Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S B. Chandraiah And Sons vs Union Of India
2026 Latest Caselaw 664 Tel

Citation : 2026 Latest Caselaw 664 Tel
Judgement Date : 13 April, 2026

[Cites 2, Cited by 0]

Telangana High Court

M/S B. Chandraiah And Sons vs Union Of India on 13 April, 2026

Author: P. Sam Koshy
Bench: P. Sam Koshy
                               Page 1 of 6



       IN THE HIGH COURT FOR THE STATE OF TELANGANA
                       AT HYDERABAD

          THE HONOURABLE SRI JUSTICE P. SAM KOSHY

                 Arbitration Application No.87 of 2025

                      Date of order : 13.04.2026


BETWEEN :


M/s.B. Chandraiah and Sons
                                                           ... Applicant
                                 and
Union of India
                                                         ... Respondent


ORDER :

The instant Arbitration Application has been filed by the applicant

under Section 15(2) read with Section 11 of the Arbitration and

Conciliation Act, 1996 and the scheme for appointment of Arbitrators,

1996 praying the Court to appoint a sole arbitrator having degree in

engineering or equivalent or having passed final or direct final

examination of Sub-Division-II of Institution of Surveyors (India)

recognized by Government of India as per the arbitration in Clause 6(c)

at Serial Page No.83 of the contract agreement and condition 70 of

General Conditions of Contracts I.A.F.W.2249 for resolution of disputes

arisen in the performance of Contract.

2. Heard Mr.C. Vijaya Kumar Reddy, learned counsel for the

applicant; and Mr. K. Mohan, learned counsel for the respondent.

3. The applicant herein is a Partnership Firm engaged in the business

of taking up and carrying out contract works with Military Engineering

Services (M.E.S.), Public Work Department (P.W.D.), and Railways and

also other works of civil nature; and respondent herein is the Union of

India represented by Chief Engineer R & D, Military Engineer Services,

Picket, Secunderabad.

4. Learned counsel for the applicant submitted that respondent had

floated a tender vide No.82410/80/E8, dated 29.03.2010, which was

subsequently amended vide letter No.82410/82/E8, dated 15.04.2019,

for construction of Multi-Level Car parking at GTRE, Bangalore; the

applicant herein had participated in the tender process; since the

applicant was declared as the lowest bidder, the respondent-Union had

accepted the offer of the applicant; accordingly, the applicant was

allocated work contract agreement bearing number

C.A.No.CERD/BAN/06 of 2010-2011; the said contract work was

scheduled to be completed by 26.12.2011; though the contract work

initially got prolonged, however the same was finally completed on

22.03.2017, and the respondent had accordingly issued completion

certificate vide their letter No.8458/East/631/E8, dated 27.03.2017.

5. Learned counsel for the applicant submitted that the applicant had

addressed an application to the respondent on 26.10.2020, requesting

the respondent to clear dues / amount payable to the applicant;

however, vide letter No.82410/575/E8, dated 10.11.2020, the

respondent rejected the claim of applicant stating that the claim of

applicant of applicant is out of purview of the contract; on the basis of

rejection of the respondent, the applicant invoked Clause 6(c) of the

contract agreement duly suggesting three names of retired officers of the

Department of Military Engineer Services, and requested the respondent

to chose one among the three name; however, the respondent, vide reply

dated 12.01.2021, disagreed to choose a name from among the three

names suggested by the applicant and stated that the arbitrator should

be appointed by Engineer-in-chief under condition 70 of the General

Conditions of Contracts (GCC) IAFW 2249; finally, the applicant has

approached this Court by filing Arbitration Application No.55 of 2021

seeking for appointment of a sole arbitrator; vide order dated 23.06.2022,

a learned Single Judge of this Court was pleased to appoint Hon'ble Sri

Justice Ramesh Ranganathan, Retired Chief Justice of the High Court of

Uttarkhand; however, the said Sole Arbitrator resigned as sole arbitrator

on 15.10.2022.

6. Learned counsel for the applicant further submitted that, on

25.07.2024, the applicant again requested the respondent for

appointment of a sole arbitrator by mutual agreement; since there was

no response from the respondent, the applicant was constrained to file

Arbitration Application No.246 of 2024 before this Court; however, the

said arbitration application was dismissed as withdrawn on 13.03.2025

with a permission to file a fresh application under Section 15(2) of the

Arbitration and Conciliation Act, 1996; accordingly, the applicant herein

again filed the instant arbitration application before this Court.

7. On 20.06.2025, notice was ordered to the respondent, and the

learned counsel appearing on behalf of respondent had entered

appearance and filed counter-affidavit in the matter.

8. Perused the record.

9. Having heard the contentions put forth on either side and also

taking into the consideration the nature of dispute, there seems to be a

clear dispute raised by either party which needs to be decided in the

course of arbitration proceedings by invoking Clause 6(c) of the contract

agreement entered into between the applicant and respondent.

Therefore, this Court is of the considered opinion that the instant

arbitration application can be allowed by referring the matter to a sole

arbitrator from the Impanelled Arbitrators (Engineers), Hyderabad from

the Indian Council of Arbitrators.

10. Accordingly, this Court appoints Mr. K. Ravi Kishore, Chief

Engineer, Military Engineer Services (M.E.S.), resident of H.No.10-3-

274/7, Humayun Nagar, Hyderabad 500 028, as the sole Arbitrator to

resolve the dispute between the parties.

11. Needless to state that both parties are at liberty to raise all claims

and counter claims before the sole arbitrator who in turn shall conduct

the arbitration proceedings in accordance with provisions of the Act.

The venue of arbitration shall be decided mutually by the parties subject

to consultation and agreement of the learned Arbitrator. The fee payable

to the learned Arbitrator shall also be decided mutually by the parties in

consultation and agreement with the learned Arbitrator.

12. The Arbitration Application stands allowed as above. No costs.

13. As a sequel, miscellaneous petitions, pending if any, shall stand

closed.

___________________ P. SAM KOSHY, J

Date: 13.04.2026 Note:

The Registry is directed to furnish copy of this order to the learned sole arbitrator

B/o.

Ndr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter