The General Manager Project vs Smt. Minati Som & 5 Ors
2023 Latest Caselaw 823 Tri

Citation : 2023 Latest Caselaw 823 Tri
Judgement Date : 4 October, 2023

Tripura High Court
The General Manager Project vs Smt. Minati Som & 5 Ors on 4 October, 2023
                      HIGH COURT OF TRIPURA
                            AGARTALA

                         LA.App 37 of 2023

The General Manager Project

                                                          ---Appellant(s)
                                 Versus

Smt. Minati Som & 5 Ors.
                                                     ---Respondent(s)

For Appellant(s) : Mr. Samrat Ghosh, Advocate. For Respondent(s) : Mr. U.K. Majumder, Advocate.

Mr. M. Saha, Advocate.

HON'BLE MR. JUSTICE T. AMARNATH GOUD

Order

04.10.2023.

This is an appeal under Section 54 of the Land Acquisition

Act, challenging the legality, propriety and validity of the Judgment &

Award dated 06.09.2022 passed by the learned LA. Judge, West

Tripura, Agartala, Court No-4 in the Case No.Misc.L.A 55 of 2017.

[2] It is the case of the respondent-claimant, total land

measuring 0.10 acres classified as Bastu (Tilla) of plot No.6545/p

under Khatian No.1582 was acquired by the L.A. Collector, West

Tripura, Agartala and the value of the land has been assessed @ Rs.

62,500/- per acre along with 30% solatium and interest @ 12% per

annum w.e.f. 16.05.2002 to 15.11.2002 and thereby calculated the

amount of compensation to the tune of Rs.8,400/- (Rupees eight

thousand and four hundred) only. The claimants further stated that the

acquired land is developed and located very nearer to the God

Chaturdas Devata Bari, Growth Centre, TSR Camp Road,

Bodhjungnagar P.S., Cattle Farm, Khayerpur Bazar, Old Agartala H.S.

School, Panchayet Office, Post Office, Fire Service Station, Aralia

Bazar, Veterinay Hospital etc. It is surrounded by so any mills,

industries, railway line, rail station and national highways which

increased its potential value. Accordingly, the claimants claimed

Rs.40,00,000/- per kani as compensation for such acquisition.

[3] The O.P. No. 1 i.e. the requiring department contested the

case by filing counter statement justifying the award passed by the LA

Collector and urged that claim of the claimant for enhacement of the

amount of compensation is not tenable in the eye of the law and the

same is liable to be rejected. It is mentionable that earlier GREF was

the requiring department and was impleaded as OP No.1 but

subsequently on the petition of NHIDCL they have been added as OP

No.1 in place of GREF.

[4] The O.P. No.2 the L.A. Collector through counter statement

has stated that the claim statement filed by the claimant side is not

maintainable and that the land was acquired after due compliance with

necessary statutory formalities. That the L.A. Collector after due

consideration of mandatory provisions of the L.A. Act determined the

compensation at the highest side of the prevailing market price. It is

also contended that the acquired land was Bastu (Tilla) class of land

situated far from the road having no potential value and there were no

amenities of modern facilities like electricity. The L.A. Collector,

therefore, prays for making the award made by them final and

absolute.

[5] The learned court below in consideration of the pleadings

of the parties framed the following issues:

(1) Whether the award given by the LA Collector is not proper.

(2) Whether there exists any ground for enhancement of compensation? If so, what should be the quantum of compensation.

[6] The learned court below after examining the pleadings and

documents so placed before him, has observed in the following

manner:

The referring claimants are entitled to get Rs.8,00,000/- per kani only for the acquired land as per their shares. They will also get 30% solatium and 12% interest on enhanced amount of compensation computing from the date of notification under Section 4 of the L.A. Act up to the date of award by L.A. Collector or the date of taking possession of acquired land whichever is earlier as per Section 23(2) and Section 23(1-A) of the said Act respectively. The referring claimants will further get interest @ 9% per annum from the date of taking over possession for one year and thereafter @ 15% per annum after expiry of said one year till payment upon the said excess amount of compensation as per Section 28 of the L.A. Act. As per law laid down by the Hon'ble Supreme Court in Mehrawal Khewaji Trust V. State of Punjab & Ors, 2012 AIR SCW 2822, the interest will also be counted on additional amount as awarded under Section 23(1-A) above and upon the solatium awarded under Section 23(2) of the L.A. Act.

[7] Aggrieved by such award, the appellant herein has filed

this present appeal to set aside and quash the said judgment aware

dated 06.09.2022.

[8] Heard Mr. Samrat Ghosh, learned counsel appearing for

the appellant also heard Mr. M. Saha, learned counsel for the

respondent No.6.

[9] Mr. Samrat Ghosh, learned counsel appearing for the

appellant vehemently contended that the order passed by the court

below is erroneous and it was passed on the strength of Exhibit of 1.

He further contended that the order passed by the court below does

not give any detail regarding enhancing the amount of compensation

from Rs.25,000/- per kani to Rs.8,00,000/- per kani. He further prays

that the matter be remanded back to the court below since the

judgment and award dated 06.09.2022 has been passed arbitrarily

without any justification by which the appellant is deprived by the

impugned award.

[10] Mr. U. K. Majumder, learned counsel for the respondent-

claimant submitted before this court that subject property involved in

this matter pertain to khatian no.729 covering plot Nos.7326/p and

7321/p under the notification No.F.9(44)-REV/ACQ/VI/2002 dated

22.03.2002 which has already been decided by this court in LA.App 44

of 2023. It is also contended by the counsel for the claimant-

respondent that the claimant claimed compensation for Rs.3,00,000/-

(Rupees three lacs) only, but the claimant is entitled for more and fair

compensation. Accordingly, the LA Judge by the impugned order in

challenge has enhanced the amount of compensation and awarded Rs.

Rs.8,00,000/- (Rupees eight lakhs) only per kani for the acquired land

which appears to be just and proper and it does not need any

reconsideration by this court. He also contended that the present

matter may not be remanded back and the appeal filed by the

appellant needs to be dismissed. He further placed on record an order

dated 30.05.2023 passed by this court in LA.App No.44 of 2023 filed

by the General Manager Project wherein this court has considered the

contentions of the respondent and dismissed the appeal by confirming

the judgment and award dated 08.06.2022 passed by the L.A. Judge in

Misc(LA) 47 of 2017. Counsel for the claimant-respondent further

contended that the matter so decided in LA.App 44 of 2023 is identical

to the present case in hand wherein the plots were also under the

same Khatian No.729 and the amount of compensation so awarded

was Rs.8 lakhs per kani.

[11] On perusal of the judgment and award dated 30.05.2023

passed by this court in LA.App No.44 of 2023, this court feels that the

present appeal is squarely covered by the same and requires no

reconsideration. Hence, the appeal filed by the appellant stands

dismissed confirming the judgment & award dated 06.09.2022 passed

by the learned LA. Judge, West Tripura, Agartala, Court No-4 in the

Case No.Misc.(L.A) 55 of 2017.

[12] In view of the above, the instant appeal stands dismissed.

As a sequel, stay, if any, stands vacated. Pending application(s), if

any, also stands closed.

JUDGE

Dipak

Digitally signed by

DIPAK DAS DIPAK DAS Date: 2023.10.09 17:05:57 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter