Citation : 2021 Latest Caselaw 10191 Bom
Judgement Date : 3 August, 2021
1 908-WP.5680-20.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
908 WRIT PETITION NO.5680 OF 2020
RAJENDRAKUMAR MOTILALSA SAWAJI AND OTHERS
VERSUS
THE STATE OF MAHARASHTRA AND OTHERS
...
Advocate for Petitioners : Mr. Deshmukh S.A.
AGP for Respondent Nos.1 to 6-State : Mr. S.R.Yadav-Lonikar.
...
CORAM : RAVINDRA V. GHUGE, AND
S. G. MEHARE, JJ.
DATE : 03.08.2021
PER COURT :-
1. The learned advocate for the petitioners had sought time
to address the Court today after going through the reply of the
State. It is submitted that he seeks further time for going
through the reply and search out certain documents which the
petitioners would file in this Court after moving an application
requesting for leave to file such documents.
2. The learned advocate for the petitioners submits that an
ad-interim order was passed by this Court, by which,
construction to the extent of twelve (12) meters width of the
road was permitted. Said activity is going on.
2 908-WP.5680-20.odt
3. We find that the Hon'ble Apex Court has held in catena
of judgments that a public project should not be stalled by
interim orders of the Court and if the petitioners have any
right, which is impinged by the conduct of the acquiring body,
they would be entitled for compensation as is prescribed in
law.
4. The learned AGP submits that the road in the possession
of the State ever since 1960 onwards, was of 30 meters. So
also, by the introduction of Section 20-A (introduced by way of
an amendment) to the Specific Relief Act, injunction by a Court
in a suit involving a contract relating to an infrastructure
project specified in the schedule, is not to be granted, as it may
cause impediment or delay in the progress or completion of
such infrastructure project. The schedule below Section 20-A
indicates that roads and bridges are covered under
infrastructure projects.
5. In view of the above, we are listing this petition for
hearing on 27.08.2021. The respondents - authorities would
be at liberty to proceed with the project. We, however, make it
clear that if even an inch of land of the petitioners is consumed
3 908-WP.5680-20.odt
in the said project, they would stand legally entitled to
compensation under the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013.
(S. G. MEHARE, J.) (RAVINDRA V. GHUGE, J.)
...
vmk/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!