Citation : 2026 Latest Caselaw 2293 Ori
Judgement Date : 12 March, 2026
IN THE HIGH COURT OF ORISSA AT CUTTACK
AFR W.P.(C) No.1293 of 2025
Tripathy Naik & others .... Petitioners
Mr. Avijit Patnaik, Advocate
-Versus-
State of Odisha & others .... Opposite Parties
Mr. S.K. Swain, AGA for O.P. Nos.1 to 6
Mr. T. Mishra, Advocate for O.P. No.7
CORAM:
JUSTICE R.K. PATTANAIK
DATE OF HEARING:27.11.2025
DATE OF JUDGMENT:12.03.2026
1.
Instant writ petition is filed by the petitioners assailing the impugned decision of opposite party No.2 as at Annexure-7 by order dated 8th August, 2024 as illegal, arbitrary and contrary to law and for a direction to the opposite parties to construct the HL bridge at Jharabereni in place of the approved site at Tileiposi on the grounds inter alia that the same is necessary in the interest of justice.
2. The petitioners as the residents of village-Jharabereni under Budhapal G.P. have questioned of arbitrary shifting of the site vis-à-vis the construction of HL bridge over Tikira river which is a project under the Panchayatiraj & Rural Development Department, Government of Odisha primarily on the ground that they are not benefited by the decision of
the Government. Bereft of unnecessary details, the brief facts of the case are that in the year 2020-21, opposite party No.1 proposed construction of HL bridges at different rural area of the State including the site at serial No.1 of the proposal at village-Jharabereni. According to the petitioners, after the proposal of the Government in the year 2020-21 as per Annexure-1, opposite party No.3 visited the spot on 18th March, 2023 for inspection/site verification and also for the soil test located at Tileiposi site, but it was found unfit for the reasons, such as, (a) right angle crossing is not available;
(b) it involves large scale of private lands in the left approach; (c) the left approach has to pass parallel to the river bank for some distance after which sharp bend is required, which is not desirable; (d) in the right approach, a private mango orchard and private land exists and inside village-Tileiposi, the existing road has become too narrow having dwelling houses on both sides; and (e) uncertainty in completion of the bridge at the site.
3. Referring to a copy of the inspection report as at Annexure-2 series, according to the petitioners, the proposed site was found unfit for construction of HL bridge, whereafter, Jharabereni Pradhan Sahi Ghat situate around the same vicinity was identified, pursuant to which, the opposite parties made a visit to the spot for site inspection and prepared an enquiry report dated 29th August, 2023 with a conclusion that the same is fit for construction of the bridge. A copy of the enquiry report is at Annexure-3 referring to which the above claim has been advanced by the
petitioners. It is pleaded on record that the opposite parties allowed to construction work of HL bridge to the contractor at Tileiposi site over Tikira river which was earlier rejected for the reason that it was unfit by an allotment order in his favour vide Annexure-4. The petitioners being aggrieved by the work order issued to the contractor challenged the decision of the opposite parties on the following grounds, namely,(i) the shifting of the site could not have been directed especially when the site inspection report as per Annexure-2 series recommended such construction to be unsuitable which was followed by the representation dated 12th February, 2024 submitted to opposite party No.2;(ii) the opposite parties arbitrarily proposed such shifting of the site claiming that there has been inspection of the site at Tileiposi in presence of the concerned officials and upon recommendation received, the construction of the bridge has been considered suitable, inasmuch as, the decision dated 17th February, 2024 is violative of Article 14 of the Constitution of India; (iii) opposite party No.2 did not follow the direction of the Court in W.P.(C) No.4632 of 2024 and instead of complying the same with a Committee constituted, the alleged construction at Tileiposi has been approved even by not giving opportunity to the petitioners and as such, the entire exercise is biased without any valid reasons and contrary to the earlier inspection/site verification and soil test report as per Annexure-3 series; and (iv) the decision is in violation of the existing Biju Setu Yojana Guidelines, according to which, there should not be
any existing bridge within 4 km upstream and downstream of the proposed bridge measured along with the stream, but the opposite parties ignored the same for the reason best known to them as there are two other bridges situate within 2.2 to 2.8 kms of the recommended bridge site at Tileiposi Ghat; and (v) the impugned decision as per Annexure-7 not by considering the grievance of the petitioners and ignoring Annexure-2 series without valid reasons assigned and providing them opportunity of hearing at the time of verification and having not conducted the inspection/site verification regard being had to the impact assessment project with aspects like connectivity/population, public safety etc. deserves to be quashed.
4. Perused the counter affidavit filed by the State through opposite party Nos.1 to 6. Gone through the counter of opposite party No.7 and the rejoinder of the petitioners.
5. According to the State, such grievance of the petitioners, in view of adverse report received with regard to the proposed work site, a joint inspection was held led by the Director, Rural Development Department and Engineer-in- Chief, Rural Development (Odisha), Bhubaneswar at Tileiposi Ghat and also Jharabereni site on 6th May, 2023 and suggested to take up the survey work either at 500 metre upstream of the approved location at Tileiposi or a suitable location in between the two Ghats and in view such instructions received, opposite party No.5 took up the survey work on 3rd June, 2023 to examine and revise the site
plan/alignment but due to protest of the local villagers, it could not be carried out. It is pleaded that the villagers of the Tileiposi, demanding construction of bridge at the original approved site, submitted representations at different levels and because of such protest of both the villagers, opposite party No.5 requested opposite party No.6 to take up the survey by engaging/deputing Bridge Experts to finalize the alignment of the bridge site and as a result, the team constituted was requested on 19th January, 2024 and to visit the site for the said purpose. The Bridge Expert team inspected the site on 8th February, 2024 and suggested the alignment near Tileiposi Ghat with straight approaches in either side and submitted report to opposite party No.6 on 17th February, 2024. It has been further pleaded that pursuant to direction of the Court in W.P.(C) No.4632 of 2024, opposite party No.2 constituted a District Level Committee under the Chairmanship of Additional District Magistrate, Deogarh and including therein, the CDO & EO, Jilla Parisada, Deogarh; Sub-Collector, Deogarh and others to conduct field visit and as such, it was held on 29th July, 2024 with submission of report suggesting construction of bridge over Tikira river at Tileiposi Ghat and in view of such report, opposite party No.2 took the decision dated 8 th August, 2024 and in the meantime, tender was invited through e-procurement by opposite party No.6 and the work approved is at serial No.19 of the tender call notice. By following due processes, the tender was finalized and M/s. S.K. Agarwalla, Special Class Contractor has been awarded
the work with an agreement stating therein the date of commencement and completion shall be on 27th December, 2023 and 26th June, 2025 respectively. It has been claimed that due to the protest and filing of W.P.(C) No.4632 of 2024, the construction work has been delayed but was commenced on 6th January, 2025. The further claim is that on 9th January, 2024, the final layout for the HL bridge was provided to the agency to take up the confirmatory boring works of the well foundation as per the approved design of the Government and further process has been followed and in the meantime, soil investigation has also been accomplished. By claiming that the above exercise has been undertaken, the State has referred to the correspondences and other documentation including the report of the Committee besides the tender call notice at Annexures-A/5 to H/5. The stand of the opposite parties is that the suitability to construct the HL bridge at Tileiposi has been recommended by the Bridge Experts and also the District Level Committee constituted by opposite party No.2 pursuant to the direction of the Court in W.P.(C) No.4632 of 2024 and accordingly, a decision has been taken vide Annexure-7 as per the original plan whereafter necessary correspondence was made by the Additional District Magistrate, Deogarh with instruction to opposite party No.5 to commence the construction work as per the alignment at Tileiposi Ghat and to report compliance. The other correspondences exchanged thereafter have also been referred to as Annexures-J/5 to N/5. It is finally pleaded that
the Committee recommended the construction of the bridge as per original approved alignment and considering the same, opposite party No.2 took a decision vide Annexure-7, which is perfectly justified and hence, not susceptible to challenge at the behest of the petitioners.
6. Opposite party No.7 supported the impugned decision dated 8th August, 2024 with the pleading in the counter that the District Level Committee was constituted, which was headed by the Additional District Magistrate, Deogarh and it recommended the construction of the HL bridge over Tileiposi Ghat on Tikira river as the most suitable site as has been approved by the Government, which is also cost effective. It is further pleaded that the foundation stone was laid on 9th January, 2025 and construction of the bridge was started on 10th January, 2025 with the land agreement entered into on the same date but the work has been stopped from 25th January, 2025 in view of interim order of this Court and as a result, there has been irreparable loss sustained and prejudice cause to them. It is claimed further that there is no direct or short-cut road or bi-road connecting the HL bridge at village Sarapal over NH 53 and the bridge is located after convergence of two rivers Tikira and Aunli and the people having no all-weather road connectivity to the G.P. HQs at Budhapal which is on other side of the river and that apart, the residents around have no option except to travel through villages-Tebuda, Ramachandrapur, Sundarpal of Angul district and village-Sendha of Deogarh district covering 9-10 kms to reach the G.P. HQs at Budhapal for
education, healthcare, weekly market, business and banking etc. and availing Government schematic benefits and during rainy season, the people are to depend on ferry boats endangering their lives and in so far as the plea that the site is not in accordance with BSY Guideline regarding 4 km norm, the same is not applicable and there is full justification of the proposed bridge at Tileiposi and while claiming so, a sketch map as at Annexure-A/7 is referred to and therefore, the decision of opposite party No.2 is based on the Expert report and Committee's recommendation, hence, not to be disturbed.
7. Perused the rejoinder affidavit of the petitioners wherein it is pleaded that no opportunity has been provided to the petitioners to participate in the entire process and the decision of opposite party No.2 is without following the guidelines issued by the Government especially by not considering the other report of opposite party No.3 pointing out several short-comings as per Annexure-2. That apart, the petitioners pleaded that in the report at Annexure-2, the recommendation has been made for shifting of the alignment towards upstream of Tileiposi Ghat towards Jharabereni in respect of BSY Guidelines but the same has been blatantly flouted. It is also pleaded that the opposite parties have approved a bridge proposal across Tikira river and started all such initiative to construct it but suitability of the location for construction and the recommendation as per Annexure-2 has been completely ignored. The contention is that the opposite parties misinterpreted the inspection report
of opposite party No.3 and even termed it as adverse and not only that the report of the Bridge Expert team has also been misunderstood. Like opposite party No.3, the Expert team suggested a straight approach in the report and vested the responsibility of finalizing the alignment on opposite party No.6 and therein, non-approval of the bridge at Tileiposi Ghat is rather evident and with such other facts pleaded, the petitioners questioned the decision of opposite party No.2 for not considering the suitability of the site and therefore, such decision needs a revisit.
8. Heard Mr. Patnaik, learned counsel for the petitioners, Mr. Swain, learned AGA for the State and Mr. Mishra, learned counsel for opposite party No.7.
9. The bone of contention is for shifting of construction of HL Bridge over the river on the ground that such construction is taking place at the site, which was earlier considered unfit. Mr. Patnaik, learned counsel for the petitioners submits that the inspection/site verification was held previously and for the reasons stated therein, it was proposed that the same is not suitable but in ignorance of such a report and recommendation, the decision has been taken by opposite party No.2 and that too, it was without providing them any opportunity of hearing. The further submission is that opposite party No.2 did not consider the aspects gone into and taken to judicial notice of at the time of inspection of the proposed site with the necessary recommendations made and conclusion that the construction
of the bridge there was not suitable. For other reasons pleaded on record, referring to which, Mr. Patnaik, learned counsel submits that the decision of opposite party No.2 is arbitrary and in the meantime, the construction work has been allotted to the Contractor at the same site, which was earlier considered unfit and unsuitable. It is claimed that in spite of a representation addressed to opposite party No.2 with the grievance of the petitioners as there is objection to the construction of the site in question, it has not been dealt with properly, instead followed by the impugned order at Annexure-7, which is, therefore, not sustainable in the eye of law for being violative of Article 14 of the Constitution of India. In other words, the recommendation as per Annexure-6 and the final decision by opposite party No.2 dated 8th August, 2024 vis-à-vis construction of the HL Bridge at the proposed site with a conclusion that it shall have suitable alignment is not legally tenable, and hence, the impugned order i.e. Annexure-7 is liable to be interfered with for the ends of justice.
10. On the other hand, Mr. Swain, learned AGA for the State would submit that necessary paraphernalia have been observed by opposite party No.2 and even the District Level Committee was constituted and upon receipt of inspection report as per Annexure-6 and recommendations made, taking into account the interest of the public at large proceeded, it has been decided that the construction over the river at the Tileiposi Ghat is best suitable, which has also received the approval of the Government concurring the
observations of the Committee thereby directing execution of the construction work at the Ghat, which is, therefore, perfectly justified and hence, it needs no revision.
11. Mr. Mishra, learned counsel for opposite party No.7 would submit that even though there has been any such report as per Annexure-2 pursuant to the Court's direction in W.P.(C) No.4632 of 2024 dated 29th February, 2024, opposite party No.2 constituted the District Level Committee and upon receiving the recommendations in respect of all the sites reached at a conclusion that the Tileiposi Ghat is a suitable location for construction of HL Bridge and therefore, no illegality has been committed, inasmuch as, all such aspects have been duly taken cognizance of and hence, the impugned order at Annexure-7 is in accordance with the suggestions of the Committee corroborated by the inspection report i.e. Annexure-6, the Court should not intervene with the decision.
12. On a reading of Annexure-6, the Court finds that the proposed site was inspected on 8th February, 2024 by the team of experts along with the Executive Engineer, Deogarh RD Division and other officials. It is revealed in the said report that the Bridge Experts of the Project Management Unit, RD Department, Government of Odisha found the location at Tileiposi Ghat having suitable alignment. The site in question was vividly studied and according to the Expert team, it was considered appropriate, as there is one existing road connecting to the PWD Road on Tileiposi site.
The said recommendation having been received by opposite party No.2 and considering the opinion of the District Level Committee, decision has been taken by opposite party No.2 vide Annexure-7. Insofar as the earlier inspection report as per Annexure-2 series is concerned, it reveals that the same site was inspected between 8th February, 2023 and 10th February, 2023 and even the soil investigation was held and it was recommended that the same is not suitable for the reasons already discussed hereinbefore. On a reading of Annexure-2 series, it is revealed that the recommendation by the Special Secretary to the Government in RD Department is on the premise and for the reasons outlined therein. The concern expressed in the report at Annexure-2 series has been taken judicial notice of with regard to the issues acquiring private lands and proper access for the villagers of Jharabereni in approaching Budhapal via Tileiposi. Considering the report at Annexure-2 series, it cannot be said that there has been any technical objection for the construction of bridge at Tileiposi Ghat. The issues involved and highlighted upon therein have been well taken care of by opposite party No.2 after receiving the recommendation of the team of experts and opinion of the District Level Committee.
13. In fact, all the sites were inspected including the one, for which, administrative approval has been accorded by the Government. The question is, whether, the Court is to accept and prefer one report or the other while considering the correctness of the decision of opposite party No.2?
Admittedly, the expert team inspected the site and furnished the details of such inspection with recommendations. As earlier stated, there has been no real technical objection of any of the inspection teams since the recommendations are primarily in relation to the location and better preferences besides convenience or otherwise caused to the inhabitants of the villages situated around and nearby. The Court is of the considered view that the decision of the local administration regarding construction of the bridge can only be challenged provided the decision-making process is vitiated on account of irrationality or procedural impropriety rather than considering merit-based evaluation of the technical reports.
14. No doubt, any such decision may be subject to scrutiny. The objection to the construction of the bridge is based on Annexure-2 series, whereas, it has been followed by site inspection/verification by a bridge team and upon receiving the recommendations from them and opinion of the District Level Committee, it has been considered suitable. According to the Court, the challenges are generally to be restricted to the issues of legality of the decision, rather, than evaluation of the technical aspects of the alleged construction. Law is well settled that Courts are generally reluctant to interfere with the technical decisions by experts while undertaking an exercise of judicial review. Law is equally settled that the decision-making process may be subjected to scrutiny, if it is biased, unfair or influenced by ulterior motives rather than public interest. That apart, a
Court is to examine whether the decision is so irrational that no Authority could have reached at it despite having expert inputs. In other words, the principles of Wednesbury Unreasonableness are to be applied to find out whether there is any irrationality in the decision-making process. The procedural impropriety on the part of an Authority failing to follow the mandatory statutory procedures or principles of natural justice can also be the basis questioning the legality of a decision. But according to Court, when opinions and suggestions of the experts are obtained, there is a need of judicial restraint. In other words, the Courts are to restrain especially in technical matters and rarely to substitute any such decision of the Authority with their own even when a contrary expert report exists. As a necessary corollary, if an administrative decision is based on an expert report found to be reasonable, it should not be easily overturned referring to a contrary view and suggestion, as at times, reports contradict each other but it is often realized that the suggestions are though different but carry equally plausible conclusion. Unless a contrary report indicates a severe risk, such as, structural danger, improper planning etc. with such other deficiencies glaringly visible, a decision of the local administration is not to be ignored or tampered with. Any such report revealing technical shortages, which could ultimately result in risk and danger and ignored by the administration, it would definitely be a subject of challenge to prove that the decision of the Authority to be flawed. To reiterate, the Court is of the ultimate view that judicial
review of a decision-making process shall have to be based on the factors discussed hereinabove instead of dealing with the merits of the decision itself. If the decision is so unreasonable that no prudent person or Authority could have ever arrived at, in such a situation, the Court has to intervene even though there have been reports received and suggestions considered. If there is mala fide in the decision or any such decision is ill-motivated, under such circumstances, the Court has a role and responsibility to interfere, but presence of a contrary expert report does not automatically invalidate a decision of the Authority. The Court is only to examine whether the Administration considered all the relevant expert views and made a reasoned decision or whether acted blindly. If the administrative decision is based on a well-considered report, it is to upheld despite contradictory opinion expressed.
15. In the case at hand, the adverse report is as per Annexure-2 series, but it has been given a go by by opposite party No.2 and accepted the site inspection report of the Bridge Experts of Project Management Unit of the concerned Department. It is also revealed from the export report at Annexure-6 that the site inspection was held by the officials and the Executive Engineer, Deogarh RD Division. Such inspection has been held pursuant to the Court's order in W.P.(C) No.4632 of 2024 and not only that, opposite party No.2 constituted a District Level Committee and considered its recommendation. As earlier mentioned, both reports though not really harp upon the technical
deficiencies rather on ideal location and whether one site or the other would cause convenience to the inhabitants of the local villages situated at and around the proposed site by the construction of the bridge as proposed. The Court finds that a fresh inspection was held at the site even with a District Level Committee formed by opposite party No.2 and only upon receiving the recommendations/opinions, the decision as per Annexure-7 has been arrived at. It cannot be said that there is any mala fide on the part of opposite party No.2 to sideline the interest of the petitioners or the villages to which they belong to. All such exercise has been undertaken by opposite party No.2, which can be said to be just and reasonable. The expert opinion has been obtained by opposite party No.2 and considering the apprehension expressed by the petitioners and their concern, opposite party No.2 reached at a conclusion that the construction of HL Bridge at Tileiposi Ghat is more appropriate with issues earlier flagged having been addressed to. In absence of any such serious concern shown by the expert team and as there has been due process followed by opposite party No.2 before reaching at the decision, which received corroboration by the opinion of the District Level Committee, this Court, being alive to the settled position of law and the principles discussed hereinbefore, is of the ultimate view that the site proposed and approved by the Government for the construction of HL Bridge needs no reconsideration. In other words, the Court is of the conclusion that the impugned order at Annexure-7 by
opposite party No.2 cannot be said to be irrational, illegal and perverse so as to interfere with it in exercise of writ jurisdiction. The conclusion is that there has been no wrong or illegality committed by opposite party No.2 in the decision-making process and the conclusion at the end is backed by an expert report and also the recommendation of the District Level Committee and accordingly, it is ordered.
16. In the result, the writ petition stands dismissed.
(R.K. Pattanaik) Judge Alok/Manoj
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!