opinion amongst the
authorities themselves. Since it is a matter of rehabilitation and
improvement of roads, when the petitioners have also now expressed their
973.wp.9620.22.odt
willingness even before filing of the petitions to complete the work within
18 months, in our considered view we are not embarking into any decision
touching the technical aspect. So the fetters on the powers of this Court in
view of catena of judgments in the matter of Tata Cellular Vs. Union of
India; (1994) 6 SCC 651, Afcons Infrastructure Ltd. Vs. Nagpur Metro Rail
Corporation Ltd.; (2016) 16 SCC 818 and M/s. N.G. Projects Limited Vs
M/s. Vinod Kumar Jain & Ors.; (Civil Appeal No.1846 of 2022 arising out of
SLP (c) No.2103/2022 dated 21.03.2022) would not be applicable to the
peculiar facts and circumstances of the matters in hand.
19. True it is that the petitioners have not been able to expressly
attribute any mala fides for the respondents in aborting the process.
However, in our considered view the facts and circumstances discussed
herein above are peculiar enough and we have demonstrated that the
petitioners being ready to complete the work even in 18 months, avoiding a
possible loss to the public exchequer could be the decisive circumstances
even in the absence of any specific allegations regarding mala fides of the
respondents.
20. It is not a matter of any deviation from the explicit terms of the
invitation to offer to work within period of 18 months as against 24 months.
The decision in the matter of Bharat Coking Coal Limited (supra) a minor
deviation from explicit terms of the notice inviting tender was held to be not
sufficient in itself in the absence of mala fides to set aside the tender at the
behest of unsuccessful bidders. We do not intend to and are not sitting in
973.wp.9620.22.odt
appeal to judge the propriety of the decision of the respondents to go for a
fresh bid but at the same time we cannot turn a blind eye when the facts
and circumstances discussed herein above are so peculiar and the decision of
the respondents has the potential of burdening the public exchequer.
21. The submission of the learned DSGI that there is no concluded
contract and the petitioners' offer having not been accepted there being no
privity of contract is a submission too naive to accept. When these are the
matters involving public authorities, any decision of theirs can be examined
to ascertain if the decision being taken is arbitrary or otherwise more so
when it has the tendency of burdening the public exchequer. We therefore
discard the submission of Mr. Talhar that in the absence of any concluded
contract the petitioners cannot be heard.
22. As far as the submission of Mr. Talhar regarding stipulation in
the notice inviting tender and the other annexures restricting the jurisdiction
to the Delhi High Court is equally untenable in law. This being a High Court
exercising powers under Article 226 of the Constitution of India, the parties
could not have by agreement excluded its jurisdiction and power as has
been laid down in the matter of Maharashtra Chess Association (supra).
23. To sum up, the decision of the respondents to abort the process
of tender wherein the petitioners were the successful L1 bidders on the sole
ground that the notice inviting tender stipulated 24 months as the period for
completion of the work instead of 18 months and even when the petitioners
expressed their readiness and willingness to complete the work at the same
973.wp.9620.22.odt
cost offered by them which does not suffer from the sin of post tender
negotiations, the decision of the respondents is clearly arbitrary and would
lead to a loss of public money. The cases are fit to be interfered with.
24. Both the petitions are allowed. The fresh tenders issued by the
respondents are quashed and set aside. The respondents are directed to
resume and complete the tender process wherein the petitioners are
participating but with a rider that the petitioners shall be bound to complete
the works within 18 months irrespective of the stipulation in the notice
inviting the offers.
25. Rule is made absolute in both the petitions in above terms.
(Y.G. KHOBRAGADE, J.) (MANGESH S. PATIL, J.) habeeb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!