Citation : 2023 Latest Caselaw 498 UK
Judgement Date : 24 February, 2023
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
24TH FEBRUARY, 2023
ARBITRATION APPLICATION No. 42 OF 2022
Between:
Ashoka Foam Multiplast Private Ltd. ...Applicant
and
The New India Assurance Company Ltd. ...Respondent
Counsel for the applicant. : Mr. Dharmendra Barthwal, the learned
counsel.
Counsel for the respondent. : Mr. V.K. Kohli, the learned Senior
Counsel assisted by Mr. Kanti Ram, the
learned counsel.
JUDGMENT :
I have heard the learned counsel for the applicant,
and the learned Senior Counsel for the respondent at length.
I proceed to dispose of the present Arbitration Application,
preferred by the applicant, under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (the Act), to seek
appointment of a sole arbitrator.
2. The applicant is a company engaged in
manufacturing and sale of plastic molded furniture, aluminum
composite panel and mattresses. The applicant purchased a
Standard Fire and Special Perils Policy, having Policy No.
34080011180100000205, from the respondent-Insurance
Company, covering his factory assets. The total insured
value was Rs. 58,25,00,000/-. The said policy covered the period from 07.10.2018 to 06.10.2019. The applicant paid a
onetime premium of Rs. 6,71,978/- including GST. In Clause
13 of this Standard Fire and Special Perils Policy, there is an
arbitration clause, which provides that in case any dispute or
difference arises, as to the quantum to be paid under the said
policy, such difference shall, independently of all other
questions, be referred to the decision of the sole arbitrator to
be appointed in writing by the parties. In case they cannot
agree upon an arbitrator within 30 days, the same shall be
referred to a panel of three arbitrators. The said clause reads
as follows :-
"13. If any dispute or difference shall arise as to the quantum to be paid under this policy (liability being otherwise admitted) such difference shall indeperdently of all other questions be referred to the decision of a sole arbitrator to be appointed in writing by the parties to or if they cannot agree upon a single arbitrator within 30 days of any party invoking arbitration, the same shall be referred to a panel of three arbitrators, comprising of two arbitrators, one to be appointed by each of the parties to the dispute/difference and the third arbitrator to be appointed by such two arbitrators and arbitration shall be conducted under and in accordance with the provisions of the Arbitration and Conciliation Act, 1996.
It is clearly agreed and understood that no difference or dispute shall be referable to arbitration as hereinbefore provided, if the Company has disputed or not accepted liability under or in respect of this policy.
It is hereby expressly stipulated and declared that it shall be a condition precedent to any right of action or suit upon this policy that the award by such arbitrator/ arbitrators of the amount of the loss or damage shall be first obtained."
3. It appears that, unfortunately, on 30.09.2019 a fire
broke out at the petitioner's factory premises, leading to
large scale destruction. On the same day, the applicant put
the respondent to notice of the said fire, and the applicant
itself assessed its loss to the tune of Rs. 20-25 crores. The
respondent-Insurance company appointed M/s JSR Insurance
Surveyors & Loss Assessors (JSRSLA) as their surveyors to
survey and assess the loss suffered by the applicant. The
surveyor and assessor, appointed by the respondent, made
its report dated 13.09.2021. As against the applicant's claim
of Rs. 20.92 crores (revised), the net loss assessed on
reinstatement basis was 12.06 crores. The net liability
assessed for the Spring Mattress Division, which was not an
insured division, was Rs. 4.42 crores approximately. The net
liability for the ACP division, which was an insured divsion,
was assessed at Rs. 4.42 crores. On 28.02.2022, the
surveyor and assessor made an Addendum Report to the tune
of Rs. 3.51 crores approximately, which was stated to be
"quite just and reasonable".
4. The case of the applicant is that, even after
passage of more than 2 years & 3 months from the date of
the fire incidence, its claims were not settled by the
respondent. The applicant claims that the Director of the
applicant was called to Dehradun, and was presented with a
settlement agreement, wherein the applicant was offered a
sum of Rs. 2.10 crores approximately in full and final
settlement of all its claims under the aforesaid policy. The
applicant has averred in the present Arbitration Application as
follows :-
7. That the petitioner having been left with no choice and after financial slump from COVID-19 vide his letter dated 10-09-2021 then gave his consent for claim settlement for fire incident at Rs. 11.33 crores. The figure of Rs. 11.33 crores is the assessed loss (after depreciation and dead stock with GST) for the ACP Division and Spring Mattress Division. However the Surveyor assessed the net liability of the respondent company as Rs 8,82,49,289/- True copy of petitioner's consent letter dated 10-09-2021 is being filed herewith and marked as Annexure no. 4 to this petition.
8. That after several representations and reminders, the respondent then coerced the petitioner to sign a settlement agreement which was prepared by the respondent at Dehradun and asked the petitioner to come to Dehradun and sign the same. The copy of the alleged settlement agreement was never given or provided to the petitioner. The petitioner approach the respondent at Dehradun and could not go through the settlement agreement but due to the coercion and misrepresentation of the respondent in order to receive sum amount signed the same without knowing the complete purport of the said agreement while the respondent kept assuring the petitioner that he would get the desired compensation. It is pertinent to mention that the petitioner signed under financial duress, coercion and undue influence as the petitioner was under extreme financial difficulties and the Respondent company made it abundantly clear pre- requisite condition that before disbursement of any amount of claim, the petitioner will have to sign the documents. True copy of the settlement agreement dated 29-06-2022 is being filed herewith and marked as Annexure no.5 to this petition.
9. It is submitted that the petitioner actually suffered a loss of Rs. 11.33 crores in the said incident and against the loss of Rs 11.33 crores and net liability of the respondent company was worked out by the surveyor as Rs Rs 8,82,49,289/- and out of the said amount meagre amount of Rs. 2,10,75,850/- was disbursed on 05-07-2022 to the banker of Petitioner. The coercive action and undue pressure put on by the Respondent Company is apparent from this aspect alone that the Respondent company has failed to pay even the amount, as assessed by the surveyor. The said amount had been paid almost after two years of the loss. The respondent company only agreed to pay the partial/on account amount only in case the petitioner execute the agreement. The execution and
submission of the discharge voucher as per the language of the respondent company was precondition for the release of the said amount. Being at receiving end, the Petitioner firm was left with no other choice except to succumb to the unlawful pressure of the Respondent company, which was enjoying superior position in the subjected matter. It is all this reason the Petitioner immediately addressed the detailed letter highlighting the coercive action of the Respondent company. The Respondent company had not bothered to give any reply to the same thereby acknowledging the facts stated in the said letter of protest. Beside above till date no explanation has been given by the Respondent company, on which basis the amount had been deducted from the amount assessed by the surveyor. This is an explicit case of dispute of QUANTUM, as even the amount, as assessed by the surveyor has not been paid and the discharge voucher as obtained without free consent, does not qualify as valid discharge. The petitioner has filed only few documents to prove that the dispute arose between the petitioner and respondent. The petitioner reserves its rights to file all the relevant documents before Ld. Arbitrator appointed by this Hon'ble Court. The petitioner also deprecated the very unethical, unfair, unprofessional and indifferent attitude of the respondent Company. True copy of petitioner's protest letter dated 05-07-2022 is being filed herewith and marked as Annexure no.6 to this petition.
5. The applicant has placed on record its protest letter
dated 05.07.2022, alleging that the settlement documents
have been drafted by the respondent as per its desire, with a
prejudiced, unfair and unreasonable frame of mind. The
applicant also claimed that it is a matter of fact that none of
the clauses in the said document were ever disclosed to it, or
brought to its knowledge. The applicant claims that the said
settlement was thrusted upon it to deprive it of fair and
reasonable amount against its bonafide claims, and that the
said exercise was absolutely unlawful pressure tactics used by
the respondent, misusing its superior position, to coerce and
harass the applicant to succumb to their dictates, whilst the
applicant was facing through a state of financial distress. The
applicant stated that it was a matter of record that
considerably inordinate and abnormal delay was caused by
the respondent in processing the claim, when the applicant
was in dire need of funds, consequent to the incidence of fire
loss on 30.09.2019. Keeping in view the peculiar financially
distressed situation, and being under duress and coercion,
the applicant was left with no option than to sign on the
documents prepared by the respondent, in order to get at
least some relief in the form of partial payment of its claim.
It is stated that after a lapse of more than 2 years & 3
months, today, i.e. 05.07.2022, the applicant could receive
payment of only Rs. 2,10,75,850/-, as partial payment
against the claim amount of Rs. 8,82,49,289/-, as assessed
by the surveyor. The applicant made accusation of the
respondent acting in an unethical, unfair, unprofessional and
indifferent manner. This letter was followed by another
protest letter dated 27.07.2022.
6. The respondent denied the allegations made
against it by the applicant in its communication dated
08.08.2022. The respondent stated that the settlement was
negotiated between the parties, and it was accepted by the
applicant after negotiations. The applicant had signed the
agreement through its Managing Director, and the allegations
of thrust, or coercion were denied. The applicant responded
to the said reply of the respondent on 22.08.2022, and
invoked the arbitration agreement, suggesting the name of a
retired District and Sessions Judge, Delhi, to act as the sole
arbitrator.
7. Since no Arbitral Tribunal was constituted by the
parties, this application has been preferred.
8. Upon service, the respondent has filed its
objection. The respondent has opposed the application
stating that there was accord and satisfaction, and there were
no outstanding arbitrable disputes between the parties under
the aforesaid policy. The respondent states that the applicant
had arrived at the said settlement out of its own free will,
without undue influence or coercion, and, in token thereof, it
signed the voucher for Rs. 2,10,76,627/-, whereafter the
payment was made in terms of this settlement agreement
signed between the parties.
9. When the matter was heard by this Court on
06.01.2023, and the settlement agreement was referred to,
this Court observed that it referred to an Addendum Report
dated 28.03.2022 prepared by the surveyor, which had not
been placed on record. Accordingly, the respondent was
directed to place the same on record, which has been filed
along with the supplementary affidavit of the respondent.
10. The submission of Mr. Barthwal, the learned
counsel for the applicant, is that, since the parties,
admittedly, entered into the aforesaid agreement, contained
in the Standard Fire and Special Perils Policy, which contains
an arbitration agreement for settlement of disputes relating
to claims of the applicant, and, since, the applicant has
invoked the arbitration agreement, the said disputes are
liable to be referred for arbitration. He submits that even the
issue of the settlement, being arrived at with undue influence
and coercion, is an arbitrable dispute, which should be
referred for determination of the Arbitral Tribunal.
11. On the other hand, the submission of Mr. Kohli, the
learned Senior Counsel for the respondent, is that, since
there is accord and satisfaction recorded between the parties,
with the execution of the settlement agreement, there is no
surviving dispute between the parties, which could be
referred to arbitration under Clause 13 of the Standard Fire
and Special Perils Policy.
12. Mr. Kohli has referred to the order dated
10.06.2022 passed by the Gujarat High Court in Balkrishna
Spintex Private Limited v. The New India Assurance
Company Limited, (R/PETN. under Arbitration Act No. 66 of
2020); the judgment of the Supreme Court in New India
Assurance Company Limited v. Genus Power
Infrastructure Limited, (2015) 2 SCC 424; and the
judgment of the Supreme Court in United India Assurance
Company Limited v. Antique Art Exports Private
Limited, (2019) 5 SCC 362.
13. Mr. Kohli submits that the Supreme Court has held
that the onus, to establish, prima facie, that the settlement
was arrived at under coercion, fell upon the applicant, which,
according to Mr. Kohli, the applicant has failed to establish.
14. In Genus Power Infrastructure Limited (supra),
the Supreme Court observed in paragraph nos. 9 and 10 as
follows :-
"9 It is therefore clear that a bald plea of fraud, coercion, duress or undue influence is not enough and the party who sets up a plea, must prima facie establish the same by placing material before the Chief Justice/his designate. Viewed thus, the relevant averments in the petition filed by the respondent need to be considered, which were to the following effect:
"(g) That the said surveyor, in connivance with the respondent Company, in order to make the respondent Company escape its full liability of compensating the petitioner of such huge loss, acted in a biased manner, adopted coercion, undue influence and duress methods of assessing the loss and forced the petitioner to sign certain documents including the claim form. The respondent Company also denied the just claim of the petitioner by their acts of omission and commission and by exercising coercion and undue influence and made the petitioner Company sign certain documents, including a pre-prepared discharge voucher for the said amount in advance, which the petitioner Company were forced to do so in the period of extreme financial difficulty which prevailed during the said
period. As stated aforesaid, the petitioner Company was forced to sign several documents including a letter accepting the loss amounting to Rs 6,09,55,406 and settle the claim of Rs 5,96,08,179 as against the actual loss amount of Rs 28,79,08,116 against the interest of the petitioner Company. The said letter and the aforesaid pre-prepared discharge voucher stated that the petitioner had accepted the claim amount in full and final settlement and thus, forced the petitioner Company to unilateral acceptance of the same. The petitioner Company was forced to sign the said document under duress and coercion by the respondent Company. The respondent Company further threatened the petitioner Company to accept the said amount in full and final or the respondent Company will not pay any amount towards the fire policy. It was under such compelling circumstances that the petitioner Company was forced and under duress was made to sign the acceptance letter."
10. In our considered view, the plea raised by the respondent is bereft of any details and particulars, and cannot be anything but a bald assertion. Given the fact that there was no protest or demur raised around the time or soon after the letter of subrogation was signed, that the notice dated 31-3-2011 itself was nearly after three weeks and that the financial condition of the respondent was not so precarious that it was left with no alternative but to accept the terms as suggested, we are of the firm view that the discharge in the present case and signing of letter of subrogation were not because of exercise of any undue influence. Such discharge and signing of letter of subrogation was voluntary and free from any coercion or undue influence. In the circumstances, we hold that upon execution of the letter of subrogation, there was full and final settlement of the claim. Since our answer to the question, whether there was really accord and satisfaction, is in the affirmative, in our view no arbitrable dispute existed so as to exercise power under Section 11 of the Act. The High Court was not therefore justified in exercising power under Section 11 of the Act."
15. In Antique Art Exports Private Limited (supra),
the Supreme Court relied upon, inter alia, on its judgment in
Genus Power Infrastructure Limited (supra). The
Supreme Court, in Antique Art Exports Private Limited
(supra), observed as follows :-
"15. From the proposition which has been laid down by this Court, what reveals is that a mere plea of fraud, coercion or undue influence in itself is not enough and the party who alleged is under obligation to prima facie establish the same by placing satisfactory material on
record before the Chief Justice or his Designate to exercise power under Section 11(6) of the Act, which has been considered by this Court in New India Assurance Co. Ltd. case [New India Assurance Co. Ltd. v. Genus Power Infrastructure Ltd., (2015) 2 SCC 424 : (2015) 2 SCC (Civ) 130] as follows : (SCC p. 429, para 9)
"9. It is therefore clear that a bald plea of fraud, coercion, duress or undue influence is not enough and the party who sets up a plea, must prima facie establish the same by placing material before the Chief Justice/his designate."
20. The submission of the learned counsel for the respondent that after insertion of sub-section (6-A) to Section 11 of the Amendment Act, 2015 the jurisdiction of this Court is denuded and the limited mandate of the Court is to examine the factum of existence of an arbitration and relied on the judgment in Duro Felguera, S.A. v. Gangavaram Port Ltd. [Duro Felguera, S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC (Civ) 764] The exposition in this decision is a general observation about the effect of the amended provisions which came to be examined under reference to six arbitrable agreements (five agreements for works and one corporate guarantee) and each agreement contains a provision for arbitration and there was serious dispute between the parties in reference to constitution of Arbitral Tribunal whether there has to be Arbitral Tribunal pertaining to each agreement. In the facts and circumstances, this Court took note of sub-section (6-A) introduced by the Amendment Act, 2015 to Section 11 of the Act and in that context observed that the preliminary disputes are to be examined by the arbitrator and are not for the Court to be examined within the limited scope available for appointment of arbitrator under Section 11(6) of the Act. Suffice it to say that appointment of an arbitrator is a judicial power and is not a mere administrative function leaving some degree of judicial intervention; when it comes to the question to examine the existence of a prima facie arbitration agreement, it is always necessary to ensure that the dispute resolution process does not become unnecessarily protracted."
16. Mr. Kohli submits that, even when Section 11(6A)
of the Act was in force, the Supreme Court rejected the
submission that the Court would not examine the issue,
whether the accord and satisfaction was, prima facie, vitiated
by coercion, or undue influence. He submits that now Sub-
Section 6A of Section 11 of the Act stands deleted and,
therefore, it is for this Court to examine the said issue of
coercion, before referring the parties to arbitration. He has
also referred to the recitals of the settlement agreement
entered into between the parties. The recitals, on which he
has relied upon, are as follows :-
"e) Considering the nature of issues involved, both parties engaged in mutual, transparent free and fair negotiations on various aspects of the claim including questions of liability and quantum of loss, and it has been finally & mutually agrees that the Insurer would pay and the Insured would accept a sum of Rs. 2,10,76,627 in full and final settlement of the Claim as under on Non Standard basis:-
Sr. Items damaged. Amount
No. agreed
1& Rs. 2,10,76,627
2&
3& Building, Plant & Machinery, Furniture Fixture
4 and Fittings and Stocks
f) Insured has conveyed unequivocal acceptance of the
above amounts towards all items of the claim in full and final settlement.
g) Both parties have agreed that on payment of the above amount by Insurer the Claim shall stand fully and finally settled and the Insurer shall stand discharged from any further liability in respect of the same;
h) The parties consider it necessary to record the aforesaid final agreement on the Claim, in the light of various previous discussions and exchange of correspondence to avoid any disputes, differences or litigation whatsoever at a later date."
17. Mr. Kohli has also placed reliance on Clauses 5, 6
and 7 of the settlement agreement, which reads as follows :-
"5. This Agreement or payment by the Insurer shall not entitle the Insured to raise any further claim or dispute at a later date on any pretext or for any one or more of the individual items comprised under the Claim.
6. That this Agreement shall constitute and may be used as evidence of full and final settlement of the Claim and as an accord and satisfaction thereof, after mutual discussions, negotiations and resolution of all disputes and differences that had arisen in the previous stages of the claim.
7. No dispute or difference shall survive in respect of the Claim (individually and/or collectively) after the execution of this Agreement and payment by the Insurer of the amount of Rs. 2,10,76,627/- stated above."
18. On the other hand, Mr. Barthwal submits that,
recently, in a similar situation, the Delhi High Court has
appointed the sole arbitrator to adjudicate the disputes
between the parties before it, arising out of a similar policy,
to arbitration, and the issue of accord and satisfaction has
been left for determination by the learned Arbitral Tribunal.
He has placed before me the order dated 09.01.2023 passed
in M/s Shree Ram Polymer v. The New India Assurance
Co. Ltd., (Arbitration Petition No. 841 of 2022), by a learned
Single Judge of the Delhi High Court, wherein Mr. Justice S.P.
Garg (Retd.) has been appointed as the sole arbitrator. The
respondent in the said case was also the New India Assurance
Co. Ltd., which is the respondent in the present application as
well.
19. I have perused the pleadings, and the documents
filed by the parties, and I have also considered their rival
submissions, and the decisions relied upon by them.
20. First and foremost, there is no dispute about the
fact that the parties entered into the agreement styled as
"Standard Fire and Special Perils Policy", which contains an
arbitration clause in Clause 13 for settlement of disputes with
regard to the quantum of claim to be paid under the said
policy.
21. The defense set up by the respondent is that of
accord and satisfaction, by virtue of the settlement
agreement executed between the parties on 29.06.2022. The
applicant has claimed that the same is vitiated by coercion.
22. In the light of the aforesaid judgments of the
Supreme Court, I have to, prima facie, satisfy myself,
whether the plea of coercion raised by the applicant is an
acceptable plea, which would require further examination, or
it is a plea, which cannot be accepted in the light of the facts
and circumstances of the case. At this stage, I may also refer
to the judgment of the Supreme Court in Oriental
Insurance Company Limited and Another v. Dicitex
Furnishing Limited, (2020) 4 SCC 621, relied upon by Mr.
Barthwal. This case also relates to a Standard Fire and
Special Peril Policy obtained by the respondent-Dicitex
Furnishing Limited. In this case, the first surveyor had
assessed the loss at Rs. 12,28,60,369/-, and the second
surveyor had made an assessment of the loss at Rs.
7,16,30,148/-. Dicitex Furnishing Limited was paid an
amount of RS. 7,16,30,148/-, which the appellant-Insurance
Company claimed was the clean discharge, and full and final
settlement of the claim of Dicitex Furnishing Limited. The
appellant-company claimed that there was accord and
satisfaction, which was disputed by the claimant-Dicitex
Furnishing Limited, with the plea of coercion. The conclusion
drawn by the Supreme Court is in paragraph no. 26 of the
judgment, which reads as follows :-
"26. An overall reading of Dicitex's application [under Section 11(6)] clearly shows that its grievance with respect to the involuntary nature of the discharge voucher was articulated. It cannot be disputed that several letters -- spanning over two years--stating that it was facing financial crisis on account of the delay in settling the claim, were addressed to the appellant. This Court is conscious of the fact that an application under Section 11(6) is in the form of a pleading which merely seeks an order of the court, for appointment of an arbitrator. It cannot be conclusive of the pleas or contentions that the claimant or the party concerned can take in the arbitral proceedings. At this stage, therefore, the court which is required to ensure that an arbitrable dispute exists, has to be prima facie convinced about the genuineness or credibility of the plea of coercion; it cannot be too particular about the nature of the plea, which necessarily has to be made and established in the substantive (read : arbitration) proceeding. If the court were to take a contrary approach and minutely examine the plea and judge its credibility or reasonableness, there would be a danger of its denying a forum to the applicant altogether, because rejection of the application would render the finding (about the finality of the discharge and its effect as satisfaction) final, thus, precluding the applicant of its right event to approach a civil court. There are decisions of this Court (Associated Construction v. Pawanhans Helicopters Ltd. [Associated Construction v. Pawanhans Helicopters Ltd., (2008) 16 SCC 128] and Boghara Polyfab [National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117] which upheld the concept of economic duress. Having regard to the facts and circumstances, this Court is of the opinion that the reasoning in the impugned
judgment [Dicitex Furnishing Ltd. v. Oriental Insurance Co. Ltd., 2015 SCC OnLine Bom 5055] cannot be faulted."
23. As noticed hereinabove, the incidence of fire in the
applicant's factory took place on 30.09.2019. The said
incidence of fire was communicated by the applicant to the
respondent on the very same day. The respondent appointed
a surveyor, who first made its report on 13.09.2021. The net
loss assessed was to the tune of Rs. 12,60,25,881/- (Rs. 12.6
crores). The net liability assessed for the ACP Division was
Rs. 4,42,39,403.00 (4.42 crores). The loss in the Spring
Mattress Division, to the tune of Rs. 4.42 crores, was
excluded, since that was not insured. The respondent, then,
got an addendum report prepared after nearly six months of
the initial report given by the surveyor and assessor. The
addendum report is dated 28.03.2022. Even in the
addendum report, which is stated to be "Final Assessment
Against ACP Division On Market Value Basis (Without GST)",
the surveyor and assessor assessed the loss at Rs.
35,127,711.00, which was stated to be "quite just and
reasonable".
24. The applicant has averred that, even after making
of the said addendum report, the respondent failed to make
payment of the amount due to the applicant. The relevant
averments made in this application have been set out
hereinabove. The applicant has, inter alia, stated, firstly, that
the Survey Report itself was biased, and in ignorance of the
regulations of the IRDA. The applicant further states that the
applicant gave its consent for settlement of its claims at
Rs.11.33 crores on 10.09.2021, which was the loss assessed
after depreciation and dead stock with GST for the ACP
Division, and the Spring Mattress Division. However, the
surveyor had assessed the net liability of the respondent-
company at Rs. 8,82,49,289/-. The applicant has further
stated that, after several representations and reminders, the
respondent coerced the applicant to sign the settlement
agreement prepared by the respondent at Dehradun, after
asking the applicant to come to Dehradun to sign the same.
The applicant further states that its actual loss is to the tune
of Rs. 11.33 crores, in reply whereof the net liability worked
out by the respondent was to the tune of Rs. 8,82,49,289/-.
Even out of this amount, a meager amount of Rs.2,10,75,850/- was disbursed to the applicant on
05.07.2022. The applicant had no choice, but to succumb to
the unlawful pressure of the respondent-company, who was
enjoying a superior position. However, as soon as the
applicant received the amount of Rs. 2,10,75,850/-, the
applicant lodged its protest letter on the same day, as taken
note of hereinabove.
25. The fact that the claim of the applicant was
surveyed and assessed nearly two years after the incidence
of fire; and was further surveyed and assessed and reduced
vide the addendum report dated 28.03.2022, i.e. after nearly
two and a half years of the incidence of fire; the fact that
even this reduced amount of Rs. 35,127,711/-, which the
surveyor and assessor found to be "quite just and
reasonable", was not paid till the applicant signed the
settlement agreement at Dehradun on 29.06.2022; the fact
that the applicant immediately, on receipt of the settlement
amount of Rs. 2,10,75,850/-, lodged its protest, vide its
detailed communication dated 05.07.2022, all go to show,
prima facie, that the issue of coercion, in the execution of the
settlement agreement, is an issue, which would require
adjudication, and it cannot be said at this stage that the
present is a clear case of "accord and satisfaction" with the
execution of the settlement agreement, and receipt of the
amount thereunder by the applicant.
26. The facts, which were present before the Supreme
Court in the aforesaid decisions in Genus Power
Infrastructure Limited (supra) and Antique Art Exports
Private Limited (supra), were materially different on the
facts in the present case. In Genus Power Infrastructure
Limited (supra), in paragraph no. 10, the Supreme Court
took note of the fact that there was no protest or demur
raised around the time or soon after the letter of subrogation
was signed. The notice was issued by the claimant on
31.03.2011, which was nearly three weeks after the
execution of the letter of subrogation.
27. As noticed hereinabove, in the present case, the
applicant issued the protest letter on the very same day, on
which day the amount of Rs. 2,10,75,850/- was received, i.e.
05.07.2022. Prima facie, it appears that a business
enterprise, which has suffered a huge fire in its factory,
leading to losses, as assessed by the surveyor and assessor
of the respondent-company, to the tune of Rs. 11-12 crores,
which have not been settled for two and a half years, would
be in a state of financial stringency.
28. Similarly, in Antique Art Exports Private
Limited (supra), the incidence of fire took place on
25.09.2013 and 25.10.2013. The protest was lodged by the
claimant after three years of the full and final settlement, and
discharge of claim on 11.07.2016. It was in these
circumstances that the Supreme Court found that the plea of
coercion was, prima facie, not established.
29. In the light of the judgment of the Supreme Court
in Dicitex Furnishing Limited (supra), I am of the view
that it is not for me, at this stage, to return a finding, as to
whether, or not, the settlement agreement is vitiated by
coercion, as alleged by the applicant. All that I have to see is
whether the said plea of coercion is completely unacceptable
in the facts and circumstances of this case. I do not find that
the said plea of coercion is completely unacceptable, and
should be rejected outrightly in the facts of this case.
Accordingly, I reject the objection of the respondent, and
allow the present Arbitration Application.
30. Since a similar claim is already pending
adjudication before Mr. Justice S.P. Garg, Retd. Judge, Delhi
High Court, I appoint Mr. Justice S.P. Garg, Retd. Judge,
Delhi High Court, having Mobile No. - 9910384627, to act as
the sole Arbitrator in the present case as well.
31. It goes without saying that the observations made
hereinabove have been made only for the purpose of
examining the submissions of the parties, and no final finding
of fact has been returned by me in these proceedings. It
shall be open to the parties to raise their pleas before the
sole arbitrator, which shall be examined on their own merits,
in accordance with law.
32. The present Arbitration Application stands disposed
of in the aforesaid terms.
33. Consequently, pending applications, if any, also
stand disposed of.
________________ VIPIN SANGHI, C.J.
Dt: 24th February, 2023 Rahul
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!