In a crucial case arising out of a lease termination by Eastern Railway over alleged overloading of a parcel consignment, the Calcutta High Court delves into the contours of judicial review in public contracts. At the heart of the dispute was whether the termination, based on a single instance of overloading, violated contractual terms, natural justice, and the petitioner’s rights under public law. The judgment raises vital questions on the extent to which courts can interfere in contractual decisions made by public authorities, especially where safety and misconduct are concerned. Read on to explore how the Court balanced contractual obligations, administrative discretion, and the doctrine of proportionality in the context of railway logistics.

Brief facts:

The case arose from an e-auction by Eastern Railway for leasing parcel space in Train No. 12311, Netaji Express, where the petitioner, Mohammed Sabir, emerged as the successful bidder. During the lease term, Railway authorities detected an overweight consignment at Deen Dayal Upadhyaya Station, causing a train delay and prompting a penalty. Subsequently, the Railway terminated the contract, forfeited the security deposit, and issued a fresh e-auction notice. The petitioner challenged these actions, alleging violation of natural justice as the weighment was done without his presence and arguing that Clause 14.3 permits termination only after three overloading instances. He also claimed non-receipt of the appellate order dismissing his appeal. After a prior writ was disposed of with liberty to seek further remedies, the present petition was filed seeking restoration of the contract, refund of the penalty and deposit, and compensation.

Contentions of the Petitioner:

The petitioner argued that the weighment was conducted without his presence, violating Clause 27.8 and breaching natural justice. He claimed the overloading allegation was unfounded, as the brake van had been sealed under Clause 10.4, and the delay was due to defective buffers. Challenging the termination and forfeiture as illegal, he cited Clause 14.3, which allows such action only after three overloading instances, whereas this was the first. He further alleged coercion in signing the Delivery Register and paying a penalty under threat of arrest, contrary to Clause 14.4 of the Freight Marketing Circular. The imposition of penalty, termination, and forfeiture for a single offence was said to be disproportionate. Lastly, he asserted that the appellate order was never served and was based on non-existent Clauses 17.3 and 28.3.

Contentions of the Respondent:

The Railway asserted that the consignment exceeded the 4,000 kg limit by 134%, posing a serious safety risk due to reduced buffer height and potential derailment. The weighment was conducted per a joint report with officials present, and halting the train for the petitioner’s presence was impractical. Relying on Clause 18.1, the Railway justified termination and forfeiture due to serious misconduct. It contended the petitioner’s representative did not request re-weighment, and the appellate order was sent via speed post. Under Clause 9.7, loading within permissible limits was the petitioner’s responsibility, and staff sealing did not absolve it. The re-auction followed SOP 2018 to prevent revenue loss, and the petitioner was free to participate.

Observations of the Court:

Justice Partha Sarathi Chatterjee observed, “An act of overloading to the extent of 8,344 kgs, where the permissible tolerance limit was 4,000 kgs—amounting to over 134% of the allowable limit... was considered by the Railway authorities as not being in line with good industry practices and amounting to serious misconduct on the part of the contractor. Experts opined that such excessive overloading could have led to a serious accident involving the passenger train. Furthermore, the contractor had furnished incorrect information in the manifest regarding the number of packages and the weight of the parcels. Therefore, considering the misconduct, I find no justification to hold that the decision was perverse or that the punishment was disproportionate.”

The Court emphasized the limited scope of judicial review in contractual matters, stating, “Undeniably, it is a well-settled principle of law that the scope of judicial review in contractual matters is limited.” The Court noted that writ jurisdiction is a public law remedy, applicable only when a public law element is involved, and interference is warranted if the State’s actions are illegal, irrational, or unreasonable.

Moreover, the Court observed that the contract allowed the Railway to terminate without notice under Clause 18.1 for serious misconduct, such as overloading by 134%, which posed a safety risk. The Court found no contractual provision mandating the petitioner’s presence during re-weighment in emergencies, stating, “he could not cite any contractual provision mandating that re-weighment be carried out in the presence of the contractor or his representative in cases where overloading necessitates unloading at any intermediate station.”

The presumption of regular performance of official acts was upheld, as the petitioner failed to prove mala fide intent. On natural justice, the Court referred State of Uttar Pradesh vs. Sudhir Kumar Singh & Ors. and Gorkha Security Services v. Government (NCT of Delhi), noting, “The rules of natural justice are not embodied rules, nor are they elevated to the status of fundamental rights,” and their application depends on the case’s facts. The petitioner’s acceptance of the contract’s terms, which allowed termination without notice, negated prejudice claims. The Court clarified that Clause 14.3, requiring three overloading instances for termination, was inapplicable to gross overloading (134%), which constituted serious misconduct.

The decision of the Court:

In the light of the foregoing discussion, the High Court dismissed the writ petition, finding no infirmity in the Railway’s decision-making process or perversity in terminating the contract and forfeiting the security deposit.

Case Title: Mohammed Sabir Vs. Union of India & Ors.

Case No.: WPA 8641 of 2024

Coram: Justice Partha Sarathi Chatterjee

Advocate for Petitioner: Sr. Adv. Milan Chandra Bhattacharjee and Adv. Sulagna Bhattacharya

Advocate for Respondent:  Sr. Adv. Soumik Nandi and Adv. Pradyut Saha

 

Picture Source :

 
Ruchi Sharma