Citation : 2022 Latest Caselaw 7481 AP
Judgement Date : 29 September, 2022
THE HON'BLE SRI JUSTICE C.PRAVEEN KUMAR
AND
THE HON'BLE SRI JUSTICE A.V. RAVINDRA BABU
I.A.Nos.2 to 4 of 2022
in
Writ Appeal No.672 of 2022
COMMON ORDER:- (per the Hon'ble Sri Justice C. Praveen Kumar)
Heard Sri Dammalapati Srinivas, learned Senior
Counsel, for the appellant and Sri S. Sriram, learned
Advocate General, appearing for the Respondents/State.
2. Since both the Counsel argued the I.As. at length, we
were forced to delve into the matter in detail. It is made
clear that the observations if any made in the order are
after considering the prima facie case and for deciding
these Interlocutory Applications only.
3. The facts, in issue, are as under:-
(a) The respondent/State of Andhra Pradesh issued
G.O.Ms.No.2 Infrastructure & Investment (Ports-I)
Department, dated 30.01.2008, awarding contract of
developing an all weather deep water Port at
Machilipatnam to a consortium company. A Concession
Agreement was entered into on 21.04.2008. Initially,
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
consortium was incorporated in the name of M/s.Vajra Sea
Port Pvt. Limited, as a special purpose vehicle to execute
the Concession Agreement. Later on, a revised Concession
Agreement dated 07.06.2010 was executed whereby the
appellant was to develop, build, own, operate and maintain
the Port at it's own cost and expenses during the
Concession period and transfer the Port to Government of
Andhra Pradesh at the end of the concession period.
(b) Various conditions and clauses came to be
incorporated in the revised Concession Agreement. Since
the appellant failed to take up the project, though nearly
twelve years have elapsed from the date of the original
agreement and for the reasons mentioned therein,
G.O.Ms.No.66 dated 08.08.2019 impugned in Writ Petition
No.12980 of 2019, came to be issued canceling the
Concession Agreement dated 07.06.2010 with immediate
effect in Public interest. The land, which was leased to the
appellant was resumed to the Government with immediate
effect.
4. Vide order dated 25.08.2022, learned Single Judge
dismissed the writ petition. Challenging the same, the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
present Writ Appeal is filed. Along with Writ Appeal,
I.A.Nos.2 and 3 came to be filed while I.A.No.04 of 2022 is
filed on a little later date.
5. Sri Dammalapati Srinivas, learned Senior Counsel for
the appellant mainly submits that as per the terms of the
Concession Agreement, the Government is required to
fulfill certain obligations and only then the appellant shall
fulfill its part. He would submit that one of the conditions
in the agreement was that the Government should
handover the land agreed to be given, free from all
encumbrances and only then the Respondent-Government
can contend that there was non-fulfillment of the
agreement. In the absence of the same, it cannot be said
that there was non-fulfillment of the terms of the
Agreement.
6. Learned Senior Counsel further submitted that the
finding given by the learned Single Judge that the
appellant herein did not enter into the State Support
Agreement with the Government of Andhra Pradesh does
not stand to the test of reasoning given therein. According
to him, as per Clause 3.2.1(b), the appellant company
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
submitted a draft State Support Agreement to the
Government of Andhra Pradesh on 07.07.2010 itself along
with a covering letter, a month after the Concession
Agreement, but, the respondents have not shown any
interest in signing the agreement despite innumerable
requests made and the reminders given till April, 2019.
Though, a specific averment to this effect was made in para
33 of the affidavit in the writ petition, there was no reply to
the same in the counter filed by the Government. Having
regard to the fact that the Government has not exercised
the condition of waiver, as stipulated in the agreement and
in the absence of any answer to the averment in the
counter affidavit, with regard to signing the agreement, the
finding of the learned Single Judge that the appellant failed
to enter into an agreement, is incorrect.
7. In so far as non-handing over of entire land is
concerned, learned Senior Counsel would contend that
Clause 3.2.1 specifically contemplates that the rights and
obligations of concessionaire under this agreement are
subject to satisfaction in full, of conditions to be fulfilled on
or before the Financial Closure, as per the Detailed
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
Proposal Report, unless any of the condition has been
waived as provided in Clause 3.2.2. He took us through
Clause (b) and (d) of 3.2.1, to contend that merely giving
some land may not satisfy the requirement of the contract.
According to him, the entire extent of land as agreed upon
should be given in one go and the said land should be free
from all encumbrances, failing which would be contrary to
Clause 3.2.1.
8. In so far as the Financial Closure is concerned, the
learned Senior Counsel would contend that unless the
State spells out the State Support Agreement, it is difficult
to get financial support. Learned Senior Counsel referred
to the letter dated 25.04.2012, wherein, the appellant
requested the Government of Andhra Pradesh to extend the
time for Financial Closure and other Major Milestones in
terms of Clause 4.7 of the Revised Concession Agreement.
He took us through the letter dated 25.05.2019, wherein, a
request for finalization of State Support Agreement was
made, but, there was no reply from the State to any of
these letters, and as such, finding fault with the appellant
is unacceptable.
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
9. Coming to the next issue namely that the authorities
failed to follow the procedure, more particularly, Principles
of natural justice while terminating the Concession
Agreement, learned Senior Counsel took us through Clause
10.10 of the Revised Concession Agreement. Commenting
on the findings of learned Single Judge on this aspect, he
would submit that invoking Section 39 of the Indian
Contract Act, 1872 does not fit in to the facts in issue,
since there was no refusal on the part of the appellant to
perform the contract. However, he would submit that
immediately after the judgment is pronounced by the
learned Single Judge, "Letter of Award" was issued to the
third party. In any event, learned Senior Counsel would
contend that since prima facie case is made out showing
the illegalities committed by the State, and having regard
to the substantial amount spent by the appellant over the
project pleads that it would be just and reasonable to order
Status quo, so that third party rights are not created.
10. Sri S. Sriram, learned Advocate General, appearing
for the respondents, would submit that the project is not
taken up till date, though the agreement was entered in the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
year 2008 itself. He would submit that in the month of
August, 2021, the Government issued G.O.Ms.No.9,
wherein, the Government after careful consideration of the
matter, approved the revised DPR prepared by M/s.RITES,
towards development of Machilipatnam Port under Land
Lord model and accorded administrative sanction to take
up Phase-1 works with total cost of Rs.5155.73 Crores, to
be completed within six months duly, keeping the State
Support as provided in G.O.Ms.No.14, intact.
11. The Letter of Award dated 25.08.2022 issued by
Superintending Engineer (Marine), which is placed on
record along with affidavit by the State, would show that
the bid of M/s.Megha Engineering & Infrastructures
Limited was accepted and the said firm has been awarded
contract for construction of Greenfield Port at
Machilipanam in Krishna District on Engineering,
Procurement & Construction Contract Basis, for an
amount of Rs.3668.83 Crores. A Performance Security in
the form of an unconditional Bank Guarantee for
Rs.36,69,00,000/- was directed to be submitted within 28
days from the date of LoA, and the bank guarantee shall be
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
valid by 180 days after the expiry of the Defects
Notification Period, which shall be extended from time to
time as per the Contract. It is also stated that Agreements
are also entered with the Lowest Bidder.
12. Learned Advocate General further submitted that the
Development of Machilipatnam Port in the manner
indicated in G.O.Ms.No.9 dated 17.08.2021 and the
subsequent process initiated for identifying lowest bidder
was in public domain by virtue of Tender that was issued
on 15.03.2022. The petitioner failed to participate in the
said process in spite of knowing the same and as such he
has no locus standi to challenge the Policy decision of the
Government with regard to development of Ports.
13. In so far as the merits of the case learned Advocate
General would contend that as per Clause 3.2.1 the right of
way for the Port Project is free from all encumbrances. The
petitioner cannot postpone the execution of the project on
the ground that entire land was not given at once. He took
us through the meaning of the word 'Port Assets' and 'State
Support Agreement' as defined in Clauses 1.46 and 1.56.
Referring to Clause 3.2.3, he would submit that the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
Concessionaire shall make all reasonable endeavours to
procure the 'satisfaction in full' of the conditions precedent
set out in Clause 3.2.1 and GoAP shall make all reasonable
endeavors to procure fulfillment of the conditions set-forth
in Sub-clauses (a),(b),(c),(e) and (i) of Clause 3.2.1.
14. Referring to Clause 3.2.4, he would contend that, if
the Concessionaire failed to satisfy its obligations under
Clause 3.2.3 on or before the Financial Closure, as per the
Detailed Proposal, the GoAP may notwithstanding anything
to the contrary contained in the Agreement, terminate the
Agreement in accordance with the provisions of Clause 10
without being liable in any manner whatsoever to the
Concessionaire.
15. He also took us through Clause 3.5 to show that the
entire extent of land need not be given in one go. In so far
as State Support Agreement, said to have been submitted
by the petitioner, he would submit that the conditions
mentioned by the petitioner in the said agreement are
inbuilt in the main agreement itself, which is evident if the
same is juxtaposed with the clauses of the agreement. He
also relies upon clause 4.3.1 and clause (c) of 4.3 to
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
contend that the condition stipulated therein namely
achieving financial closure and making the finances
available in a timely manner are not achieved. He took us
through the letters written by the petitioner, but, in none of
these letters, there is any reference to Government going
back on executing the State Support Agreement. He also
laid much stress on the letter dated 14.03.2017 addressed
by the petitioner to the Government in refusing to accept
2360.52 Acres of land adjoining the Sea.
16. Coming to the Clause 10.10, learned Advocate
General would contend that the judgment of Hon'ble
Supreme Court held that mere absence of notice prior to
an advance order does not violate the principles of natural
justice unless prejudice is shown on account of non-
issuance of notice prior to an advance order. According to
him, there is a contractual dispute and the needs to be
disputed basing on the terms of the agreement. He took us
through Section 39 of the Indian Contract Act, 1872 in
support of his plea. Having regard to the above and the
events which took place later, he would submit that the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
Writ Appeal itself is liable to be dismissed leave alone
granting any interim relief.
17. The point that arises for consideration is whether
the petitioner/appellant is entitled for the interim
relief, as sought for, more particularly in I.A.Nos.2 to
4 of 2022?
18. Along with the Writ Appeal, I.A.No.3 of 2022 came to
be filed, seeking suspension of the order of the learned
Single Judge in W.P.No.12980 of 2019 dated 25.08.2022.
It is to be noted here that when the writ petition itself was
dismissed and the interim order was to restrain the
respondents from finalizing the tenders, which has been
finalized immediately after the judgment is pronounced,
the question of suspending the judgment of learned Single
Judge as sought for in I.A.No.03 of 2022 does not arise and
even if done, nothing useful to the appellant would get
restored, as the interim order passed earlier got merged
with the final order.
19. In so far as the relief claimed in I.A.No.02 of 2022 is
concerned, namely to restrain the respondents from
handing over the Machilipatnam Port to third parties, it is
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
to be noted that subsequent to the judgment of the learned
Single Judge, a Letter of Award was issued on 25.08.2022
in favour of the lowest bidder and thereafter agreements
were entered into between the Government of Andhra
Pradesh and the lowest bidder. Therefore, prima facie the
relief of restraining the respondents, from handing over of
the project, as sought for in I.A.No.02 of 2022, also cannot
be granted.
20. Coming to the relief in I.A.No.04 of 2022 namely
suspension of G.O.Ms.No.66 dated 08.08.2019 and
G.O.Ms.No.9 dated 17.08.2021, Sri Dammalapati Srinivas,
learned Senior Counsel, would contend that, it is not
necessary to challenge the constitutional validity of
G.O.Ms.No.9 since the entire case is based on
G.O.Ms.No.66, and as such, the delay in seeking
suspension may not matter much. According to him, if
G.O.Ms.No.66 is quashed, the appellant would be entitled
for the relief claimed.
21. Sri S. Sriram, learned Advocate General, appearing
for the respondents, opposed the same.
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
22. In so far as suspension of G.O.Ms.No.9 dated
17.08.2021 is concerned, it is to be noted that validity of
the G.O. is not under challenge. Apart from that, though
this G.O.Ms.No.9 was made part of the material papers
filed along with the writ petition, no effort was made to
seek suspension of G.O.Ms.No.9, leave alone challenging
its validity. Though, the said G.O. was in the public
domain, the petitioner herein did not participate in the
Tender process. Explanation, which is now sought to be
given in our view, cannot be accepted. Apart from that as
per the new model of the Port, the total quantity of land
required for the project was reduced to about 830 Acres to
begin with and the value of the project was also reduced by
nearly Rs.700 Crores. Therefore, prima facie the request of
the appellant seeking suspension of the G.O.Ms.No.9
cannot be accepted at this stage.
23. In so far as G.O.Ms.No.66 dated 08.08.2019 is
concerned, it is to be noted that W.P.No.12980 of 2019,
was filed challenging the validity of the G.O.Ms.No.66, and
interim suspension of the said G.O. was sought. But, the
learned Single Judge on appreciation of the material
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
available on record found that the balance of convenience
was not in favour of the petitioner, warranting suspension
of the said G.O. Having regard to the above, and as the
writ petition itself came to be dismissed after analyzing
every aspect of the matter, suspending the said G.O. would
not arise.
24. Coming to the argument advanced touching the
merits of the case, the timeline for completion of the project
was expressly provided in Clause 4.3.1 of the Agreement,
which requires the appellant to secure Financial Closure
within twelve (12) months from the commencement date
i.e. the date on which agreement was entered into between
Government of Andhra Pradesh and Concessionaire. It is
also to be noted here that the agreement was entered into
in the year 2008/2010 but till date, the project did not
budge forward, though substantial extent of land was
offered from time to time, which we will refer to a little
later.
25. Before proceeding further, it is also to be noted that
both the parties have agreed to revise the timelines after
grant of extensions, as contemplated in the letter, dated
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
10.09.2015, and the conduct of both parties is required to
be tested with reference to the timelines revised there
under. Prima facie it is to be noted here that the
commencement date would be the date of approval of
revised DPR i.e. in the year 2015 and the financial closure
of 12 months from thereon and the completion of the
Agreement would be 36 months from the commencement
date. The same was reduced in G.O.Ms.No.15 dated
12.05.2016. Hence, the conduct of the parties is relevant
for the present purpose, and the findings given therein,
cannot be said to illegal or incorrect.
26. It would be appropriate to refer Clause 3.2.1 (b) of the
Revised Concession Agreement which reads as under:-
3.2.1 (b) : the concessionaire shall been granted the following in connection with the project including:
(i) right of way for the Port Project free from all encumbrances, and;
(ii) permission/licence to enter upon and utilize the area within the port boundaries for the construction pursuant to and in accordance with this agreement.
A reading of the same would prima facie indicate that there
was no condition precedent, for the Government to
handover the entire extent of land to the petitioner in one
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
go. It only prima facie show that the Concessionaire shall
be granted right of way for the Port Project free from all
encumbrances. The word 'Project or Port Project' is limited
to areas inside the defined Port boundaries and, includes
but it is not limited to, the construction, provision of
facilities etc. as defined in Clause 1.48. Therefore, the
conditions precedent for providing land is the way to the
Port Project should be free from all encumbrances, which is
said to have been complied with.
27. It is also to be noted that initially the Government
agreed to handover, land to extent of 6262 Acres, but,
subsequently, the extent of land was reduced to 4800
Acres as per G.O.Ms.No.15 dated 12.05.2016. Prima facie,
nowhere, in the initial agreement or in the subsequent
G.O., it is mentioned that the entire extent of land will be
handed over in a single spell. But, when the Government
vide letter dated 10.03.2017 offered the petitioner to take
over the land to an extent of 2360.52 Acres for
development of Port, the appellant rejected the said
proposal of the Government vide reply dated 14.03.2017,
wherein, he requested the Government to hand over the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
entire extent of land of 5324 Acres free from all
encumbrances.
28. The appellant herein seeks to interpret the said
clause in the agreement as qualified refusal on account of
the encroachments, found in certain extents. It is no
doubt true that in some of the communications, there is a
reference to some encroachments here and there, but the
contents of letter dated 14.03.2017, signifies its refusal to
accept the land without being given the possession of the
entire extent of land, as agreed i.e. 5324 Acres, with
provision of external infrastructure etc. Prima facie in our
view and as observed by the learned Single Judge, this was
never a condition precedent in the agreement.
29. At this stage, it would be appropriate to refer to
Clause 3.5 of the Agreement, which prima facie states that
the entire extent of land as required to be handed over to
the appellant would be during the concession period,
which would extend over a period of thirty [30] years.
Since the said terms of the conditions have not challenged,
the argument of the learned Senior Counsel that the
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
project could not be take up as the entire land was not
given, cannot be accepted at this stage.
30. In so far as the Clauses 3.2.3 and 3.2.4 are
concerned - 3.2.3 obligates the Concessionaire to make all
reasonable endeavor to procure the satisfaction in full of
the conditions specified in Clause 3.2.1 [a, b, c, e & l].
Clause 3.2.4 contemplates that if the Concessionaire fails
to fulfill the obligations in 3.2.3 on or before Financial
Closure, the respondents can terminate the Contract in
accordance with Clause 10.10 and vice versa, meaning
thereby, the appellant is responsible for satisfaction of
some conditions, while the respondents have to satisfy the
same. Prima facie the said Clause would show that the
first respondent herein shall fulfill clauses a, b, c, e and l of
Clause 3.2.1 while the appellant shall satisfy Clause 'd' of
Clause 3.2.1 which deals with State Support Agreement.
31. As observed earlier and as held by the learned Single
Judge that it is Concessionaire who should satisfy Clause
(d) and non-satisfaction of the same, prima facie in our
view may not be a ground to refuse commencement of
work. Clause 3.2.4 empowers the respondent to terminate
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
the contract if Clause 3.2.1 (d) has not been complied with.
It is also to be noticed that the correspondence relied upon
to show that Clause 3.2.1 (d) was acted upon, was prior to
G.O.Ms.No.15 dated 12.05.2016. The said correspondence
relied upon, prima facie, may not help the case of the
appellant, in view of the revised timeline in the letter dated
10.09.2015, which was approved in G.O.Ms.No.15.
32. As stated earlier, the State on its part, communicated
to the appellant, its readiness to handover land
admeasuring 2360.52 acres of land and 519 acres of
assigned land vide its letter dated 10.03.2017 which was
rejected vide letter dated 14.03.2017. The argument of
learned Senior Counsel that since the entire land was not
handed over under the agreement, they could not secure
Financial Closure for want of entire extent of land to be
mortgaged in Clause 3.6 and for that reason the appellant
did not accept 2800 acres of land offered in the year 2017
cannot be accepted. In fact Clause 3.5 as referred to
earlier explains the situation.
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
33. In the letters dated 08.04.2019 and 09.04.2019,
addressed by the petitioner to the Principal Secretary,
Investment (Ports) Department, it has been mentioned that
the preliminary construction activities for the development
of the Port has commenced at the site. It is also mentioned
that the acquisition of land for development of Port is fast
progressing through MUDA. That being the position, prima
facie, we feel that there is no reason why the petitioner
failed to go ahead the Project with the land made available
and as to why he refused to take the land offered in the
year 2017. In the said letter, the request was for
exemption of payment of seigniorage fees. But, strangely in
the letter dated 25.05.2019, it has been mentioned that the
construction activities of Port development are expected to
commence very soon and hence a request is made that
lease of land free from encumbrances with right of way,
conclusion of State Support Agreement etc. be expedited by
the GoAP. Both these letters, prima facie in our view run
contra to each other.
34. Therefore, from the total analysis of the facts, prima
facie it appears that the writ petitioner disabled himself
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
from performing, that it could not proceed with Financial
Closure on account of any of its obligation of non-
conclusion of State Support Agreement, is clearly
untenable, more particularly, when it was its obligations to
secure the same as per Clause 3.2.1 (d). It also appears
from record that the writ appellant started imposing new
conditions for starting the ground work, which is evident
from the letter, dated 14.03.2017 and the correspondence
thereafter. In that view of the matter, it cannot, prima
facie, be said that the Government did not cooperate for
executing the State Support Agreement. The fact of the
matter, prima facie appears to be that even after issuance
of G.O.Ms.No.15, the appellant started imposing new
conditions.
35. The learned Senior Counsel appearing for the
appellant laid much stress on the word 'in full satisfaction'
as expressed in Clause 3.2.1 in so far as issuance of State
Support Agreement by the State and in view of the
admitted default by the State in this regard. But, having
regard to the finding given above and the findings of the
learned Single Judge, while referring the Clauses 3.2.3 and
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
3.2.4 wherein it is found that the obligation of the
Concessionaire was to secure State Support Agreement;
the consequences of the default as agreed under the
agreement; coupled with the conduct of the appellant
would show that such a plea is untenable.
36. Clause 10.10 of the Concession Agreement, deals
with Termination of the Agreement. After referring to host
of judgments and the common law principle, in England,
coupled with the judgment of Hon'ble Supreme Court in
Air India Limited vs. GATI Limited1, it was held that in
case of a repudiatory breach of contract, it would be open
to the injured party, under Section 39 of the Indian
Contract Act, 1872, to simply accept the repudiation by the
offending party and in such cases, the procedure set out in
the contract need not be followed. Prima facie, we find no
reason to disagree with the view expressed by the learned
Single Judge.
37. Therefore, in view of the judgment of the Hon'ble
Supreme Court in Raunaq International Limited vs.
1 2015 SCC Online Del 10220
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
I.V.R. Construction Limited and others2, the events
subsequent to the disposal of the writ petition; including
finalization of the tender for the Greenfield Area Port on
EPC basis, issuance of Letter of Award; entering into
agreement with lowest bidder; no challenge to G.O.Ms.No.9
and having regard to the requests made in Interlocutory
Applications, which could not be granted at this stage and
the order of the learned Single Judge, which cannot be said
to be perverse, we feel that it is in-equitable to grant Status
quo, as sought for by the appellant, more so when the
balance of convenience is not in favour of the petitioner.
For the aforesaid reasons, we find no grounds to grant the
interim relief including an order of status quo, as sought for
by the petitioner/appellant.
38. Accordingly, I.A.Nos.2 to 4 of 2022, are dismissed.
There shall be no order as to costs.
_______________________________ JUSTICE C.PRAVEEN KUMAR
_________________________________ JUSTICE A.V. RAVINDRA BABU Date:29.09.2022 MS
2 (1999) 1 SCC 492
CPK, J & AVRB,J I.A.Nos.2 to 4 of 2022 in W.A.No.672 of 2022
THE HON'BLE SRI JUSTICE C.PRAVEEN KUMAR
AND
THE HON'BLE SRI JUSTICE A.V. RAVINDRA BABU
I.A.Nos.2 to 4 of 2022 in Writ Appeal No.672 of 2022 (per the Hon'ble Sri Justice C. Praveen Kumar) Date:29.09.2022
MS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!