Citation : 2022 Latest Caselaw 7850 P&H
Judgement Date : 27 July, 2022
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH
214 CRM-10005-2020 in/and
CRM-A-461-2020
Decided on : 27.07.2022
State of Punjab
... Applicant
Versus
Natha Singh alias Hardev Singh alias Dev
... Respondent
CORAM : HON'BLE MR.JUSTICE G.S. SANDHAWALIA
HON'BLE MR.JUSTICE VIKAS SURI
Present: Mr. Abhaypal Singh Gill, AAG, Punjab.
G.S. Sandhawalia, J. (Oral)
Challenge by the State in the present application filed under
Section 378 (3) Cr.P.C. is for grant of leave against the judgment of
acquittal dated 18.04.2015 recorded by the Special Court, Bathinda.
The said application is barred by 1671 days in filing. The
reasons given to show sufficient cause to condone the inordinate delay are
sought to be justified by the counsel for the State, but we are not in
agreement for the reasons which have been put forth in the application.
Even though it has been pointed out that action had been taken against the
delinquent official who kept the file pending with him for 7 months, but the
said period is sought to be between 24.07.2019 and eventually when the
appeal was put for rechecking on 05.02.2020, since it was thereafter filed on
10.02.2020.
Apart from that also the State has proceeded in a leisured
manner as if it is placed at a better pedestal than the ordinary litigant and,
therefore, can seek some preferential right or treatment for condoning the
delay. However, the precedents as such do not support that any different
formula is to be adopted in the cases of the State.
1 of 7
Initially, in the case of State of Nagaland Vs. Lipok AO
and others, 2005 (3) SCR 108, a cord had been struck by the Apex Court
that on account of impersonal machinery the State could be granted some
leverage. However, thereafter in the case of Office of the Chief Master
General & others Vs. Living Media India Ltd. and another, (2012) 3
SCC 563 it was held that the department could not take advantage of
various earlier decisions and claim differential treatment on account of
impersonal machinery. Appropriate explanation had to be given and only
sheer mentioning of various dates could not make out a case of sufficient
cause to condone the huge delay. Relevant portion of the said judgment
reads as under:-
"12) It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us.
Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of
2 of 7
limitation undoubtedly binds everybody including the Government.
13) In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red-tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government departments. The law shelters everyone under the same light and should not be swirled for the benefit of a few. Considering the fact that there was no proper explanation offered by the Department for the delay except mentioning of various dates, according to us, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge delay. Accordingly, the appeals are liable to be dismissed on the ground of delay."
Thereafter, the Apex Court in the case of Esha
Bhattacharjee Vs. managing Committee of Raghunathpur Nafar
Academy and others, (2013) 12 SCC 649 has held that increasing
tendency to perceive delay as a non-serious matter and, hence,
lackadaisical propensity can be exhibited in a nonchalant manner requires
to be curbed, of course, within legal parameters. The concept of liberal
approach has to encapsule the conception of reasonableness and it cannot
be allowed a totally unfettered free play. The principles laid down in the
said case read as under:-
"15. From the aforesaid authorities the principles that can broadly be culled out are:
3 of 7
i) There should be a liberal, pragmatic, justice-oriented, non-pedantic approach while dealing with an application for condonation of delay, for the courts are not supposed to legalise injustice but are obliged to remove injustice.
ii) The terms "sufficient cause" should be understood in their proper spirit, philosophy and purpose regard being had to the fact that these terms are basically elastic and are to be applied in proper perspective to the obtaining fact- situation.
iii) Substantial justice being paramount and pivotal the technical considerations should not be given undue and uncalled for emphasis.
iv) No presumption can be attached to deliberate causation of delay but, gross negligence on the part of the counsel or litigant is to be taken note of.
v) Lack of bona fides imputable to a party seeking condonation of delay is a significant and relevant fact.
vi) It is to be kept in mind that adherence to strict proof should not affect public justice and cause public mischief because the courts are required to be vigilant so that in the ultimate eventuate there is no real failure of justice.
vii) The concept of liberal approach has to encapsule the conception of reasonableness and it cannot be allowed a totally unfettered free play.
viii) There is a distinction between inordinate delay and a delay of short duration or few days, for to the former doctrine of prejudice is attracted whereas to the latter it may not be attracted. That apart, the first one warrants strict approach whereas the second calls for a liberal delineation.
ix) The conduct, behaviour and attitude of a party relating to its inaction or negligence are relevant factors to be taken into consideration. It is so as the fundamental principle is that the courts are required to
4 of 7
weigh the scale of balance of justice in respect of both parties and the said principle cannot be given a total go by in the name of liberal approach.
x) If the explanation offered is concocted or the grounds urged in the application are fanciful, the courts should be vigilant not to expose the other side unnecessarily to face such a litigation.
xi) It is to be borne in mind that no one gets away with fraud, misrepresentation or interpolation by taking recourse to the technicalities of law of limitation.
xii) The entire gamut of facts are to be carefully scrutinized and the approach should be based on the paradigm of judicial discretion which is founded on objective reasoning and not on individual perception.
xiii) The State or a public body or an entity representing a collective cause should be given some acceptable latitude.
16. To the aforesaid principles we may add some more guidelines taking note of the present day scenario. They are: -
a) An application for condonation of delay should be drafted with careful concern and not in a half hazard manner harbouring the notion that the courts are required to condone delay on the bedrock of the principle that adjudication of a lis on merits is seminal to justice dispensation system.
b) An application for condonation of delay should not be dealt with in a routine manner on the base of individual philosophy which is basically subjective.
c) Though no precise formula can be laid down regard being had to the concept of judicial discretion, yet a conscious effort for achieving consistency and collegiality of the adjudicatory system should be made as that is the ultimate institutional motto.
d) The increasing tendency to perceive delay as a non- serious matter and, hence, lackadaisical propensity can
5 of 7
be exhibited in a non-challant manner requires to be curbed, of course, within legal parameters."
In the present case explanation given in the application for
condonation of delay would go on to show that an application under
Section 311 Cr.P.C. had been filed for summoning Balwinder Singh,
Balkar Singh and Sudhir Kumar as prosecution witnesses. On account of
the fact that the same had been dismissed, Criminal Revision No.2852 of
2015 had been filed in this Court. Thereafter, the trial Court had decided
the main case and acquitted the respondent and the criminal revision had
been withdrawn on 05.09.2017 since the same had become infructuous.
The file was then put up before the Law Officer with both the orders
dated 18.04.2015 and and 05.09.2017 and an opinion was then rendered
on 28.12.2017 that it is a fit case to file an appeal. The same had been
endorsed by the Advocate General's Office on 15.01.2018 and sent to the
District Attorney, Bathinda on 07.02.2018, who had then written to the
SSP, Bathinda on 07.03.2018. The SSP, Bathinda had written a letter on
05.04.2018 for grant of sanction and the sanction order was only obtained
on 09.11.2018. It was received in the office of Advocate General on
14.11.2018 and then documents were called for vide letter dated
15.11.2018. The official of the police station visited the office of
Advocate General and then the case was put up for vetting on
24.07.2019.
Thus, the reading of the dates would go on to show that the
delay has occurred not at one point of time, but on several occasions.
Firstly, we are of the considered opinion that if the State was interested to
6 of 7
prosecute the respondent, there was no need to file the criminal revision
before this Court, which was eventually dismissed as withdrawn.
Thereafter, in spite of obtaining an opinion on 28.12.2017 from the Law
Officer, the sanction could not be obtained till 09.11.2018 and after
receiving the same, the case was put up for vetting only on 24.07.2019.
Thus, now to fall back that there was delay on the part of one delinquent
official for 7 months i.e. between 24.07.2019 to 05.02.2020 when the
appeal was filed in February, 2020 would not make out sufficient cause
to condone the inordinate delay, which has occurred prior in time as
noticed above on two occasions.
Keeping in view the above reasons and keeping in mind the
principles laid down by the Apex Court, we are of the considered opinion
that there is no reason to condone the inordinate delay. Accordingly,
both the application for condoning the delay of 1671 days and the
application filed under Section 378 (3) Cr.P.C. for grant of leave are
dismissed.
(G.S. SANDHAWALIA)
JUDGE
(VIKAS SURI)
July 27, 2022 JUDGE
Naveen
Whether speaking/reasoned: Yes/No
Whether Reportable: Yes/No
7 of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!