Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India vs M/S Mk Infrastructure (P) Ltd
2025 Latest Caselaw 7 Sikkim

Citation : 2025 Latest Caselaw 7 Sikkim
Judgement Date : 8 May, 2025

Sikkim High Court

Union Of India vs M/S Mk Infrastructure (P) Ltd on 8 May, 2025

Author: Bhaskar Raj Pradhan
Bench: Chief Justice, Bhaskar Raj Pradhan
            THE HIGH COURT OF SIKKIM:GANGTOK
                                    (Civil Appellate Jurisdiction)

------------------------------------------------------------------------------------------
DIVISION BENCH: THE HON'BLE MR. JUSTICE BISWANATH SOMADDER, CHIEF JUSTICE
                THE HON'BLE MR. JUSTICE BHASKAR RAJ PRADHAN, JUDGE
 ---------------------------------------------------------------------------------------
                                  Arb. A. No. 04 of 2024

                 Union of India,
                 Represented by Chief Engineer,
                 Project Swastik,
                 C/O 99 A.P.O.,
                 Pin - 931717.                                                         .....        Appellant
                                                versus
                M/s M.K. Infrastructure (P) Ltd.,
                Represented by Director Smt. Lalita Kandoi,
                Resident of 4 Agrasen Road,
                Siliguri, West Bengal,
                PIN - 734005.                               ..... Respondent
        --------------------------------------------------------------------------

                  Appeal under section 37(1) of the Arbitration and
                              Conciliation Act, 1996
          [against the judgment dated 05.12.2023 passed by the learned Commercial Court,
         Gangtok, in Commercial (Arbitration) Case No. 02 of 2023 in M/s M.K. Infrastructure
                                     (P) Ltd. vs. Union of India]
        --------------------------------------------------------------------------
        Appearance:
        Ms Sangita Pradhan, Deputy Solicitor General of India assisted by Ms
        Natasha Pradhan and Ms Sittal Balmiki, Advocates for the Appellant.
        Mr. Amit Lal Chakravorti, Advocate and Mr. Gourav Mandal, Advocate
        for the Respondent.

        ---------------------------------------------------------------------------------------------------------


                                 JUDGMENT

( 8th May, 2025 )

Bhaskar Raj Pradhan, J.

The process of arbitration is initiated on a consensus

of the parties when they desire to resolve their disputes

arising out of the agreement through the process of

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

arbitration instead of following the normal process of courts.

The effort of the legislature in enacting the Arbitration and

Conciliation Act, 1996 (in short, the Arbitration Act) is to

ensure that this process is fair, efficient and capable of

meeting the needs of the specific arbitration and to minimise

the supervisory role of courts in the arbitral process. It is

precisely for this reason that section 19 provides that the

arbitral tribunal shall not be bound by the Code of Civil

Procedure, 1908 or the Indian Evidence Act, 1872. It further

provides that the parties are free to agree on the procedure

to be followed by the arbitral tribunal in conducting its

proceedings. Failing any agreement, the arbitral tribunal

may conduct the proceedings in the manner it considers

appropriate. The power of the arbitral tribunal while

conducting the proceedings in the manner it considers

appropriate, includes the power to determine the

admissibility, relevance, materiality and weight of any

evidence.

2. The ambit and scope of section 34 of the

Arbitration Act is no longer res integra. Interference in an

arbitration dispute for setting aside an arbitral award is

limited to sub-section (2) and sub-section (3) of section 34.

section 34 has been interpreted by the Hon'ble Supreme

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

Court with sufficient clarity. It is the settled legal position

that in an application under section 34, the Court is not

expected to act as an Appellate Court and re-appreciate the

evidence. Interference would be warranted when the award

is in violation of "public policy of India", which has been held

to mean "the fundamental policy of Indian law". It would be

impermissible to interfere on the merits of the award. An

award could also be interfered with on the ground that it is

in conflict with justice or morality which is now understood

as a conflict with "most basic notions of morality or justice". It

is only such arbitral award that shocks the conscience of the

Court that can be set aside on the ground of patent illegality

appearing on the face of the award and goes to the root of

the matter. Mere erroneous application of law would not be

a ground for interference. A perverse decision would amount

to patent illegality.

3. In Punjab State Civil Supplies Ltd. vs. Sanman Rice

Mills1, the Hon'ble Supreme Court held as under:

"Conclusion:

20. In view of the above position in law on the subject, the scope of the intervention of the court in arbitral matters is virtually prohibited, if not absolutely barred and that the interference is confined only to the extent envisaged under Section 34 of the Act. The appellate power of Section 37 of the Act is limited within the domain of Section 34 of the Act. It is exercisable only to find out if the court, exercising power under

2024 INSC 742

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

Section 34 of the Act, has acted within its limits as prescribed thereunder or has exceeded or failed to exercise the power so conferred. The Appellate Court has no authority of law to consider the matter in dispute before the arbitral tribunal on merits so as to find out as to whether the decision of the arbitral tribunal is right or wrong upon reappraisal of evidence as if it is sitting in an ordinary court of appeal. It is only where the court exercising power under Section 34 has failed to exercise its jurisdiction vested in it by Section 34 or has travelled beyond its jurisdiction that the appellate court can step in and set aside the order passed under Section 34 of the Act. Its power is more akin to that superintendence as is vested in civil courts while exercising revisionary powers. The arbitral award is not liable to be interfered unless a case for interference as set out in the earlier part of the decision, is made out. It cannot be disturbed only for the reason that instead of the view taken by the arbitral tribunal, the other view which is also a possible view is a better view according to the appellate court.

21. It must also be remembered that proceedings under Section 34 of the Act are summary in nature and are not like a full-fledged regular civil suit. Therefore, the scope of Section 37 of the Act is much more summary in nature and not like an ordinary civil appeal. The award as such cannot be touched unless it is contrary to the substantive provision of law; any provision of the Act or the terms of the agreement."

4. The records reveal that the parties had entered

into a contract for construction of living shelters, structures,

sheds on Jawaharlal Nehru Marg in the State of Sikkim. The

contract had an arbitration clause. When dispute arose

between the parties, the respondent invoked the arbitration

clause and approached the appellant for appointment of an

Arbitrator. On 02.01.2019, Col. S. Gopikrishnan was

appointed as the sole Arbitrator. Subsequently, Col. Anil

Kothiyal replaced Col. S. Gopikrishnan for adjudication of

the dispute. Pleadings were thereafter exchanged. The

respondent filed its statement of claims on 15.01.2022. On

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

24.02.2022, statement of defence was filed by the appellant.

The respondent thereafter filed a rejoinder on 06.05.2022

which was followed by a reply to the rejoinder by the

appellant on 22.06.2022. Thereafter, on 16.07.2022, the

appellant filed paragraph wise reply to the claims filed by

the respondent. It was only, thereafter, that the sole

Arbitrator passed the arbitral award on 27.12.2022.

5. The arbitral award dealt with all the claims made

by the respondent. It was held that the appellant did not

cancel the contract in the initial stages giving sufficient time

to the respondent to complete the subject work. The

respondent could not complete the work on time and sought

for extension at various occasions which was granted. The

site was handed over to the respondent on 04.04.2009, after

which, several diligence notices were issued to accelerate the

progress of the work but the respondent failed to mobilize

resources resulting in delay in completion of work. When the

respondent did not resume the work, final notice was issued

on 24.10.2015. Inspite of the final notice, respondent did

not commence work which led to the cancellation of the

contract according to the terms of condition-54 of the

General Conditions of Contract. Accordingly, the sole

Arbitrator rejected all the claims of the respondents and

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

awarded the claim of the appellant for balance amount to be

recovered from the respondent and the cost thereof; cost of

reference to arbitration; and interest at the rate of 12% after

three months from the date of award of the judgment till

date of receipt of payment.

6. The respondent preferred an application under

section 34 of the Arbitration Act for setting aside the arbitral

award. The challenge to the arbitral award was substantially

on the merits of the dispute between the parties.

7. Before the learned Commercial Court, the

respondent contended that the arbitral award ought to have

been passed on or before 01.01.2020, i.e., within 12 months

from the date of entering upon reference as per the

Arbitration and Conciliation (Amendment) Act, 2015 (for short,

the 2015 Amendment). It was further contended that the

subsequent sole Arbitrator who was appointed on

30.06.2021, should have passed the award on 29.06.2022,

but it was passed on 27.12.2022, with a delay of five months

and twenty-nine days. It was contended by the respondent

that there was no extension of time either by the parties or

by the Court and as such, the award was passed beyond the

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

timeframe envisaged under section 29-A of the Arbitration

Act.

8. The learned Commercial Court was in agreement

with the submissions made by the respondent and vide

judgment dated 05.12.2023, allowed the section 34

application on the ground that the sole Arbitrator, who

passed the impugned arbitral award, had become functus

officio on 01.10.2020 and the arbitral award passed on

27.12.2022 was non-est. It was held that the arbitral award

was passed on 27.12.2022 which was beyond the stipulated

time under section 29-A(1) and (3) of the Arbitration Act as

amended by the 2015 Amendment. It was further held that

there was nothing on record to show that prior to or after

the expiry of the prescribed period, the Court had made any

extension as prescribed under section 29-A(4). Accordingly,

it set aside the arbitral award.

9. The learned Commercial Court did not examine

anything else. The learned Commercial Court did not

examine the scope of section 34. The learned Commercial

Court did not find that the arbitral award was against the

public policy of India or the fundamental policy of Indian law

or in conflict with the most basic notions of morality and

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

justice. The arbitral award was also not held to be against

any substantive provision of law or Act. More importantly,

the learned Commercial Court did not examine whether the

issue of non-compliance of section 29-A(1) as amended by

the 2015 Amendment was only an erroneous application of

law and therefore, not a ground for interference.

10. The moot question for this Court to examine in

this appeal under section 37 of the Arbitration Act is,

whether the ground on which the learned Commercial Court

set aside the reasoned arbitral award is a valid ground for

setting aside an award under section 34 of the Arbitration

Act?

11. The effect of the impugned judgment is, therefore,

to set aside the final award passed at the behest of the

losing party after the sole Arbitrator had completed the

process of arbitration invoked by the respondent. This is not

what was envisaged by the legislature when it provided

specific grounds for challenge under section 34 of the

Arbitration Act. Whether the sole Arbitrator failed to pass the

arbitral award within the timeframe set by section 29-A(1)

and (3) of the Arbitration Act (as amended by the 2015

Amendment) would not fall under any of the specific grounds

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

provided in sub-sections (2) and (3) of section 34 in the facts

of the present case. The arbitral award, to a very limited

extent, may be open to challenge if it is passed after

inordinate and unexplained delay. That would render it in

conflict with the public policy of India or patent illegality

that shocks the conscience of the Court. This is so as we

cannot lose sight of the fact that one of the objective of

alternative dispute resolution by the process of arbitration is

to have expeditious and effective disposal of disputes

through a private forum of party's choice. This was not,

however, what was argued and evident in the facts of the

case.

12. Section 29-A(1) is a procedure for the arbitrator to

follow and does not confer any right or impose any

obligation on the parties. This would be true both under the

2015 Amendment as well as the Arbitration and Conciliation

(Amendment) Act, 2019 (for short, the 2019 Amendment).

Further, sub-section (3), even under the 2015 Amendment of

section 29-A, makes it evident that the timeline set for the

Arbitrator under sub-section (1) was not sacrosanct as the

said provision provides that the timeline could be extended

for a further period of six months by consent of the parties.

Even thereafter, by virtue of the provision of sub-section (4)

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

thereof, the Court could further extend the period for

making the award by six months.

13. The rules of procedure are essentially intended to

subserve the cause of justice - being the handmaidens of

justice - and not for punishing the parties in the conduct of

the proceedings.

14. In Narinder Singh & Sons vs. Union of India2, the

Hon'ble Supreme Court observed that the newly enacted

section 29-A emphasises on quick and prompt adjudication.

Idioms carping "delay" and "hurry" in adjudication highlight

the importance of both speedy disposal and reasonable

opportunity, as both are essential for an even-handed and

correct decision. Neither should be sacrificed nor inflated as

to prolong or trample a just and fair adjudication. A

pragmatic and common-sense approach would invariably

check any discord between the desire of expeditious disposal

and adequacy of opportunity to establish one's case.

15. As per record, the reference was made on

02.01.2019 and when the 2019 Amendment came into force

2021 INSC 747

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

on 30.08.2019, the arbitration proceeding was pending as

the award was passed only on 27.12.2022.

16. The learned Commercial Court was of the view

that section 29-A of the Arbitration Act (as it stood during the

time when the first Arbitrator was appointed), brought into

force by the 2015 Amendment on 23.10.2015, would be the

applicable law. As such, the learned Commercial Court

considered the date of reference as the starting point for the

period provided therein. The learned Commercial Court

examined section 29-A post 2015 Amendment, w.e.f.,

23.10.2015 which remained in force till it was further

substituted by section 29-A, w.e.f., 30.8.2019. It noted the

requirement under sub-section (1) of passing the award

"within a period of twelve months from the date the arbitral

tribunal enters upon reference." It noted that under sub-

section (3), the parties may, by consent, extend the period

specified in sub-section (1) for making an award for a

further period not exceeding six months. It also noted that

sub-section (4) provided "If the award is not made within the

period specified under sub-section (1) or the extended period

specified under sub-section (3), the mandate of the

arbitrator(s) shall terminate unless the Court has, either prior

to or after the expiry of the period so specified, extended the

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

period." Reading the said provision in its entirety, the

learned Commercial Court opined that the arbitrator was

required to pass an award within a period of twelve months

from the date the arbitral tribunal enters upon reference.

The learned Commercial Court observed that there was

nothing on record to show that the parties consented to

extend the period for making the arbitral award by another

six months and even if such consent is presumed, the final

award ought to have been made on or about 1.10.2020.

17. Insofar as the question sought to be raised by the

learned Deputy Solicitor General of India before this Court is

concerned, the learned Commercial Court noted the

submission that the time limit for passing the award within

a period of twelve months would begin from the date of

completion of pleadings and since the pleadings were

completed on 16.7.2022 and the arbitral award was passed

on 27.12.2022, the impugned order was well within the

prescribed time. However, the learned Commercial Court did

not examine in detail whether the 2015 Amendment or the

2019 Amendment was applicable, as it opined that since the

2015 Amendment was effective from 23.10.2015 until it was

further substituted on 30.8.2019 by the 2019 Amendment,

the 2015 Amendment would be the applicable law.

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

18. The appellant challenges this opinion of the

learned Commercial Court and contends that section 29-A

as amended by the 2019 Amendment would be the

applicable law and therefore, the starting point of the twelve

months period would be the date of completion of pleadings

under sub-section (4) of section 23.

19. The learned Deputy Solicitor General of India

relying upon the judgment of the Hon'ble Supreme Court in

Tata Sons Pvt. Ltd. vs. Siva Industries and Holdings Ltd.3

submitted that the 2019 Amendment would be applicable in

the present case and as the award was passed within twelve

months from the date of completion of pleadings as required

under section 29-A(1), sub-section (7) of section 29-A would

have no relevance.

20. The learned counsel for the respondent counters

this argument by submitting that since the first sole

Arbitrator Col. S. Gopikrishan was appointed on

02.01.2019, the arbitration proceeding is to be governed by

the 2015 Amendment as it remained in force till 30.08.2019

from when the 2019 Amendment came into force.

2023 INSC 13

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

21. In Tata Sons (supra), the Hon'ble Supreme Court

was deciding a lis relating to an international commercial

arbitration. However, it arrived at some findings of facts that

would be relevant for the present case. It was held that the

provision of section 29-A was introduced into the Arbitration

Act, w.e.f., 23.10.2015 by Act 3 of 2016, i.e., the 2015

Amendment and further section 29-A was substituted by Act

33 of 2019; i.e., the 2019 Amendment, w.e.f., 30.8.2019. It

also held that whereas the 2015 Amendment in terms of

section 26 of Act 3 of 2016 was prospective in nature, the

2019 Amendment did not contain any provision equivalent to

section 26 of Act 3 of 2016 evincing a legislative intent

making the application of the amended provision

prospective.

22. These findings of the Hon'ble Supreme Court in

Tata Sons (supra) would be applicable even for cases relating

to domestic arbitrations. The Hon'ble Supreme Court also

concluded that the 2019 Amendment is remedial in nature

insofar as international commercial arbitration is concerned,

in that, it carves out international commercial arbitrations

from the rigour of the timeline of six months. Viewed in this

light, we notice that the 2019 Amendment of section 29-A

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

also changes the timeline for passing of a domestic award

within twelve months from the date the arbitral tribunal

"enters upon the reference", to twelve months from the date

of "completion of the pleadings" under sub-section (4) of

section 23. In such view of the matter, therefore, we are of

the considered opinion that even for domestic arbitrations

the 2019 Amendment to section 29-A would be remedial in

nature. As such, the change in the starting point of the

twelve months to the date of completion of pleadings instead

of date of reference for the arbitrator to make an award does

not confer any rights or obligation on any party. We are,

therefore, of the view that section 29-A(1), as a mandate,

being remedial in nature even for domestic arbitration, it

should be applicable to all pending arbitral proceedings as

on the effective date, i.e., 30.8.2019, from which date the

2019 Amendment came into effect. It is not in dispute that in

the present case the arbitral proceedings between the two

parties were pending as on 30.8.2019.

23. If we, therefore, consider the 2019 Amendment of

section 29-A is the applicable procedural law, the arbitral

award passed on 27.12.2022 was well within the time frame

of twelve months envisaged in section 29-A(1) of the

Arbitration Act from the date of completion of pleadings.

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

24. There is nothing on record to suggest that the

respondent protested on the jurisdiction of the sole

Arbitrator beyond the period of twelve months under sub-

section (1) as being functus officio beyond the period before

the arbitral award. The protest came only when the arbitral

award rendered by the sole Arbitrator was against the

respondent in the form of section 34 application.

25. Infact, the arbitral award records that the

respondent requested for granting time up till 15.01.2022 to

submit his statement of claims and he submitted his claim

vide letter dated 15.01.2022, which was received on

01.02.2022. Therefore, it would be unthinkable that the

respondent desired the award to be made even before he

would submit his statement of claims. The appellant,

according to the arbitral award, submitted his statement of

defence on 24.02.2022. The arbitral award also records that

the respondent submitted his rejoinder to the statement of

defence on 06.05.2022, after making a request to allow them

time up to 30.04.2022. It further records that time and

again the respondent had sought time for pleadings and

hearing till 05.09.2022. These facts establish that the

extension of time was at the behest of the respondent.

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

26. We also take judicial notice of the fact that during

the period of arbitration, COVID-19 pandemic had set in and

the Hon'ble Supreme Court in Suo Moto Writ Petition (C) No.

3/2020 in Re: Cognizance for extension of limitation, had

directed that the period between 15.03.2020 till 28.02.2022

shall stand excluded in computing the period prescribed

under sections 23(4) and section 29-A of the Arbitration Act.

Therefore, not only did the parties got extended period for

completion of pleadings under section 23(4), but the sole

Arbitrator also got an extension of the period envisaged in

section 29-A for passing the award within timelines

prescribed therein. If the learned Commercial Court had

examined the issue raised by the respondent regarding the

timeline the Arbitrator had to follow as narrated in

paragraph 7 above in light of the orders passed by the

Hon'ble Supreme Court in Suo Moto Writ Petition (C) No.

3/2020 in Re: Cognizance for extension of limitation,

exempting the period of 15.03.2020 till 28.02.2022, it would

have noticed that almost the entire period was directed to be

excluded due to the Covid-19 pandemic.

27. We summarize our findings as under:

i) The learned Commercial Court had failed to

consider the limited jurisdiction it had while examining

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

the challenge to the arbitral award under section 34 of

the Arbitration Act.

ii) The ambit and scope of section 34 of the

Arbitration Act is limited to the extent provided in sub-

sections (2) and (3), thereof. An appeal under section

34 is not a regular appeal.

iii) In the facts of the present case, the learned

Commercial Court exceeded its jurisdiction under

section 34 of the Arbitration Act.

iv) Section 29-A(1) of the Arbitration Act is a

procedure to be followed by the arbitral tribunal and

does not confer any right or impose any obligation on

the parties. It is also remedial in nature.

v) Section 29-A(1) does not lay down any sacrosanct

timeline as sub-section (3) permits further extension of

six months by consent of parties. Even thereafter, sub-

section (4) gives the power to the Court to extend the

period further by six months.

vi) Section 29-A(1) as amended by the 2019

Amendment and not the 2015 Amendment would

govern the procedure to be followed by the Arbitrator as

the arbitration was pending when the 2019 Amendment

was brought into force on 30.08.2019.

Union of India vs. M/s M.K. Infrastructure (P) Ltd.

28. We are, therefore, of the opinion that the

impugned judgment dated 05.12.2023, setting aside the

arbitral award passed by the sole Arbitrator, was

unwarranted. We, therefore, set it aside.

29. Arbitration Appeal is allowed and stands disposed

of, accordingly.





     (Bhaskar Raj Pradhan)                                 (Biswanath Somadder)
           Judge                                                Chief Justice




     Approved for reporting : Yes
     Internet: Yes
bp
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter