Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Prime Civil Infrastructure Private ... vs Jodhpur Development Authority ...
2026 Latest Caselaw 7014 Raj

Citation : 2026 Latest Caselaw 7014 Raj
Judgement Date : 29 April, 2026

[Cites 6, Cited by 0]

Rajasthan High Court - Jodhpur

Prime Civil Infrastructure Private ... vs Jodhpur Development Authority ... on 29 April, 2026

[2026:RJ-JD:20508]

      HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                       JODHPUR
                S.B. Arbitration Application No. 17/2025

Prime Civil Infrastructure Private Limited, Having Its Head-Office
At A-203, Gokul Arcade, Swami Nityanand Marg, Ville Parle
(East), Mumbai-400057 Through Its Power Of Attorney Holder
Shri Goutam Jain S/o Shri Bhoor Chand Jain, Aged About 53
Years, Resident Of 85 Vaishali Enclave Near Dps Circle Jodhpur
Raj
                                                                       ----Petitioner
                                     Versus
Jodhpur Development Authority, Through Its Commissioner,
Jodhpur.
                                                                   ----Respondent


For Petitioner(s)           :    Mr. Vineet Dave for Mr. Kaushik Dave.
For Respondent(s)           :    Mr. Rajat Dave.



          HON'BLE MR. JUSTICE MUKESH RAJPUROHIT

Order

29/04/2026

1. Application herein is under section 11 of the Arbitration &

Conciliation Act, 1996 with the prayer to appoint a sole arbitrator

to decide/ adjudicate upon the dispute between the parties arising

out of a Bid Document being EOI/2015-16; NIT No.34 dated

24.11.2015.

2. Case set up in the application is that the Applicant is a

private limited company and is engaged in infrastructure

development projects throughout Rajasthan. The Government of

Rajasthan, through the Jodhpur Development Authority (JDA),

invited bids for constructing flats under the Chief Minister's Jan

Awas Yojana-2015 (CMJAY) aimed at Economically Weaker Section

and Low Income Group categories on government land (Khasra

(Uploaded on 01/05/2026 at 03:17:22 PM)

[2026:RJ-JD:20508] (2 of 6) [ARBAP-17/2025]

No. 136, Village-Tanawada, Jodhpur, Phase-I). According to the

policy, 75% of the land was to be used for construction, while the

remaining 25% was allotted free of cost to the developer as

compensation.

2.1 The applicant submitted its bid on 29.02.2016, which was

accepted as the lowest responsive bid on 04.07.2016. The

applicant was required to submit a layout plan for approval and a

bank guarantee worth 1% of the contract value within seven days

of receiving the Letter of Acceptance (LoA). The contract became

effective from 04.07.2016. The applicant complied by submitting

the layout plan and bank guarantee as stipulated.

2.3. On 19.08.2016, the JDA issued the LoA, confirming that the

layout and unit building plans were approved by the Local Level

Project Approval Committee, and directed the applicant to execute

the agreement.

2.4. The applicant commenced work as per the bid documents,

which detailed the rights and obligations of both parties, including

JDA's obligation to maintain financial capacity to fund the project

(Clauses 3.3 and 1.2). Payments were to be released through an

ESCROW account in eight stages, later revised to eighteen stages

in April 2021. However, JDA failed to maintain sufficient funds in

the ESCROW account, which impeded progress.

2.5. The applicant repeatedly communicated concerns about the

shortage of funds, delays in approvals for external development

works such as water supply and electrification, and the need for a

tripartite pari-passu mortgage agreement to secure financing.

Despite multiple requests, JDA did not respond.

(Uploaded on 01/05/2026 at 03:17:22 PM)

[2026:RJ-JD:20508] (3 of 6) [ARBAP-17/2025]

2.6. From 22.07.2022 onwards, the applicant sought formation of

a Dispute Review Expert/Board (DRE/DRB) as required by

Appendix-B of the contract, but JDA failed to constitute it.

Meanwhile, JDA issued show-cause notice 22.11.2023, alleging

project delays and threatening contract termination, ignoring their

own contractual lapses.

2.7. The applicant responded by highlighting the minimal funds

received in the ESCROW account, which was sufficient for only

about two days of work, and the absence of necessary approvals.

2.8. On 10.01.2025, JDA terminated the contract, debarred the

applicant, and forfeited the performance security, citing

insufficient progress. The applicant challenged these actions,

attributing delays to JDA's failures. Despite assurances during a

meeting on 26th December 2022, no DRE/DRB was formed.

2.9. Consequently, the applicant invoked arbitration as per

Appendix-B and Section 21 of the Arbitration and Conciliation Act,

1996, however, JDA refused arbitration citing a pending Section 9

application in Commercial Court No.1, Jodhpur, which the

applicant clarified was solely for interim relief.

2.10. Resultantly, the applicant now seeks the court's intervention

under Section 11 of the Arbitration and Conciliation Act, 1996,

requesting appointment of a sole arbitrator since JDA failed to

form the DRE/DRB and refused to nominate an arbitrator, thereby

violating the contract's dispute resolution mechanism.

3. Per contra, learned counsel for the respondent-non-applicant

contends that the applicant's application under Section 11(6) of

the Arbitration Act, 1996, is wholly misconceived and without

merit, as the applicant has not demonstrated the existence of any

(Uploaded on 01/05/2026 at 03:17:22 PM)

[2026:RJ-JD:20508] (4 of 6) [ARBAP-17/2025]

arbitral dispute justifying the appointment of an arbitrator. The

reliance on Clauses 2.0 and 3.0 of Appendix-B is unfounded

because Clause 2.0(d) allows for the formation of a Dispute

Resolution Board (DRB/DRE) only during the execution of work

which was discontinued in December, 2021. Furthermore, prior to

seeking arbitration proceedings, the applicant failed to first

approach the Dispute Review Board. Therefore, the dispute cannot

be referred to arbitration under Clause 3.0. Accordingly, the

application deserves to be dismissed, he urges.

4. I have gone through the record and heard the learned

counsel for the parties.

5. I am unable to persuade myself with the objection taken by

learned counsel for the non-applicant/ respondent that prior to

seeking arbitration proceedings, the applicant failed to first

approach the Dispute Review Board as per Clause (2) of the

contract signed between the parties. However, it seems that the

shoe is on the other foot. The applicant has been throughout

pursuing the respondents to seek resolution by regular

correspondence / communications and yet the respondents

turned deaf ears to the same without taking any steps.

6. It has been specifically pleaded so even in the application

that the applicant requested the respondents to form DRE/DRB to

facilitate the ironing out the differences between the parties vide

communication dated 22.07.2022, but to no avail.

7. The Clause-3 as contained in Appendix-B pertaining to

arbitration is reproduced herein-below :-

"3.0 Arbitration :

(Uploaded on 01/05/2026 at 03:17:22 PM)

[2026:RJ-JD:20508] (5 of 6) [ARBAP-17/2025]

(a) Any dispute in respect of which the recommendations (fi any) of DRE/DRB has not become final and binding, shall be finally settled by arbitration in accordance with the Indian Arbitration and Conciliation Act, 1996, or any statutory amendment thereof.

(b) The arbitral tribunal will comprise three members, one each to be appointed by the Procuring Entity and the Contractor. The third Member, who will also act as the presiding member, will be appointed by mutual consent of the first two members. If these two Members fail to reach an agreement on the third members then, on request by either or both parties, appointment will be made by the ACS, UDH, Jaipur."

8. The aforesaid arbitration clause is not disputed. Moreover,

there is no quibble about the fact that there is an existing dispute

between the parties, but there is a dispute as to which forum

should adjudicate the same. However, on a court query qua the

pre arbitration proceedings as per Clause-3 ibid, it transpires that

nothing worthwhile has come forth after issuance of legal notice.

The dispute can, therefore, only be resolved by way of arbitration

as mutually agreed by executing the contract to the effect. Parties

are bound by the covenant already executed by them on mutually

agreeable terms.

9. It is not clear from the petition as to what is the total

outstanding amount against the work carried out by the applicant,

which he claims is unpaid as on today. Though in the legal notice

dated 07.10.2024 para 34 thereof, it is stated that as per the

show cause notice issued by the respondent, the applicant had

accomplished work only of Rs.14,09,58924/- against work order of

Rs.19,71,90,000/-. However, the same is disputed by the

respondent and subject matter of adjudication through arbitration

proceedings. It is not for this Court to make any observation qua

the same. The applicant is at liberty to raise its outstanding

(Uploaded on 01/05/2026 at 03:17:22 PM)

[2026:RJ-JD:20508] (6 of 6) [ARBAP-17/2025]

money claim before the learned arbitrator at the time of entering

into the reference by filing the claim petition in accordance with

law.

10. Be that as it may, in view of the undisputed arbitration

clause, the instant application deserves to be allowed.

11. Accordingly, Hon'ble Mr. Justice Mr. Vineet Kothari (Retd.),

Mobile No.9480822552, R/o- 947, 11th 'D' Road, Sardarpura, B.M.

Kothari Marg, Jodhpur, Rajasthan, is appointed as the sole

Arbitrator to adjudicate the dispute between the parties.

12. The intimation of aforesaid be given by the learned counsel

for the parties as well as by the Registry to Hon'ble Arbitrator. The

above appointment is subject to necessary disclosure being made

under Section 12 of the Act of 1996.

13. The parties are at liberty to participate in the arbitration

proceedings through video conferencing subject to the approval

and convenience of the learned Arbitrator.

14. All the disputes as well as defence raised before this Court is

left open to be adjudicated by the learned Arbitrator.

15. Application stands disposed of.

(MUKESH RAJPUROHIT),J 36-/Jitender//-

(Uploaded on 01/05/2026 at 03:17:22 PM)

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter