Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Maha Hotel Projects Pvt Ltd vs State Of Telangana
2026 Latest Caselaw 536 Tel

Citation : 2026 Latest Caselaw 536 Tel
Judgement Date : 9 April, 2026

[Cites 6, Cited by 0]

Telangana High Court

Maha Hotel Projects Pvt Ltd vs State Of Telangana on 9 April, 2026

 *THE HON'BLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
                           AND
         *THE HON'BLE SRI JUSTICE G.M.MOHIUDDIN

                    + WRIT APPEAL No.27 of 2026

%09.04.2026
Between
# Maha Hotel Projects Private Limited
                                                            ...Appellant
vs.
$ State of Telangana and 6 others
                                                         ...Respondents

!Counsel for the appellant     :Sri Suraj Prakash, learned Counsel
                                representing Ms.Vanaparthi Vaishali


^Counsel for respondents       : Sri A.Sudarshan Reddy, learned
                                 Advocate General for the State of
                                 Telangana       duly    assisted    by
                                 Sri I.V.Siddhivardhana, learned Special
                                 Government Pleader for respondent
                                 Nos.1 to 3 and 5.

                                Dr.Abhishek Manu Singhvi, learned
                                Senior Counsel and Sri Gyanendra
                                Kumar Seni, learned counsel
                                representing Sri Rajesh Maddy, learned
                                counsel for respondent No.4.

                                Sri N.Bhujanga Rao, learned Deputy
                                Solicitor General of India appearing for
                                respondent No.7

<Gist :
>Head Note :
? Cases referred
1. (2018) 1 SCC 407
2. (2021) 13 SCR 737
3. AIR 1955 SC 74
                                         2



         IN THE HIGH COURT FOR THE STATE OF TELANGANA
                         AT HYDERABAD
     THE HON'BLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
                              AND
            THE HON'BLE SRI JUSTICE G.M.MOHIUDDIN

                      WRIT APPEAL No.27 of 2026

                               DATE:09.04.2026

Between:
Maha Hotel Projects Private Limited
                                                                  ....Appellant
                                       And

State of Telangana and 6 others

                                                                ....Respondents

                                  JUDGMENT

Heard Sri Suraj Prakash, learned counsel representing

Ms.Vanaparthi Vaishali, learned counsel for the appellant;

Sri A.Sudarshan Reddy, learned Advocate General for the State of

Telangana duly assisted by Sri I.V.Siddhivardhana, learned Special

Government Pleader, appearing for respondent Nos.1 to 3 and 5;

Dr.Abhishek Manu Singhvi, learned Senior Counsel and

Sri Gyanendra Kumar Seni, learned counsel appearing through video

conference for Sri Rajesh Maddy, learned counsel for respondent No.4

and Sri N.Bhujanga Rao, learned Deputy Solicitor General of India

appearing for respondent No.7, and perused the record.

2. This Writ Appeal, preferred under Clause 15 of the Letters

Patent, is directed against the order dated 20.11.2025 passed by the

learned Single Judge in W.P.No.30461 of 2025, whereby the writ

petition filed by the appellant came to be dismissed with costs of

Rs.10,00,000/-. The writ petition was instituted challenging the

decision of the Empowered Committee (Tourism) of the State of

Telangana taken in its meeting dated 22.09.2025, whereunder a No

Objection Certificate (NOC) was granted in favour of the 4th

respondent, being the successful resolution applicant under the

Insolvency and Bankruptcy Code, 2016 (for short 'the IBC') for change

in shareholding and control of the project company, M/s. Golden

Jubilee Hotels Private Limited, subject to certain terms and

conditions, to facilitate implementation of the approved resolution

plan.

Factual matrix (in brief)

3. The lis giving rise to the present proceedings has a long and

chequered history spanning over two decades. The State of Andhra

Pradesh (now the State of Telangana), through its Youth

Advancement, Tourism & Culture Department (YATC), conceived a

project for the development of a Five-Star Hotel at Madhapur,

Hyderabad, on a Build-Operate-Transfer (BOT) basis. In furtherance

thereof, a Request for Proposal (RFP) was issued in the year 2005

inviting bids from eligible entities for developing, financing,

constructing, operating, and maintaining the project.

4. Pursuant to the said process, a consortium comprising the

appellant's predecessor, namely My Home Group (Lead Developer),

VBC Group (Financial Member), and EIH Ltd. (Technical Member),

was declared the successful bidder, and in terms of the RFP

conditions. A Special Purpose Vehicle (SPV), viz., M/s. Golden Jubilee

Hotels Private Limited (GJHPL), was incorporated as the project

company for implementation of the project.

5. Thereafter, Lease Agreements and a Development and

Management Agreement (DMA), both dated 09.05.2007, were executed

between the State and GJHPL for a tenure of 33 years, governing the

rights and obligations of the parties in respect of the project. The

consortium structure, with the appellant as the Lead Developer

holding a substantial and controlling equity stake (with approximately

84% shareholding being held by the lead and financial members and

the remaining 16% by EIH Ltd., the technical member), formed the

foundational basis of the project. The project was conceived as a two-

tower development, and upon completion of construction of the first

tower, commercial operations of the 'Trident Hotel, Hyderabad'

commenced in September, 2013, with the second tower being

substantially completed thereafter.

6. Subsequently, disputes arose inter se the consortium

members, on account of alleged financial mismanagement and

diversion of revenues by the technical member, EIH Ltd., which,

according to the appellant, resulted in severe financial distress to

GJHPL. It is alleged that such actions led to the erosion of the

financial position of the project company, culminating in its loan

account being classified as a Non-Performing Asset (NPA) by the

lending consortium of banks led by Bank of Baroda. Consequently,

Bank of Baroda initiated proceedings under Section 7 of the IBC

before the National Company Law Tribunal (NCLT), Hyderabad Bench,

and the Corporate Insolvency Resolution Process (CIRP) against

GJHPL was admitted by order dated 27.02.2018.

7. In the course of the CIRP, the 4th respondent, being the

successful resolution applicant, submitted a resolution plan offering,

inter alia, financial settlement to the creditors, which came to be

approved by the Committee of Creditors (CoC) with a voting share of

68.26%, and was thereafter approved by the NCLT, Hyderabad Bench,

vide order dated 07.02.2020. A material and express condition of the

said resolution plan was that its implementation was contingent upon

obtaining prior written consent of the State Government, including

respondent Nos.1 and 5 (YATC and Shilparamam Society), for

effecting a change in shareholding and control of GJHPL, which was

stipulated as a condition precedent to the plan coming into force.

8. The appellant, aggrieved by the prospect of such change in

control, instituted W.P.No.17129 of 2020 before this Court seeking to

restrain the State from granting such consent, placing reliance on the

provisions of the Telangana Infrastructure Development Enabling

(TIDE) Act, 2001. The said writ petition came to be dismissed by

order dated 28.04.2023 and W.A.No.1135 of 2023 preferred

thereagainst was also dismissed. The Special Leave Petition (C)

No.22186 of 2024 filed before the Hon'ble Supreme Court was likewise

dismissed, wherein it was, inter alia, held that the provisions of the

IBC, 2016 would prevail over the TIDE Act to the extent of any

inconsistency.

9. Owing to delays in obtaining the requisite governmental

approvals, the 4th respondent initially sought to terminate the

resolution plan on the ground of non-fulfilment of the condition

precedent; however, upon subsequent negotiations between the

stakeholders, including the State Government and the lenders, the

process was revived. Thereafter, the State Government, acting

through the Empowered Committee (Tourism), in its meeting dated

22.09.2025, accorded its conditional consent to the implementation of

the resolution plan. The said consent was subject to several terms

and conditions, which are extracted hereunder:

1) Lease with the M/s. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd..

(M/s. Blackstone) will be valid fill the balance period of the earlier lease agreement upto the year 2041 only, without any extension.

2) The company will make upfront payment of Rs. 88.23 crores within 15 days from the date of agreement, which is principal amount due from the previous agency ie., M/s. Golden Jubilee Hotels (P) Ltd.. (GJHPL) to TGTDC.

3) On 07-04-2019, sole arbitrator has pronounced award in favour of developer M/s. Golden Jubilee Hotels (P) Ltd., (GJHPL) against which COP 39/2020 is filed by YAT&C Department. The M/s. Golden Jubilee Hotels (P) Ltd., (GJHPL) has claimed an amount of Rs. 42.50crores including interest in this case. M/s. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd.. (M/s. Blackstone) shall agree to forego this claim against Government of Telangana and TGTDC.

4) The Lease Rental to the TGTDC will be calculated at the rate of Rs. 7,500/- per sq. yrds from the date of agreement ie, May 2007.

5) M/S. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd., (M/s. Blackstone) will take steps to complete tower 2 and make it operational in 24 months from the date of the agreement.

6) Tripartite agreement will be entered between TGTDC. M/s. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd., (M/s. Blackstone) and current operator ie., East India Hotels (EIH) to continue to operate tower I and tower 2, till the end of lease period. Separate agreement can be worked out between M/s. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd., (M/s. Blackstone) and EIH regarding the operations part.

7) All court cases in which M/s. BREP Asia II Indian Holding Co. (NQ) Pte., Ltd., (M/s. Blackstone) has a claim against Government of Telangana and TGTDC, shall be withdrawn. Likewise, court cases pertaining to matters settled in this agreement will be withdrawn by the Government of Telangana.

8) Post NCLT judgement, the escrow account, where surplus funds are deposited by the operator has accumulated Rs. 240 crores as on August 2025. TGTDC will file claims before the NCLT for its unsettled dues ie., Rs. 69.83 crores which is the Interest on the pending Lease Rental & Annual Development Premium (ADP).

10. Aggrieved by the aforesaid decision of the Empowered

Committee granting consent to the 4th respondent and permitting

change in control of the project company, the appellant instituted the

underlying W.P.No.30461 of 2025 challenging the same as being

arbitrary, illegal, and violative of its Constitutional and contractual

rights, including on the ground that its accrued rights as Lead

Developer could not be divested without due process of law and

without compensation. The said writ petition, came to be dismissed

by the learned Single Judge by order dated 20.11.2025, with costs,

thereby giving rise to the present writ appeal.

Submissions on behalf of the appellant

11. Learned counsel for the appellant, assailed the impugned order

and has advanced submissions as under:

i) That the action of the State in effectively divesting and

extinguishing the appellant's accrued proprietary and

contractual rights as the Lead Developer of the consortium is

ex facie arbitrary, illegal, and unconstitutional, being in

violation of Articles 14 and 300A of the Constitution of India.

That such deprivation has been effected without issuance of any

notice, without affording an opportunity of hearing, and without

payment of any compensation, and further in complete

disregard of the termination procedure expressly stipulated

under the Lease Deed and the DMA dated 09.05.2007, which

continue to subsist and have not been terminated in

accordance with law.

ii) That the consent granted by the State Government vide decision

dated 22.09.2025 introduces substantive conditions which are

alien to, and inconsistent with, the resolution plan approved by

the NCLT. In particular, it was pointed out that the imposition

of revised lease rental at Rs.7,500/- per Sq.yd. with

retrospective effect, the requirement of foreclosure/waiver of

arbitral claims, and most significantly, the stipulation for

continuation of M/s.EIH Ltd. as the operator of the hotel under

a tripartite arrangement, are not contemplated under the

approved resolution plan, and thus amount to an impermissible

modification thereof, which is legally untenable in view of the

binding nature of a resolution plan under the IBC.

iii) That the impugned action suffers from manifest arbitrariness

and hostile discrimination inasmuch as two similarly situated

members of the original consortium have been treated

unequally without any rational basis. While the appellant,

being the Lead Developer and majority stakeholder, has been

completely ousted and its rights extinguished, the technical

member, M/s.EIH Ltd., has been permitted not only to continue

but to operate the project, thereby conferring an unjustified and

preferential treatment.

iv) That the project in question constitutes valuable State largesse

and, therefore, any transfer or reallocation thereof is required to

be undertaken through a transparent, fair, and competitive

process consistent with constitutional principles. It was

contended that the State has, in the present case, bypassed the

established norms of public procurement and has effectively

awarded the project to the 4th respondent through private

negotiations arising out of insolvency proceedings, without any

public tender or competitive bidding, thereby violating settled

principles governing distribution of State largesse under Article

14 of the Constitution.

v) That the proposed transfer of 100% shareholding of GJHPL to

the 4th respondent, which is a foreign entity, would result in

100% Foreign Direct Investment (FDI) in a fully developed and

operational hotel project, which is impermissible under the

extant Consolidated FDI Policy of India. Learned counsel

submitted that while FDI may be permissible in construction

and development of new hotel projects, the same is not

allowable in respect of already completed and operational

hospitality infrastructure, and therefore, the impugned decision

is contrary to national policy and public interest.

vi) That the learned Single Judge has also erred in dismissing the

writ petition on the ground of re-litigation. It was argued that

the cause of action in the present case arises specifically from

the decision of the Empowered Committee dated 22.09.2025,

which constitutes a fresh and independent cause of action and

had never been the subject matter of challenge in any prior

proceedings. Consequently, the finding of re-litigation is wholly

unsustainable in law. It was further contended that the

imposition of exemplary costs of Rs.10,00,000/- on the

appellant is arbitrary and unjustified, particularly in light of the

substantial legal and constitutional issues raised for

adjudication.

Submissions on behalf of the respondents

12. Learned Advocate General for the State and learned Senior

counsel for respondent No.4 has supported the impugned order and

advanced their submissions as under:

i) That in view of Section 238 of the IBC, the IBC has an

overriding effect over all other laws for the time being in force

notwithstanding any inconsistency. The resolution plan, once

approved by the NCLT under Section 31 of the IBC, attains

binding force and is enforceable against all stakeholders,

including the State Government, the corporate debtor, and its

shareholders. The appellant, being merely a shareholder of the

corporate debtor, is bound by the approved resolution plan and

cannot seek to resist its implementation.

ii) That the project in question was awarded to the SPV, namely

GJHPL, which is a distinct juristic entity in law, separate from

its shareholders. The rights in respect of the project vest in the

corporate debtor and not in its shareholders individually. The

appellant's rights are limited to its status as a shareholder, and

upon commencement of the CIRP, such rights are subject to the

scheme of the IBC. It was further submitted that the consent

accorded by the State is not in the nature of a fresh grant of

contract or largesse, but is merely an enabling act to give effect

to the resolution plan approved.

iii) That the approved resolution plan itself expressly stipulated

obtaining the consent of the State Government for change in

shareholding and control of GJHPL as a condition precedent for

its implementation. Therefore, the decision of the Empowered

Committee dated 22.09.2025 is in complete conformity with the

terms of the resolution plan and constitutes a valid exercise of

contractual and statutory discretion by the State. It was further

submitted that the conditions imposed by the State, including

financial and operational stipulations, are in the nature of a

commercial settlement of pre-existing disputes and liabilities,

and fall squarely within the domain of 'commercial wisdom' of

the Committee of Creditors and the State, which is not

amenable to judicial review.

iv) That the approved resolution plan does not mandate any

specific operator, and the issue of operation of the hotel is left to

the commercial discretion of the successful resolution

applicant. The decision to retain M/s.EIH Ltd. as the operator is

based on operational and commercial considerations to ensure

continuity of the hotel as a going concern without disruption. It

was further contended that the position of the technical

member post-CIRP is not comparable to that of the Lead

Developer, whose rights stand subsumed and extinguished by

operation of law under the insolvency framework, and therefore,

no case of hostile discrimination under Article 14 is made out.

v) That the fundamental issue relating to the primacy of the IBC

and the authority of the State to act in furtherance of an

approved resolution plan has already been conclusively

adjudicated in the earlier round of litigation, including

W.P.No.17129 of 2020, W.A.No.1135 of 2023, and the SLP(C)

No.22186 of 2024. The present proceedings constitute a

disguised attempt to reopen and re-agitate issues which stand

settled.

vi) Insofar as the challenge based on the Consolidated FDI Policy is

concerned, it was submitted that the 4th respondent is bound to

comply with all applicable foreign investment laws and

regulations, and any alleged violation thereof falls within the

domain of the competent statutory authorities, including the

Reserve Bank of India (RBI) and the Central Government. It was

contended that the writ court, in exercise of its jurisdiction

under Article 226 of the Constitution, cannot adjudicate upon

such economic and policy matters in the abstract, particularly

in the absence of any demonstrable or patent illegality.

13. We have taken note of the respective contentions urged and

perused the material on record.

Consideration by this Court

Issue of Overriding Effect of the IBC and the Binding Nature of

the Resolution Plan

14. It is pertinent to note that the issue of the overriding effect of

the IBC and the binding nature of an approved resolution plan forms

the fulcrum of the present dispute. The principal grievance of the

appellant is that the State has, in effect, transferred a public project

in favour of the 4th respondent without adhering either to a process of

public tender or to the procedure contemplated under the original

project agreements. On a careful examination, the allegation is found

to be untenable, as it fails to take note of the statutory scheme and

overriding effect of the IBC. The IBC is a comprehensive and special

legislation enacted to consolidate and amend the laws relating to

reorganisation and insolvency resolution of corporate persons in a

time-bound manner. Section 238 of the IBC contains a non-obstante

clause and reads as follows:

Section 238. Provisions of this Code to override other laws. - The provisions of this Code shall have effect, notwithstanding anything inconsistent therewith contained in any other law for the time being in force or any instrument having effect by virtue of any such law.

15. The legal position with regard to the primacy of the IBC is no

longer res integra. The Hon'ble Supreme Court, in Innoventive

Industries Ltd. v. ICICI Bank & Another 1, has held that the non-

obstante clause, in the widest terms possible, is contained in Section

238 of the IBC, so that any right of the Corporate Debtor under any

other law cannot come in the way of the IBC, Further, in

Ghanashyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset

Reconstruction Company Limited 2, the Apex Court while

interpreting the issue of binding effect of resolution plan upon the

creditor, has held as under:

58. Bare reading of Section 31 of the I&B Code would also make it abundantly clear, that once the resolution plan is approved by the Adjudicating Authority, after it is satisfied, that the resolution plan as approved by CoC meets the requirements as referred to in Sub-section (2) of Section 30, it shall be binding on the Corporate Debtor and its employees, members, creditors, guarantors and other stakeholders.

Such a provision is necessitated since one of the dominant purposes of the I&B Code is, revival of the Corporate Debtor and to make it a running concern.

(2018) 1 SCC 407

(2021) 13 SCR 737

16. In the present case, it is not in dispute that the resolution plan

submitted by the 4th respondent came to be approved by the NCLT,

Hyderabad Bench, by order dated 07.02.2020. The said plan, by its

very terms, contemplated the transfer of entire shareholding and

control of the corporate debtor, namely GJHPL, which is the project

company holding the leasehold rights in respect of the subject

property. It is also an admitted fact that the implementation of the

resolution plan was made conditional upon obtaining the consent of

the State Government for such change in shareholding and control.

17. Viewed thus, the contention of the appellant that the State has

awarded a "fresh project" to the 4th respondent dehors a public tender

process is liable to be rejected. The State, in granting its consent vide

decision dated 22.09.2025, was not exercising its power to distribute

State largesse, but was acting as a stakeholder bound by the

statutory framework of the IBC and in compliance with the terms of

the approved resolution plan. As is evident from the record, the

consent accorded by the Empowered Committee was in furtherance of

the resolution process and subject to certain conditions governing

financial dues, lease rentals, and operational continuity.

18. It is to be noted that the appellant's contention that the project

was awarded to the consortium as distinct from the SPV is untenable

and does not merit any practical or legal consequence. The

contractual and legal structure, as borne out from the record, clearly

demonstrates that the project was implemented through the SPV,

GJHPL, which alone entered into the Lease Deed and the DMA with

the State. Therefore, the rights of the consortium members, including

the appellant, were mediated exclusively through their shareholding

in the said corporate entity. In this context, the well-settled principle

laid down by the Hon'ble Supreme Court in Bacha F. Guzdar v.

Commissioner of Income Tax, Bombay 3, that a company is a

distinct juristic person separate from its shareholders, assumes

significance. The appellant, being merely a shareholder of the

corporate debtor, cannot assert an independent or superior right in

respect of the project, dehors the corporate entity.

19. Further, once the corporate debtor underwent insolvency

resolution and its ownership and control stood transferred in

accordance with the approved resolution plan, the rights in relation to

the project necessarily followed such change, and no independent or

surviving claim in respect thereof can be asserted by the erstwhile

shareholders dehors the corporate debtor. Thus, the role of the State,

cannot be equated with that of a sovereign authority making a fresh

grant, but must be understood as that of a contracting party acting in

furtherance of a binding statutory resolution process.

Issue regarding the plea of violation of Article 300A of the

Constitution of India

20. The appellant's submission that its alleged "accrued proprietary

rights" have been taken away without payment of compensation,

AIR 1955 SC 74

thereby violating Article 300A of the Constitution of India is

erroneous. The appellant did not possess any independent or direct

right in respect of the leasehold property or the project in question. Its

rights, if any, were derivative in nature and flowed solely from its

shareholding in the corporate debtor, namely GJHPL.

21. It is relevant to note that the extinguishment or dilution of the

appellant's interest is a direct consequence of the insolvency of the

corporate debtor and the implementation of the approved resolution

plan. It cannot be construed as a deprivation of property dehors the

authority of law. The appellant, being a shareholder of a company that

has undergone insolvency resolution, cannot claim a vested or

indefeasible right to continue in control of the corporate debtor or its

assets. The loss occasioned to the appellant is in the nature of a

commercial consequence of insolvency proceedings and not a

compulsory acquisition by the State so as to attract a requirement of

compensation under Article 300A.

22. It is well settled that upon commencement and culmination of

the CIRP under the IBC, the assets of the corporate debtor, including

its contractual and leasehold rights, would be dealt with in

accordance with an approved resolution plan, which is binding on all

stakeholders by virtue of Section 31 read with Section 238 of the IBC.

Thus, the resolution process constitutes a "procedure established by

law" within the meaning of Article 300A, even if it were to be assumed

that the appellant was to be treated as having any right.

23. Further, the contention that the State was under a legal

obligation to compensate the appellant is also misconceived. The

appellant, having suffered the consequences arising out of the

insolvency of the SPV, cannot assert any surviving proprietary claim

so as to impede the implementation of a resolution plan approved in

accordance with law.

Issue of the alleged modification of the Resolution Plan and

Violation of Article 14

24. The Appellant has contended that the conditional consent

accorded by the State, particularly insofar as it contemplates the

continuation of M/s. EIH Ltd. as the operator of the hotel, amounts to

an impermissible modification of the resolution plan approved by the

Adjudicating Authority. This contention, in the considered view of this

Court, proceeds on an incorrect understanding of the terms of the

approved resolution plan.

25. On perusal of the resolution plan, it is evident that the plan

does not indicate any stipulation mandating the removal of the

existing operator. On the contrary, the plan leaves the issue of

operation and management to the commercial discretion of the

successful resolution applicant. The option to continue or replace the

operator is embedded within the framework of the plan itself. In such

case, the decision of the 4th respondent to retain M/s. EIH Ltd. as the

operator, as part of a transitional or continuing arrangement, cannot

be construed as a modification of the resolution plan, but is rather a

manifestation of commercial prudence aimed at ensuring continuity of

the corporate debtor as a going concern.

26. Insofar as the allegation of discrimination under Article 14 is

concerned, this Court is unable to accept the contention that the

appellant and M/s. EIH Ltd. are similarly situated entities. The

appellant, being the Lead Developer and majority shareholder,

exercised control over the affairs of the corporate debtor, and its

position stood extinguished as a consequence of the CIRP. M/s. EIH

Ltd., on the other hand, was a minority shareholder and functioned

primarily as a technical and operational service provider under a

distinct contractual arrangement. Post-CIRP, its role is confined to

that of an operator, without any controlling interest in the

management or financial affairs of the corporate debtor. In such

circumstances, the differential treatment, if any, is founded on

intelligible differentia having a rational nexus with the object sought to

be achieved, namely, ensuring continuity and efficient operation of the

project.

Issue of Public Procurement, FDI Policy, and the Scope of

Judicial Review

27. The contention of the appellant that the project ought to have

been subjected to a fresh process of public tender cannot be accepted,

as the same is fundamentally inconsistent with the statutory scheme

of the IBC. The object of the IBC is to ensure resolution of the

corporate debtor as a going concern in a time-bound manner and to

maximise the value of its assets. Any insistence on re-tendering a

project which forms an integral part of the assets of the corporate

debtor would not only disrupt the resolution process but also defeat

the very purpose of the IBC.

28. It is to be noted that the selection of the 4th respondent as the

successful resolution applicant was not the result of any extraneous

or opaque private negotiation, but was undertaken through a

structured and competitive process within the framework of the CIRP,

under the supervision of the CoC and subject to the approval of the

Adjudicating Authority. Such a process, being statutorily recognised,

stands on a distinct footing and cannot be equated with a grant of

State largesse requiring adherence to the conventional norms of

public tender.

29. Insofar as the allegation regarding violation of the Consolidated

FDI Policy is concerned, the same does not warrant interference in the

exercise of writ jurisdiction. The regulatory framework governing FDI

is administered by specialised authorities, including the RBI and the

competent departments of the Central Government. Whether the

transaction in question conforms to the applicable FDI norms is a

matter to be examined by such authorities in accordance with law

and on the basis of the factual matrix presented before them. Further,

in the absence of any manifest or ex facie illegality demonstrated, this

Court would be slow to undertake an adjudication on such issues,

which lie within the domain of economic and regulatory policy. The

learned Single Judge was, therefore, justified in declining to entertain

the said contention and in leaving it open to be considered by the

competent authorities, if and when the occasion so arises.

Issue of Re-litigation and the Imposition of Costs

30. This Court is constrained to note that the appellant has, at

multiple stages, sought to challenge the CIRP and its consequential

outcomes, including proceedings before the Adjudicating Authority,

the Appellate Tribunal, this Court in W.A.No.1135 of 2023 in

W.P.No.17129 of 2020, and thereafter before the Hon'ble Supreme

Court in SLP(C) No.22186 of 2024. The present proceedings arise from

a challenge to the decision dated 22.09.2025 of the Empowered

Committee, which is in furtherance of, and flows directly from, the

implementation of the resolution plan approved under the IBC.

31. The fundamental question as to whether the State is competent

to grant its consent for change in shareholding of GJHPL

notwithstanding the provisions of the TIDE Act, stands concluded

against the appellant in the judgment rendered in W.P.No.17129 of

2020, which has attained finality upon affirmation up to the Hon'ble

Supreme Court. The subsequent decision dated 22.09.2025 does not

give rise to an independent or fresh cause of action, but is merely a

consequential step in furtherance of the approved resolution plan.

Permitting the appellant to re-agitate the very same issues under the

guise of a subsequent development would amount to an abuse of the

process of law.

32. Therefore, the learned Single Judge, cannot be faulted for

dismissing the writ petition. Insofar as the imposition of costs of

Rs.10,00,000/- is concerned, the same appears to have been awarded

having regard to the nature of the litigation and the repeated

challenges mounted by the appellant. This Court does not find any

sufficient ground to interfere with the exercise of discretion by the

learned Single Judge in this regard.

Conclusion

33. For the foregoing reasons, this Court is of the considered view

that the writ appeal is devoid of merit and the decision of the

Empowered Committee of the State Government dated 22.09.2025 is

upheld, as it does not suffer from any Constitutional or legal infirmity

warranting interference by this Court.

34. Accordingly, the Writ Appeal is dismissed as being devoid of

merit. The impugned order dated 20.11.2025 passed by the learned

Single Judge in W.P.No.30461 of 2025 is hereby affirmed. The

appellant shall, if not already complied with, deposit a sum of

Rs.10,00,000/- (Rupees Ten Lakhs only) towards costs with the

Telangana State Legal Services Authority, as directed by the learned

Single Judge, within a period of six (06) weeks from the date of this

judgment.

As a sequel, miscellaneous petitions, pending if any, stand

closed. No costs.

_______________________________ APARESH KUMAR SINGH, CJ

______________________________ G.M.MOHIUDDIN,J Date:09.04.2026 Note: LR copy to be marked B/o.

SZT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter