Citation : 2023 Latest Caselaw 6493 Raj
Judgement Date : 29 August, 2023
[2023:RJ-JD:27887-DB]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR D.B. Spl. Appl. Writ No. 694/2023
Jai Ram @ Jaya Ram S/o Kripa Ram, Aged About 78 Years, Resident Of Village Genva (Chokha), Harala Bhakhari Bypass Road Jodhpur.
----Appellant Versus
1. State Of Rajasthan, Through Secretary, Department Of Public Works, Government Of Rajasthan. Jaipur.
2. Jodhpur Development Authority, Jodhpur Through Its Secretary.
3. National Highway Authority Of India, Through Project Director, Project Implementation Unit, Rajeevayan 188, Umed Heritage Ratanada, Jodhpur.
4. Union Of India, Through Secretary, Ministry Of Road, Transportation And National Highway, New Delhi.
5. Sub Division Officer (North) Cum Land Acquisition Officer, Jodhpur.
----Respondents
For Appellant(s) : Mr. Moti Singh
For Respondent(s) : Mr. Ankur Mathur with Mr.
Harshwardhan Thanvi.
HON'BLE MR. JUSTICE ARUN BHANSALI
HON'BLE MR. JUSTICE RAJENDRA PRAKASH SONI
Judgment
29/08/2023
1. This appeal is directed against the order dated 24.08.2023
passed by the learned Single Judge in SBCWP No.8528/2023,
whereby the application filed on behalf of the respondent Nos. 3 &
5 under Article 226(3) of the Constitution of India has been
allowed and the interim order dated 28.06.2023 granted in the
writ petition was vacated.
[2023:RJ-JD:27887-DB] (2 of 7) [SAW-694/2023]
2. The writ petition was filed by the appellant-petitioner, inter-
alia, seeking to question the amended award No.70 dated
24.05.2023 (Annex.21), notice dated 25.05.2023 (Annex.22) and
sought quashing of supplementary award No.411 dated
30.12.2019 (Annex.9) issued by the Land Acquisition Officer for
the structure and building situated over the land of Khasara
Nos.867/3 & 867/4 of Village Gewa and sought further
consequential reliefs.
3. It appears that initially an ex-parte interim order was
granted on 28.06.2023, whereby the respondents were restrained
from construction of the road over Khasara Nos. 867/3 & 867/4.
4. The respondent Nos. 3 & 5 filed application under Article
226(3) of the Constitution of India seeking vacation of the interim
order.
5. Learned Single Judge, after hearing the parties, referring to
the judgment of Hon'ble Supreme Court in N.G. Projects Limited v.
M/s Vinod Kumar Jain & Ors. : (2022) 6 SCC 127 found that the
cause of action in the petition pertained to amended award dated
24.05.2023, whereby the compensation was reduced and that the
determination of the said aspect in the writ petition will only have
financial consequence, which does not require stopping of the
construction of a public project, that is a ring road to the town and
consequently allowed the application and vacated the interim
order.
6. Learned counsel for the appellant-petitioner made vehement
submissions that the learned Single Judge was not justified in
vacating the interim order on the assumption that the petition
[2023:RJ-JD:27887-DB] (3 of 7) [SAW-694/2023]
pertained to reduction in quantum of compensation only. It was
submitted that the appellant-petitioner had also questioned the
supplementary award No.411 dated 30.12.2019 (Annex.9) on the
basis that the land in question was never acquired by the
respondents, which belongs to the appellant - petitioner and
therefore, they have no right to construct the road on the said
disputed khasaras, the order impugned by the learned Single
Judge has been passed ignoring the said specific plea raised by
the appellant-petitioner and therefore, the order impugned
deserves to be quashed and set-aside.
7. Elaborate submissions were made seeking to establish the
ownership of the appellant-petitioner over the disputed land, lack
of any notification for its acquisition and that the said land is being
used for construction of road without any legal authority.
8. Learned counsel appearing for the respondent No.3 & 5 i.e.
National Highways Authority of India ('NHAI') and Land Acquisition
Officer made submissions that the appellant-petitioner is not
entitled to raise the issues as sought to be raised now before the
Division Bench, inasmuch as, the plea raised by the appellant-
petitioner in this regard came to be rejected by the learned Single
Judge in a previous writ petition filed by the petitioner being
SBCWP No.3995/2020, decided on 12.04.2023, against which
DBSAW No.367/2023 was filed, which was withdrawn with liberty
to approach the learned Single Judge by way of a review petition
and the said review petition being S.B. Civil Writ Review
No.36/2023 is still pending consideration before the learned Single
Judge.
[2023:RJ-JD:27887-DB] (4 of 7) [SAW-694/2023]
9. It was further submitted that the trigger for filing of the
present writ petition has only been the amended award No.70
dated 24.05.2023 (Annex.21) and merely because while
questioning the validity of the said amended award, the petitioner
chose to reiterate the challenge laid in SBCWP No.3995/2020,
cannot be a basis to get it re-examined once the earlier petition
came to be dismissed.
10. It was submitted that the learned Single Judge was justified
in vacating the interim order as the issue, which could be raised in
the writ petition now is the reduction of quantum of award and
there cannot be any irreparable injury to the petitioner and the
balance of convenience was very much in favour of construction of
the ring road as laid down by the Hon'ble Supreme Court in the
case of N.G. Project Limited (supra). It was prayed that the appeal
be dismissed.
11. We have considered the submissions made by learned
counsel for the parties and have perused the material available on
record.
12. It is no doubt true that the petitioner in the writ petition has
laid foundation seeking to question the very action of the
respondents in constructing the road purportedly over Khasara
Nos.867/3 & 867/4 and went on to question the amended award
No.70 dated 24.05.2023 (Annex.21).
13. It is also not in dispute that the petitioner had earlier filed
SBCWP No.3995/2020, wherein the following reliefs were
sought :-
[2023:RJ-JD:27887-DB] (5 of 7) [SAW-694/2023]
"i. The impugned notice dated 4.2.2020 (annexure 9) and entire proceedings undertaken by the respondents for acquisition of the land of the humble petitioner situated in khasra no.867/3 and 867/4 at village genva chokha may kindly ordered to be declared illegal and may kindly be quashed and set aside and the respondents may kindly be restrained from acquiring the land of the humble petitioner for the purpose of construction of ring road.
ii. Any other appropriate relief which this Hon'ble court deems just and proper in the facts and circumstances of the case may kindly be passed in the favour of petitioner."
14. It may be noticed that the challenge laid to notice dated
04.02.2020 in SBCWP No.3995/2020 was as a consequence to
the supplementary award No.411 dated 30.12.2019 (Annex.9),
which has been challenged in the present writ petition. It would be
seen that in earlier writ petition, the relief claimed pertained to
quashing of the entire proceedings undertaken by the respondents
qua the land comprised in Khasara Nos.867/3 & 867/4. The said
SBCWP No.3995/2020 came to be dismissed by the learned Single
Judge, inter-alia, with the following observations:-
"This Court further observes in writ petition no.3995/2020, the lands in question were recorded in favour of the Forest Department and the Revenue Department, and that, the petitioner therein is an encroacher on the said land, which was subsequently, vested in the respondent-NHAI for the development works in question. The documents relied by the respondents clearly substantiate the impugned action of the respondents. The whole purpose, being such enactment, was the best public infrastructure and provision of best National Highways in the country. Therefore, in the firm opinion of this Court, the project in question, which is for the benefit of public at large, ought not be stopped."
15. The determination made above was very specific holding that
the lands in question were recorded in favour of the Forest
Department and Revenue Department and the appellant-petitioner
is an encroacher on the said land, which subsequently vested in
the NHAI for development work in question and that the
documents relied on by the respondents substantiate the action of
[2023:RJ-JD:27887-DB] (6 of 7) [SAW-694/2023]
the respondents. As such, the claim made by the appellant-
petitioner stood specifically negated by the learned Single Judge in
SBCWP No.3995/2020.
16. Against the order passed in SBCWP No.3995/2020, DBSAW
No.367/2023 was filed, which came to be withdrawn on
21.04.2023 with liberty to approach the learned Single Judge by
way of a review petition and now it is submitted that the Writ
Review No.36/2023 filed, is pending consideration before the
learned Single Judge.
17. The said aspects i.e. filing of the previous petition and its
disposal were noticed by the learned Single Judge in the order
impugned and apparently as the issue raised pertaining to the
supplementary award dated 30.12.2019 (Annex.9) had already
been determined, qua the fresh issue raised pertaining to the
amended award dated 24.05.2023 (Annex.21), the learned Single
Judge came to the conclusion that the same would only have
financial consequence and for the said purpose the stay of the
project, was unnecessary.
18. The said determination made does not call for any
interference in the present appeal as the facts, as noticed, are
clear wherein in the previous petition challenge was laid to the
consequential order to the supplementary award dated
30.12.2019 (Annex.9) and the pleas raised came to be negated
and the challenge now is pending consideration in a review
petition before the learned Single Judge. Till such time that the
order is reviewed, the determination as made by the learned
Single Judge in SBCWP No.3995/2020 stands.
[2023:RJ-JD:27887-DB] (7 of 7) [SAW-694/2023]
19. Further merely because on account of a fresh trigger / cause
of action on account of the amended award dated 24.05.2023
(Annex.21), a fresh petition has been filed, wherein the challenge
as laid in SBCWP No.3995/2020 has been reiterated and instead
of the notice dated 04.02.2020, the award dated 30.12.2019 has
been challenged, the same could not have been considered /
reconsidered by ignoring the previous determination made in
SBCWP No.3995/2020.
20. Further, in case the claim made is that the challenge laid to
the supplementary award dated 30.12.2019 is a fresh challenge,
the same is highly belated besides the fact that in SBCWP
No.3995/2020 itself the challenge, if any, should have been laid as
multiple petitions for the same cause of action, cannot be
maintained.
21. In view of the above discussion, it cannot be said that the
learned Single Judge was not justified in coming to the conclusion
that as in the writ petition, the issue pertained to reduction / for
maintaining the compensation awarded, which would only have a
financial consequence, there was no necessity to stop the
construction of a public project, cannot be faulted.
22. Consequently, there is no substance in the present appeal,
the same is, therefore, dismissed.
(RAJENDRA PRAKASH SONI),J (ARUN BHANSALI),J 77-Rmathur/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!