Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S K.S. Bhati, Contractor Firm vs State Of Rajasthan
2023 Latest Caselaw 10380 Raj

Citation : 2023 Latest Caselaw 10380 Raj
Judgement Date : 4 December, 2023

Rajasthan High Court - Jodhpur

M/S K.S. Bhati, Contractor Firm vs State Of Rajasthan on 4 December, 2023

Author: Arun Bhansali

Bench: Arun Bhansali, Rajendra Prakash Soni

   [2023:RJ-JD:41803-DB]

         HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
                          JODHPUR
                      D.B. Spl. Appl. Writ No. 582/2023

   M/s K.S. Bhati, Contractor Firm, Through Its Sole Proprietor
   Keshu Singh Bhati S/o Beju Singh Ji, Aged 64 Years, R/o 80,
   Rajendra Nagar, Pali (Raj.).
                                                                          ----Appellant
                                          Versus
   1.       State Of Rajasthan, Through The Registrar, Co-Operative
            Societies, Rajasthan, Nehru Sahkar Bhawan, Bhawani
            Singh Road, Jaipur.
   2.       The Rajasthan Co-Operative Dairy Federation Limited
            (Rcdf), Through The Managing Director, Rcdf, Saras
            Sankul, Jawahar Lal Nehru Marg, Jaipur.
   3.       The Manager, Jodhpur Cattle Feed Plant, Basni Industrial
            Area, Ii Phase, Jodhpur.
   4.       Sudhanshu Gurjar, The Manager, Jodhpur Cattle Feed
            Plant, Basni Industrial Area, Ii Phase, Jodhpur.
   5.       M/s Hanuman Singh Rawat, Navdurga Colony, Jawahar Ki
            Naadi, Behind Hmt, Chandravardai Nagar, Beawar Road,
            Ajmer.
                                                                       ----Respondents


   For Appellant(s)             :     Mr. Ramendra Singh Saluja.
                                      Mr. Achraj Singh Saluja.
   For Respondent(s)            :     Mr. J. Gehlot.
                                      Mr. K.K. Bhati.
                                      Mr. Nitin Trivedi.



               HON'BLE MR. JUSTICE ARUN BHANSALI

HON'BLE MR. JUSTICE RAJENDRA PRAKASH SONI

Judgment

(PER HON'BLE MR. JUSTICE ARUN BHANSALI) 04/12/2023

1. This appeal is directed against the order dated 6.6.2023

passed by learned Single Judge in S.B. Civil Writ Petition

[2023:RJ-JD:41803-DB] (2 of 10) [SAW-582/2023]

No.6308/2023, whereby, the writ petition filed by the Appellant -

Firm has been dismissed.

2. The petition was filed aggrieved of the order dated

20.4.2023 directing the petitioner firm to discontinue the work of

bagging, loading and stacking and diamond (byepass) work from

21.4.2023 and against the tender summary report dated

20.4.2023 showing respondent no.5 to have obtained L-1 rank

above the petitioner with L-2 rank.

3. It was inter alia indicated that Rajasthan Cooperative Diary

Federation Limited issued an E-bid for bagging, loading and

stacking related work and diamond (byepass) work.

4. On 01.04.2023 before issuance of the said E-bid, the

petitioner-firm had an existing contract of work from 16.10.2021

till 20.4.2023. Pursuant to the said E-bid, 7 bidders submitted

their documents for technical bid, for which, opening date was

indicated as 12.4.2023.

5. A notice of shortfall in the documents for the technical bid

was issued to all the bidders except the petitioner firm. In

compliance of the said notice, the bidders submitted the requisite

documents. The financial bid was opened on 20.4.2023 vide the

tender summary report, wherein, respondent no.5 was shown as

the lowest bidder and the petitioner firm was shown as the second

lowest bidder.

6. The petitioner firm gave notice for demand of justice pointing

out the alleged illegalities committed by respondent no.4, which

was replied to by the official respondent indicating that two firms

were ousted from bidding process. On the same day, work order

[2023:RJ-JD:41803-DB] (3 of 10) [SAW-582/2023]

was issued in favour of respondent no.5, who was required to

commence the work from 21.4.2023 i.e. the next date.

7. Aggrieved of the same, the writ petition was filed.

8. Submissions were made that under Section 14(6) of the

Rajasthan Transparency in Public Procurement Act, 2012, the

authority is clearly prohibited in adopting a criteria for procedure

other than those mentioned in the bidding document and as

Clauses 7 & 8 of the terms and conditions contained in the bid

document provided a clear prohibition with regard to

supplementing of documents after opening of the technical bid,

the notice of shortfall issued was in violation of the said clauses. It

was alleged that bidding process was done with the sole intention

to extend the undue favour to respondent no.5.

9. The allegations made in the petition were contested based on

preliminary objection that the petition was not maintainable as

alternative remedy was available. The contract of the petitioner

firm came to an end on 20.4.2023 and the respondent no.5 has

already started work w.e.f. 21.4.2023, the prohibition contained in

Clauses 7 & 8 has no application.

10. Learned Single Judge, after hearing the parties, came to the

conclusion that as respondent no.5 has already been awarded the

work order in question, which work has been started by

respondent no.5, any interference at this stage would amount to

unsettling an already settled position, more so when the Court did

not find any illegal infirmity, illegality and irregularity in the whole

process and, consequently, dismissed the writ petition.

11. Learned counsel for the appellant made vehement

submissions that the judgment impugned does not deal with any

[2023:RJ-JD:41803-DB] (4 of 10) [SAW-582/2023]

of the issues raised by the appellant, inasmuch as, when the

specific case of the appellant was that Clauses 7 & 8 of the E-bid

were violated along with Rule 60(4) of the Rajasthan Transparency

in Public Procurement Rules, 2013 ('the Rules of 2013'), the said

aspect was not at all considered and, therefore, the order

impugned deserves to be set aside.

12. Further submissions were made that a bare look at the

Clauses 7 & 8 of the E-bid would reveal that the bidder was to

upload all the documents in the technical bid and no change /

correction would be permitted, however, despite the fact that

respondent no.5 in his technical bid did not annex the PF

inspection report, in the shortfall document submission, the

shortfall pertaining to latest certified PF Inspection Report (IR)

was indicated, which was purportedly submitted by him.

13. It was emphasized that besides the fact that the document

submitted did not fulfill the requirement of the E-bid, calling for

the said document was in express violation of Rule 60(4) of the

Rules of 2013 as the same amounts to substantive change to

qualification information.

14. Learned counsel also made submissions that the technical

bid for lack of the said document was liable to be rejected and if

rejected, the petitioner firm was L-1 and was entitled to be

granted the work order / continue with his work, which he was

already performing to the satisfaction of the respondents and,

therefore, the petition should have been accepted by the Court.

15. Reliance was placed on PSEB v. Bhatia International Ltd.:

(2006) 13 SCC 284 and Goldyan Technoseve Ltd. v. State of M.P.:

(2011) 5 SCC 103 and Maharashtra Housing Development

[2023:RJ-JD:41803-DB] (5 of 10) [SAW-582/2023]

Authority v. Shapoorji Pallonji & Company Private Limited: (2018)

3 SCC 13.

16. Learned counsel appearing for respondent no.5 made

submissions that allegations made by the petitioner firm had no

substance. It was submitted that no specific favour was shown to

the respondent no.5, inasmuch as, all the 6 tenderers other than

the petitioner were issued the shortfall notice for the purpose of

producing the document, which were missing, based on which, the

respondent no.5 produced the requisite document, which is not in

dispute and, therefore, the plea raised has no substance.

17. It was submitted that the document / shortfall, which was

sought from respondent no.5 was non-material and the same was

covered by Rule 61 of the Rules of 2013, which provides for

waiver of non-conformities in the bid that do not constitute

material deviation and submission of necessary information of

document within reasonable period. It was emphasized that the

shortfall document only pertain to the latest inspection report of

the PF department. It is not the case of the petitioner that there

was any default insofar as the respondent no.5 was concerned

and, therefore, the plea raised has no substance.

18. It was reiterated, as was done before learned Single Judge

that bulk of the time of the work order is already over and about

4½ months remain, which may not be unsettled. It is prayed that

the appeal be dismissed.

19. Learned counsel for the petitioner reiterated that the

shortfall was not non-material as claimed and, therefore, the

appeal be allowed.

[2023:RJ-JD:41803-DB] (6 of 10) [SAW-582/2023]

20. We have considered the submissions made by learned

counsel for the parties and have perused the material available on

record.

21. The claim of the appellant - petitioner essentially is that as

the respondent no.5 the successful bidder had failed to fill in

column 13 of the E-bid and upload the document in this regard,

which required him to produce the latest inspection report from

the PF department, his technical bid should have been rejected

and, thereafter, his financial bid should not have been opened,

wherein, the appellant would have been L-1 and entitled to the

work order.

22. The terms and conditions of the bid pertaining to the E-

tender inter alia required uploading of all the documents as

required in the technical bid and also provided that no change or

correction would be permitted except for the name and rate of the

bidder.

23. When pursuant to the E-bid, 7 bidders applied, 6 bidders

were issued the shortfall notice (Annex.4 to the writ petition) inter

alia pointing out the documents missing in the bid documents,

which ranged from experience certificate, latest certified PF

inspection report, valid labour licence etc. Qua the respondent

no.5, the shortfall indicated was latest certified PF inspection

report (IR), the respondent no.5 uploaded the requisite material

available with him. Whereafter, the technical bid was opened and

respondent no.5 was found as L-1 and was given the work order,

based on which, he started the work from the next day.

[2023:RJ-JD:41803-DB] (7 of 10) [SAW-582/2023]

24. The challenge laid to the action of the respondents in seeking

the shortfall document is essentially based on the bid condition

and provisions of Rule 60(4) of the Rules of 2013.

25. The Rule 60 of the Rules of 2013 inter alia reads as under:

"60. Clarification of bids- (1) To assist in the examination, evaluation, comparison and qualification of the bids, the bid evaluation committee may, at its discretion, ask any bidder for a clarification regarding its bid. The committee's request for clarification and the response of the bidder shall be in writing. (2) Any clarification submitted by a bidder with regard to its bid that is not in response to a request by the committee shall not be considered.

(3) No change in the prices or substance of the bid shall be sought, offered, or permitted, except to confirm the correction of arithmetic errors discovered by the committee in the evaluation of the financial bids.

(4) No substantive change to qualification information or to a submission including changes aimed at making an unqualified bidder, qualified or an unresponsive submission, responsive shall be sought, offered or permitted.

(5) All communications generated under this rule shall be included in the record of the procurement proceedings."

26. A perusal of the above Rule reveals that the same gives a

discretion to the Bid Evaluation Committee to ask any bidder for a

clarification in writing and a response should also be in writing.

The Rule prohibits change in the prices or the substance of the bid

except to confirm the correction of arithmetic errors discovered by

the committee in the evaluation of the financial bids. Sub-Rule (4)

provides that no substantive change to qualification information or

to a submission including changes aimed at making an unqualified

[2023:RJ-JD:41803-DB] (8 of 10) [SAW-582/2023]

bidder, qualified or an unresponsive submission, responsive shall

be sought, offered or permitted.

27. This Rule facilitates seeking of clarification from the bidder

and provides restrictions under Sub rules 3 and 4 with regard to

prices or substance of the bid and substantive change to

qualification information.

28. A bare look at the technical bid reveals that under column 6

information regarding registration under the PF Act, 1952, was

sought along with certified copy of the registration and under

column 13, latest inspection report was sought. It is not in dispute

that respondent no.5 had produced the registration with the PF

department and apparently, the purpose for getting produced the

latest inspection report, was to ensure that the bidder was

complying with the provisions of the PF Act.

29. It is nobody's case that periodical inspection by the PF

department with a specified interval has been provided in the

statute so as to claim that non-production by respondent no.5 was

for the purpose of suppression of a particular aspect.

30. Rule 61 of the Rules of 2013 inter alia reads as under:-

"61. Non-material Non-conformities in bids- (1) The bid evaluation committee may waive any nonconformities in the bid that do not constitute a material deviation, reservation or omission, the bid shall be deemed to be substantially responsive. (2) The bid evaluation committee may request the bidder to submit the necessary information or document like audited statement of accounts, PAN, etc. within a reasonable period of time. Failure of the bidder to comply with the request may result in the rejection of its bid.

[2023:RJ-JD:41803-DB] (9 of 10) [SAW-582/2023]

(3) The bid evaluation committee may rectify non- material nonconformities or omissions on the basis of the information or documentation received from the bidder under sub-rule (2).

31. The Rule authorizes the Bid Evaluation Committee to waive

any non-conformities, which do not constitute a material

deviation, reservation or omission and to make a request to the

bidder to submit the necessary information or document like

audited statements of accounts, PAN etc. and it can rectify non-

material, non-conformities based on the information received.

32. The above Rule is indicative enough of the fact that seeking

of documents by the Bid Evaluation Committee is not prohibited.

The allegations made regarding favouring respondent no.5 cannot

be countenanced for the simple reason that shortfall notice was

given to 6 bidders out of 7 bidders and apparently no special

favour was shown to respondent no.5.

33. In view of the above fact situation, wherein, the purpose for

seeking the inspection report essentially was to find out if there

were any violations of the requirements of PF Act and has nothing

to do with the substance of the bid or amounts to substantive

change in the qualification information so as to violate provision of

Rule 60 of the Rules of 2013. Rather, the clarification sought is in

consonance with provisions of Rule 61 of the Rules of 2013.

34. So far as the judgments relied on by learned counsel for the

appellant - petitioner are concerned, in the said judgments the

facts were entirely different, wherein, in the case of PSEB (supra),

a new tender document after the last date was sought to be

submitted as the tender documents submitted by the company

were forged by its employee, in the case of Goldyan Technoserve

[2023:RJ-JD:41803-DB] (10 of 10) [SAW-582/2023]

Ltd (supra), the required quality certificate was not produced

along with bid document, which was found to be in violation of the

tender conditions. Similarly, in the case of Maharashtra Housing

Development Authority (supra), it was found that bid submitted by

the respondent was not a valid bid. The facts and document

involved in the present case, as discussed hereinbefore, are

different and, therefore, the judgments have no application.

35. Consequently, for the reasons indicated above, no case is

made out for interference. The present Special Appeal is,

therefore, dismissed.

(RAJENDRA PRAKASH SONI),J (ARUN BHANSALI),J

Sumit/-

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter