Citation : 2022 Latest Caselaw 6007 P&H
Judgement Date : 4 July, 2022
CWP Nos.7519 and 7715 of 2020(O&M) 1
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
Reserved on 16.05.2022
Date of Decision-04.07.2022
1. CWP No.7519 of 2020(O&M)
Talwandi Sabo Power Limited ... Petitioner
Versus
Union of India and others ... Respondents
2. CWP No.7715 of 2020(O&M)
Nabha Power Limited ... Petitioner
Versus
State of Punjab and others ... Respondents
CORAM:-HON'BLE MR. JUSTICE RAJ MOHAN SINGH
Present: Mr. Ashwani Chopra, Sr. Advocate with
Ms. Rupa Pathania, Advocate,
Mr. Satyaveer Singh, Advocate,
Mr. Vidul Kapoor, Advocate and
Mr. Aditya Swaroop, Advocate
for the petitioner in CWP No.7519 of 2020.
Mr. Akshay Bhan, Sr. Advocate with
Mr. A.S. Talwar, Advocate
for the petitioner in CWP No.7715 of 2020.
Mr. Satya Pal Jain, Addl. Solicitor General of
India with Mr. Ajay Kalra, Central Govt. Counsel
for the Union of India.
Mr. C.L. Pawar, Sr. DAG, Punjab.
Mr. Pankaj Mulwani, DAG, Haryana.
Mr. Abhilaksh Grover, Advocate
for PSPCL.
Mr. Sehaj Bir Singh, Advocate
for PSTCL.
***
RAJ MOHAN SINGH, J.
1 of 46
[1]. Vide this common order/judgment, CWP No.7519
of 2020 titled Talwandi Sabo Power Limited Vs. Union of India
and others and CWP No.7715 of 2020 titled Nabha Power
Limited are being decided. Since common questions of law
and facts are involved, therefore, common fact are being
noticed.
[2]. In both the cases, identical power purchase
agreements were executed. In CWP No.7519 of 2020,
agreement was executed on 01.09.2008, whereas in CWP
No.7715 of 2020, agreement was executed on 18.01.2010.
The terms and conditions of both the power purchase
agreements are identical.
[3]. In CWP No.7519 of 2020, petitioner seeks
issuance of an appropriate writ in the nature of certiorari or
any other appropriate direction to quash notices dated
29.03.2020 and 14.04.2020 issued by Punjab State Power
Corporation Limited/respondent No.3 and also notice and E-
mail dated 16.05.2020 issued by respondent No.4 in the
context of denying the petitioner's right/lawful payments in lieu
of capacity charges under power purchase agreement dated
01.09.2008. Further directions are sought against respondent
No.4 to correct the State Energy Account (SEA) for the month
of March and April 2020, thereby correctly reflecting the
declared capacity of the petitioner's plant.
2 of 46
[4]. In CWP No.7715 of 2020, petitioner seeks
issuance of an appropriate writ in the nature of certiorari,
seeking quashing of State Energy Account (SEA) for the
month of March 2020 (to the extent of 30th March 2020 and
31st March 2020) and April 2020 issued by Punjab State Load
Dispatch Centre/respondent No.4 to the extent that the
declared capacity/availability of the petitioner's project has
been declared as zero being illegal and factually incorrect.
Further petitioner seeks quashing of notices dated 29.03.2020
and follow up letters dated 14.04.2020, 13.05.2020 and
20.05.2020 issued by the Punjab State Power Corporation
Limited (PSPCL)/respondent No.2 to the petitioner, requesting
the petitioner not to declare availability from its project and
also stating that Punjab State Power Corporation Limited is
relieved from making payment of capacity charges and Late
Payment Surcharge (LPS) on delayed payment of invoice to
the petitioner on the ground of provisions in the power
purchase agreement dated 18.01.2010. Further directions are
sought against respondent No.2 to pay capacity charges to
the petitioner in terms of provisions of power purchase
agreement dated 18.01.2010 and also to quash E-mail notices
dated 01.04.2020, 02.04.2020, 29.05.2020 and similar notices
issued on daily basis by Punjab State Load Dispatch
Centre/respondent No.4, refusing to issue dispatch
instructions to the petitioner being illegal and against law.
3 of 46
Necessary directions are sought against respondent No.4 i.e.
Punjab State Load Dispatch Centre to correct the State
Energy Account for the months of March and April 2020,
thereby reflecting correct declared capacity/availability of the
petitioner's project.
[5]. Petitioners are generating companies under
Section 2(28) of the Electricity Act, 2003. Petitioners have
executed power purchase agreements for supply of power
from their thermal power plants to Punjab State Power
Corporation Limited (PSPCL) through its Managing Director,
The Mall, PSEB, Head Office, Patiala. Power purchase
agreement in terms of its Article 1 defines Allocated
Contracted Capacity, which means the Contract Capacity
allocated to the Procurer/PSEB/PSPCL as provided in
Schedule 13 thereof subject to adjustment as per the terms of
the agreements. The aforesaid Schedule 13 shows that
Contract Capacity allocated to PSEB/PSPCL/Procurer is
100%. Availability Based Tariff (ABT) shall mean all the
regulations contained in the Central Electricity Regulatory
Commission (terms and conditions of Tariff) Regulations,
2004 as amended from time to time. Availability factor shall
have the meaning ascribed thereto in Availability Based Tariff
(provided that in place of installed capacity and normative
auxiliary consumption it shall be Contractual Capacity).
4 of 46
Availability Capacity shall have the meaning ascribed thereto
in Availability Based Tariff (ABT).
[6]. Capacity Charge shall have the meaning ascribed
thereto in Schedule 7. Declared Capacity in relation to a Unit
or the Power Station at any time means the net capacity of the
Unit or the Power Station at the relevant time (expressed in
MW at the Interconnection Point) as declared by the Seller in
accordance with the Grid Code and dispatching procedures
as per the Availability Based Tariff.
[7]. Force Majeure Event shall have the meaning
ascribed thereto in Article 12.3(ii)(1). Dispatch Instruction
means any instruction issued by the Procurer through the
SLDC to the Seller, in accordance with applicable Grid Code
and the agreement.
[8]. Grid Code/IEGC means any set of regulations
issued by Appropriate Commission as amended from time to
time and legally binding on the Seller's and the Procurer's
governing the operation of the Grid System or any succeeding
set of regulations/code.
[9]. Quoted Tariff shall mean the sum total of Quoted
Energy Charges and Quoted Capacity Charge. Quoted
Energy Charge shall mean the Charge derived from the Net
Quoted Heat Rate. Quoted Capacity Charge shall mean the
5 of 46
sum total of Quoted Non Escalable Capacity Charge and
Quoted Escalable Capacity Charge. Quoted Non Escalable
Capacity Charge and Quoted Escalable Capacity Charge
shall have the meaning as ascribed thereto in Schedule 11.
[10]. Power Purchase Agreement prescribed a two-fold
tariff regime i.e. Capacity Charges paid to the generating
company on the basis of Declared Availability of the
generating company irrespective of whether PSPCL and
SLDC have scheduled electricity or not. Energy Charges are
paid to the generating company on the basis of Scheduled
Generation (the actual electricity supplied).
[11]. On 22.03.2020, Government of Punjab ordered a
State- wide lockdown due to COVID-19 outbreak. The
electricity falling under the category of essential services was
exempted from shut down order and it was ordered that the
restrictions shall not be applicable on such essential services.
[12]. On 24.03.2020, Government of India, Ministry of
Home Affairs while exercising powers under Disaster
Management Act, 2005 passed an order restricting activities.
Power generation, transmission and distribution units and
services were kept as essential services.
[13]. On 25.03.2020, Ministry of Power, Government of
India (MOP) also issued an order, directing all the State
6 of 46
authorities to ensure smooth and uninterrupted power. On
27.03.2020, Ministry of Power issued another order in relation
to its earlier order dated 28.06.2019 regarding payment
security mechanism through Letter of Credit. Ministry of
Power vide its order dated 28.03.2020 under Section 107 of
the Electricity Act, directed the Central Electricity Regulatory
Commission (CERC) that for those projects covered under
Section 63 of the Electricity Act like the petitioner projects,
DISCOMs may claim relief as per force majeure provisions in
the respective power purchase agreements.
[14]. On 29.03.2020, Punjab State Power Corporation
Limited issued two force majeure notices to the petitioners
requesting the petitioner not to declare availability of their
project under the agreements. It was conveyed that PSPCL
was not obliged to pay and disburse capacity charges and
Late Payment Surcharge (LPS) to the petitioners under the
agreements in view of purported lower demand from the
consumers of State of Punjab. On 30.03.2020, Department of
Power, State of Punjab issued an order under Section 108 of
the Electricity Act, 2003 to the Punjab State Electricity
Regulatory Commission (PSERC) to treat the spread of
COVID-19 pandemic and consequent lockdown as a force
majeure event.
7 of 46
[15]. Petitioners contested the declaration of force
majeure on the ground that the event purportedly claimed by
PSPCL as a force majeure event does not fall under any of
the force majeure events listed under Article 12.3 of the
Power Purchase agreements. PSPCL has no cause of action
to issue the notice invoking Article 12 of the Power Purchase
Agreement as there is no specific clause under the aforesaid
Article 12.3 under which the restrictions can be imposed by
the Government of Punjab for constituting a force majeure
event. Even PSPCL is not an affected party under Article 12.3
of the Power Purchase Agreement. The alleged force majeure
event does not prevent PSPCL from scheduling/procuring
power from generating plants. PSPCL even continues to
schedule power from several other counterparties with which
power purchase agreements were executed. In the present
cases, PSPCL has failed to establish existence of force
majeure event.
[16]. In case of Talwandi Sabo Power Limited, State
Load Dispatch Centre due to invocation of force majeure,
issued notice/E-mail dated 16.05.2020 and stopped
scheduling the power from the petitioner without treating the
declared availability of the petitioner for the purposes of
preparing the State Energy Account in accordance with State
8 of 46
Grid Code. As a result of that, the petitioner has been denied
its right to capacity charges.
[17]. In case of Nabha Power Limited, State Load
Dispatch Centre stopped issuing dispatch instructions to the
petitioner from 29.03.2020. Petitioner declared its capacity
and capability to produce electricity as per law. State Load
Dispatch Centre sent E-mail dated 01.04.2020 to the
petitioner on the ground that notice regarding curtailing of
power under force majeure condition in view of provisions of
power purchase agreement has already been given to the
petitioner by PSPCL on 29.03.2020 and subsequently PSPCL
is not giving any requirement since the date of issue of said
notice and accordingly schedule is not being provided in the
absence of requirement from PSPCL.
[18]. State Load Dispatch Centre did not issue the
dispatch instructions even on 02.04.2020 and reiterated the
stand that in the absence of PSPCL giving any requirement,
State Load Dispatch Centre is unable to provide dispatch
instructions to the petitioner. Petitioner replied to the E-mail of
State Load Dispatch Centre that in case of no demand of
power from PSPCL, State Load Dispatch Centre is obligated
to issue dispatch instructions as State Load Dispatch Centre
is an independent authority having defined obligations and
duties in law. Even in cases of other generating companies,
9 of 46
State Load Dispatch Centre continued to accept the declared
capacity of Inter-State Generating Stations (ISGS) supplying
power to respondent No.2, even though similar force majeure
notices were issued by PSPCL in those cases also.
[19]. On 06.04.2020, Ministry of Power issued an
order, clarifying that notwithstanding the lockdown, the
obligation to pay for capacity charges as per power purchase
agreement shall continue. Despite the aforesaid order,
PSPCL and SLDC did not act in accordance with law. The
aforesaid letter dated 06.04.2020 was in consonance with
Section 107 of the Electricity Act, 2003, which prescribed that
in the discharge of its functions, the Central Commission shall
be guided by such directions in matters of policy involving
public interest as the Central Government may give to it in
writing.
[20]. Thereafter, on 07.04.2020, Punjab State Electricity
Regulatory Commission in Suo-Moto Petition No.11 of 2020
also took cognizance of Late Payment Surcharge (LPS) order
issued by the Department of Power, Government of Punjab.
For power generating companies whose tariff has been
adopted by the Commission under Section 63 of the Act, the
Punjab State Electricity Regulatory Commission directed that
PSPCL may claim relief from its obligations regarding the rate
10 of 46
at which LPS is to be paid as per the force majeure provisions
given in the respective power purchase agreements.
[21]. The stand of the PSPCL is that force majeure
event has led to a situation where PSPCL is unable to perform
its obligations under the agreement and therefore, it would not
be liable to pay any amount towards capacity charges.
[22]. In case of Nabha Power Limited, State Load
Dispatch Centre has issued State Energy Account for the
month of April 2020 on 07.05.2020, wherein the declared
capacity/availability of the petitioner's project was shown as
zero for the entire month of April.
[23]. With this background on record, the present
petitions have been filed for the reliefs claimed therein.
[24]. After filing of the present petitions, matter came up
for hearing on 22.07.2020 and following order was passed:-
"The matter has been taken up through video- conferencing in the light of the pandemic Covid-19 situation and as per instructions.
As per reply filed by respondent No.4-PSTCL, the impugned order passed by respondent No.3-(PSPCL) has been withdrawn vide memo dated 20.05.2020 as reflected in para No.6 of the reply and at this stage, the dispute remains with regard to capacity charges for about two months as noticed in order dated 29.05.2020.
11 of 46
After hearing the learned counsel for the parties, perusal of the record and considering the nature of issue in question, the Court feels that the matter needs detailed deliberations.
Admitted.
To be heard within three months after resumption of normal functioning of the Court.
In the meantime, the parties are free to explore if the issue in question can be settled amicably.
The petitioner is free to move any application in case the averments made in para No.6 of the reply is found to be against the record.
A photocopy of the order be placed on the connected file.
22.07.2020 (JITENDRA CHAUHAN) gsv JUDGE" [25]. Perusal of the aforesaid order would show that as
per stand taken by the State Load Dispatch Centre, the
dispute remains only with regard to capacity charges.
[26]. Learned counsel for the respondents have
contested the claims of the petitioners on the ground that
events of force majeure are fully applicable to the generating
companies in view of unprecedented situation arising out of
COVID-19 pandemic and the present writ petitions are not
maintainable as the petitioners have alternative remedy under
the Arbitration and Conciliation Act, 1996 as well as before
12 of 46
Punjab State Electricity Regulatory Commission in terms of
Section 86 of the Electricity Act, 2003 read with Section 17 of
the Power Purchase Agreements.
[27]. Learned counsel for Punjab State Power
Corporation Limited and State Load Dispatch Centre have
contended that Section 86 of the Electricity Act, 2003 is a
special provision for adjudication of the disputes between the
licenses and generating companies. Such disputes can be
adjudicated upon either by the State Commission or by the
person to whom its referred for arbitration. Section 86 of the
Act is to override the general provision of the Arbitration and
Conciliation Act, 1996.
[28]. Learned counsel for the respondents relied upon
Gujarat Urja Vikash Nigam Ltd. Vs. Essar Power Ltd.,
2008 AIR (Supreme Court) 1921, A.P. Power Coordination
Committee and others Vs M/s Lanco Kondapalli Power
Ltd. and others, 2016(3) SCC 468, M/s Adani Power Ltd.
Vs. Gujarat Electricity Regulatory Commission and
others, 2016(15) SCC 665, Chairman & Managing Director
Southern Power Distribution Company of Andhra
Pradesh Tirupati and others Vs. Sudalagunta Sugars Ltd.,
2013 AIR (Andhra Pradesh) 1, State of Bihar and others
Vs. Jain Plastics and Chemical Ltd., 2002(1) SCC 216,
Union Construction Co. Pvt. Ltd. Vs. Chief Engineer
13 of 46
Eastern Command, Lucknow and another, 1960 AIR
(Allahabad) 72, The Empire Jute Co. Ltd. and others Vs.
The Jute Corporation of India Ltd. and another, 2007 (14)
SCC 680, Booz Allen and Hamilton Inc. Vs. SBI Home
Finance Ltd. and others, 2011(5) SCC 532, Rashtriya Ispat
Nigam Ltd. and another Vs. M/s Verma Transport
Company, 2006 (7) SCC 275 and Ashish Gupta Vs. IBP Co.
Ltd. and another, 2006 AIR (Delhi) 57 and contended that
the dispute between licenses and generating companies is to
be decided by the State Commission or the Arbitrator
nominated by it, whereas under Section 11 of the Arbitration
and Conciliation Act, 1996, the Court can refer such disputes
to an arbitrator appointed by it. Harmonious construction of
the provisions of the Electricity Act 2003 and the Arbitration
and Conciliation Act, 1996 would provide that whenever there
is a dispute between a licensee and the generating
companies, only the State Commission or Central
Commission (as the case may be) or Arbitrator nominated by
it, can resolve such a dispute, whereas all other disputes
would be decided in accordance with Section 11 of the
Arbitration and Conciliation Act, 1996. This is also evident
from Section 158 of the Electricity Act, 2003. Power purchase
agreement is a contract between the parties and terms of any
contract are nothing but the agreed terms of the contracted
parties and therefore, the claim arising out of contractual
14 of 46
obligations cannot be espoused in a writ jurisdiction. Any
breach of contract cannot be made subject matter of writ. The
contractual obligation and enforcement thereto, would give
rise to the disputed questions of rival claims and for that, writ
is not an appropriate Forum.
[29]. I have heard learned counsel for the parties and
with their assistance have also perused the material on
record.
[30]. Admittedly, the surviving claim is with regard to
payment of capacity charges for the relevant period in both
the writ petitions as per power purchase agreements. First of
all, status/functions/obligations of State Load Dispatch Centre
has to be highlighted in the present set of circumstances.
Section 32 of the Electricity Act, 2003 deals with functions of
State Load Dispatch Centre, which reads as under:-
"32. Functions of State Load Despatch Centres-(1) The State Load Despatch Centre shall be the apex body to ensure integrated operation of the power system in a State.
(2) The State Load Despatch Centre shall-
(a) be responsible for optimum scheduling and despatch of electricity within a State, in accordance with the contracts entered into with the licensees or the generating companies operating in that State;
(b) monitor grid operations;
15 of 46
(c) keep accounts of the quantity of electricity transmitted through the State grid;
(d) exercise supervision and control over the intra- State transmission system; and
(e) be responsible for carrying out real time operations for grid control and despatch of electricity within the State through secure and economic operation of the State grid in accordance with the Grid Standards and the State Grid Code.
(3) The State Load Despatch Centre may levy and collect such fee and charges from the generating companies and licensees engaged in intra-State transmission of electricity as may be specified by the State Commission."
[31]. State Load Dispatch Centre may give such
directions and exercise such supervision and control as may
be required for ensuring the integrated grid operations and for
achieving the maximum economy and efficiency in the
operation of power system in the State. All the persons
connected with the operation of the power system viz.
licensee, generating company and any other person
connected with the operation of the power system, shall
comply with the directions issued by the State Load Dispatch
Centre under Section 33(1) of the Electricity Act, 2003. In turn,
State Load Dispatch Centre shall comply with the directions of
the Regional Load Dispatch System. In case of any dispute
with reference to the quality of electricity or safe, secure and
16 of 46
integrated operation of the State Grid or in relation to any
direction given under sub-Section (1) of Section 33 of the Act,
it shall be referred to the State Commission for decision.
[32]. As per Punjab State Electricity Regulatory
Commission (Punjab State Grid Code) Regulations, 2013,
State Load Dispatch Centre in addition to the functions as
stated in Section 32 of the Electricity Act has functions
including system operation and control including intra-state
transfer of power, covering contingency analysis and
operations planning on real time basis, scheduling/re-
scheduling of generation, system restoration following grid
disturbances, metering and data collection, compiling and
furnishing date pertaining to system operation and operation
of State Unscheduled Interchange (UI) pool account and State
reactive energy account. The roles and responsibilities of
State Load Dispatch Centre have been discussed in Section
2.3.1 of the aforesaid Regulations, 2013.
[33]. State Load Dispatch Centre has the responsibility
of implementing State Grid Code and shall not unduly
discriminate against or unduly prefer any one or any group of
persons or STU in the conduct of any business.
[34]. Section 2.3.4 of Punjab State Electricity Regulatory
Commission (Punjab State Grid Code) Regulations, 2013
deals with role of distribution licensee.
17 of 46
[35]. As per Section 2.3.4 (d) of the aforesaid
Regulations, 2013, the distribution licensee shall inform the
SLDC about the details of 15
minutes/hourly/daily/weekly/monthly demand and energy
requirement and also contracts entered into for importing
power from different sources and coordinate with SLDC in real
time operation. It shall follow the directions of SLDC in
scheduling its exchange of power and help in controlling the
operation of the system by adjustment of drawal from the
system. They shall take special care for drawal/injection of
reactive power from/to the State Power System.
[36]. As per Section 6.3.7 of the aforesaid Regulations,
2013, SLDC shall carry out its own demand estimation from
the historical date and weather forecast data from time to
time. All distribution licensees/users and other concerned
persons shall provide relevant data and other information as
required by SLDC for demand estimate. All distribution
licensees/users shall provide to the SLDC their estimates of
demand for the year ahead on monthly-basis at each inter
connection point for the next financial year by 1st October
each year. All distribution licensees/users shall also provide
daily demand for the month ahead at each inter-connection
point by 25th for the next month.
18 of 46
[37]. As per Section 6.3.8 of the aforesaid Regulations,
2013, all distribution licensees/users shall provide to SLDC on
day ahead basis at 11.00 hours each day their estimated
demand for each 15-minute block for the ensuring day along
with the estimates of load that may be shed when required, in
discrete blocks with the details of arrangements of such load
shedding.
[38]. As per Section 11.2 of the aforesaid Regulations,
2013, State Grid Code deals with the procedures to be
adopted for scheduling of the net injection/drawals of State
Entities on a day ahead basis with the modality of the flow of
information between the SLDC/ALDCs/Power Exchange and
State Entities. The procedure for submission of capability
declaration by each SGS/CPPs/IPPs and submission of
requisition/drawal schedule by other State Entities is intended
to enable SLDC to prepare the despatch schedule for each
SGS/CPPs/IPPs and drawal schedule for each
beneficiary/Distribution Licensee. It also provides
methodology of issuing real time despatch/drawal instructions
and rescheduling, if required, to State Entities along with the
commercial arrangement for the deviations from schedules,
as well as, mechanism for reactive power pricing.
This code also provides the methodology for re-scheduling of
wind and solar energy on three (3) hourly basis and the
19 of 46
methodology of claiming the Renewal Regulatory charge for
dealing with the variable generation of the wind and solar
energy stations within State. For this, appropriate meters and
Data Acquisition System facility (for real time as well as stored
data) shall be provided for accounting of UI charges and
transfer of information to SLDC.
The provisions contained in this Part are without prejudice to
the powers conferred on SLDC under Sections 32 and 33 of
the Electricity Act, 2003.
[39]. As per Section 11.3.3 of the aforesaid Regulations,
2013, despatch instructions to SGS shall be in standard
format to be finalized by SLDC. These instructions will
recognize declared availability and other parameters that have
been made available by the SGS to SLDC. These instructions
shall include time, Power Station, Generating Units (Total
export in case of CPP), name of operators sending and
receiving the same. Standard despatch instructions may
include:-
o To switch a SGS into or out of Service;
o To schedule generation;
o Details of reserve to be carried on a unit;
o To increase or decrease MVAR generation to
maintain voltage profile as per unit capability at that time;
20 of 46
o To begin pre-planned Black Start procedures;
o To hold spinning reserve;
o To hold Generating Units of SGS on standby;
o To control MW/MVAR Drawal.
[40]. As per Section 11.3.12 of the aforesaid
Regulations, 2013, it shall be incumbent upon the SGS to
declare the plant capabilities faithfully i.e., according to their
assessment. In case, it is suspected that they have
deliberately over/under declared the plant capability
contemplating to deviate from the schedules given on the
basis of their capability declarations (and thus make money
either as undue capacity charge or as the charge for
deviations from schedule), the SLDC may serve the notice
and ask the SGS to explain the situation with necessary
backup data.
[41]. As per Section 11.3.13 of the aforesaid
Regulations, 2013, the SGS shall be required to demonstrate
the declared capability of its generating station as and when
asked by the SLDC. In the event of the SGS failing to
demonstrate the declared capability, the capacity charges due
to the generator shall be reduced as a measure of penalty.
The quantum of penalty for the first mis-declaration for any
duration/block in a day shall be the charges corresponding to
21 of 46
two days fixed charges. For the second mis-declaration the
penalty shall be equivalent to fixed charges for four days and
for subsequent mis-declarations, the penalty shall be
multiplied in the geometrical progression over a period of a
month.
[42]. As per Section 11.3.17 of the aforesaid
Regulations, 2013, the SLDC shall be responsible for
computation of actual net injection/drawal of concerned Users,
15 minute-wise, based on the above meter readings.
Subsequently, SLDC will prepare and issue the Unscheduled
Inter-change (UI) account. All computations carried out by
SLDC shall be open to all entities for checking/verifications for
a period of 15 days. In case any mistake/omission is detected,
the SLDC shall forthwith make a complete check and rectify
the same.
[43]. As per Section 11.3.18 of the aforesaid
Regulations, 2013, the operating log books of the generating
station shall be available for review by the SLDC. These
books shall keep record of machine operation and
maintenance.
[44]. As per Section 12.3 of the aforesaid Regulations,
2013, State Load Dispatch Centre has the following
responsibilities:-
22 of 46
12.3.1 SLDC shall monitor actual power drawal against
scheduled power drawal and regulate internal generation
and demand to maintain this schedule. SLDC shall also
monitor reactive power drawal and availability of
capacitor banks.
12.3.2 Generating Stations within Punjab, other than
ISGS and of BBMB, shall follow the despatch
instructions issued by SLDC.
12.3.3 Distribution licensees, Open Access
Customers and Other Users shall comply with the
instructions of SLDC for managing load & reactive power
drawal as per system requirement.
[45]. As per Section 14.1.14 of the aforesaid
Regulations, 2013, in the preparation of energy accounts,
SLDC shall take into consideration the following aspects:-
o Agreements for supply and/or transmission of power,
bilateral agreements, short term and spot purchases
affected by any licensee and User;
o Policy guidelines or decisions of State Grid Code
Review Committee;
o Decisions/directives of the Commission;
o Components of tariff as approved by the Commission;
and
23 of 46
o Such accounts by BBMB and NRPC.
[46]. As per Section 14.1.6 of the aforesaid Regulations,
2013, Monthly State Energy Accounts for Punjab shall be
prepared by SLDC by 7th of every month and shall be
conveyed to all concerned for raising bills. Such energy
accounts shall be subject to inspection/verification/checking
and raising any objection within 15 days of date of issue. If no
objection is raised, energy accounts shall be finalized. In
case, any objection is raised, same shall be deliberated in
Commercial and Metering Committee and finalized as per
their decision. Supplementary bills/credit note shall be raised
accordingly.
[47]. Perusal of the aforesaid facts would show that
State Load Dispatch Centre has definite obligations under the
law and these obligations are independent and free from any
overlapping obligations of any other person. State Load
Dispatch Center has to act independently on defined
parameters as laid down under Section 32 of the Electricity
Act and under different Sections of Punjab State Electricity
Commission (Punjab State Grid Code) Regulations, 2013.
[48]. As per Central Electricity Regulatory Commission
(Terms & Conditions of Tariff) Regulations, 2004, "Availability"
in relation to a thermal generating station for any period
means the average of the daily average Declared Capacities
24 of 46
(DCs) for all the days during that period expressed as a
percentage of the installed capacity of the generating station
minus normative auxiliary consumption in MW and shall be
computed in accordance with a specific formula.
[49]. Declared Capacity means the capability of the
generating station to deliver ex-bus electricity in MW declared
by such generating station in relation to any period of the day
or whole of the day, duly taking into account the availability of
fuel.
[50]. Scheduled Generation at any time or for any period
or time block means schedule of generation in MW ex-bus
given by the Regional Load Despatch Centre.
[51]. Regulation 15 of the aforesaid Regulations of 2004
deals with components of tariff. Section 15 of Central
Electricity Regulatory Commission (Terms & Conditions of
Tariff) Regulations, 2004 is reproduced hereasunder:-
"15. Components of Tariff: (1) Tariff for sale of electricity from a thermal power generating station shall comprise of two parts, namely, the recovery of annual capacity (fixed) charges and energy (variable) charges.
(2) The annual capacity (fixed) charges shall consist of:
(a) Interest on loan capital;
(b) Depreciation, including Advance Against Depreciation;
25 of 46
(c) Return on equity;
(d) Operation and maintenance expenses; and
(e) Interest on working capital.
(3) The energy (variable) charges shall cover fuel cost."
[52]. Regulation 16 of the aforesaid Regulations, 2004
deals with the norms of operation, which are dependent upon
target availability for recovery of full capacity (fixed) charges,
target plant load factor for incentive, gross station heat rate,
secondary fuel oil consumption, auxiliary energy consumption
and stabilization period.
[53]. Scheduling as given in Regulation 27 of the
aforesaid Regulations, 2004 if read in conjunction with Indian
Electricity Grid Code, then it would give following methodology
of scheduling and calculating availability:-
(i) The generator shall make an advance declaration of capability of its generating station. The declaration shall be for that capability which can be actually made available.
The declaration shall be for the capability of the generating station to deliver ex-bus MW for the next day either as one figure for the whole day or as different figures for different periods of the day. The capability as declared by the generator, also referred to as the declared capacity, shall form the basis of generation scheduling.
26 of 46
(ii) While making or revising its declaration of capability, the generator shall ensure that the declared capability during peak hours is not less than that during other hours. However, exception to this rule shall be allowed in case of tripping/re-synchronization of units as a result of forced outage of units.
(iii) Generation scheduling shall be done in accordance with the operating procedure stipulated in the Indian Electricity Grid Code.
(iv) Based on the declaration of the generator, the Regional Load Dispatch Centre shall communicate their shares to the beneficiaries out of which they shall give their requisitions.
(v) Based on the requisitions given by the beneficiaries and taking into account technical limitations on varying the generation and also taking into account transmission system constraints, if any, the Regional Load Dispatch Centre shall prepare the economically optimal generation schedules and drawl schedules and communicate the same to the generator and the beneficiaries.
The Regional Load Dispatch Centre shall also formulate the procedure for meeting contingencies both in the long run and in the short run (Daily scheduling).
(vi) The scheduled generation and actual generation shall be ex-bus at the generating station. For beneficiaries, the scheduled and actual net drawals shall be at their respective receiving points.
(vii) For calculating the net drawals schedules of beneficiaries, the transmission losses shall be
27 of 46
apportioned in their drawals schedules for the time being.
Provided that a refinement may be specified by the Commission in future depending on the preparedness of the respective Regional Load Dispatch Centre.
(viii) In case of forced outage of a unit, the Regional Load Dispatch Centre shall revise the schedules on the basis of revised declared capability. The revised declared capability and the revised schedules shall become effective from the 4th time block, counting the time block in which the revision is advised by the generator to be the first one.
(ix) In the event of bottleneck in evacuation of power due to any constraint, outage, failure or limitation in the transmission system, associated switchyard and sub- stations owned by the Central Transmission Utility or any other transmission licensee involved in inter-state transmission (as certified by the Regional Load Dispatch Centre) necessitating reduction in generation, the Regional Load Dispatch Centre shall revise the schedules which shall become effective from the 4th time block, counting the time block in which the bottleneck in evacuation of power has taken place to be the first one. Also, during the first, second and third time blocks of such an event, the scheduled generation of the generating station shall be deemed to have been revised to be equal to actual generation, and the scheduled drawals of the beneficiaries shall be deemed to have been revised to be equal to their actual drawals.
(x) In case of any grid disturbance, scheduled generation of all the generating stations and schedules
28 of 46
drawal of all the beneficiaries shall be deemed to have been revised to be equal to their actual generation/drawal for all the time blocks affected by the grid disturbance. Certification of gird disturbance and its duration shall be done by the Regional Load Dispatch Centre.
(xi) Revision of declared capability by the generator(s) and requisition by beneficiary(ies) for the remaining period of the day shall also be permitted with advance notice. Revised schedules/declared capability in such cases shall become effective from the 6th time block, counting the time block in which the request for revision has been received in the Regional Load Dispatch Centre to be the first one.
(xii) If, at any point of time, the Regional Load Dispatch Centre observes that there is need for revision of the schedules in the interest of better system operation, it may do so on its own, and in such cases, the revised schedules shall become effective from the 4th time block, counting the time block in which the revised schedule is issued by the Regional Load Dispatch Centre to be the first one.
(xiii) Generation schedules and drawal schedules issued/revised by the Regional Load Dispatch Centre shall become effective from designated time block irrespective of communication success.
(xiv) For any revision of scheduled generation, including post facto deemed revision, there shall be a corresponding revision of scheduled drawals of the beneficiaries.
29 of 46
(xv) A procedure for recording the communication regarding changes to schedules duly taking into account the time factor shall be evolved by the Central Transmission Utility.
[54]. Regulation 28 of the aforesaid Regulations, 2004
deals with demonstration of declared capability. The
generating company may be required to demonstrate the
declared capability of its generating station as and when
asked by the Regional Load Despatch Centre of the region in
which the generating station is situated.
[55]. Regulation 30 of the aforesaid Regulations, 2004
deals with billing and payment of capacity charges. Billing and
payment of capacity charges shall be done on monthly basis.
Each beneficiary shall pay the capacity charges in proportion
to its percentage share in installed capacity of the generating
station. Beneficiaries shall have full freedom for negotiating
any transaction for utilization of their capacity shares. In such
cases, the beneficiary having allocation in the capacity of the
generating station shall be liable for full payment of capacity
charges and energy charges corresponding to its total
allocation and schedule respectively. If any capacity remains
un-requisitioned during day-to-day operation, the Regional
Load Despatch Centre shall advise all beneficiaries in the
region and the other Regional Load Despatch Centres so that
such capacity may be requisitioned through bilateral
30 of 46
arrangements either with the concerned generating company
or with the concerned beneficiaries under intimation to the
Regional Load Despatch Centre. The capacity charges shall
be paid to the beneficiaries including those outside the region
to the generating company every month in accordance with
the prescribed formulas.
[56]. Perusal of the aforesaid provisions would show that
State Load Dispatch Centre has definite obligations at
different stages and capacity charges are independent of
actual energy consumed by the beneficiary.
[57]. State Load Dispatch Centre is supposed to function
as an independent body under the Electricity Act 2003 and as
per different regulations as discussed in the preceding paras.
Power purchase agreement between the parties in its very
nature cannot be held to be purely a contract giving civil
consequence and pure contractual dispute.
[58]. In the facts and circumstances of the present case,
primary dispute revolves around inaction on behalf of Punjab
State Load Dispatch Centre in not performing its part of
obligation in terms of schedule and other obligations. There is
no dispute as such against PSPCL so far as statutory
obligations on the part of Punjab State Load Dispatch Centre
are concerned. In order to maintain the writ petition, the Court
has to consider the nature of agreement as to whether the
31 of 46
same is in relation to personal interest of the party or the
corporation being instrumentality of the State as entered into
such agreement in public interest. The Ministry of Power,
Government of India issued guidelines for procurement of
power through competitive bidding under Section 63 of the
Electricity Act, 2003. Section 63 of the Act provides
notwithstanding anything contained in Section 62 of the Act,
the Appropriate Commission shall adopt the tariff if such tariff
has been determined through transparent process of bidding
in accordance with the guidelines issued by the Central
Government. The Central Government has issued guidelines
for determination of tariff by bidding process for procurement
of power by distribution licensees. The aforesaid guidelines
have provided in detail about the procedure for invitation of
the bid, the tariff structure, capacity charges, energy charges,
the bidding process, bid submission and evaluation and award
of contract in conclusion. Power purchase agreement should
be in consonance with Section 63 of the Act and tariff has to
be determined through transparent process of bidding in
accordance with the guidelines. Therefore, it can be safely
concluded that the entire process is guided and controlled by
the guidelines framed by the Central Government and the
contract entered into between the licensor and the licensee is
more akin to a standard form of contract which has to pass
the test laid down under Section 63 of the Electricity Act. The
32 of 46
contract in question is strictly based on the guidelines issued
by the Central Government and no party can deviate from the
said guidelines unless such deviation is approved by the
appropriate Commission. The power purchase agreements
entered into between the petitioners and PSPCL cannot be
said to be a purely private contracts. Even the enormity of the
project and the cost involved in building a power plant would
have a public character element, looking into the fact that the
contract was for supply of very high power/energy and that
would be a project in public interest.
[59]. In view of aforesaid position, power purchase
agreement is an agreement of such nature, which would have
a public interest element, which is controlled and guided by
relevant statutory provisions and dispute pertaining to the
interpretation or otherwise of such a contract, would be
amenable to the writ jurisdiction of the High Court. Reference
can be made to Reliance Power Ltd. Vs. State of UP, 2019
SCC Online All 4845.
[60]. In view of ratio laid down in M/s Hindustan Sugar
Mills Vs. State of Rajasthan and others, 1981 AIR (SC)
1681, Sanjeev Kumar Dwivedi Vs. State of Bihar and
others, 2006(7) RCR (Civil) 765 and ABL International Ltd.
and another Vs. Export Credit Guarantee Corporation of
India Ltd. and others, 2004 (3) SCC 553, the instrumentality
33 of 46
of State has to act for the public good. Any action contrary to
the public good and interest unfairly and unreasonably, would
violate constitutional guarantee under Article 14 of the
Constitution of India. Services rendered by the petitioners are
not gratuitous in nature, rather the work done by the
petitioners is for public good. In such cases, even claim
arising out of contractual obligations would be amenable to
the writ jurisdiction of the High Court. The existence of
purported alternative remedy under the statue does not oust
the jurisdiction of the High Court under Article 226 of the
Constitution of India in view of ratio laid down in Balkrishna
Ram Vs. Union of India, 2020(2) SCC 442.
[61]. The impugned actions on behalf of PSPCL and
SLDC are blatant defiance of the order passed by the Ministry
of Power on 06.04.2020, directing all the distributing
companies to ensure that the obligation to pay for the capacity
charges as per power purchase agreement shall continue.
Despite the expressed direction given by the Ministry of
Power, the respondents have not acted in accordance with
law due to mala fides and arbitrariness and the impugned
actions are violative of Articles 14, 19 and 21 of the
Constitution of India.
[62]. The present writ petitions deal with the questions of
enforcement under the Disaster Management Act, 2005 and
34 of 46
such reliefs are not capable of being adjudicated by the
Punjab State Electricity Regulatory Commission. The facts are
not in dispute. There is no dispute as such with PSPCL. The
dispute is only in respect of inaction on behalf of Punjab State
Load Dispatch Centre, who has not done its legal obligation
under the Act. The aforesaid authority is not even privy to
power purchase agreement, therefore, the redressal of any
such dispute before Punjab State Electricity Regulatory
Commission cannot be effectively done. PSPCL and SDLC
are independent statutory bodies under the Electricity Act and
are supposed to function independently as per defined
parameters laid down in Electricity Act as well as in Punjab
State Electricity Regulatory Commission (Punjab State Grid
Code) Regulations, 2013. PSPCL and SLDC have
discriminated the petitioners while not treating them alike with
other companies like NTPC etc., who are similarly situated
and have been granted necessary reliefs. Even in those cases
also, force majeure under the power purchase agreement was
invoked.
[63]. Under the Electricity Act, Punjab State Load
Dispatch Centre is legally bound to record the declared
capacity/capacity charges of the petitioners. The relief
involves in the present writ petition is against the Punjab State
Load Dispatch Centre to record the petitioners declared
35 of 46
capacity for the relevant period, during which force majeure
was declared/invoked.
[64]. In view of aforesaid, the writ petitions is
maintainable. The objection with regard to earlier litigation in
respect of penalty imposed upon Talwandi Sabo Power
Limited and redressal thereof in the Appropriate Forum i.e.
Punjab State Electricity Regulatory Commission has to be
simply noted for the sake of information only. In that case,
there was no force majeure event. The litigation was in
respect of deduction of amount by the Corporation towards
penalty in the bill of the year 2017. CWP No.10553 of 2017
titled Talwandi Sabo Power Limited Vs. State Grid Code
Review Committee and others was decided as per consensus
and the matter was relegated to the Punjab State Electricity
Regulatory Commission.
[65]. In the instant case, there is no such consensus
arrived at between the parties for relegation before Punjab
State Electricity Regulatory Commission under Section 86 of
the Electricity Act, 2003 read with Article 17 of the Power
Purchase Agreement. The present dispute is purely rested
upon statutory role of Punjab State Load Dispatch Centre,
therefore, the petitioners can maintain the present writ
petitions.
36 of 46
[66]. So far as the objection with regard to alternative
remedy under Section 8 of the Arbitration and Conciliation
Act, 1996 is concerned, the same is unsustainable as it is a
settled law that presence of an arbitration clause in an
agreement, cannot oust the jurisdiction of the Writ Court in
view of ratio laid down in Harbans Lal Sahni Vs. Indian Oil
Corporation, (2003) 2 SCC 107 and Ramjee Power
Construction Vs. Union of India, 2006(86) DRJ 304.
[67]. Admittedly, there is no arbitration clause between
the petitioners and Punjab State Load Dispatch Centre. Even
the Hon'ble Apex Court in ABL International Limited and
another case (supra) has held that a writ petition involving a
consequential claim of monetary relief is also maintainable.
[68]. The impugned actions on behalf of Punjab State
Load Dispatch Centre are contrary to the decision dated
06.04.2020 passed by the Ministry of Power, wherein it has
been expressly stated that notwithstanding the lockdown, the
obligation to pay for capacity charges as per power purchase
agreement shall continue. Despite the aforesaid decision,
PSPCL has not withdrawn impugned notices and SLDC has
not acted in terms of defined duties arising out of Electricity
Act, 2003 and Punjab State Electricity Regulatory
Commission (Punjab State Grid Code) Regulations, 2013.
37 of 46
The orders passed by the Ministry of Power have the force of
law and are binding in nature.
[69]. As per Article 7 of the Power Purchase Agreement,
parties to the agreement shall comply with the provisions of
applicable law, which includes the orders passed by the
Ministry of Power in the given context. Inaction on behalf of
Punjab State Load Dispatch Centre is in blatant disregard to
the order dated 06.04.2020 passed by the Ministry of Power
and the aforesaid order has stated in the notice dated
14.04.2020 that the said order relates to stoppage of payment
by DISCOMs against scheduled power. However, the order of
Ministry of Power dated 06.04.2020 categorically stated that
the obligation to pay capacity charges as per power purchase
agreement shall continue. Similar contentions were made by
other State DISCOMs which have been rejected in the
following cases:-
(i) Jhabua Power Ltd. Vs. MP Power Management Co.
Ltd, order dated 18.11.2021 in Petition No.10 of 2021
[MPERC]-No further appeal was filed to APTEL.
(ii) GGMR Warora Energy Ltd. Vs. DNH Power
Distribution Co. Ltd., order dated 20.01.2022 in
Petition No.594/MP/2020 [CERC].
38 of 46
[70]. The impugned actions on behalf of PSPCL and
PSLDC are contrary to the guidelines issued by the Ministry of
Home Affairs under the Disaster Management Act, 2005.
Section 72 of the Disaster Management Act overrides any
other law for the time being in force. On the one hand, the
petitioners were directed to remain available to generate
power under Disaster Management Act, 2005 (and expose
itself to criminal prosecution for violation), whereas on the
other hand, PSPCL has invoked force majeure and denying
the lawful claims of the petitioners while complying with the
provisions of Disaster Management Act, 2005 and guidelines
issued by the competent authority. The impugned actions
have no rational basis or intelligible differentia for such
discrimination, in which the petitioners have been chosen,
whereas others have been granted similar reliefs despite
invoking force majeure by PSPCL. Punjab State Power
Corporation Limited has not been accepting the declared
capacity of the petitioners and in case of Nabha Power
Limited, the same cannot be declared to be zero. Even
insufficiency of finances or funds or the agreement becoming
onerous to perform is covered under force majeure exclusions
in terms of Article 12.4 of the Power Purchase Agreement.
PSLDC has not accepted the declared capacity of the
petitioners and the National Regional Load Dispatch Centre
has accepted the declared capacity of the similarly placed
39 of 46
powers generating companies even though force majeure
notices were issued to such companies as well.
[71]. It can be noticed that impugned notices are
contrary to the terms of the Power Purchase Agreement
inasmuch as that PSPCL has invoked force majeure on the
ground of "impact on cash flows" and "financial constraints". If
the aforesaid assertion is tested at the threshold of Article
12.4 of the Power Purchase Agreement, where any
"insufficiency of finances or funds or the agreement
becoming onerous to perform" is expressly excluded as a
force majeure event. The reduction in load/demand in the
State of Punjab due to imposition of lockdown, does not fall
under the ambit of force majeure as the same does not affect
performance of PSPCL for fulfilling the obligations arising out
of Power Purchase Agreement. The same grounds were
highlighted by other State DISCOMs, which have been
rejected in Jhabua Power Ltd. case (supra) and GMR
Warora Energy Ltd case (supra). In the event of agreement
becoming onerous to perform, it does not qualify as an event
of force majeure and there has to be a legal or physical
impossibility in procuring power from the petitioners in view of
ratio laid down in Energy Watchdog Vs. CERC, (2017) 14
SCC 80. Capacity charges are unfettered even in the event of
invocation of force majeure.
40 of 46
[72]. In DNH Power Vs. NTPC, 2018 SCC Online
CERC 100, it was held that if the notice of invocation of force
majeure is bad in law or not in consonance with Power
Purchase Agreement, then the capacity charges must be
payable. Capacity charges are different under the Grid Code
itself. Capacity charges are dependent upon many factors,
which will contribute in order to establish capacity. The actual
consumption thereof is something different for which the
energy has to be assessed towards monetary consideration.
[73]. In case of Talwandi Sabo Power Limited, issuance
of multiple notices by PSPCL alleging force majeure is nothing
but an attempt to improve its argument with regard to the
alleged force majeure event. PSPCL vide its notice dated
14.04.2020, raised new grounds in an attempt to justify the
invocation of the force majeure event, which were absent in
the previous notice dated 29.03.2020. Such an attempt cannot
be permitted as the same is an attempt diluting its earlier
stance in view of ratio laid down in Mohinder Singh Gill and
another Vs. The Chief Election Commissioner, New Delhi
and others, (1978) 1 SCC 305 and State of Punjab Vs.
Bandeep Singh, (2016) 1 SCC 724.
[74]. Evidently, as per Ministry of Home Affairs notice
dated 24.03.2020, power generation, transmission and
distribution units and services were exempted from the
41 of 46
lockdown. PSPCL issued the impugned notice dated
29.03.2020 in utter disregard to the aforesaid order dated
24.03.2020. The alleged drastic reduction in load/demand
would not constitute a force majeure event under the Power
Purchase Agreement. PSPCL in other cases even after
issuance of force majeure notices, has paid the capacity
charges to the similarly situated generating companies by
acknowledging the fact that the alleged drastic reduction in
load/demand, does not constitute a force majeure event and
that only lend credence to the fact that PSPCL and PSLDC
have acted in wholly illegal and arbitrary manner.
[75]. Capacity charges cannot be denied to the
petitioners. The obligation to pay capacity charges is
sacrosanct and the same cannot be repudiated even in the
case of invocation of force majeure event by PSPCL. Capacity
charges include various expenditures such as cost towards
financial obligations of the project, salary of direct and indirect
employees, consumables (excluding coal), operation and
maintenance etc.
[76]. Perusal of Articles 4.3 and 4.4 of the Power
Purchase Agreement would show that even in case of non-
scheduling of power declared available by the petitioners,
PSPCL is liable to pay capacity charges. Article 4.3.1 of the
Power Purchase Agreement would show that the Procurer
42 of 46
would pay the tariff for all of the available capacity upto the
contracted capacity and scheduled energy of the power
station according to its then existing contract capacity,
throughout the term of this agreement. In terms of Article 4.3.2
of the Power Purchase Agreement, the Seller shall sell all the
available capacity upto the contracted capacity of the power
station to the Procurer pursuant to dispatch instructions,
unless otherwise, instructed by the Procurer. Under Article
4.4.3 of the Power Purchase Agreement, if the Procurer does
not avail of power upto the available capacity provided by the
Seller and the provisions of Article 4.4.2 of the Power
Purchase Agreement have been complied with (permission to
the Seller to sell power being part of available capacity of the
power station to third party), the Seller shall be entitled to sell
such available capacity not procured, to any person without
losing the right to receive the capacity charges from the
Procurer for such un-availed available capacity.
[77]. In the light of aforesaid contractual position, the
petitioners have absolute right to claim capacity charges in
terms of Articles 4.3 and 4.4 of the Power Purchase
Agreements. Force Majeure in terms of Article 12 of the
Power Purchase Agreements, does not envisage such
provision for non-payment of capacity charges. The parties
43 of 46
cannot resile from their payment obligations on account of
force majeure.
[78]. The action of PSLDC is found to be contrary to
State Grid Code. Under Regulations 11.3.10, 11.3.12 and
11.3.13 of the Punjab Grid Code and Article 8.3 of the Power
Purchase Agreements, the petitioners are duty bound to
correctly declare their availability/declared capacity every day
corresponding to their capabilities to generate electricity.
PSLDC in turn, is duty bound to consider the declared
capacity and prepare the SEA accordingly. PSLDC cannot
deviate from its statutory obligations in this regard.
[79]. Section 32 of the Electricity Act, 2003 has obligated
Punjab State Load Dispatch Centre to discharge its statutory
functions being responsible for optimum scheduling and
dispatch of electricity within a State, in accordance with the
contracts entered into with the licensees or the generating
companies operating in that State. Punjab State Load
Dispatch Centre is an independent body and is not supposed
to act on the instructions of PSPCL.
[80]. Regulation 14.1.6 of the Punjab State Electricity
Regulatory Commission (Punjab State Grid Code)
Regulations, 2013 specifies that Monthly State Energy
Accounts for Punjab shall be prepared by SLDC by 7th of
every month and shall be conveyed to all concerned for
44 of 46
raising bills. Such energy accounts shall be subject to
inspection/verification/checking and raising any objection
within 15 days of date of issue. If no objection is raised,
energy accounts shall be finalized. In case, any objection is
raised, same shall be deliberated in Commercial and Metering
Committee and finalized as per their decision. Supplementary
bills/credit note shall be raised accordingly. In the aforesaid
Regulation, Commercial and Metering Committee (CMC) is
the designated authority to deliberate upon the issue and
decide the same in case, objection is raised within the
prescribed time.
[81]. For the reasons recorded hereinabove, I am of the
considered opinion that Punjab State Load Dispatch Centre
has not performed its legal obligation as per mandate of the
Electricity Act, 2003, Power Purchase Agreements and
Punjab State Electricity Regulatory Commission (Punjab State
Grid Code) Regulations, 2013. The inaction on behalf of
Punjab State Load Dispatch Centre is liable to be
deprecated. The impugned actions/notices are hereby
quashed. However, Punjab State Load Dispatch Centre shall
proceed to act in accordance with defined duties/obligations
under the Electricity Act, 2003, Power Purchase Agreements
and Punjab State Electricity Regulatory Commission (Punjab
State Grid Code) Regulations, 2013 in the context of
45 of 46
scheduling the energy. In case of any objection in terms of
Regulation 14.1.6 of the Punjab State Electricity Regulatory
Commission (Punjab State Grid Code) Regulations, 2013,
consequent action would follow.
[82]. With these observations, both the writ petitions are
allowed. The issue is relegated to Punjab State Load Dispatch
Centre for doing the needful in accordance with law.
(RAJ MOHAN SINGH)
JUDGE
04.07.2022
Prince
Whether reasoned/speaking Yes/No
Whether reportable Yes/No
46 of 46
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!