HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO WRIT PETITION No.30938 of 2022 ORDER:
The petitioner had been awarded various contracts for
O&M to Annual Maintenance of Weed free on Chinchinada
channel from KM 6.200 to KM 8.850 and its branch channels
under the jurisdiction of WUA-Penumadam, Repairs and
replacement of shutters and hosting equipment for branch
channels and Direct pipes on Chinchinada Channel under
the jurisdiction of Water Resources Section Palakollu and
O&M Formation of Cross bund on Gummuluru Minor Drain
@ KM 0.600 near Gummuluru Village in WUA, Penumandam
jurisdiction in West Godavari District, under various
Agreements. After execution of the said works, a final bill for
Rs.5,88,500/- had been prepared and submitted to the
concerned for payment. As the payment of the said amount
has not been made by the respondents, the petitioner had
approached this Court, by way of this writ petition.
2. It is the contention of the petitioner that even
though the respondents admitted that the petitioner is
entitled for payment of the aforesaid sums of money, no 2
payment is being made. The petitioner contends that such
non-payment of money is clearly arbitrary and high-handed
requiring the interference of this Court.
3. This Court, in various orders, including the
judgment of a learned Single Judge of this Court dated
05.10.2021 in W.P.No.10038 of 2021 and batch had taken
the view that such non-payment of dues is arbitrary and that
such dues need to be cleared by the respondents at the
earliest.
4. The learned Government Pleader submits that the
respondent authorities are verifying the claims of the
petitioner and would be in a position to make payment only
after such verification is completed.
5. In view of the aforesaid directions of this Court in
various cases and after hearing the submissions of the
learned counsel for the petitioner, learned Government
Pleader for Irrigation, this writ petition is disposed of with a
direction to the respondents to complete the verification
process within a period of three weeks from the date of
receipt of a copy of this order and thereafter to pay the 3
amount due to the petitioner depending upon the outcome of
the verification, within a period of six weeks. It is clarified
that in the event of the verification process not being
completed within the aforesaid period of three weeks, the
respondents shall pay the amount due to the petitioner,
without insisting upon any further time for verification. It
would also be open to the petitioner to agitate his/her/their
claim for interest, if any payable by the respondents, in an
appropriate forum. There shall be no order as to costs.
As a sequel, pending miscellaneous petitions, if any,
shall stand closed.
____________________________ R. RAGHUNANDAN RAO, J.
01.11.2022 RKS 4
HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO
WRIT PETITION No.30938 of 2022
01.11.2022
RKS