Thursday, 21, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Garg Construction Co vs State Of Haryana Through Its Additional ...
2025 Latest Caselaw 6619 P&H

Citation : 2025 Latest Caselaw 6619 P&H
Judgement Date : 24 December, 2025

[Cites 7, Cited by 0]

Punjab-Haryana High Court

Garg Construction Co vs State Of Haryana Through Its Additional ... on 24 December, 2025

Author: Jasgurpreet Singh Puri
Bench: Jasgurpreet Singh Puri
ARB-674-2025(O&M)               -1-


                           227
       IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                      CHANDIGARH

                                               ARB-674-2025(O&M)
                                               Date of Decision: 24.12.2025


GARG CONSTRUCTION COMPANY
                                                              ....Petitioner(s)

                                      Versus

STATE OF HARYANA THROUGH ITS ADDITIONAL CHIEF
SECRETARY AND OTHERS
                                       .....Respondent(s)

CORAM: HON'BLE MR. JUSTICE JASGURPREET SINGH PURI

Present:    Mr. Ashwani Talwar, Senior Advocate with
            Mr. Sahej Mahajan, Advocate,
            for the petitioner.

            Mr. Chirag Wadhwa, DAG, Haryana.

                         ****

JASGURPREET SINGH PURI, J. (Oral)

1. The present petition has been filed under Section 11(6) of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act')

praying for appointment of an independent Arbitrator to adjudicate the

disputes and differences which have arisen between the parties pertaining to

an agreement entered into between the parties.

2. Mr. Ashwani Talwar, learned Senior Counsel with Mr. Sahej

Mahajan, Advocate submitted that there was a contract between the parties,

in which there exists an arbitration clause i.e. Clause 24.3, which has been

attached as Annexure P-2. He submitted that it has been provided in the

aforesaid arbitration clause that in case the work value is more than Rs.10

1 of 4

ARB-674-2025(O&M) -2-

crores, then the matter will be adjudicated by a Tribunal of three Arbitrators

and if the work value is less than Rs.10 crores then the matter will be

referred to a Sole Arbitrator. He further submitted that in the present case,

although the claim value is more than Rs.10 crores butconsidering the cost

factor, a Sole Arbitrator may be appointed by this Court. He further

submitted that a dispute arose between the parties and the applicant invoked

the aforesaid arbitration clause by issuing a notice dated 17.09.2025

(Annexure P-11) but no response was received from the respondents and

therefore, the present petition has been filed seeking appointment of an

independent Arbitrator.

3. On the other hand, Mr. Chirag Wadhwa, learned DAG, Haryana

submitted that the respondents have no objection in case a Sole Arbitrator is

appointed by this Court. He submitted that there is no dispute with regard to

existence of the aforesaid arbitration clause and invocation of the said

arbitration clause by way of issuance of a notice vide Annexure P-11.

4. He further submitted that the only objection of the respondents

is that in the aforesaid clause itself there is a provision for pre-deposit of

claim fee of 2% of the claim amount at the time of invoking the arbitration,

which was not adhered to by the petitioner. He submitted that in case this

Court is to appoint any Arbitrator then considering the cost factor, an

independent Sole Arbitrator may be appointed in this regard.

5. I have heard the learned counsel for the parties.

6. The existence of the aforesaid arbitration clause and invocation

of the said arbitration clause by way of issuance of a notice vide Annexure

P-11 has not been disputed by learned State counsel. The only objection

2 of 4

ARB-674-2025(O&M) -3-

raised by the learned State counsel was with regard to pre-deposit of 2% of

the claim amount at the time of invocation of the arbitration proceedings.

However, the aforesaid clause pertaining to 2% although is in existence but

it is an unconscionable clause and this law has been so discussed by

judgment of Supreme Court in Lombardi Engineering Limited versus

Uttarakhand Jal Vidyut Nigam Limited, (2024) 4 SCC 341. This Court is

also of the considered view that the aforesaid clause of 2% would violate the

provisions of Article 14 of the Constitution of India and this 2% pre-deposit

itself can always be considered by the learned Arbitrator at an appropriate

stage and in case it is so required, then the same can be adjusted at any

appropriate stage of arbitration or at the final stage by way of adjustment etc.

Therefore, the aforesaid objection is not sustainable for the purpose of

appointment of an Arbitrator under Section 11 of the Act. So far as the

constitution of Arbitral Tribunal is concerned, as per the aforesaid clause it

provides that if the contract value is more than Rs.10 crores then an Arbitral

Tribunal consisting of three Arbitrators shall be constituted. However, both

the learned counsels for the parties have jointly submitted that considering

the cost factor, a Sole Arbitrator may be appointed instead of appointment of

any Arbitral Tribunal consisting of three members.

7. In view of the aforesaid facts and circumstances, the present

petition is allowed. Hon'ble Mr. Justice Ajay Tewari, a former Judge of this

Court, resident of House No. 3038, Sector 21-D, Chandigarh and # R-8,

Third Floor, Green Park Extension, New Delhi, Mobile No. 9780008141,

Email ID: [email protected], is nominated as the Sole

3 of 4

ARB-674-2025(O&M) -4-

Arbitrator to adjudicate the dispute between the parties, subject to

compliance of statutory provisions including Section 12 of the Act.

8. Parties are directed to appear before the learned Arbitrator on

date, time and place to be fixed and communicated by the learned Arbitrator

at his convenience.

9. Fee shall be paid to the learned Arbitrator in accordance with

the Fourth Schedule of the Arbitration Act, as amended.

10. Learned Arbitrator is also requested to complete the

proceedings as per the time limit prescribed under Section 29-A of the Act.

11. A request letter alongwith a copy of the order be sent to

Hon'ble Mr. Justice Ajay Tewari, a former Judge of this Court.




24.12.2025                            (JASGURPREET SINGH PURI)
rakesh                                          JUDGE
         Whether speaking                       :   Yes/No
         Whether reportable                     :   Yes/No




                                       4 of 4

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter