Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kamladitya Construction Pvt Ltd vs The State Of Bihar
2023 Latest Caselaw 2137 Patna

Citation : 2023 Latest Caselaw 2137 Patna
Judgement Date : 5 May, 2023

Patna High Court
Kamladitya Construction Pvt Ltd vs The State Of Bihar on 5 May, 2023
          IN THE HIGH COURT OF JUDICATURE AT PATNA
                     Civil Writ Jurisdiction Case No.6949 of 2019
     ======================================================

Kamladitya Construction Pvt Ltd. registered under the Companies Act, 1956, having its office at Plot No. 201, Co-operative Colony, Bokaro Steel City, Bokaro (Jharkhand)- through its authorized signatory, Vinod Kumar Singh, Son of Late Krishna Deo Narayan Singh @ Lalan Singh, Resident of Rampur, Noornagar, P.O. and P.S.- Jalalpur Bazar, District- Chapra (Saran)- at present residing at 201, Co-operative Colony, Bokaro Steel City, Bokaro, Jharkhand- 827001.

... ... Petitioner/s Versus

1. The State of Bihar through the Chief Secretary, Government of Bihar, Patna.

2. Principal Secretary, Water Resources Department, Government of Bihar, Patna.

3. Engineer-in-Chief, Headquarters, Water Resources Department, Government of Bihar, Patna.

4. Chief Engineer, Water Resources Department, Siwan.

5. Superintending Engineer, Planning and Monitoring-II, Water Resources Department, Government of Bihar, Patna.

6. Executive Engineer, Saran Canal Division, Mairwan, Bihar.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s : Mr. Umesh Prasad Singh, Sr. Advocate Mr. Vaibhava Veer Shankar, Advocate For the Respondent/s : Mr. Vinay Kriti Singh, Sr. Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE P. B. BAJANTHRI and HONOURABLE MR. JUSTICE ARUN KUMAR JHA ORAL JUDGMENT (Per: HONOURABLE MR. JUSTICE P. B. BAJANTHRI)

Date : 05-05-2023

On 04.05.2023 following order was passed:-

"Heard the matter for sometime.

02. This is third round litigation arising out of the same contract and different issues. After disposal of CWJC No. 4661 of 2017 on 02.05.2017, the petitioner was granted one year time to execute the balance work. Such a communication has been made on 24.10.2017 (Annexure-P/16). The Patna High Court CWJC No.6949 of 2019 dt.05-05-2023

petitioner had sent a letter that balance work would not be executed within the extended time limit stipulated by the respondents i.e. dated 29.11.2018.

03. Today, learned counsel for the respondents, on instruction, from the Engineer-in-Chief, Water Resources Department, Government of Bihar, Patna, Mr. Ishwar Chandra Thakur, submitted that the petitioner had executed 30 to 35 percent of particular work as on 24.10.2017 and remaining 65 percent of work was required to be executed within one year, would be unreasonable, for the reasons that original contract was for a period of 30 months.

04. Taking note of these dates and events, we propose the petitioner to execute the balance work within a time limit to be stipulated by this Court. In this regard, whether petitioner is willing to execute the balance work without escalating the price or not?

05. The petitioner's counsel is hereby directed to secure instruction from his client by tomorrow i.e. on 05.05.2023.

06. Re-list this matter on 05.05.2023 at 02:15 PM."

2. Today, learned counsel for the petitioner on

instruction submitted that petitioner is prepared to execute the

balance work in terms of agreement dated 26.02.2015 entered

within a period of two years. Reason assigned for two years is

that there would be rainy season and certain difficulties could be

faced by the contractor in executing the work. In this regard, we

had oral discussion with the Engineer-in-Chief, Water Resources

Department, Government of Bihar, Mr. Ishwar Chandra Thakur, Patna High Court CWJC No.6949 of 2019 dt.05-05-2023

who is present in the Court.

3. Accordingly, two years time is granted to

complete and execute the balance work in terms of agreement

dated 26.02.2015. Two years would be calculated from

01.06.2023 to 31.05.2025. In the event of non-completion of

balance work by the petitioner, Respondent is at liberty to take

action against petitioner in accordance with law. The impugned

orders dated 14.03.2019 and 18.03.2019 (Annexure-P/23) are

set aside. With the above observations, the present writ petition

stands disposed of.

(P. B. Bajanthri, J)

( Arun Kumar Jha, J)

rakhi/-

AFR/NAFR                NAFR
CAV DATE                N.A.
Uploading Date          10.05.2023
Transmission Date       N.A.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter