Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kiran Nanik Motwane And Anr vs Uday Indukumar Jasani And 16 Ors
2022 Latest Caselaw 4372 Bom

Citation : 2022 Latest Caselaw 4372 Bom
Judgement Date : 26 April, 2022

Bombay High Court
Kiran Nanik Motwane And Anr vs Uday Indukumar Jasani And 16 Ors on 26 April, 2022
Bench: R. I. Chagla
                                                       NMS-1450-2019.DOC




 jsn&spk

       IN THE HIGH COURT OF JUDICATURE AT BOMBAY
          ORDINARY ORIGINAL CIVIL JURISDICTION

                  NOTICE OF MOTION NO.1450 OF 2019
                                 IN
                         SUIT NO.843 OF 2019

 Kiran Nanik Motwane & Anr.                                   ...Plaintiffs
       Vs.
 Uday Indukumar Jasani & Ors.                              ...Defendants


 Mr. Vishal Kanade and Mr. Anirudh Hariani, Mr. Virendra Pereira
       and Aneesha Munshi i/b. Divya Shah Associates for the
       Applicants / Plaintiffs.
 Mr. Ravi Kadam, Senior Counsel, Mr. Rohan Kadam with Mr.
       Sanjay Kadam, Mr. Sanjeel Kadam, Ms. Sayli Rajpurkar,
       Nitisha Lad i/b. Kadam & Co. for the Defendant Nos.1 and 2.
 Mr. A.Y. Sakhare, Senior Advocate with Ms. Pooja Yadav, Ms.
       Shilpa Redkar and Mr. Rohan Mirpuri for Defendant Nos.3
       to 8 - MCGM.
 Dr. Birendra Saraf, Senior Advocate, Aseem Nafade, Anuj Narula
       and Tarang Jagtiani i/b. Jhangiani Narula and Associates for
       the Applicant in Interim Application No 463 of 2021.
 Mr. Yuvraj Choksy, Pragya Dahiya i/b. Khaitan & Co. for
 Defendant Nos.12 and 13.

                               CORAM:    R.I. CHAGLA, J.

 JUDGMENT RESERVED ON                    21ST MARCH, 2022.

 JUDGMENT PRONOUNCED ON                  26TH APRIL, 2022.
 ORDER

1. By the present Notice of Motion, the Applicants /

Plaintiffs have sought an interim order and injunction restraining

NMS-1450-2019.DOC

Defendant Nos.1 and 2, their employee, agents and servants, or any

person claiming by or through them, from carrying out construction

of any kind on Plot No. A (being old Plot No.435A corresponding

to CTS Nos. E/323 (part) and E/325 collectively admeasuring

795.176 square meters or thereabouts). Further injunction is sought

by the Applicants / Plaintiffs restraining Defendant Nos.1 and 2

from allotting flats and / or executing any agreements, arrangements

or understandings with third parties, inducting them into the flats

proposed to be constructed in the building on Plot No. A (being old

Plot No.435A corresponding to CTS Nos. E/323 (part) and E/325

collectively admeasuring 795.176 square meters or thereabouts.

2. Consequential relief has also been sought against

Defendant Nos.3 to 8 from issuing occupation certificate, in part or

full to permit the prospective purchasers to occupy any unit in the

building alleged to be illegally constructed on Plot A. Relief of

appointment of Court Receiver has been sought and licensed

surveyor as well as certain disclosures.

The brief background of facts is as follows:-

NMS-1450-2019.DOC

3. One Motwane Private Limited ("MPL") was owner of

plot of land bearing CTS Nos. E/323, E/324 and E/325 situated and

lying at 14th and 15th Road, Khar (West), Mumbai 400 052 (larger

property). MPL was company owned by the Motwane family.

4. On 31st March, 1990, the larger property was

notionally divided and conveyed to the different members of the

Motwane Family as under:-

(i) Plot A admeasuring 795.176 Square meters was conveyed

to Late Hardevi Motwane and Defendant No.9 inclusive of 15%

proportionate recreational ground (RG) area;

(ii) Plot B admeasuring 1887.357 square meters was

conveyed to the Plaintiffs, Defendant No.14, the Late Girdhar

Motwane and the late Maina Nanik Motwane.

(iii) Plot C admeasuring 793.263 Square meters was

conveyed to Defendant Nos.9 and 11.

NMS-1450-2019.DOC

5. The Plaintiffs are the owners and residents of Plot B.

Defendant Nos.1 and 2 are the Developers who are developing Plot

No. A.

6. Defendant No.1 was granted an IOD to develop Plot A

on 17th December, 2009. By the year 2013, Defendant No.1's

construction had reached stilt + 2 Podiums + 10 storeys. As of

2019, the construction had reached 12th storey out of the proposed

stilt + 2 Podiums + 14 storeys.

7. The Plaintiff addressed a notice to the Municipal

Commissioner on 24th November, 2013 through their Advocates

wherein it is alleged that development plan had been submitted by

Defendant No.1 on the basis of larger property instead of plot A

alone. Though the developer of Plot A was to keep a minimum

distance of 1.5 meters from the shared perimeter / boundary of Plot

B, Defendant No.2 had kept open space around the new building at

Plot A but had calculated the said space from the walls of the

bungalow of Plot B and not from the common perimeter / boundary

line between Plots A and B on the North and West side. The

developer of Plot A had built a podium upto the boundary line

NMS-1450-2019.DOC

which according to Plaintiffs, further open space was required to be

kept for any future redevelopment of Plot B. It was thus the

contention of the Plaintiffs that minimum open space had not been

kept. Further the Developer had failed to ensure provision of 15%

RG area on Plot A. The Plaintiffs have claimed that they were not

aware of the construction until recently when they claimed to have

learnt that the Developer had constructed a podium column at the

perimeter between Plot A and B.

8. It is the Plaintiffs case that though in September, 2009

the Plaintiffs had learnt that the then owners of Plot A had

negotiated with Defendant No.2 of redevelopment of Plot A and

that the Plaintiffs also learnt that owners for Plot No. A had entered

into agreement dated 16th February, 2010 with Defendant No.2 for

the said purpose, it was only around August, 2013 that the Plaintiffs

and Defendant No.14 observed that the Defendant Nos.1 and 2 had

carried out the aforementioned construction of podium column

touching the common perimeter between Plot A and B without

leaving requisite open space as provided under Development

Control Rules ("DCR"). The Plaintiffs and Defendant No.14 had

appointed their architect to conduct a site inspection to assess the

NMS-1450-2019.DOC

situation and submit report. It was only upon receiving a report

dated 18th November, 2013 from their chartered architect that the

violations of DCR which the Defendant No.2 had committed was

brought to the knowledge of the Municipal Commissioner on 24th

November, 2013.

9. In 2015, Defendant No.1's architect applied to the

Municipal Commissioner for loading fungible FSI on the plot and

for condonation of deficiencies.

10. Pursuant to the application of Defendant No.1, the

Municipal Corporation of Greater Mumbai ("MCGM") published a

report dated 14th November, 2015 assessing plans submitted by

Defendant No.1. This report recorded that there was no imbalance

of FSI and necessary RG area had been deducted within Plot A. The

Commissioner had issued directions dated 19th May, 2015 to

recalculate open space from notional boundaries between Plot A

and Plot B in the North and West sides.

11. Pursuant to the Commissioner's directions for

recalculation of open spaces, there was a recalculation of open

NMS-1450-2019.DOC

space by MCGM from notional boundary between Plot A and Plot

B in the North and the West and upon which MCGM observed that

there was open space deficiencies with the podium touching the

boundary only at one point. However, given due consideration of

the fact that the plot being odd and irregular shaped, the MCGM

rendered it fit for regularization under 64 B of DCR, 1991.

12. The MCGM further recommended that a

registered undertaking be obtained from the developer of Plot A to

disclose the fact to the prospective buyers that the building had

deficient open spaces and waiving any right to object to the

proposed development on the adjacent plot. The future occupants of

Plot A would also not object to the proposed development of Plot

with deficient open space. The Fire Officer has granted his no

objection to the development upon being satisfied that the fire

safety requirements were met. The report of the MCGM was

"approved as proposed" by the Commissioner.

13. The Plaintiffs were aggrieved qua the

reservation of RG area and the open space deficiencies between

NMS-1450-2019.DOC

Plot A and Plot B would impair their commercial rights to

development.

14. It is to be noted that on 14th January, 2014, the

MCGM had issued stop work notice to Defendant No.2 alleging

unauthorized construction.

15. Thereafter, the MCGM upon its report dated

14th November, 2015 being approved and proposed by the

Commissioner had issued revised IOD on 22nd June, 2018 for

construction upto the 12th floor and on 26th October, 2018 issued a

commencement certificate for construction upto the 12th floor.

16. The Plaintiffs being aggrieved by the IOD

granted by the MCGM and IOD granted by the Commissioner filed

the present Suit on 5th March, 2019. The two main contentions in

the present Suit were that the first and second Defendants were

illegally attempting to usurp the rights of the owners of Plot B by

failing to keep a reservation of 15% RG area on Plot A apart from

the fact that plan which had been submitted by Defendant Nos.1

and 2 were of the larger property and thus RG area was being

NMS-1450-2019.DOC

considered of the larger property. Next grievance of the Plaintiff

was that the first and second Defendants were liable to keep

minimum 1.5 meter open space from the shared perimeter /

boundary between Plot A and Plot B. However, Defendant Nos.1

and 2 had not left adequate open space of 1.5 meters on North and

West side of Plot A and had incorrectly calculated open space from

the walls of bungalow on Plot B instead of from common boundary.

The Plaintiffs contention was that they would suffer commercial

loss since they would be obliged to keep further requisite space on

their Plot B which they wished to develop.

17. It is the Plaintiffs contention that Defendant

Nos.1 and 2 had illegally submitted plans for approval with respect

to the larger property and not the subject Plot A which they were

developing though the larger property had been sub-divided. Thus

instead of considering Plot A's development, the MCGM and the

Commissioner considered the development potential of the larger

property.

18. The Plaintiffs had moved a Notice of Motion

No.1450 of 2019 for ad-interim relief. This Court had prima facie

NMS-1450-2019.DOC

found that the Defendant Nos.1 and 2 had failed to keep requisite

open space on the North and West side on the proposed

development of Plot A near the boundary line shared with Plot B.

There was inadequate open spaces left by Defendant Nos.1 and 2

and that podium had been constructed on the West side of Plot A

touching boundary between both plots. That Defendant Nos.1 and 2

had submitted plans for redevelopment on basis of larger plot which

included plot B, though they had right to only use 795 square

meters of plot A. This Court had granted ad-interim relief in terms

of prayer clause (a) and (b) of the Interim Application upon

considering that there was hardly any space left by the Defendant

Nos.1 and 2 in Plot A for fire engine to pass between the building

coming up and boundary of plot A. This Court had considered that

if the prospective purchasers had investigated the title of Defendant

No.2 and inspected the site, they would know what Defendant No.2

was indulging in may not be wholly legal. Further, those people

who are prejudiced, may claim for return of money or

compensation. Accordingly, the first and second Defendant by the

ad-interim injunction order passed in terms of prayer clauses (a) and

(b) were restrained from carrying out further construction and

selling more flats to third parties. Defendant No.1 had already sold

NMS-1450-2019.DOC

flats to certain purchasers including the intervenors in the Interim

Application (L) No.26802 of 2021.

19. The Defendants accordingly took a decision to

revise the building plans to meet the Plaintiffs allegations in the

Plaint. Under the revised plan, the Defendant Nos.1 and 2 proposed

to maintain open space of 1.5 meter in the North and West along the

boundary shared with Plot B. For creating the space, the existing

portion of the podium touching the West boundary line between

Plot A and Plot B was to be demolished. Defendant Nos.1 and 2

continued to retain the RG area of the proposed building within Plot

A's area. It had been noted by the MCGM in its report in 2015 that

RG area had been deducted from the gross area of Plot A and not

from the larger property. Further, six meter open space would be

maintained on the southern side of the plot for ingress / egress of

firefighting tenders / vehicles. In addition fireman's lift would be

installed which would open at requisite mid landing points on the

staircase.

20. Defendant Nos.1 and 2 moved Defendant No.8

(Fire Officer) for his assessment as to whether revised plans met

NMS-1450-2019.DOC

fire safety norms and assured fire safety. On 7th July, 2020, the Fire

Officer issued no objection in respect of the revised plans and

certified that it assured fire safety. The Fire Officer took due notice

that under the MCGM Circular dated 6th August, 2019, the

provisions of 6 meters open space on the one side for a building

upto 70 meters in height was permissible, if there was a provision

for fire men's lift in the building. This was proposed in the revised

building plan of plot A. Accordingly, the Fire Officer accorded

satisfaction that provisions of 6 meters open space on the South side

of Plot A for ingress / egress of firefighting tenders and the

provision of a separate fire men's lift assured adequate safety from

fire and / or fire related hazards.

21. The Defendants put up their revised plans before

MCGM for their approval. In view of the MCGM expressing its

unwillingness to consider these plans on the premise that the Single

Judge's ad-interim Order prohibited them from processing the

revised plans, Defendant Nos.1 and 2 took out Interim Application

No.2439 of 2020 seeking directions against the MCGM to process

their revised plans. An order was also sought for vacation of the ad-

interim order. This Court by order dated 13th August, 2020

NMS-1450-2019.DOC

observed that there was no restraint against the Municipal

Authorities from considering the revised plans and deciding the

application.

22. Mr. Sakhare learned Senior Counsel appearing

for the MCGM had stated that the Officer of the MCGM will decide

the application in accordance with the applicable norms / law at the

earliest possible. All contentions were kept open. The first and

second Defendants were granted liberty to renew their applications

in terms of prayer clause (b) should the Municipal Authority decide

their application favourably.

23. On 24th August, 2020, the Defendant Nos.1 and

2 submitted revised development plan to Municipal Corporation.

The Defendant's architect has submitted indicative report for

concessions to the MCGM. The major amendment to the plans as

per the revised plans were demolition of part portion of existing 2

level podiums on the south and west of Plot A in order to provide 6

meter clear open space. Further, demolition of part podiums on west

and north side of Plot A to provide minimum 1.5 meters open space

in those places. The refuge area was to be provided on staircase

NMS-1450-2019.DOC

mid-level now relocated within building line at 6th and 13th floor,

separate Fire Man's lift with smoke check lobby proposed at mid-

landing level in the external staircase. Further, Defendant's

Architect sought condonation of open space deficiencies as well as

joint open space deficiencies. The Defendant's architect sought

condonation in view of the demonstrable hardship as under:-

a) The proposal was for redevelopment of an existing

building;

b) Vertical construction was not possible beyond height

restriction issued by the Civil Aviation Authorities.

       c)     The plot was odd shaped;

       d)     In order to make the project financially viable, it was

              necessary to consume the admissible FSI;

       e)     The building had already come upto 12th floor.




24. Pursuant to architect's certificate as well as

revised development plans put up by Defendant Nos.1 and 2, the

MCGM issued a '4C' report. The report recorded that:-

a) The MCGM had scrutinized the plans through the

NMS-1450-2019.DOC

Auto DCR system;

b) Thereafter, a site visit had been carried out to assess

the case for hardship.

c) Pursuant to these steps, the MCGM found that

hardships cited by Defendant No.2 were justified;

d) The MCGM further noted that the revised plans had

been certified by the Fire Officer for fire safety.

e) Measures proposed by the Architect for

neighbourhood safety, structural safety and health

safety and that the same could be taken care of by

appointing structural engineer, site supervisor and

licensed plumber.

25. The Commissioner approved the revised plans

on 6th November, 2021 by writing the remark "approved as

proposed".

26. On 20th November, 2020, the Defendant Nos.1

and 2 filed Interim Application No.6700 of 2020 for orders that

effectively seek vacation of the ad-interim order.

NMS-1450-2019.DOC

27. The Plaintiffs thereafter amended their Plaint

and took out Interim Application No.463 of 2021 for reliefs

restraining the Defendants from acting upon and / or implementing

the revised plans and the latest 7th July, 2020 Fire No Objection

Certificate (NOC) and all preceding NOC's. Further, injunctive

relief was sought restraining Defendant Nos.1 and 2 from creating

any third party rights pursuant to the Revised Plans.

28. A preliminary objection has been raised as to the

maintainability of the Suit by the MCGM in the Written

Submissions filed by them dated 10th January, 2022. Mr. Sakhare,

learned Senior Counsel for Defendant Nos.3 to 8 - MCGM has

submitted that the objection to the maintainability of the suit is in

view of the bar under Section 149 of the MRTP Act. This bar will

apply to the challenge in the present Suit which is to the permission

granted by MCGM in its capacity as planning authority under the

MRTP Act 1966. The Civil Court does not have jurisdiction to go

into such challenge as raised in the present Suit. Reliance is placed

on the decision of this Court in Satish Vs. Dr. Gopal1 in this context.

Mr. Sakhare has further submitted that the Suit is not maintainable

1 2015(5) Mh.L.J.463

NMS-1450-2019.DOC

in view of lack of statutory notice mandated under Section 527 of

the MMC Act, 1988. In this context, he has placed reliance on the

decision of this Court in Noor Mohd Vs. Mahi Housing and

Development Board2.

29. The preliminary challenge as to the

maintainability of the Suit has been dealt with by the Plaintiffs and

it is their contention that these objections are raised for the first time

and were not raised in the Interim Application No.2439 of 2020

filed by Defendant Nos.1 and 2. Thus the MCGM has waived their

objections on maintainability of the present Suit by their conduct.

The MCGM has neither at the ad-interim stage raised the

maintainability issue not did they file an application under Order 7

Rule 11 of the Code of Civil Procedure, 1908 for rejection of the

Plaint on this ground. The non-compliance of Section 527 of the

MMC Act, 1988 is not an inherent defect which takes away the

jurisdiction of this Court. Further, this Court had in Kishore S/o.

Ramalu @ Rambhau Telang vs. Municipal Commissioner, Nagpur

& Ors.3 held that despite the exclusion of jurisdiction of the Civil

Court under Section 149 of the MRTP Act, the grievance in relation

2 2014(1) Mh.L.J 92.

 3       2015 SCC OnLine Bom 3168






                                                             NMS-1450-2019.DOC




to failure to comply with statutory provisions can be examined by

the Civil Court. It is the further contention of the Plaintiffs that this

Court has held that the Suits required to be filed after one month

notice to the MCGM and / or within six months next after the

accrual of cause of action under Section 527 of the MMC Act does

not apply in case of acts of MCGM which have been done de hors

the provisions or in contravention of MMC Act. In support of this

contention reliance has been placed on decision of this Court in

Shraddha Associates, Pune & Anr. Vs. St. Patrick's Town CHS Ltd.

& Ors.4. The Plaintiffs contentions in the Plaint are that the MCGM

has acted de hors the provisions of the Act and thus the lack of

notice in writing of one month and / or the Suit being commenced

within six month next after the accrual of the cause of action

contemplated under Section 527 offers no assistance to the MCGM.

30. The Defendants have distinguished the decision

of this Court in Kishore (Supra) on the facts arising in that case

where notice under Section 53 of the MRTP Act was issued to

remove the unauthorized construction but time prescribed therein

was less than 30 days statutory period mandated under the Act.

 4       2003(2) Mh.L.J. 219.






                                                              NMS-1450-2019.DOC




Accordingly, this Court had held that it had jurisdiction to entertain

the Suit, since the notice was a nullity for giving less time for

removing the unauthorized development then the period prescribed

within the Act. Thus this case offers no assistance to the Plaintiffs

as it is based on the general principal of law that notwithstanding

expressed statutory bar, the Court would have jurisdiction to

entertain the Suit, wherein an action taken is nullity in law and / or

without jurisdiction. In the present case the decision of the

Commissioner of MCGM is not a nullity since he has acted within

the jurisdiction conferred under regulation 6(B) of the DCPR. The

decision relied upon by the Plaintiffs in Shraddha Associates

(Supra) has also been distinguished by the Defendants. It is

contended that the Commissioner has acted dehors the provision of

the Act or contrary thereto. In the present case the Corporation has

acted in accordance with the DCR, DCPR and the extant law.

Therefore, this decisions has no applications.

31. Prior to considering the issue of maintainability

of the Suit, it would be necessary to refer to the other submissions

of the Plaintiffs as well as the Defendants.

NMS-1450-2019.DOC

32. Mr. Kanade, learned Counsel appearing for the

Plaintiffs has submitted that the impugned plans which include the

original sanctioned plans and revised plans submitted by Defendant

Nos. 1 and 2 to the Municipal Corporation of Greater Mumbai

contain congenital defects which cannot be cured or condoned and

are thus, ex facie illegal. He has submitted that the Defendant Nos.

1 and 2 despite knowing that the subject plot A was to be developed

and which subject plot admeasured 795 sq.mtr., submitted plans for

a multi storey building on the basis that they were to develop the

larger property admeasuring 3475 sq.meter. This was without the

knowledge of the Plaintiffs, as the Defendant Nos. 1 and 2 neither

informed the Plaintiffs nor obtained consent of the Plaintiffs for

submitting the plans showing the entire layout of the larger

property. It is an admitted position that the Defendant Nos. 1 and 2

proceeded with construction even beyond the commencement

certificate which led to issuance of stop work notice issued by the

MCGM in the year 2014.

33. Mr. Kanade has further submitted that had the

1st and 2nd Defendants sought permission on the basis of the

subject plot A alone, then the structure of the nature of the subject

NMS-1450-2019.DOC

building, which has been carried out, would never have been

permitted. The original plans, if they had been prepared in respect

of the subject plot A, would not be compliant either with the

provisions of DCR 1991 or DCPR 2034.

34. Mr. Kanade has submitted that Regulation

37(31) provides for podium to be permitted in plot admeasuring

1000 meters or more. Since, the subject plot A admeasured only

795.176 sq. meters, the podium could not have been permitted to be

erected in the subject plot A. He has submitted that an illegal

building has been constructed on subject plot A which is almost

touching the common boundary between plot A and plot B on the

northern and western sides. Had the plans been submitted only in

respect of Plot A, it would never have been sanctioned as it would

be de hors the open space requirement of Regulation 41 of the

DCPR 2034 and fire safety requirements of Regulation 47 of DCPR

2034.

35. Mr. Kanade has further submitted that since the

original plans submitted were on the basis of the larger property,

consent/NOC of the neighbouring plot owners (including Plaintiffs

NMS-1450-2019.DOC

and other co-owners of plot B and plot C) was necessary. In fact

even though NOC/consent of co-owners of plot B and C was

necessary, MCGM while sanctioning the original plans stated that

the proposal can be processed further in accordance with law,

without insisting on undertakings / NOC from the complainant.

However, this was made subject to verification of the facts that the

sanctioned proposal does not affect or imbalance the FSI of the

adjoining plot i.e. notionally sub-divided plot B owned by the

complainant i.e. Plaintiff No. 1 and provided 15% RG in proportion

to the plot under development does not in any way create any

imbalance in the RG of the portion owned by the Complainant.

Thereafter, the Municipal Commissioner has stated on the same file

that "We will go by the opinion of the law officer as given in the

matter. However, the open spaces shall be recalculated from the

boundaries of the notionally divided sub-plot." Inspite of the

directions of the Municipal Commissioner, neither was the NOC of

the co-owners taken nor were the open spaces recalculated from the

boundaries of the notionally divided sub-plot. In another report

dated 7th November 2015, the MCGM stipulated that Defendant

Nos. 1 and 2 were required to submit a registered undertaking to

disclose the fact to prospective buyers that the building had

NMS-1450-2019.DOC

deficient open spaces and that the developer/occupants would not

object to development on the adjacent plot with deficient open

space. However, this has not been done by Defendant Nos. 1 and 2.

This can be seen from the proforma agreement for sale, uploaded by

the Defendants on the MahaRERA website which does not contain

such disclosure or stipulation.

36. Mr. Kanade has made submissions on the

revised plans, namely that the revised plans do not address or

alleviate the objections of the Plaintiffs. He has submitted that from

a comparison of the original sanctioned plan and the revised plan, it

becomes evident that the subject building remains in the same place

on the subject plot A and there are no changes in the open area on

the Northern side and only minimal changes on the western side. He

has submitted that the Municipal Corporation of Greater Mumbai

themselves acknowledged in the 4C Report that the original plan

had congenital defects. Therefore, it is impossible to rectify the

illegalities and deficiencies without demolishing the entire structure

due to the illegal construction on subject plot A of the Plaintiffs.

There is a fetter on the Plaintiffs' right to develop Plot B in the

future. This is due to lack of sufficient open spaces, as the building

NMS-1450-2019.DOC

on the subject Plot A is almost touching the boundary between Plot

A and Plot B.

37. Mr. Kanade has further submitted that the

construction of a mechanised car parking on the south - side of the

Plot A does not provide, "clear open space" as contemplated under

Regulation 47(1)(B)(a) of DCPR 2034. The structure of the car

parking space will prevent fire engine access to the end of the

subject plot and is thus, a fire hazard and de hors the provisions of

DCPR 2034.

38. Mr. Kanade has highlighted from the plans

which include the original plans and the revised plans that clearly

there is deficient open space at the northern and western side of plot

A and that the building constructed on the subject plot A is at the

distance of 1.5 meters of plot B, whereas the extant law

contemplates for such a building that 9 meters clear open space be

left on one side accessible from the road for fire safety under

Regulation 47 of the DCPR 2034 and 6 meters open space on all

sides and the rear under Regulation 41 of the DCPR 2034.

NMS-1450-2019.DOC

39. Mr. Kanade has submitted that the MCGM

failed to consider the objections raised by the Plaintiffs to the

revised plans submitted by the Defendant Nos. 1 and 2 and which is

in gross breach of the principles of natural justice. He has submitted

that the MCGM ought to have considered such objections and

representations filed by the Plaintiffs, prior to passing orders

condoning illegalities in the revised/further revised plans.

40. Mr. Kanade has placed reliance on the decision

of this Court in Rajendra Thacker & ors Vs. Municipal Corporation

of Greater Mumbai & ors.5 in the context of his submission that the

hardship to be considered by the Municipal Corporation of Greater

Mumbai is not only the hardship created by the builders /

developers/architects but the Commissioner is also required to take

into account the hardship which may be caused by the proposed

modification in the plans to other directly affected persons such as

residents, purchasers and neighbours. While exercising the powers,

the Municipal Commissioner shall be duty bound to take into

account such representations made by the residents, purchasers and

neighbours. The order passed by the Municipal Commissioner must

5 2004 SCC OnLine Bom 401

NMS-1450-2019.DOC

indicate that he has applied his mind to the existence of

demonstrable hardships. It must also indicate that the commissioner

has applied his mind to ensure that the grant of such

modification/relaxation will not affect the health, safety, fire safety,

structural safety of the inhabitants of the building or

neighbourhood.

41. The Plaintiffs had informed the MCGM of the

violations of the DCR 1991/DCPR 2034 by Defendant Nos. 1 and 2

by letters dated 1st September 2020 and 5th October 2020.

However, MCGM did not respond to the said letters. The Municipal

Commissioner also did not consider the objections raised by

Plaintiffs while permitting such modifications / relaxations in the

plans submitted by the Defendant Nos. 1 and 2 in the 4C Report.

Thus, there has been violation of principles of natural justice as also

a breach of the law laid down by this Court in Rajendra Thacker

(supra).

42. Mr. Kanade has also made submissions on non

compliance of the open space requirements by Defendant Nos. 1

and 2 under Regulation 41 of DCPR 2034. He has submitted that

NMS-1450-2019.DOC

revised plan and further revised plan do not provide for requisite

open space. Due to presence of a dead wall and lack of light and

ventilation at least 6 meters of open space is required to be kept

open on the sides and rear of the plot where proposed building is

between 32 to 70 meters in height and plot size is 1000 meters or

less. There is only open space of 6 meters proposed to be kept on

one side i.e. southern side which does not face plot B. Further, clear

open space of 6 meters is not maintained, as there is a proposed

mechanized parking at the western or the southern side. Such

deficiency in open area cannot be condoned, since it affects the

neighbouring buildings. Considering the concessions granted by the

Respondent Corporation, the illegal building in the subject plot A

will be at a distance of 1.5 meters of plot B whereas the extant law

contemplated for such building to leave 6 meters open space from

all the sides and rear.

43. Mr. Kanade has thereafter, made submissions on

non-compliance with the requirements under Regulation 47 of the

DCPR 2034 by Defendant Nos. 1 and 2 and which is in relation to

fire safety. He has submitted that the Defendant Nos. 1 and 2 are in

breach of Regulation 47(1)(B)(a) of the DCPR 2034 since they have

NMS-1450-2019.DOC

not left the requisite 9 meters clear open space on at least one side

of the building accessible from the road for fire safety. He has

submitted that the administrative circular/transitional policy relied

upon by the Defendant Nos. 1 and 2 does not have statutory effect

and cannot override the provisions of the parent statue which is

DCPR 2034 and in particular Regulation 47 thereof. Defendant

Nos. 1 and 2 had made no case at all for condonation of deficiencies

in relation to the open space for fire safety. The Defendants'

reliance on the Circular dated 15th July 2019 is erroneous and

misplaced.

44. Mr. Kanade has further dealt with the issues

with regard to the locus of neighbouring plot owners to challenge

the construction by placing reliance upon the decision of this Court

in Fatima w/o Caetano Joao Vs. Village Panchayat of Merces 6. This

Court has held that a neighbour who is affected by an illegal

construction has an obligation in his favour based on the Suit for

perpetual injunction. This Court had therefore, found no difficulty

in holding that a neighbour would have right to maintain a Suit.

 6        2000 (3) Mh. L.J. 624






                                                           NMS-1450-2019.DOC




45. Mr. Kanade has made submissions with regard

to the intervenor applications by which the interveners seeking

impleadment as party Defendants in the Suit by submitting that the

intervenors are not bonafide purchasers for value without notice.

There is no privity of contract between the Intervenors and

Defendant Nos. 1 and 2 which can be fulfilled qua the Plaintiffs by

intervening in the present suit.

46. Mr. Ravi Kadam, learned Senior Counsel

appearing for the Defendant Nos. 1 and 2 has submitted that the ad-

interim order which had been passed by this Court on 26th August

2019 by which ad-interim relief had been granted in terms of prayer

clauses (a) and (b) of this Notice of Motion, was upon consideration

of the original plans. He has submitted that in view of the

subsequent facts as well as the submission by the Defendant Nos. 1

and 2 of the revised plan to the MCGM and the sanction thereof, the

premise on which the ad-interim order had been passed is no longer

available. He has submitted that as a matter of fact, the grievance of

the Plaintiffs expressed in the Plaint filed in the above Suit were

addressed in 2015 itself. The MCGM had granted revised

permissions on the basis of the Report dated 14th November 2015.

NMS-1450-2019.DOC

In the said Report, it was mentioned that there was no imbalance of

FSI and necessary RG had been deducted within the subject plot A.

The Commissioner had issued a direction to recalculate open space

from the notional boundaries between Plot A and Plot B in the

North and the West. Pursuant to the directions, open space was

recalculated by the MCGM as directed. The MCGM observed that

there were open space deficiencies with the podium touching the

boundary at only one point thereon. However, the "odd and

irregular shaped nature" was a "demonstrable hardship" that

justified condonation under Regulation 64 [b] of DCR 1991. It was

further mentioned in the subject Report that the fire officer has

granted NOC to the development upon being satisfied with the fire

safety requirements.

47. Mr. Kadam has further submitted that in view of

the Plaintiffs' grievances having been resolved, there was no

necessity for the Plaintiff to file the Suit nearly four years thereafter.

He has submitted that the Defendant Nos. 1 and 2 had preferred an

Appeal from the ad-interim order passed by this Court on 26th

August 2019 and which Appeal (L) No. 465 of 2019 was admitted

NMS-1450-2019.DOC

by Division Bench of this Court and liberty was granted to apply for

interim relief.

48. Mr. Kadam has submitted that in view of

commercial considerations and the obligation to complete the

development on subject plot A, the Defendant Nos. 1 and 2 took a

decision to revise the building plans to meet the Plaintiffs'

allegations in the Plaint. Under the revised plans, open space was to

be maintained of 1.5 meters in the North and West along with the

common boundaries between subject plot A and plot B. For creating

this open space, the existing portion for podium touching the west

boundary line between the subject plot A and plot B was to be

demolished. Defendant Nos. 1 and 2 were to retain the RG area of

the proposed building within the subject plot's area, 6 meters of

open space would be maintained on the South side of the subject

plot A for ingress / egress of fire fighting tenders/vehicles. A

fireman's lift would be installed which would open at requisite mid

landing point at the staircase. The revised plans took care of the

grievance of the Plaintiffs and hence, there was no subsisting basis

for continuing the injunction granted under the ad-interim order.

NMS-1450-2019.DOC

49. Mr. Kadam has submitted that upon the

Defendant Nos. 1 and 2 submitting the revised development plan to

the MCGM for approval and these Defendants' Architects

indicative concession Report to the MCGM, a 4C Report on the

revised plans and the Report submitted by the Defendants' Architect

was issued by MCGM. In the Report submitted by the Architects of

Defendant Nos.1 and 2 condonation had been sought in view of the

hardship expressed which included the following :-

(i) The proposal was for redevelopment of an existing

building.

(ii) Vertical construction was not possible beyond height

restriction issued by the Civil Aviation authorities.

(iii) The plot was odd shaped as noticed in the previous

MCGM Report of 14th November 2015.

(iv) In order to make the project financially viable, it was

necessary to consume the admissible FSI.

(v) The building had already come upto 12th floor.

NMS-1450-2019.DOC

50. The MCGM had considered the aforementioned

hardship submitted by the Defendants' Architect in the Report. The

MCGM found that the hardship cited by the Defendant No. 2 was

justified after conducting a site visit and scrutiny. Further, the

revised plan had been certified by the fire officer for fire safety. The

MCGM thus accepted that the measures had been proposed by the

Architect for neighbourhood safety, structural safety and health

safety and that the same could be taken care of by appointing

structural engineer, the supervisor and license plumber. The

Municipal Commissioner approved the revised plan on 6th

November 2020 as "approved as proposed".

51. Mr. Kadam has submitted that the MCGM had

rigorously vetted and scrutinized the 2nd Defendant's application

which was thereafter put up before the Municipal Commissioner

who has duly applied his mind. There is a discretion vested in the

Municipal Commissioner under Regulation 6(B) to allow cases of

demonstrable hardship defined in Regulation 2(36) of DCPR 2034.

Thus, discretion exercised by the Municipal Commissioner in the

present case has been exercised in circumstances that fall within the

said definition and in accordance with the policy set out under the

NMS-1450-2019.DOC

2019 Circular. He has submitted that the Plaintiffs' reliance on the

decision of the Division Bench of this Court in Rajendra Thacker

(supra) is misplaced. In that case the Commissioner had condoned

illegalities in nearly 111 proposals without due application of mind.

It was in this context that this Court held that the Commissioner is

required to take into account the hardship which may be caused by

any proposed modification to the building plans which directly

affect residents, purchasers and neighbours. The representations of

such persons, if made, are required to be considered. He has

submitted that in the case of Rajendra Thacker (supra) there is no

mention of giving a right of hearing to neighbours such as the

Plaintiffs. To contend otherwise would make development or

redevelopment impossible since all neighbours would have a supra

veto right over property that does not belong to them. At the

highest, this Court in Rajendra Thacker (supra) suggests that the

rights of the neighbours to fire safety must not be compromised by

an arbitrary exercise of discretion. In the present case, the MCGM

and fire officer have acted in accordance with law. They have relied

upon the 2019 circular by which the MCGM issued transitional

policy and under which the they took cognizance of the Chief Fire

Officer's recommendation that fire safety would be assured and

NMS-1450-2019.DOC

adequate for developments, between 32 and upto 70 meters in

height. The deficiencies in open space could be condoned by the

Commissioner if a case for demonstrable hardship was made out.

The Plaintiffs have accepted that the 2019 circular assures fire

safety since the same was not challenged.

52. Mr. Kadam has submitted that the Defendant

Nos. 1 and 2 have complied with the circular dated 15th July 2019

issued by the MCGM by providing in the revised plan clear open

space of 6 meters on the south side of plot A, which in the east

borders at 12.20 meters wide 14th Road and providing for fireman's

lift. The fire officer being satisfied with the provisions in the

revised plan for fire safety issued NOC on 7th July 2020 in

accordance with the transitional policy of the MCGM dated 15th

July 2019.

53. Mr. Kadam has therefore, submitted that there is

full compliance with Regulation 47 of the DCPR 2034. He has

submitted that the Plaintiffs' have confused the two Regulations i.e.

Regulation 41 with Regulation 47 of DCPR 2034. He has submitted

that Regulation 41 falls within Part VIII of the DCPR which

NMS-1450-2019.DOC

prescribes "General Building Requirements". It is plainly of town

planning, a prescription concerned with a person's construction of

his building on his own plot. It has no bearing / relevance to urban

safety requirements. It is primarily concerned with ensuring that a

proposed building has retained open space for its occupants to have

light and ventilation. He has submitted that this Regulation is very

different from Regulation 47 which falls under Part IX which is

titled 'Urban Safety Requirement'. Regulation 47 provides for fire

protection requirements and which the Defendant Nos. 1 and 2 have

taken care of in accordance with the transitional policy Circular

dated 15th July 2011 issued by the MCGM. The fire officer has also

granted NOC upon being satisfied with the provisions made in the

revised plans submitted by the Defendant Nos. 1 and 2. The

MCGM has after considering factors such as neighborhood safety,

structural safety, health safety as well as demonstrable hardships

were satisfied by the Defendant Nos. 1 and 2 sanctioned the revised

plans. The Municipal Commissioner had exercised discretion under

Regulation 6(B) of DCPR 2034 upon considering the demonstrable

hardship which was as under:-

(i) Redevelopment proposal of an existing building.

NMS-1450-2019.DOC

(ii) Necessary to consume the admissible FSI to make

the proposal financially viable.

(iii) Height restriction on the building from The Civil

Aviation department.

(iv) Work already completed up to the 12th floor.

54. Mr. Kadam in context of the discretionery power

exercisable by the Municipal Commissioner under Regulation 6(B)

of DCPR 2034 has relied upon the decisions of the Division Bench

of this Court in Sanjeev Kokil Vs. State of Maharashtra7 and

Rustomjee Central Park CHS Vs. MCGM & Ors.8

55. Mr. Kadam has further submitted that the

present Suit suffers from gross delay and laches as the Plaintiffs

have moved merely five years from the date of IOD and when the

proposed building on the subject plot A had already come upto 12

storeys. The Defendant Nos. 1 and 2 had expended significant sums

in putting up the construction. Flats have also been sold to the flat

purchasers who have been awaiting anxiously for possession of

7 2013 (2) MhLJ 107 8 Writ Petition (L) No.2317 of 2019, decided on 19th December, 2019.

NMS-1450-2019.DOC

their homes. Thus, there is no conceivable basis for continuing the

existing ad-interim injunction against the subject plot A and from

creation of third party rights thereon. He has accordingly, submitted

that the ad-interim injunction order in terms of prayer clauses (a)

and (b) be vacated and the Defendant Nos. 1 and 2 be permitted to

complete the construction of subject plot A and/or create third party

rights thereon.

56. Mr. Sakhare, learned Senior Counsel appearing

for the Defendant Nos. 3 to 8 - MCGM has submitted that the

MCGM has in accordance with the provisions of DCR 1991 and

DCPR 2034 granted concessions sought for by the Defendant Nos.

1 and 2 in the original building plans as well as in the revised

building plans. He has submitted that the Municipal Commissioner

in exercise of powers under Regulation 6(B) of the DCPR 2034

sanctioned the revised plans on 6th November 2020 for the

proposed building comprising stilt + 1st and 2nd podium + 3rd to

17th upper floors. He has submitted that the sanctions granted from

time to time are in respect of the fire safety; open space deficiency;

permitting lift well, staircase lobby, fireman lift, smoke check lobby

free of FSI by charging premium and parking spaces. He has

NMS-1450-2019.DOC

submitted that the fire NOC had been issued by the Chief Fire

Officer considering the revised plans. He has further submitted that

the deficiency in the open space has been considered by the MCGM

and the same has been granted qua Regulations 41(2), 41(4), 43 and

47(1) (B) (a) of DCPR 2034 after site inspection by concerned

officers of MCGM. Further, factors such as neighbourhood safety,

structural safety, health safety and demonstrable hardship arising in

the present case have also been considered. The other sanctions

namely, permitting the lift well, staircase lobby, fireman lift, smoke

check lobby free of FSI as per Regulation 31(1)(iv) of DCPR 2034

have been granted by charging premium. This is permissible under

DCPR 2034 and policy circulars dated 22nd August 2017 and 30th

January 2020. The concession in parking spaces is by allowing

mechanized parking tower of 12 parking spaces having height 14.70

meter at south west open spaces and to allowing 2 stack parking

protruding upto 0.50 meter in required 4.50 meter open spaces.

Considering the hardship and planning constraints, by the

Municipal Commissioner in exercise of powers under Regulation

6(B) of the DCPR 2034 has sanctioned the revised plans.

NMS-1450-2019.DOC

57. Mr. Sakhare has accordingly submitted that the

concessions and sanctions have been granted by the MCGM and the

Municipal Commissioner to the original plans and revised plans are

in exercise of powers under the MRTP Act and in accordance with

the provisions of DCPR 2034, after proper scrutiny and application

of mind. Accordingly, the challenge canvassed by the Plaintiffs in

the above Suit apart from being not maintainable, are devoid of

merits and liable to be rejected.

58. Having considered the rival submissions, it

would first be necessary to consider the challenge to the

maintainability of the Suit raised by the Defendants. There is a two

fold challenge, one is with regard the Suit being barred under

Section 149 of the MRTP Act and the second is to the

maintainability of the Suit for non-compliance of notice

requirement under Section 527 of the MMC Act.

59. The objections which have been raised by the

MCGM qua the maintainability of the Suit is required to be

considered in the light of the fact that when the Interim Application

No.2439 of 2020 was moved by the Defendant Nos.1 and 2 seeking

NMS-1450-2019.DOC

permission of this Court for having their revised plans considered

by Defendant Nos.3 to 7, the MCGM had not raised any objection

to the maintainability of the Suit either under Section 149 of the

MRTP Act or Section 527 of the MMC Act. In fact, this Court had

passed an order in the Interim Application clarifying that there was

no restraint against MCGM from considering the revised plans. The

MCGM were to decide the application in accordance with the

applicable norms / law and all contentions of the parties were kept

open. The first and second Defendants were granted liberty to

renew their application in terms of the prayer clause for permission

for the first and second Defendants to implement the revised plans

and carry out the construction on the subject property upon

approval of the same from MCGM. Thus it would appear that the

MCGM had waived their objection to the maintainability of the

present Suit. Further, the MCGM has not filed any application

under Order 7 Rule 11 of the Code of Civil Procedure, 1908 for

rejection of the Plaint.

60. It has also held by this Court in the decision

relied upon by the Plaintiffs, namely Kishore (Supra) that exclusion

of jurisdiction of a Civil Court under Section 149 of the MRTP Act

NMS-1450-2019.DOC

is not applicable where the Plaint alleges failure on the part of the

MCGM to comply with statutory provisions. Such case can be

examined by the Civil Court. In the present case the Plaintiffs have

pleaded that the MCGM has failed to comply the statutory

provisions namely, the DCR 1991 and DCPR 2034. Mr. Sakhare

learned Senior Counsel for the MCGM had placed reliance upon the

decision of this Court in Satish (Supra). This decision was also

concerned with Section 149 of the MRTP Act. The Trial Court

whilst deciding the preliminary issue as regards the jurisdiction of

the Civil Court found that the Civil Court has no jurisdiction to go

into the validity of the permission granted by the Planning

Authority as per the sanctioned plans which finding was upheld by

this Court. However, considering the Plaintiffs' wider challenge in

the present Suit as to non-compliance by the MCGM of statutory

provisions and not merely challenge to the validity of the

permission granted by the MCGM, this Suit would be maintainable.

61. In so far as non issuance of the statutory notice

under Section 527 of the MMC Act which Mr. Sakhare has claimed

to be fatal to the present Suit and which warrants dismissal at the

very threshold, it would be necessary to note that the MCGM had

NMS-1450-2019.DOC

not insisted on such statutory notice when the Interim Application

taken out by the Defendant Nos.1 and 2 in the present Suit being

Interim Application No.2439 of 2020 had been moved. This Interim

Application had been entertained by this Court and relief granted.

MCGM has thus waived such objection to the maintainability of the

Suit on the ground of lack of statutory notice.

62. The decisions relied upon by the Defendants are

inapplicable in the present case, considering the challenge in this

Suit which is filed on the premise that there has been a failure of

compliance with statutory provisions and / or acts done by the

MCGM de hors the statutory provisions. This can be examined by

the Civil Court.

63. Having considered the Suit to be maintainable, it

would be appropriate to consider the other rival submissions with

regard to the injunction sought for by the Plaintiffs restraining the

Defendant Nos.1 and 2 from carrying out construction of any kind

on subject plot A and from allotting flats and / or executing

agreements, arrangements or understandings with third parties,

inducting them into flats proposed to be constructed in the building

NMS-1450-2019.DOC

on subject Plot A. It is necessary to note that by an ad-interim order

dated 26th August, 2019, the learned Single Judge of this Court

granted ad-interim relief in these terms. This was in light of the

sanction granted by the MCGM to the original plans submitted by

first and second Defendants. The learned Single Judge prima facie

found that the first and second Defendants had submitted plans in

relation to the larger property and not plot A alone, though the

larger plot had been sub-divided. There was not enough open space

which was left by the first and second Defendants and that the first

and second Defendants were attempting to usurp the rights of the

owners of Plot B by failing to keep a reservation of 15% RG area

and by considering RG area of the larger property.

64. The Plaintiffs had filed the present Suit in the

year 2019 on these grievances which were noticed by the learned

Single Judge of this Court in the ad-interim order. It is necessary to

note that the Plaintiffs had expressed these grievances after much

delay and laches as upto 12 storeys of the subject building had

already been constructed on the subject Plot A. The Plaintiffs are

the owners of the adjacent Plot B. Further, the MCGM had in the

year 2015 in its report dated 14th November, 2015 already noted

NMS-1450-2019.DOC

that there was no imbalance of FSI and that necessary RG area had

been deducted from the gross area of plot A and not from the larger

property. Further, the MCGM had prior to issuance of the said

report considered the deficiencies in open spaces in Plot A's

development. The Municipal Commissioner had issued directions

on 19th May, 2015 to recalculate the open space from the notional

boundaries between Plot A and B in the North and West. The

MCGM had in its report considered that the boundary recalculation

of the open spaces from the notional boundary between Plot A and

B revealed that there were open spaces deficiencies with podium

touching boundary only at one point. However, in view of the Plot

A being of "odd and irregular shaped", the MCGM rendered it fit

for regularization under 64 B of DCR, 1991. The fire safety officer

had granted no objection to the developer upon being satisfied that

the fire safety requirements were met. The MCGM recommended

that a registered undertaking be obtained from the developer of

subject Plot A, waiving any right to object to any proposed

development on the neighboring plot. The future occupants of

subject Plot A would also waive their right to object to any

proposed development on Plot B with deficient open space. It

would thus appear that the Plaintiffs grievances were sufficiently

NMS-1450-2019.DOC

addressed by the MCGM, four years before the Plaintiff filed the

present Suit.

65. The Defendant Nos.1 and 2 - Developers of Plot

A had taken the further step in deciding to revise their building

plans to fully meet with the Plaintiffs allegations in the Plaint. They

had accordingly in the revised plans proposed to maintain open

space of 1.5 meters in the North and West along the boundary

shared with plot B and for which the existing portion of the podium

touching boundary line between Plot A and Plot B was to be

demolished. Defendant Nos.1 and 2 were to continue to retain the

RG area of the proposed building within plot A's area. Further, six

meter of open space would be maintained on the southern side of

the plot for ingress / egress of firefighting tenders / vehicles. In

addition fireman's lift would be installed which would open at

requisite mid landing points on the staircase. It is necessary to note

that on 7th July, 2020, the Fire Officer was satisfied with the fire

safety as NOC has been issued in respect of the revised plans. This

was upon taking into consideration the MCGM circular dated 6th

August, 2019 which had permitted 6 meter open space on one side

NMS-1450-2019.DOC

of the building upto 70 meters in height if there was a provision for

fire men's lift in the building.

66. The Defendant Nos.1 and 2 had taken out

Interim Application No.2439 of 2021 in the present Suit for

clarification from this Court that the ad-interim order dated 26th

August, 2019 does not preclude Defendant Nos.3 to 7 - MCGM to

process and approve the revised plans submitted by the Applicants.

This Court had clarified that there is no restraint against MCGM

from considering the revised plans and to decide the application.

The Applicants were granted liberty to renew their application in

terms of prayer clause (b) of the said Interim Application which

sought permission to implement the revised plans and carry on

further construction on the subject Plot A upon receiving approval

from the MCGM. In that case, all contentions were expressly kept

open.

67. The revised plans were thereafter submitted to

the MCGM and it is necessary to note that the Plaintiffs had filed

submissions opposing the revised plans being sanctioned. It was the

Plaintiffs contention that on a comparison of the original sanctioned

NMS-1450-2019.DOC

plans and revised plans, it became evident that, the building remains

in the same place and there were no changes to the open area on the

northern side and minimal changes on the western side with the

construction of Plot A carried out by Defendant Nos.1 and 2 which

fettered the Plaintiffs right to develop Plot B due to lack of

sufficient open spaces. Further, there was submission with regard to

the proposal to construct mechanized car parking on the south side

of Plot A which does not provide clear open space as contemplated

under Regulation 47(1) (B) (a) of DCPR 2034. The structure of the

car parking space prevents fire engine access at the end of the plot

and is therefore, a fire hazard and dehors the provisions of DCPR

2034.

68. In Rajendra Thacker (Supra) this Court held that

hardship considered by the MCGM is not only the hardship created

by builders / developers / architects but the Municipal

Commissioner is also required to take into account the hardship

which may be caused by the proposed modification to other directly

affected persons such as residents, purchasers and neighbours. In

the event such persons make representations, the MCGM is duty

bound to take into account such representations and the order must

NMS-1450-2019.DOC

indicate that the Commissioner has applied his mind to ensure that

the grant of such modification / relaxation will not affect the health,

safety, fire safety, structural safety of the inhabitants of the building

or neighbourhood. The MCGM had been informed by the Plaintiffs

vide letters dated 3rd September, 2020 and 5th October, 2020 of the

violations of DCR 1991 and DCPR 2034. It is the Plaintiffs

grievance that the MCGM had not considered the objections raised

by the Plaintiffs whilst permitting concessions in the 4C report.

69. In my view, reliance placed by the Plaintiff on

the judgment in Rajendra Thacker (Supra) is misplaced. In that case

the Commissioner had summarily condoned illegalities in nearly

111 proposals without due application of mind. Further, the law did

not define what constituted a 'demonstrable hardship'. The

Commissioner's discretionary power under DCR 1991 were

consequently unchecked and not canalized. The present case is very

different from that case. The MCGM has considered the

demonstrable hardship not only of the Defendant Nos.1 and 2 -

Developers of the subject plot A, but also of the other persons

concerned namely, residents, purchasers and neighbours. The

MCGM appears to have thoroughly vetted and scrutinized the first

NMS-1450-2019.DOC

and second Defendants' application and thereafter has put it up

before the Municipal Commissioner who had duly applied his mind

to demonstrable hardship as defined under Regulation 2(36) of the

DCPR 2034. The discretion under Regulation 6 (B) of DCPR 2034

has been duly exercised in circumstances that fall within the

definition of demonstrable hardship and the policy set out under the

2019 Circular. I am prima facie of the view that the discretionary

powers exercised by the Municipal Commissioner as well as the

sanction of the original plans and revised plans by the MCGM and

Municipal Commissioner do not fall foul of the decision of this

Court in Rajendra Thacker (Supra). Further, the Chief Fire Officer

has also granted NOC upon considering fire safety not only of Plot

A but also of surrounding plots including Plot B.

70. There is no merit in the submissions of the

Plaintiffs that the non-conformity with the open space requirements

under Regulation 41 of DCPR 2034 could not have been condoned

by the MCGM and / or Municipal Commissioner. Regulation 41

falls within Part VIII of the DCPR 2034 which prescribes "General

Building Requirements" it is clear that the open spaces prescribed

under this Regulation is with regard to the open spaces required to

NMS-1450-2019.DOC

be kept by the person / developer's construction of his building on

his own plot and does not have any bearing on urban safety

requirements. This is primary concerned with ensuring that the

proposed building has retained open space for the occupants therein

to have light and ventilation. It has no relevance to fire safety which

is provided in Regulation 47 which falls under Part IX of DCPR

2034 which prescribes "Urban Safety Requirements". It would thus

be open for the MCGM and Municipal Commissioner to grant

concessions regarding open space deficiencies by considering

demonstrable hardship of the the person / developer who has in the

present case constructed upto the 12th storey on the subject plot A.

71. I further find that there is no merit in the

submission of the Plaintiffs that there has been a violation of

Regulation 47 of the DCPR 2034 as the proposed building on Plot

A having height of more than 32 meters and upto 70 meters has not

kept clear open space at 9 meters at ground level on at least one side

accessible from the road side. I have taken into consideration the

circular issued by MCGM dated 15th July, 2019 which inter alia

provides for developments between 32 meter to 70 meter in height,

if a fireman's lift for use of firefighters to attend any fire is

NMS-1450-2019.DOC

provided, clear open space of 6 meters at ground level on at atleast

one side may be allowed. This requirement has been met in the

revised plans sanctioned by the MCGM and the Municipal

Commissioner by the provisions of 6 meters open space upon the

southern side of Plot A which in the east borders a 12.20 meters

wide 14th Road and also on the south side of Plot A (other than road

side). There is also provision of fireman's lift. The Defendant has

not challenged the MCGM Circular dated 15th July, 2019 and

hence absent such challenge, the Plaintiffs cannot claim that the

MCGM circular cannot be followed as it is contrary to the DCPR

2034.

72. It is further necessary to note that the MCGM

has sanctioned the revised Plans by considering factors such as

neighbourhood safety, structural safety, health safety and the

demonstrable hardship, which includes:-

i) Redevelopment proposal of an existing building.

ii) Necessary to consume the admissible FSI to make the proposal financially viable.

iii) Height restriction on the building from the Civil Aviation Department;

iv) Work of the subject building already completed upto the 12th floor.






                                                             NMS-1450-2019.DOC




       v)     The shape of Plot A was odd and irregular.

73. There was submission with regard to the locus

of the Plaintiffs as a neighbour to file the present Suit. This Court in

Fatima (Supra) relied upon by Mr. Kanade has held that a

neighbour who claims to be affected by an illegal construction has

an obligation in his favour based on which he can maintain a Suit

for perpetual injunction. However, it is not necessary to go into this

issue as the Suit has been entertained and I have found the suit to be

maintainable.

74. I have also considered the submissions of Dr

Birendra Saraf, learned Senior Counsel for the Applicants /

Intervenors in Interim Application (L) No.28602 of 2021. I have

arrived at a finding that the revised plans sanctioned by the MCGM

and the Municipal Commissioner cannot be found fault with. Thus,

the further construction of the proposed building on subject plot A

cannot be held up. Accordingly, the grievance of the intervenors

have been addressed.

75. I have considered the decisions of the Division

Bench of this Court relied upon by Mr. Kadam namely Sanjeev

NMS-1450-2019.DOC

Kokil (Supra) and Rustomjee Central Park CHS (Supra) in support

of his submission on exercise of power under Section 64(B) of

DCR 1991 equivalent to 6(B) of DCPR 2034. In Sanjeev Kokil

(Supra), the Division Bench of this Court held that the authority

which in this case is the Municipal Commissioner by merely

making endorsement of "approved as proposed" does not mean that

there is non-compliance of the requirement of recording reasons in

writing. It pre-supposes that he agreed with every aspect mentioned

in the proposal. Further, in Rustomjee Central Park CHS (Supra) it

was held that the Municipal Commissioner in considering whether

to condone the deficiency in open space must consider that in not

doing so there will be demonstrable hardship, in that the proposed

construction would not be possible. It is in fact for the Plaintiff to

show that as a result of the Commissioner's exercise of discretion

there is a slightest endangerment of heath safety, fire safety,

structural safety or public safety of the inhabitants. In my view, the

Plaintiffs have in the present case failed in showing this

requirement as laid down by the Division Bench of this Court.

Thus, in my prima facie view, the discretion exercised by the

Municipal Commissioner under Regulation 6(B) of DCPR 2034 in

NMS-1450-2019.DOC

sanctioning the revised plans by duly considering demonstrable

hardship cannot be found fault with.

76. Accordingly, the relief sought for in the above

Notice of Motion is not granted. The ad-interim relief granted in

terms of prayer clauses (a) and (b) of the Notice of Motion by ad-

interim order dated 26th August, 2019 stands vacated.

77. In view of rejection of the relief sought for in the

Notice of Motion, Interim Application (L) No.6700 of 2020 taken

out by Defendant Nos.1 and 2 has worked itself out and is

accordingly disposed of. Further, Interim Application 463 of 2021

taken out by the Plaintiff also does not survive and is disposed of.

Interim Application (L) No. 26802 of 2020 taken out by the

intervenors also does not survive and is disposed of.

78. The above Notice of Motion No.1450 of 2019 is

disposed of with no order as to costs.

( R. I. CHAGLA J. )

NMS-1450-2019.DOC

79. After pronouncement of the judgment, Mr.

Vishal Kanade, learned Counsel appearing for the

Applicants/Plaintiffs has applied for continuation of the ad-interim

relief granted by ad-interim order dated 26.08.2019 passed in the

above Notice of Motion No.1450 of 2019.

80. This is opposed by Mr. Kadam, learned Counsel

appearing for Defendant Nos.1 and 2 as well as by Mr. Sakhare,

learned Senior Counsel appearing for Defendant Nos.3 to 8. Mr.

Sakhare has stated that in any event the work on the subject

building cannot start until final permission is issued in pursuance

of the revised plans.

81. Considering the findings in the judgment dated

26.04.2022 and the fact that ad-interim order dated 26.08.2019 was

passed prior to the submission of the revised plans which received

the sanction of the MCGM and Municipal Commissioner, I find no

reason for continuing the ad-interim relief granted by the ad-interim

order dated 26.08.2019. Accordingly, the Application is rejected.

( R. I. CHAGLA J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter