Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

ARBAP/29/2020
2022 Latest Caselaw 2673 UK

Citation : 2022 Latest Caselaw 2673 UK
Judgement Date : 26 August, 2022

Uttarakhand High Court
ARBAP/29/2020 on 26 August, 2022
             IN THE HIGH COURT OF UTTARAKHAND

                                  AT NAINITAL
                 THE HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI


       ARBITRATION APPLICATION NO. 29 OF 2020

                             26TH AUGUST, 2022

BETWEEN:

M/s Shiva Electrical & Airport Global Technical Solutions
                                                                   .....Applicant.
And

BRIDCUL                                                          ....Respondent.

Counsel for the Applicant : Mr. Aditya Pratap Singh, learned counsel.

Counsel for the Respondent : Mr. Ajay Veer Pundir, learned counsel.

The Court made the following:

JUDGMENT:(per Hon'ble The Chief Justice Sri Vipin Sanghi)

The applicant has preferred the present Application,

under Section 11(6) of the Arbitration and Conciliation Act,

1996, to seek appointment of a sole Arbitrator under clause

25 of the contract agreement entered into between the

parties on 22.11.2013, to adjudicate the disputes, which have

arisen between the parties in terms of the agreement.

2. The applicant is a consortion of M/s Airport Global

Technical Solutions. The present application has been

preferred by the consortion, and is being pursued by the

Project Coordinator of M/s Airport Global Technical Solutions

Pvt. Ltd, which is the leading member of the joint venture in

terms of the joint venture agreement dated 27.11.2013,

which has been placed on record as Annexure No.1.

3. The case of the applicant is that the applicant

completed the works under the project and the respondent

has also acknowledged that position vide work experience

certificate dated 20.07.2019. The applicant further claims

that its dues are payable and outstanding which the

respondent was not paid. They have been enumerated in the

communication dated 03.10.2019, addressed to the Project

Manager, BRIDCUL, which is now the respondent.

4. The further case of the applicant is that the

contract between the parties contains an arbitration

agreement in clause 25. The relevant part whereof reads as

follows:-

"Clause 25 Settlement of Disputes & Arbitration Except where otherwise provided in the Contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the Contract designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or

abandonment thereof shall be dealt with as mentioned hereinafter:-

1) If the Contractor considers any work demanded of him to be outside the requirements of the Contract, or disputes any drawings, record or decision given in writing by the Engineer on any matter in connection with or arising out of the Contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days request the Project Manager, USIDCL in writing for written instruction or decision. Thereupon, the Project Manager, USIDCL shall give his written instructions or decision within a period of one month from the receipt of the Contractor's letter. If the Project Manager, USIDCL fails to give his instructions or decision in writing within the aforesaid period or if the Contractor is dissatisfied with the instructions or decision of the Project Manager, USIDCL, the Contractor may, within 15 days of the receipt of the Project Manger, USIDCL decision, appeal to the Appellate Authority specified in Schedule 'F' who shall afford an opportunity to the Contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Appellate Authority shall give his decision within 30 days of receipt of Contractor's appeal. If the Contractor is dissatisfied with this decision the Contractor shall within a period of 30 days from receipt of the decision, give notice to the Appointing Authority specified in Schedule 'F' for appointment of arbitrator failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator".

5. The further case of the applicant is that the

applicant invoked clause 25 of the contract agreement. The

applicant also approached the appellate authority, since the

applicant was not satisfied with the stand taken by the

respondent in the meeting held on 21.09.2020, minutes

whereof has been placed on record as Annexure No.12. To

the appeal preferred by the applicant, there was no response

on behalf of the respondent and, consequently, the applicant

invoked the arbitration agreement on 27.01.2020. Once

again, there has been no response and, consequently, this

application has been preferred.

6. The respondent does not dispute that the parties

had entered into the contract agreement dated 22.11.2013,

which contains an arbitration agreement in clause 25. The

respondent also does not dispute the fact that the applicant

has invoked the procedure prescribed in clause 25, and that,

eventually, the arbitration agreement was invoked by the

applicant on 27.01.2020, since no decision was taken by the

appellate authority on the appeal dated 27.01.2020. The only

defence taken by the respondent is that there is no

outstanding dispute between the parties, as the applicant has

been made payment of the entire dues under the contract.

7. As to whether, or not, the claims made by the

applicant are sustainable, is a matter which does not fall for

consideration in these proceedings before this Court, as they

relate to the merits of the claims of the applicant.

8. In view of the aforesaid, the Application is allowed.

I appoint Mr. Justice Pradeep Nandrajog, Retired Chief

Justice, Bombay High Court (Mobile No.9818000130), to act

as the sole Arbitrator to adjudicate all claims/ counter-claims

and dispute between the parties, under the aforesaid

Agreement.

(VIPIN SANGHI, C.J.)

Dated: 26th August, 2022 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter