Citation : 2021 Latest Caselaw 1255 Tri
Judgement Date : 15 December, 2021
IN THE HIGH COURT OF TRIPURA
AGARTALA
WP(C)No.193 of 2021
Sri Timirendu Bhaumik,
son of late Gopi Ballav Bhaumik,
resident of Badurtali Lane,
Krishnanagar, P.S. West Agartala,
P.O. & Sub-Division-Agartala,
District : West Tripura, PIN : 799001
......... Petitioner(s)
-Versus-
1. The State of Tripura,
represented by its Secretary,
Revenue Department, Government of Tripura,
New Capital Complex, P.S. New Capital
Complex, P.S. Kunjaban, Sub-Division-
Agartala, District : West Tripura
2. District Magistrate & Collector,
Sepahijala District
3. Sub-Divisional Magistrate,
Bishalgarh, Sepahijala District
4. Tripura State Electricity Corporation
Ltd.,
(Government of Tripura Enterprise),
Bidyut Bhavan, Banamalipur, P.O. & Sub-
Division-Agartala, District : West Tripura,
PIN : 799001, represented by its General
Manager
5. The Manager,
Tripura State Electricity Corporation Ltd.,
Transmission Sub-Division, 79 Tilla, Agartala,
District : West Tripura
6. Power Grid Corporation of India Ltd.
(Government of India Enterprise),
having its registered office at B-9,
Kutab Institutional Area, Katwaria, Sarair,
New Delhi, PIN : 110016, represented by its
Chairman-cum-Managing Director
Page 2 of 7
7. The Manager,
Power Grid Corporation of India Ltd.,
132 K.V. Kumarghat Sub-Station,
Kumarghat, Ratiabari, P.O. & P.S. Kumarghat,
District : Unakoti, PIN : 799264
8. Senior Manager,
Power Grid Corporation of India Ltd.,
Ramnagar Road No.6, P.O. Ramnagar,
Sub-Division-Agartala, District : West Tripura,
PIN : 799002
........ Respondent(s)
For the Petitioner (s) : Mr. S. Lodh, Adv.
For the Respondent (s) : Mr. K. De, Addl. G.A.
Mr. N. Majumder, Adv.
Mr. R.K.P. Singh, Adv.
Date of hearing & delivery of : 15.12.2021
Judgment and Order
Whether fit for reporting : YES
HON'BLE MR. JUSTICE S. TALAPATRA
JUDGMENT & ORDER
Heard Mr. S. Lodh, learned counsel appearing for the petitioner as well as
Mr. K. De, learned Addl. G.A. appearing for the respondents No.1, 2 and 3, Mr. N.
Majumder, learned counsel appearing for the respondents No.4 and 5 and Mr. R.K.P.
Singh, learned counsel appearing for the respondents No.6, 7 and 8.
2. By means of this writ petition, the petitioner seeks the relief viz. (a) a
direction on the respondents to acquire the land of the petitioner or to vacate the land of
the petitioner which has been utilized for constructing towers for laying transmission line.
The said land falls within the land recorded in Khatian No.2363 of Mouja-
Gokulnagar under Sepahijala District. The relevant fact as adverted in the writ petition is
that, all on a sudden, the petitioner found that some activities were going over his land by
felling down trees which were standing on the said land. According to him, all those
activities were for erecting „pillars‟. However, Mr. R.K.P. Singh, learned counsel appearing
for the respondents No.6, 7 and 8 has confirmed that those are not only pillars but the
towers for laying the transmission lines. The petitioner could not understand who the
people were involved on these activities. However, in contemplation, he wrote a letter to
the Senior General Manager, Power Grid Corporation Limited on 14.03.2020 asking him to
remove "electric pillars" within a month from the date of receipt of the said letter
[Annexure-2 to the writ petition]. It has been further stated by Mr. Singh, learned counsel
that one pillar, in addition to the tower, was constructed over the land of the petitioner.
Since no action was taken, the petitioner had written another letter on 23.06.2020 to the
Senior General Manager, Power Grid Corporation Limited. After that, on 09.09.2020, the
petitioner received a notice dated 03.03.2020 [Annexure-4 to the writ petition] from the
Tripura State Electricity Corporation Limited whereby the petitioner was informed that a
portion of his land having an area of 896.93 sq. ft. would be utilized for purpose of
construction of tower footings/stringing etc. It had been also informed that the Sub-
Divisional Magistrate, Bishalgarh will assess the necessary compensation in that regard.
3. Mr. S. Lodh, learned counsel appearing for the petitioner has made a
categorical submission that even though, the notice is dated 03.03.2020, but it was
handed down to the petitioner on 09.09.2020. To support his contention, Mr. Lodh,
learned counsel has referred to the notice dated 15.09.2020 [Annexure-5 to the writ
petition] wherefrom the following is available :
"Whereas in reference letter of the Sr. Deputy Collector O/o the District Magistrate & Collector, Sepahijala vide no.F.5(44)-VOLL-II/DM/SPJ/REV/18/960 dated, 09/6/20 in connection with objection from the land owner against
construction of 132 KV LILU of Surjyamaninagar-Rokhia at Gakulnagar under South Champamura T.K."
4. On 27.01.2021, the petitioner received one notice from the advocate of the
Power Grid Corporation Limited stating that they had lodged caveat in the Hon‟ble High
Court of Tripura, in the Court of the Additional District Judge, Sepahijala District and in the
Court of the Civil Judge, Junior Division, Sepahijala, Bishalgarh and as such in the event of
institution of the suit along with any application for temporary injunction, the said Power
Grid Corporation is entitled to get the notice of such institution in advance so that they can
have their say before any interim order is passed.
5. The respondents have filed their reply separately. The respondents No.1, 2
and 3 represented by Mr. K. De, learned Addl. G.A. have stated in their reply that for
purpose of constructing the tower, from R.S. plot No.2158/8894 recorded in Khatian
No.2363 under mouja-Gokulpur, a piece of land measuring 895.93 sq. ft. comprised in Plot
No.2158/8894 recorded under Khatian No.896.93 had been sought to be taken over. The
construction was proposed to lay down 132 KV LILU line at Surjyamaninagar, Rokhia. The
petitioner was requested to remain present on 18.09.2020 with documents to elucidate
why he had reservation against the acquisition. It appears from the reply filed by the
respondents No.1, 2 and 3 that the petitioner was unwilling to part with any land from his
land as recorded on the plot No.2158/8894. The respondents No.1, 2 and 3 have placed
on records one communication dated 02.12.2020 of the Sub-Divisional Magistrate,
Bishalgarh, Sepahijala District reflecting that the due compensation was assured. That
apart, the land may be taken over subject to observance and strict compliance of the
relevant provisions of law. But Mr. S. Lodh, learned counsel was categorical in stating that
no compensation has been made, neither the demand for vacation has been attended to.
6. Mr. Singh, learned counsel appearing for the Power Grid Corporation Limited-
respondents has stated that since the said construction of the tower/pillar is a part of a
mission mode project, there had been no time to be sluggish but to go for the erection of
the tower or the pillar for laying down the transmission line, so that those lines can be
dedicated for the beneficiaries of the said project called North Eastern Region Power
System Improvement Project which is directly monitored by the Ministry of Power,
Government of India. This project is exclusively piloted by the Government of India, the
World Bank and Tripura State Electricity Corporation Limited for the State of Tripura. But
Mr. Singh, learned counsel has denied the fact that the due process was not followed at
the time of construction.
7. Mr. N. Majumder, learned counsel appearing for the respondents No.4 and 5
has contended that the land was identified and taken over by the aid of the Sub-Divisional
Magistrate, Bishalgarh, Sepahijala District and due process of assessing the compensation
is on the verge of finalization. The moment the compensation would be determined the
petitioner will be informed for receiving the payment.
8. To this proposition, however, Mr. Lodh, learned counsel did not agree.
According to him, the process as laid down under Section 164 has been totally deviated or
breached both by the National Power Grid Corporation Limited and the Tripura State
Electricity Corporation Limited. Section 164 of the Electricity Act, 2003 provides that the
appropriate Government may, by order in writing, for placing of electric lines or electrical
plant for the transmission of electricity or for the purpose of proper coordination etc., may
take over any line or advantages for purpose of transmission of power. For that purpose,
the power as given under India Telegraph Act, 1885 can be applied by the appropriate
Government. In the Indian Telegraph Act, 1885, Section 10 deals with the placing and
maintaining of the lines. Section 10(b) clearly provides that the appropriate government
shall not acquire any right other than that of user‟s right only in the property under, over,
along, across, in or upon which the telegraph authority places any telegraph line or post.
As such, acquisition of land as projected by the petitioner is improbable, however Section
10(d) provides that in exercise of the powers conferred by the said section, the telegraph
authority shall do as little damage as possible, and, when it has exercised those powers in
respect of any property other than that referred to in clause (c), shall pay full
compensation to all persons interested for any damage, sustained by them by reason of
the exercise of those powers.
9. Mr. Singh, learned counsel appearing for the respondents No.6, 7 and 8 has
categorically stated that the construction of tower or the pillar is over and the transmission
line has been laid and within a short while, the entire power system, as indicated before,
will be delicated to the beneficiaries. Mr. Singh, learned counsel has further submitted that
at this juncture removing of the structure, pillar etc is not called for in view of the
emergent provisions of law emanating from the Indian Telegraph Act, 1885 [see Section
10 of the said Act] as adopted by Section 164 of the Electricity Act, 2003.
10. Having regard to the submissions made by the learned counsel for the
parties, this Court is of the view that the full compensation be made by the respondents to
the petitioner within eight weeks from today. If the petitioner is aggrieved by the
determination, he may approach the District Judge, Sepahijala. In this regard, a decision
of the apex Court in The Power Grid Corporation of India Limited versus Century
Textiles & Industries Limited and Ors. [judgment dated 14.12.2016 delivered in Civil
Appeal No.10951 of 2016] as relied by Mr. Singh, learned counsel for the Power Grid
Corporation Limited may be referred. It has been observed in the said decision that if the
persons from whom the right to use has been acquired, feels aggrieved by the
determination of compensation, the appropriate course of action is to file a suit before the
concerned District Judge for this purpose. It would also be apt to point out that the Central
Government has framed guidelines on 15.10.2015 in that behalf providing inter alia how
the determined quantum of compensation, including other associated facts, may be
resolved having regard to the mode and manner of assessment of compensation as laid
down. In the guidelines, there are also remedies for the persons from whom the right to
use of land is taken.
11. Further directions are not called for. Hence, the respondents are directed to
determine the full compensation and make the payment within two months from today.
The petitioner shall be at liberty, if he is aggrieved by such determination to take out
further action in the manner as stated above, or in terms of the guidelines as referred
before.
Having observed thus, this writ petition stands allowed to the extent as
indicated above.
There shall be no order as to costs.
A copy of this order be supplied to the counsel for the parties.
JUDGE Sabyasachi B
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!