Citation : 2022 Latest Caselaw 1545 Tel
Judgement Date : 28 March, 2022
THE HON'BLE SRI JUSTICE A. ABHISHEK REDDY
WRIT PETITION No.35335 of 2012
ORDER:
Aggrieved by the action of respondent No.1 in rejecting to adopt
the price escalation vide Government Memo No.6351, dated
18.05.2012, the present Writ Petition is filed.
Heard the learned counsel for the petitioner and the learned
Government Pleader for Irrigation & Command Area Development for
respondents.
The case of the petitioner, in brief, is that the petitioner has
been entrusted with the work of SRSP-stage-1 formation of double
lane road from existing single lane road from NH-7 to Cross Regulator
of Kakatiya Canal and from approach road to Rest house in SRSP,
Pochampad, Nizamabad, under an agreement vide agt.No.12/GVC-
I/2009-10, dated 22.10.2009. Accordingly, the petitioner has
executed and completed the work by March, 2012 and final bill was
paid in September, 2012. It is the grievance of the petitioner that
even though the Government has issued orders adopting price
adjustment for steel and cement, POL, Bitumen and other materials
for all ongoing civil works of all Departments, the petitioner has not
been extended the said benefit. Aggrieved by the same, the present
Writ Petition is filed.
2 AAR, J
W.P. No.35335 of 2012
Learned counsel for the petitioner has stated that the rejection
of the application of the petitioner for price escalation solely on the
ground that the orders issued by the then Government of Andhra
Pradesh have not been adopted and that there is no clause in the
agreement entered between the parties for granting the benefit of
price escalation, which is arbitrary, illegal, bad and contrary to the
Government Orders and the well established principles of law laid
down by the Hon'ble Supreme Court. Learned counsel for the
petitioner has vehemently argued that the petitioner has entered into
an agreement for execution of work of SRSP-stage-1 formation of
double lane road from existing single lane road from NH-7 to Cross
Regulator of Kakatiya Canal and from approach road to Rest house in
SRSP, Pochampad, Nizamabad, vide agreement dated 22.10.2009 and
the said works were completed in September, 2012. Learned counsel
has further stated that even though the petitioner has made several
representations, both oral as well as written, for price adjustment
before the conclusion of the contract, the official respondents did not
consider the said representations and kept the matter pending.
Learned counsel has also drawn to the attention of the Court to the
letter written by the Superintending Engineer, Sirramsagar Project,
Nizamabad, to the Administrator-cum-Chief Engineer, Sriramsagar
Project, Hyderabad, recommending the case of the petitioner on the
basis of the G.O. Ms. No.94 dated 16.04.2008 issued by the 3 AAR, J W.P. No.35335 of 2012
Government. Thereafter the Administrator-cum-Chief Engineer,
Sriramsagar Project, Hyderabad, vide letter dated 02.03.2012 has
written to the Secretary to Government (A.D), I&CAD (P.W. Maj. VIII)
Dept., Hyderabad, recommending for the price escalation as
contemplated under the GOs referred above. But, vide Memo
No.6351/M&MI(The-II)/A2/2012-2 dated 18.05.2012, the Special
Chief Secretary to Government (Irrigation) has not agreed for price
adjustment solely on the ground that the said price adjustment
clause was neither uploaded in the tender schedule nor included in
the agreement. Learned counsel has contended that once the
Government has issued the GO for granting the benefit of price
escalation for all the ongoing works, the contention of the official
respondents that the said G.O. is not applicable to the petitioner as
there is no clause in the agreement to that effect, is totally against the
very purpose and purport for which the said GO was issued.
Irrespective of the fact whether the clause for price adjustment is
uploaded in the tender schedule or included in the agreement entered
between the parties or not, as the Government has issued the GO for
the benefit of the contractors, the said benefit cannot be denied to the
petitioner. Learned counsel has relied on the judgments reported in
State of Orissa vs. Birat Chandra Dagara1 and Food Corporation
1 AIR 1997 ORISSA 142 4 AAR, J W.P. No.35335 of 2012
of India vs. A.M. Ahmed & Co2 to contend that irrespective of the
fact whether the said clause is there in the agreement or not, the
officials are bound to pay price adjustment inconsonance with the
GOs issued by the Government and they simply cannot reject the
application solely on the ground that the agreement did not provide
for grant in the price adjustment.
Per contra, the learned Government Pleader has vehemently
opposed the very maintainability of the Writ Petition and has stated
that initially the petitioner has submitted the bills without there
being any price adjustment as he was fully aware of that he was not
entitled for any price adjustment as per the terms and conditions of
the agreement entered between the parties. Learned Government
Pleader has further stated that the petitioner during the execution of
the contract at no point of time raised any dispute with regard to the
price adjustment and only at the end of the contract, that too after
receipt of payment of all the bills, he started making representations
seeking the benefit of price adjustment given under the GO Ms. No.94
dated 16.04.2008. Therefore, he prayed this Court to dismiss the
present writ petition.
Perused the record.
A perusal of the record shows that as per the agreement
entered between the parties, admittedly there is no clause for price
2 2006 (4) Arb. LR 155 (SC) 5 AAR, J W.P. No.35335 of 2012
adjustment. The works began on 22.10.2009 and the same were
supposed to be completed within one year. Thereafter, the time was
extended twice and the works were completed by September, 2012.
The petitioner has made representation on 15.02.2012 seeking price
adjustment and based on the same, a communication was sent from
the Superintending Engineer to the Administrator-cum-Chief
Engineer, Sriramsagar Project, Hyderabad, for extending the benefit
of the GOs and giving the price adjustment to the petitioner even
though there is no clause as such in the agreement. But vide Memo
dated 18.05.2012 issued by the Special Chief Secretary to
Government (Irrigation) the request of the petitioner for price
adjustment was rejected on the ground that there is no price
adjustment clause in the agreement entered between the parties and
the petitioner was also fully aware of the same.
Along with counter affidavit, the learned Government Pleader
has filed certain documents including the relevant page of the
Measurement Book wherein the petitioner has made the following
endorsement:
"Release and discharge certificate
1) I do hereby release and discharge of all the claims whatsoever effect to this work.
2) I hereby accept all the measurements full and final/settlement of work.
(Contractor)"
6 AAR, J
W.P. No.35335 of 2012
Even though the learned counsel for the petitioner has relied on
the judgments in Birat Chandra Dagara (referred supra) and A.M.
Ahmed & Co (referred supra), wherein it was held that
de hors any clause in the agreement between the parties, the
petitioner would still be entitled to for any price escalation/price
adjustment. There is absolutely no quarrel with regard to the above
proposition of law laid down by this Court, but as seen from the
record, the petitioner himself has given an endorsement in the
Measurement Book, extracted above, stating that he has no further
claim whatsoever and that he received all the claims to the full and
final settlement. In view of the same, the said judgments relied by
the learned counsel for the petitioner are of no help and are not
applicable to the facts of the present case.
In Nathani Steels Ltd. vs. Associated Construction3 the
Apex Court following the decision given in the case of P.K. Ramaiah
vs. Chairman & M.D. National Thermal Power Corporation4 has
held that once dispute is amicably settled between the parties finally,
the arbitration clause cannot be invoked by a party to resolve the
same on any ground. The Apex Court further held as under:
"Even otherwise, we feel that once the parties have arrived at a settlement in respect of any dispute or difference arising under a contract and that dispute or difference is amicably settled by way of a final settlement by and between the parties, unless that settlement is
3 1995 Supp (3) SCC 324 4 1994 Supp (3) SCC 126 7 AAR, J W.P. No.35335 of 2012
set aside in proper proceedings, it cannot lie in the mouth of one of the parties to the settlement to spurn it on the ground that it was a mistake and proceed to invoke the arbitration clause. If this is permitted, the sanctify of contract, the settlement also being a contract, would be wholly lost and it would be open to one party to take the benefit under the settlement and then to question the same on the ground of mistake without having the settlement set aside. In the circumstances, we think that in the instant case, since the dispute or difference was finally settled and payments were made as per settlement. It was not open to the respondent unilaterally to threat the settlement as non est and proceed to invoke the arbitration clause."
Having regard to the law laid down by the Hon'ble Supreme
Court in Nathani Steels Ltd. (referred supra) and more particularly
the endorsement made by the petitioner himself in the Measurement
Book that he had no further claim and received the bill amounts in
full satisfaction of all the claims, this Court does not find any merit in
the present writ petition warranting any interference of this Court
and granting the relief sought by the petitioner.
Accordingly, the Writ Petition is dismissed.
Miscellaneous petitions pending in this writ petition, if any,
shall stand closed. There shall be no order as to costs.
_________________________ A.ABHISHEK REDDY, J Date : 28.03.2022 sur
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!