Citation : 2023 Latest Caselaw 2207 UK
Judgement Date : 11 August, 2023
HIGH COURT OF UTTARAKHAND AT NAINITAL
Writ Petition (M/S) No. 2233 of 2023
MDDA RAMKY ISBT Ltd. .............Petitioner
Versus
Mussoorie Dehradun Development Authority
...........Respondent
Present:-
Mr. Arvind Desai and Mr. Divyan Agarwal, Advocates
(through video conferencing) and Ms. Gurbani Singh,
Advocate for the petitioner.
Mr. Rahul Consul, Advocate for the respondent.
JUDGMENT
Hon'ble Ravindra Maithani, J. (Oral)
By means of the instant petition, the petitioner
seeks directions to restrain the respondent from
interfering in any manner with the petitioner's
performance of its services in terms of the agreement and
further restraining the respondent from creating or
alienating any third-party rights on the project site.
2. Heard learned counsel for the parties and
perused the record.
3. It is the case of the petitioner that the
respondent issued a request for proposal for undertaking
the construction of Inter State Bus Terminal ("ISBT")
along with commercial complex on Built Operate and
Transfer basis. The petitioner submitted his proposal and
he was awarded the work on 23.06.2003. Subsequently,
the petitioner entered into an agreement with the
respondent. Some dispute arose between the parties. The
petitioner did file an application under Section 9 of the
Arbitration and Conciliation Act, 1996 ("the Act") in the
Commercial Court at Dehradun, which was registered as
Arbitration Case No.39 of 2023. The petition was
dismissed on 21.07.2023. Thereafter, the petitioner filed a
petition under Section 11 of the Act. It was registered
Arbitration Petition No.44 of 2023, which was allowed on
28.07.2023 and Arbitrator has been appointed. It is the
case of the petitioner that when the Arbitration
proceedings were still pending on 26.07.2023, the
respondent did issue a notice to the petitioner to
handover the possession of the project site.
4. Learned counsel appearing for the petitioner
would submit that the term of the agreement is till
26.10.2023. There have been some disputes between the
petitioner and the respondent that were agitated by the
petitioner in the arbitration proceedings firstly, under
Section 9 of the Act and thereafter, a fresh petition that
was filed by the petitioner for appointment of Arbitrator.
But, it is argued that the respondent, in a most arbitrary
manner, without any just reason are adamant to throw
out the petitioner from the project site without due course
of law. It is also submitted that, in fact, admittedly the
petitioner shall remain in project site till 27.10.2023
although, according to him the petitioner claims that he
has right to run the project till 2031.
5. Learned counsel appearing for the respondent
would submit that the petitioner filed an application
under Section 9 of the Act for the similar relief, which has
already been rejected on 21.07.2023, which has yet not
been challenged. Not only this, it is argued that at the
instance of the petitioner Arbitrator has already been
appointed in a proceeding that was undertaken under
Section 11 of the Act. It is argued that the respondent had
already taken possession of the project site on
27.07.2023. Learned counsel would submit that the
reliefs, which the petitioner have sought in Arbitration
proceedings, are again sought in the writ petition. For this
reason the petition is not maintainable.
6. There are gross disputed question of facts in
the instant petition. At the first instant, what is argued on
behalf of the petitioner is that the respondent intends to
disposes the petitioner without due course of law. This
question of possession has been disputed by the
respondent on the ground that the petitioner is not in
possession of the project site and the respondent has
already been taken possession on 27.07.2023. This Court
may not examine those issues in this writ petition.
Moreover, it is admitted case of the petitioner that he has
filed an application under Section 9 of the Act with regard
to the dispute that had arisen with the respondent. It is
also admitted that the application under Section 9 of the
Act has already been dismissed by the Commercial Court,
Dehradun, that order has yet not been challenged. It is
also admitted position that with regard to the dispute that
has arisen between the parties, the petitioner has sought
appointment of an Arbitrator by filing an application
under Section 11 of the Act, which has already been
allowed for constitution of the Arbitral Tribunal.
7. As stated, there are gross disputed question of
facts between the parties, which has arisen out from the
contract. The arbitration proceedings have already been
undertaken on the issue. Therefore, this Court does not
see any reason to entertain the petition. Accordingly, the
petition deserves to be dismissed at the stage of
admission itself.
8. The petition is dismissed in limine.
9. When these lines were dictated, learned
counsel for the petitioner would submit that the petitioner
should be given liberty to raise all these questions in the
appeal that may be filed against the order passed under
Section 9 of the Act.
10. Needless to say, the petitioner is always free to
raise these issues, which has been raised in the petition
before any forum as permissible under law because this
Court has not recorded any finding on any of the issues.
This Court has just not entertained the petition in view of
the nature of dispute between the parties as well as the
recourse to arbitration proceedings by the petitioner.
(Ravindra Maithani, J.) 11.08.2023 Sanjay
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!