Citation : 2022 Latest Caselaw 3686 UK
Judgement Date : 18 November, 2022
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
THE HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
ARBITRATION APPLICATION NO. 59 OF 2022
18th NOVEMBER, 2022
Between:
M/s Pipaliya Engineering and
Construction (Joint Venture) ...... Applicant/Petitioner
and
State of Uttarakhand & others ...... Respondents
Counsel for the applicant : Mr. Prabhat Bohra, learned counsel
Counsel for the respondents : Mr. Mukesh Rawat, proxy
counsel on behalf of Mr.
Shailendra Singh Chauhan,
learned counsel for respondent
No. 1
Ms. Mamta Bisht, learned
Deputy Advocate General for the
State / respondent Nos. 2
and 3
The Court made the following:
JUDGMENT:
The applicant has preferred the present
application under Section 11(6) of the Arbitration and
Conciliation Act, to seek appointment of an Arbitrator.
2) The parties had entered into contract dated
27.11.2013, relating to Bansbagar to Goothi Motor Road,
Stage-II works. The Contract Agreement No. 37 / S.E.-
P.M.G.S.Y / 2013-14 was executed under the PMGSY.
3) The case of the applicant is that the stipulated
date of start was 27.11.2013, and stipulated date of
completion was 26.02.2015. However, the work was
completed in June 2017. The applicant states that the
delay was not on account of the reasons attributable to
the contractor. The applicant claims that the final bill
paid by the respondent was for Rs.4,10,94,969/-. The
applicant states that there was delay in release of the
amount of Rs.5,09,381/- due to the negligence of the
respondent. On 10.10.2017, the applicant sought
release of the aforesaid amount, apart from release of
05 per cent retention money, and additional security
under Clause 43.2 of the General Condition of Contract.
The applicant claims that the respondent has not settled
its claim and, consequently, on 13.06.2020, the
applicant invoked the Arbitration Agreement contained in
Clause 25.5 of the General Condition of Contract. Till
date, no Arbitral Tribunal has been constituted, and
consequently, the present application has been
preferred.
4) Upon issuance of notice, the respondent has
filed its counter-affidavit. The respondent does not
dispute the fact that the parties entered into the
aforesaid agreement, which contains an Arbitration
Clause in Clause 25.5 of the General Condition of
Contract. The respondent, however, disputes the points
made by the applicant.
5) In the aforesaid circumstances, I am inclined
to allow this application. Accordingly, I appoint Mr.
Balveer Prasad, Retd. District Judge (Mobile No.
9358209910), to act as a sole Arbitrator to adjudicate all
disputes between the parties arising out of the aforesaid
agreement.
6) Arbitration Application stands disposed of,
accordingly.
________________ VIPIN SANGHI, C.J.
Dt: 18th NOVEMBER, 2022 Negi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!