Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Navayuga Engineering Company ... vs Mahira Ventures Pvt Ltd
2025 Latest Caselaw 95 Tel

Citation : 2025 Latest Caselaw 95 Tel
Judgement Date : 2 May, 2025

Telangana High Court

M/S. Navayuga Engineering Company ... vs Mahira Ventures Pvt Ltd on 2 May, 2025

Author: K. Lakshman
Bench: K. Lakshman
         HONOURABLE SRI JUSTICE K. LAKSHMAN

         ARBITRATION APPLICATON No.270 OF 2024

ORDER:

Heard Sri Vimal Varma Vasi Reddy, learned counsel for the

Applicant, and Sri E. Venkata Siddhartha, learned counsel for the

Respondents.

2. The present Arbitration Application is filed under Section 11

(5) and (6) of the Arbitration and Conciliation Act, 1996 (hereinafter

'the Act, 1996') for appointment of a sole arbitrator to adjudicate the

disputes between the Applicant and Respondents.

FACTS:-

3. M/s Navayuga Legala Estates Private Limited (NLEPL), a

group company of Navayuga Group, is the Applicant herein. It was in

possession of land admeasuring Ac.25.10 guntas in Sy.No.82(p),

83(p) and 84(p) (opposite new municipal office, old Mumbai

Highway, Serilingampally Village, Mandal and Municipality, Ranga

Reddy District (hereinafter referred to as 'subject property').

4. 2nd respondent intended to enter into a Joint Development

Agreement for development of the subject property as a freehold land

after its de-notification from SEZ in all respects. 2nd respondent

requested the Applicant to act as a facilitator to facilitate the de-

notification of the subject land from SEZ under the applicable laws

thereby to ensure handing over of the said land to NLEPL without any

encumbrances.

5. On 02.04.2018, the Applicant and 2nd respondent entered into

an agreement for development of subject property. They have also

entered into an amended agreement dated 27.06.2018 making certain

modifications to the principal agreement 02.04.2018. The respondents

agreed to hand over Rs.30 Crores worth of saleable area in the project

on completion of Phase-I as a facilitation fee to the Applicant at

construction costs agreed between the parties.

6. On 09.11.2018, 1st respondent entered into agreement

wherein it had confirmed the de-notification of the said land from the

SEZ from all respects and also confirmed delivery of possession of the

same without any encumbrances, charges and thus discharged the

Applicant's obligation as a facilitator. As per the terms of the

agreement, dated 09.11.2018, 2nd respondent agreed to facilitate Rs.30

Crores worth of saleable area exclusively in the residential project and

50% in the Phase-I and balance 50% in the Phase -II in the shape of

residential units. Respondents further agreed to handover the

residential units within the period as agreed.

7. Despite fulfilling its obligation under the agreement, the

respondents remained evasive about their obligation in compensating

the Applicant. The Applicant's all attempts remained futile. The

Applicant vide notice dated 04.05.2024 requested the respondents to

determine the area ascertainable at the cost as specified in Annexure-I

of the Amendment Agreement dated 27.06.2018 within Fifteen (15)

day from the receipt of notice.

8. Vide reply dated 21.05.2024, the respondents admitted that

the Applicant is entitled for Rs 30 Crores and denied liability for any

built up sale area. The Applicant vide letter dated 09.07.2024

requested the respondents to determine the ascertainable area. Despite

receiving and acknowledging the said notice, there was no response

from the respondents. Therefore, invoking the arbitration clause in the

said agreement, the Applicant had issued notice dated 23.07.2024

nominating Sri Justice Challa Kodanda Ram, Former Judge of this

Court, as arbitrator to resolve the disputes.

9. Vide letter dated 23.07.2024, 2nd respondent expressed its

willingness to resolve the disputes through mutual discussions

between the parties. Thus, 2nd respondent requested the Applicant to

inform the details of the persons participating in the

negotiations/meeting representing the Applicant. Thereafter, the

Applicant has filed present application seeking appointment of an

arbitrator to adjudicate the disputes between the Applicant and

respondents.

10. 1st respondent filed counter contending that there is an

arbitral dispute that arose under the said agreements. The present

application filed by the Applicant is pre-mature as Phase-1 of the

project has not been completed and so the facilitation fee is non-

payable. The said agreements provided an option to pay Rs.30 Crores

instead of saleable area, which was not accurately reflected by the

Applicant. The Applicant has not provided necessary certificates of

compliance as per the agreements and that the invocation of

arbitration was pre-mature.

11. Sri E.Venkata Siddhartha, learned counsel for the

respondent No.1 placed reliance on the principle ad down by the Apex

Court in Indian Oil Corporation Limited (supra) to contend that the

this Court also having power to decide with regard to existence of

arbitrable disputes.

12. 2nd respondent adopted the said counter.

13. Perusal of the record would reveal that the Applicant and 2nd

respondent and NLEPL have entered into an agreement dated

02.04.2018 for development of the subject property on the specific

terms and conditions mentioned therein. They have also entered into

amendment agreement dated 27.06.2018 on the specific terms and

conditions mentioned therein. Thereafter, the Applicant and 1st

respondent have entered into an agreement dated 09.11.2018 for

development of the said property. In the said agreement, it is stated

that the NLEPL has acquired valid and legal title and is in possession

of the subject property. 1st respondent is an associate of 2nd

respondent. 1st respondent is in the business of purchasing, selling and

developing land including construction of high-rise buildings.

Therefore, 1st respondent/ Developer and NLEPL, land owners,

intended to enter into an agreement for development of subject

property. The Applicant agreed to act as facilitator for de-notifying the

entire schedule property from SEZ in all respects and to hand over the

freehold land to NLEPL without any encumbrance etc. As per the

terms of the Agreement dated 09.11.2018, respondents agreed to

facilitate Rs. 30 Crores worth of saleable area exclusively in the

residential project and 50% in the phase-I and balance 50% in Phase-

II in the shape of residential units. Respondents further agreed to

handover the residential units within the period as agreed.

14. It is further agreed that in lieu of the aforesaid agreement,

date of handing over of the Units shall commence from the date of

completion of Phase-1 to the extent of 50% and balance of 50% shall

be handed over on the completion of Phase-II of the residential

development of the Project on the schedule property or else 1st

respondent shall have to pay facilitation fee of Rs.30 Crores instead of

said agreement specified under the present agreement. 1st respondent -

developer shall discharge all its obligations as regards the facilitation

fees towards NECL under the first agreement on mutual terms thereto.

15. Clause No.6 (g) of the said agreement dated 09.11.2018

deals with 'Resolving Dispute and Jurisdiction' and the same is

extracted below:-

6(g): Resolving Dispute and Jurisdiction:-

Any dispute, controversy or claim arising out of or relating to this Agreement of related agreement or other document or the validity, interpretation, breach or termination thereof (a "Dispute"), including claims seeking redress or asserting rights shall be setting amicably at the first instance of such referred dispute/s within 10 days from the date of shall be in consonance with the Arbitration and Conciliation act, 1996 (or any

statutory notice of dispute and if not resolved thereafter it shall be referred to sole arbitrator, which Hyderabad, Telangana. The decision of the arbitral tribunal shall be final and binding on modification or re-enactment for the time being in force). The Seat of arbitration shall be the parties. Pending final resolution of any dispute, the Parties shall continue to perfor their respective obligations hereunder.

This Agreement shall be subject to the exclusive territorial jurisdiction of Courts situated at Hyderabad, Telangana State, INDIA. All notice/s deemed to be served to the address of Party/ies herein a referred in this Agreement.

16. It is the specific contention of the Applicant herein that it

has fulfilled its obligations under the said agreement and respondents

failed to compensate as agreed. It has issued notices dated 04.05.2024,

09.07.2024 and 23.07.2024. Even then, there was no resolution of

disputes. Therefore, according to the Applicant, there are disputes

between the Applicant and respondents with regard to the execution of

the said agreement and the same are arbitrable in nature. Invoking the

aforesaid clause, Applicant has issued notice dated 23.07.2024

nominating Sri Justice Challa Kodanda Ram, the Former Judge of this

Court, as an arbitrator to adjudicate disputes between the Applicant

and respondents. The Applicant vide reply notice dated 09.07.2024

requested the respondents to determine the ascertainable area, execute

a deed of conveyance within 15 days. The Applicant has also

requested to arrange meeting to resolve the disputes.

17. Vide reply dated 24.07.2024, 2nd respondent expressed its

willingness to resolve the disputes through mutual discussions

between the parties. Therefore, 2nd respondent requested the Applicant

to inform the details of the participants in the discussion/meeting

representing the Applicant so that 2nd respondent can accordingly plan

for participation in the said meeting. Thereafter, there was no

correspondence. However, the Applicant had issued notice dated

23.07.2024 nominating Sri Justice Challa Kodanda Ram, the Former

Judge of this Court, as an arbitrator to resolve the disputes. Despite

receiving and acknowledging the same, there was no response from

the respondents.

18. The aforesaid facts would reveal that respondents are

opposing this application contending that the present application is not

maintainable since there is no arbitrable dispute. This Court in

exercise of its power under Section 11 of the Act, could refuse

reference to arbitration in cases which are ex-facie frivolous, non-

arbitrable, so as to ensure expeditious and efficient disposal at the

referral stage.

19. In the light of the aforesaid discussion, it is relevant to note

that in NTPC Vs. M/s SPML Infra Limited 1, the Apex Court held

that the High Court under Section 11(6) confines to the examination

of the existence of an arbitration agreement. The Apex Court further

held as follows:-

25. Eye of the Needle: The above-referred precedents crystallise the position of law that the pre-referral jurisdiction of the courts under Section 11(6) of the Act is very narrow and inheres two inquiries. The primary inquiry is about the existence and the validity of an arbitration agreement, which also includes an inquiry as to the parties to the agreement and the applicant's privity to the said agreement. These are matters which require a thorough examination by the referral court. The secondary inquiry that may arise at the reference stage itself is with respect to the non- arbitrability of the dispute.

20. The Apex Court also considered the principle laid down by

it in Indian Oil Corporation Limited vs. NCC Limited 2 and in

Vidya Drolia v. Durga Trading Corpn. 3 confirming that prima

facie, review is essential and only clear non-arbitrable disputes should

be declined.

21. In the light of the principle laid down in the aforesaid

judgments, coming to the facts of the present case, as discussed supra,

the Applicant and respondents have entered into an agreement dated

(2023) 2 SCC 539

(2023) 2 SCC 539

(2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549

09.11.2018 on the specific terms and conditions mentioned therein. It

is the specific contention of the Applicant that it has completed its

obligations under the said agreements and the respondents failed to

comply with the same. Therefore, there are disputes between the

Applicant and respondents which are arbitrble in nature.

22. As discussed supra, vide letter dated 24.07.2024, 2nd

respondent expressed its willingness to resolve the disputes through

mutual discussions. Thereafter there was no response from the

respondents.

23. In the light of the aforesaid discussion, respondents cannot

contend that the present application is pre-mature as Phase-I of the

project has not been completed, making facilitation fee non-payable.

The said aspect, this Court cannot consider. It is for the Arbitrator to

consider the said aspect.

24. As discussed supra, this Court, being the referral Court, has

to confine itself to see the existence of arbitration agreement, if the

issue is arbitrable in nature and arbitration clause. In the present case,

there is an agreement and arbitration clause. This Court is also of the

considered view that there are disputes between the Applicant and

respondents with regard to the agreement dated 27.11.2018 the same

are arbitrable in nature to be adjudicated by the arbitrator.

25. In the present case, there are disputes between the Applicant

and respondents with regard to the execution of agreement, dated

09.11.2018 and the same are arbitrable in nature.

26. Accordingly, This Arbitration Application is allowed.

Sri Justice Goda Raghuram, Former Judge of the erstwhile High

Court of Andhra Pradesh, is appointed as sole Arbitrator to adjudicate

the disputes between the parties. The parties are at liberty to take all the

defences before the learned sole Arbitrator.

As a sequel, miscellaneous applications, if any, pending in the

Arbitration Application shall stand closed.

________________________ JUSTICE K. LAKSHMAN Date:02-05-2025 Vvr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter