Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Andhra Pradesh vs P Prasad
2024 Latest Caselaw 9894 AP

Citation : 2024 Latest Caselaw 9894 AP
Judgement Date : 5 November, 2024

Andhra Pradesh High Court - Amravati

The State Of Andhra Pradesh vs P Prasad on 5 November, 2024

Author: R Raghunandan Rao

Bench: R Raghunandan Rao

 APHC010239172023
                      IN THE HIGH COURT OF ANDHRA PRADESH
                                    AT AMARAVATI                          [3508]
                             (Special Original Jurisdiction)

                    TUESDAY, THE FIFTH DAY OF NOVEMBER
                      TWO THOUSAND AND TWENTY FOUR

                                   PRESENT

         THE HONOURABLE SRI JUSTICE R RAGHUNANDAN RAO

    THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM

                         WRIT APPEAL NO: 779/2023

Between:

The State Of Andhra Pradesh and Others                        ...APPELLANT(S)

                                      AND

P Prasad and Others                                         ...RESPONDENT(S)

Counsel for the Appellant(S):

1. GP FOR LAND ACQUISITION (AP)

Counsel for the Respondent(S):

1. S.V.S.S.SIVA RAM

The Court made the following Judgment: (per Hon'ble Sri Justice R Raghunandan Rao)

The land of the respondents to an extent of Ac.36.42 cents situated in

various survey numbers of Chippagiri Village and Mandal of Kurnool District

was taken over for the purpose of construction of an Additional Summer

Storage Tank for the Indian Railways. This land was taken under the

provisions of the Andhra Pradesh Right to Fair Compensation and

Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013

(herein referred to as "the Act"). The said proceedings were challenged by the

RRR, J & MRK, J

respondents on various grounds, by approaching this Court, by way of

W.P.No.18725 of 2021. The first ground raised by the respondents was that

the timeline, required to be mentioned under the Act, had been violated.

Secondly, "the appropriate Government" mentioned under the Act would be

the Central Government, whereas, the acquisition process had been

conducted by the State Government and as such, the entire proceedings

would stand vitiated and would have to be set aside.

2. A learned Single Judge of this Court had allowed the Writ

Petition, by way of an order, dated 13.02.2023, on the ground that the

timelines set out in the Act had been breached and consequently, the

acquisition proceedings stand quashed and set aside.

3. Aggrieved by this order of the Learned Single Judge, dated

13.02.2023, the appellants herein had moved the present Writ Appeal before

this Court. The said Writ Appeal was dismissed by a Division Bench of this

Court, by passing an order, dated 13.10.2023. The Division Bench took the

view that the "appropriate Government" for conducting the acquisition

proceedings would be the Central Government in as much as, it is the Indian

Railways, which is a part of the Central Government, which was seeking the

land. The appellants, being aggrieved by this order, dated 13.10.2023, had

approached the Hon'ble Supreme Court of India, by way of S.L.P(Civil)

No.2591 of 2024. The Hon'ble Supreme Court, after granting leave, had

RRR, J & MRK, J

disposed of the Appeal, dated 29.04.2024, which was numbered as Civil

Appeal No.5471 of 2024.

4. The Hon'ble Supreme Court, in the aforesaid Judgment, held that

the view of the Division Bench of this Court, that the State Government was

not competent to initiate the acquisition process, was incorrect. The Hon'ble

Supreme Court held that the State Government would be competent to initiate

the acquisition process in respect of the land situated within the territory of

that State, so long as the acquisition is for a public purpose.

5. The Hon'ble Supreme Court, taking note of the objections of the

learned counsel for the respondents before the Hon'ble Supreme Court, had

also held that it would be appropriate to remand the matter back to the

Division Bench to consider any further objections that might be raised by the

respondents including the question of violation of the timelines prescribed

under the Act.

6. Sri N. Sai Phanindra Kumar, learned counsel appearing for the

respondents would submit that there has been a clear violation of the

timelines set out under the provisions of the Act. He would submit that Section

19 (7) of the Act stipulates that the publication of declaration and summary of

rehabilitation and resettlement under Section 19 (1) of the Act would have to

be made within 12 months from the date of the preliminary notification that

shall be issued under Section 11 (1) of the Act. The learned counsel submits

that in this case, the preliminary notification was issued under Section 11 (1)

RRR, J & MRK, J

of the Act on 04.12.2017, while the notification under Section 19 (1) was

issued only on 28.08.2019, which is beyond the period of 12 months. He

would further submit that the extension of time permitted under the second

proviso of Section 19 (7), which is relied upon by the appellants, also would

not rescue the process. He would submit that the extension of time given

under this proviso on 05.12.2018 and 06.03.2019 would be of no avail as the

said extension had been given without proper justification and without a

declaration of the Government that the circumstances exist justifying such

extension.

7. The learned counsel would also submit that the award under

Section 25 of the Act is to be passed within 12 months from the date of

declaration under Section 19 (1). In the present case, the declaration under

Section 19 (1) was issued on 28.08.2019 and the award should have been

passed by 20.08.2020, failing which the entire proceedings for acquisition

would lapse. However, the award was passed only on 30.09.2021. He would

further submit that though the first proviso to Section 25 empowers the

Government to extend the period of 12 months, the second proviso

subsequently requires the said decision to be in writing and to be uploaded on

the website of the authority concerned. He would submit that this requirement

is to ensure compliance of the requirement under the first proviso that such

extension is being given as the Government is of the opinion that

circumstances justifying such delay exist. He would submit that there is no

RRR, J & MRK, J

such circumstance set out in the orders of extension passed on 20.08.2020,

26.02.2021 and 28.08.2021.

8. The Learned Government Pleader appearing for the appellants

would submit that the proceedings of the Government, on the dates

mentioned above, clearly give reasons for grant of extension. He would submit

that the primary problem faced by the authorities was the disruption due to

Covid Pandemic and as such the Court would have to take a liberal view of

the reasons set out in the order of extension. He would also submit that the

Hon'ble Supreme Court, while disposing of the Civil Appeal No.754 of 2024,

had held that the authorities would be entitled to utilize the land and any

defect or violation of the timelines in the Act would only entitle the respondents

to additional compensation. The Learned Government Pleader would draw the

attention of this Court to the reasons set out in the various order of extension.

9. At the outset, this Court is of the opinion that the question of

disruption due to the Covid Pandemic cannot be looked into as none of the

orders of extension mention this reason. In view of the Judgment of the

Hon'ble Supreme Court in the case of Mohinder Singh Gill & Anr. vs The

Chief Election Commissioner1, this Court declines to accept the ground of

disruption due to Covid Pandemic.

10. However, this Court would have to look into the reasons set out in

the extension orders to ascertain whether a proper opinion has been formed

1978 AIR 851: 1978 (1) SCC 405

RRR, J & MRK, J

by the Government that circumstances for granting extension of time were

available.

11. The first set of extension orders relate to the extension of period

between the notification under Section 11 (1) and the declaration under

Section 19 (1) of the Act. These proceedings had been placed before this

Court. The first order of extension was on 05.12.2018, stating that the initial

summary of rehabilitation and resettlement is not clear and the scheme was

sent to the Revenue Divisional Officer, Adoni, to submit and revise

rehabilitation and resettlement scheme due to which further time is required

and a period of three months from 05.12.2018 to 04.03.2019 was granted by

way of extension. Thereafter, a further extension order, dated 06.03.2019

extending the period by six months was issued. In this order, it was stated that

the R & R scheme had been resubmitted by the Revenue Divisional Officer,

Adoni and the same has already been approved by the Joint Collector,

Kurnool, consequent to which, the scheme would have to be published, after

calling for objections. It was stated that for this purpose, time would have to be

extended as the stipulated time would lapse on 04.03.2019 and also on the

ground that general elections were to be held within a short period and the

same would require extension of time. Thereafter, the notification under

Section 19 (1) was published on 28.08.2019.

12. After the publication of notification under Section 19 (1), the

award was required to be passed by 27.08.2019. However, an order of

RRR, J & MRK, J

extension, under the second proviso to Section 25 was issued on 27.08.2020.

In this extension order, it was stated that steps were being taken to obtain the

consent of the displaced persons, for the award. However, such consent could

not be obtained as some of the affected persons were asking for conduct of a

survey to ascertain the actual extent of land available on the ground. The

extension has been given on this ground. Thereafter, a further extension order

was issued on 26.02.2021, stating that consent for passing of the award

required further time as the affected persons were asking for a higher

compensation amount. On this basis, time was extended by a further period of

six months from 28.02.2021 to 27.08.2021. After this extension, a further

extension was granted on 27.08.2021 on the ground that the amount required

for passing the award is insufficient and the revenue department had to

deposit an amount of Rs.13,35,700/- as an additional amount for further

action. On this ground, further extension of time of three months from

28.08.2021 to 27.11.2021 was granted.

13. The requirement under the second proviso to Section 19 (7) and

the requirement under the first proviso to Section 25, for extension of time, is

essentially the same. The second proviso to Section 19 (7) reads as follows:

"provided further that the appropriate government shall have the power to extend the period of 12 months, if in its opinion circumstances exist justifying the same"

14. The first proviso to Section 25 is identical.

RRR, J & MRK, J

15. The said proviso empowers the appropriate government to

extend the time if it is of the opinion that circumstances justifying such

extension exist.

16. Keeping in view the fact that the Act is to ensure adequate,

proper and timely compensation to the affected persons, the said proviso

would have to be read strictly. This would mean that mere recording of a

reason for grant of extension would not be sufficient. Any such reason,

recorded in the extension order, would have to meet the test of

reasonableness and adequacy. This would mean that the opinion of the

government should be based on objective and valid reasons. It may also be

observed that mere inefficiency of the government or negligence on the part of

the officials of the appropriate government cannot be covered up and rescued

by extension of time by the appropriate government. Any other view would

render the requirement of Section 19 (7) and Section 25, that the acquisition

process should be completed, and compensation should be paid to the

affected parties, within the stipulated period of time, would be rendered otiose.

17. Keeping this in the background, this Court would now have to see

whether the reasons set out in the various extension orders mentioned above

meet such an objective satisfaction.

18. The reason given for the first extension of time between the

notification under Section 11 (1) and Section 19 and the notification under

Section 19 (1) of the Act was that the R & R package was not ready and

RRR, J & MRK, J

required clarification from the Revenue Divisional Officer. The subsequent

notification was granted on the ground that the time for calling for objections

was not sufficient and that the general elections were due. The said reasons

only demonstrate the inaction on the part of the officials of the State

Government and such inaction cannot be condoned through extension of time.

Such extension of time would have to be for extraordinary situations which

render compliance of the timelines difficult. No such circumstances appear to

be available.

19. As far as the extension of time between the declaration under

Section 19 (1) and the passing of the award under Section 25 is concerned,

the first extension was sought on the ground that some objection was being

raised by the affected persons in relation to the extent of land being taken

over by the appropriate government. The second extension was sought on the

ground that the award could not be obtained on account of the affected

persons asking for higher compensation. The third extension was obtained on

the ground that further amount was required from the requisitioning

department. To the mind of this Court, these grounds are not sufficient to seek

extension of time and any such opinion formed by the government for

extension of time on the basis of such circumstances cannot be accepted to

be in terms of the aforesaid provisos to Section 19 (7) and Section 25 (1) of

the Act.

RRR, J & MRK, J

20. In these circumstances, the present Writ appeal is dismissed.

However, in view of the directions of the Hon'ble Supreme Court, the land

would remain vested with the Central Government and the respondents herein

would only be entitled to enhanced compensation on the basis of issuance of

a fresh notification under Section 11 (1) of the Act and completion of the

acquisition proceedings. Needless to say, any additional compensation would

have to be paid by the requisitioning authority. There shall be no order as to

costs.

As a sequel, interlocutory applications pending, if any shall stand

closed.

________________________ R RAGHUNANDAN RAO, J

_______________________________ MAHESWARA RAO KUNCHEAM, J

05.11.2024 MJA

RRR, J & MRK, J

THE HONOURABLE SRI JUSTICE R RAGHUNANDAN RAO

THE HONOURABLE SRI JUSTICE MAHESWARA RAO KUNCHEAM

WRIT APPEAL NO: 779 of 2023 (per Hon'ble Sri Justice R Raghunandan Rao)

05.11.2024

MJA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter