Citation : 2023 Latest Caselaw 15338 P&H
Judgement Date : 6 September, 2023
2023:PHHC:117834
In the High Court for the States of Punjab and Haryana
At Chandigarh
FAO-3582-2023 (O&M)
Date of Decision:-06.09.2023
Punjab State Power Corporation Ltd. ... Appellant
Versus
M/S Genus Power Infrastructure Ltd. and another ... Respondents
CORAM: HON'BLE MR. JUSTICE GURVINDER SINGH GILL
Present:- Mr. Aman Pal, Advocate and
Mr. Japsehaj Singh, Advocate for the appellant.
*****
GURVINDER SINGH GILL, J.(Oral)
1. The appellant has preferred the instant appeal, aggrieved by order dated
20.2.2023 vide which learned Additional District Judge, Patiala has dismissed
the petition filed by the appellant under Section 34 of the Arbitration and
Conciliation Act.
2. The dispute arises out of a contract entered into between the parties pertaining
to supply of material for Erection/Conversion, testing, commissioning of 11
KV Phase 3 wire lines & Dismantlement of 4 th wire along with its allied
material from existing 3 phase 4 wire system to provide urban pattern supply
to vilages and to connect rural water works, and in respect of which the
appellant had imposed a penalty of Rs.55,43,184/- on account of delay in
MOHAN SINGH 2023.09.06 19:07 I attest to the accuracy and authenticity of this order/judgment FAO-3582-2023 (O&M) (2) 2023:PHHC:117834
execution of work. The Arbitrator while accepting the claim of the
respondent awarded the said amount i.e. Rs.55,43,184/- and has also awarded
the interest on the aforesaid amount and also interest on the delayed payment
of Excise Duty etc. under Claim No.6.
3. The learned counsel while assailing the impugned order has drawn the
attention of this Court to the award wherein the learned Arbitrator while
discussing Claim No.1 pertaining to penalty of Rs.55,43,184/- has observed
that time was not the essence of the contract. Learned counsel in order to
assail said observations has drawn the attention of this Court to the agreement
entered into between the parties (Annexure A-1) so as to contend that there
was a clear stipulation that the work had to be executed within 6 ½ months.
4. I have heard the learned counsel for the appellant.
5. Mr. Maninder Arora, Advocate, on behalf of respondent-M/s Genus Power
Infrastructure is present in the Court.
6. A perusal of the Arbitrator's award would indicate that it has been noticed
that there were several amendments in scope of work, which continued till
19.7.2011 i.e. much beyond the time fixed for execution of the work. Rather,
it is also noticed that a witness examined by the appellant during the course
of cross-examination categorically stated that even the scope of work had
been increased without there being any proportionate increase in time. The
relevant extract is reproduced here under:
"...................................................................................
In fact, the very fact that Amendments continued to be issued till as late as 19.07.2011 would establish that it was not possible for the claimant to complete the work by 31.12.2009. It is on record that the claimant had applied for extension of time on at least 3 occasions, but no decision was taken thereon. Reference in this connection may be MOHAN SINGH 2023.09.06 19:07 I attest to the accuracy and authenticity of this order/judgment FAO-3582-2023 (O&M) (3) 2023:PHHC:117834
made to letters dated 13.01.2009 (C-6), 08.06.2010 (C-11) and 15.03.2011 (C-22). The witness of the respondent (RW-1) admitted during the course of his cross-examination that though the claimant had made requests for extension of time, but no action thereon had been taken by the respondent. It was also admitted by RW-1 that the scope of work had been increased, but proportionate increase in time had not been granted to the claimant. The reason for not replying to any of the letter seeking extension of time was that the grounds were general in nature or that the issues raised by the claimant stood resolved....................................."
7. The aforesaid observations would clearly indicate that it would not have been
possible for the respondent to have executed the work within the stipulated
period. The Court of learned Additional District Judge while disposing of the
petition under Section 34 of the Act, has taken note of the aforesaid facts. In
any case, the Court of learned Additional District Judge was not to sit in
appeal and the scope of interference is very limited. This Court does not find
any finding, which can be said to be perverse. No justification for any
interference is made out.
8. The appeal is sans any merit and the same is hereby dismissed.
06.09.2023 ( GURVINDER SINGH GILL )
mohan JUDGE
Whether speaking /reasoned Yes / No
Whether Reportable Yes / No
MOHAN SINGH
2023.09.06 19:07
I attest to the accuracy and
authenticity of this
order/judgment
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!