Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Amril Lal Khatri vs Varaha Indra Limited
2021 Latest Caselaw 18710 Raj

Citation : 2021 Latest Caselaw 18710 Raj
Judgement Date : 9 December, 2021

Rajasthan High Court - Jodhpur
Amril Lal Khatri vs Varaha Indra Limited on 9 December, 2021
Bench: Vinit Kumar Mathur

HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Arbitration Application No. 29/2020

Amril Lal Khatri S/o Shri Goverdhandas Ji, Aged About 73 Years, R/o Azad Chowk, Barmer, District Barmer (Raj.)

----Petitioner Versus Varaha Indra Limited, Umesh Smriti 6, Jalam Vilas Scheme, Paota 'B' Road, Jodhpur - 342006.

                                                                  ----Respondent


For Petitioner(s)          :     Mr. Vineet Dave
For Respondent(s)          :     Mr. Mohit Singhvi with
                                 Mr. Vishwas Khatri



        HON'BLE MR. JUSTICE VINIT KUMAR MATHUR

                                      Order

09/12/2021

     The   present     arbitration        application has         been   filed   for

appointment of the Arbitrator under Section 11 (6) of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as

'the Act of 1996').

Heard learned counsel for the parties.

Learned counsel for the applicant submits that in pursuance

of the contract agreement dated 14/08/2010, the parties entered

into an agreement for the purpose of construction of the road

from 225 to 269 on NH-112 of the Jodhpur-Barmer Section in

Rajasthan. The contract agreement between the parties is placed

on record as Annexure-1.

Learned counsel further submits that as per clause 13(a) of

the said agreement, in the event of dispute having been arisen

(2 of 5) [ARBAP-29/2020]

between the parties, the matter will be referred to the sole

arbitrator to be appointed by the parties.

Learned counsel submits that although the commencement

of period of contract for the construction of the road was 2010 and

the completion date was given as 31/03/2011 but factually the

work was not completed within the stipulated period. He further

submits that the applicant was under an obligation for

maintenance of the road during the Defect Liability Period also and

the Defect Liability Period was stated to be five years from the

date of completion of the road. It is also contended that as per

Clause (h) of the Defect Liability Period, the same was stated to

be 15/10/2017 or as specified in the agreement with the Main

Contractor. He submits that when the amount due to the

applicant was not paid by the respondent and the amount was

disputed, the applicant gave a registered notice on 01/07/2020

(Annex.2) to the respondent for invoking the Clause 13(a) of the

agreement for appointment of an arbitrator. He, therefore,

submits that since the notice has not been honoured by the

respondent by appointing an arbitrator, therefore, the applicant

was compelled to prefer an application before this Court under

Section 11(6) of the Act of 1996 for appointment of an arbitrator.

Per contra, learned counsel for the respondent submits that

the application preferred by the applicant for appointment of the

arbitrator is at a belated stage and the same is liable to be

dismissed on the ground that the request for arbitration has not

been made by the applicant within a period of three years from

the date of the dispute. In support of his submission, he has

relied upon the judgment of the Hon'ble Supreme Court in the

(3 of 5) [ARBAP-29/2020]

case of Bharat Sanchar Nigam Ltd. & Anr vs. M/s. Nortel

Networks India Pvt. Ltd, reported in (2020) 14 SCC 643.

Learned counsel submits that since the date of completion

of work has never been informed by the applicant nor it has been

stated in the arbitration application or notice, therefore, the

period of limitation cannot be construed as 15/10/2017 in this

case and the notice was served for arbitration after the expiry of

period of three years. Learned counsel, therefore, submits that the

arbitration application is liable to be dismissed on the ground of

not invoking the clause for appointment of the arbitrator within a

period of three years from the dispute which arose for the first

time.

I have considered the submissions made at the bar and I

have gone through the documents as well as agreement placed on

record.

It is an admitted position that the applicant and the

respondent entered into an agreement which is dated 14/08/2010

(Annex.1). In the agreement, there is an arbitration clause

mentioned in Clause 13(a) and the parties have agreed that in

case the dispute arose between them, the same would be referred

to the Arbitrator to be appointed by the parties. The fact that the

commencement of the period of work and the completion of the

same has been mentioned in Clause 6(a) of the agreement which

is dated 20/08/2010 and completion being 31/03/2011, the same

is not in dispute. As far as the defect liability period and the

liability of the applicant during the defect liability period is

concerned, the same is not disputed by learned counsel for the

respondent. As per clause 8 (h) of the said agreement, the defect

(4 of 5) [ARBAP-29/2020]

liability period is mentioned to be 15/10/2017 or as specified in

the Agreement with the Main Contractor.

On a pointed query being raised to the learned counsel for

the respondent with respect to any specific date having been

mentioned in the agreement with the Main Contractor about the

defect liability period, he is unable to inform the date and

submitted that the date which is mentioned for the completion of

the project would be construed for the defect liability period.

Para 5 of the reply reads as under :-

"5. That the contentions and the averments as contended under para no. 5 of the application are admitted by the Answering Respondent to the extent that as per the agreement dated 14.08.2010 executed between the parties the Defect Liability Period was agreement to be up to 15.10.2017 and therefore the cause of actions raised and contentions by the Applicant are liable to be done away with on the preliminary ground of Limitation. It is worth mentioning here that no security deposit is due to be paid on part of the Answering Respondents herein as the matter was resolved and closed between the parties, back in the year 2013".

A bare perusal of the reply shows that the defect liability

period is mentioned to be 15/10/2017 and, therefore, being no

other date mentioned in the main agreement, there is no reason

for this Court to take into consideration any other date than the

date 15/10/2017 as the date of the defect liability period. If

15/10/2017 is taken as the last date for the period of defect

liability period then the notice has been served by the applicant

for appointment of the arbitrator on 01/07/2020 is within a period

(5 of 5) [ARBAP-29/2020]

of three years and thus the argument of learned counsel for the

respondent that the claim of the applicant is barred by limitation

as the applicant has failed to invoke the provision of clause for

appointment of the arbitrator within a period of three years is not

sustainable.

In the circumstances, the application is allowed. Mr. Harish

Purohit, Advocate R/o. 28A, Opposite Sardar School, Hakam

Bagh, Jalore Gate, Jodhpur is appointed as a sole arbitrator to

adjudicate upon the dispute between the parties in terms of

arbitration agreement and as per the Rajasthan Manual of

Procedure for Alternative Dispute Resolution, 2009, as amended

up to date and also as per the provisions of Arbitration and

Conciliation Act.

The record of the case may be transmitted to the Mr. Harish

Purohit, Advocate.

The above appointment is subject to the necessary

disclosure under Section 12 of the Act.

Needles to say that the fees of the arbitrator will be as per

Schedule 1V of the Arbitration and Conciliation Act.

(VINIT KUMAR MATHUR),J

161-SanjayS/-

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter