Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sarat Kumar Samal vs State Of Odisha And Others .... Opposite ...
2026 Latest Caselaw 3238 Ori

Citation : 2026 Latest Caselaw 3238 Ori
Judgement Date : 8 April, 2026

[Cites 5, Cited by 0]

Orissa High Court

Sarat Kumar Samal vs State Of Odisha And Others .... Opposite ... on 8 April, 2026

Author: Murahari Sri Raman
Bench: Murahari Sri Raman
                    IN THE HIGH COURT OF ORISSA AT CUTTACK
                                 WP(C) No.36306 of 2025
                 Sarat Kumar Samal               ....     Petitioner
                                       Mr. Prabodha Chandra Nayak, Advocate
                                            -versus-
                 State of Odisha and others           ....     Opposite Parties
                                                     Ms. Biswabara Dash, ASC
                                   CORAM:
                       THE HON'BLE THE CHIEF JUSTICE
                                     AND
                 THE HON'BLE MR. JUSTICE MURAHARI SRI RAMAN
                                          ORDER
Order No.                                08.04.2026

    01.     1.    The petitioner being emerged successful in connection with

the tender call notice dated 25th March, 2022 invited by the Chief Construction Engineer, Rural Works Circle, Balasore-opposite party no.3, an agreement bearing No.04/P-1 of 2022-23 has been executed on 4th June, 2022 indicating date of commencement of work as 4th June, 2022 with stipulation as to completion on 3rd May, 2023. The petitioner completed the work in all respect on 31st March, 2023, which was intimated to the Superintending Engineer, Rural Works Division, Jaleswar on 3rd May, 2023. By letter dated 4th April, 2023, the Superintending Engineer, Rural Works Division, Jaleswar communicated the fact of completion of work in all respect on 31st March, 2023, which is one month three days before the stipulated date of completion as per agreement to the Chief Construction Engineer, Rural Works Circle, Balasore.

1.1. The Chief Construction Engineer, Rural Works Circle, Balasore issued Letter No.3491, dated 16th August, 2023 addressed to the Chief Engineer (Roads), Rural Works, Odisha, Bhubaneswar stating as follows:

"The work has been completed in all respect earlier before 10% of contract period (i.e. 1 month 3 days against 11 months) and thus eligible for incentive on early completion of project @ of 2% of contract value.

As such it is requested to consider the incentive proposal as per Clause 1.11 DTCN & Amendment 2016 Vol-I of O.P.W.D. This is for favour of kind information and necessary action."

1.2. Despite such information given to the Chief Engineer (Roads), Rural Works, Odisha, Bhubaneswar, the petitioner being not accorded with the legitimate claim in terms of Clause 1.11 of the Detailed Tender Call Notice (DTCN) and Paragraph 3.5.5(V) of Note-III of OPWD Code (Volume-I) as amended by virtue of Office Memorandum File No.07556900032016-5288/W, dated 4th May, 2016 issued by the Government of Odisha in Works Department, the petitioner has come up before this Court by way of filing this writ petition invoking provisions under Articles 226 and 227 of the Constitution of India with the following prayer(s):

"It is, therefore, most humbly prayed that this Hon'ble Court may graciously be pleased to

I. Issue a writ in the nature of Mandamus in directing the Opp. Party No.2-Chief Engineer (Roads), Rural Works, Odisha to forthwith approve the petitioner's incentive dues under Clause 1.11 of the DTCN, strictly in terms of the recommendations of the Chief Construction Engineer, Opp. Party No.3 dated 16.08.2023 (Annexure-

5) and the Superintending Engineer, Opp. Party No.4 dated 04.04.2023 (Annexure-4), and thereafter to ensure release of the incentive amount @ 2% of the contract value for the work Improvement Daxin Teghari High School PWD road to Bindhapadmapur-Talsari road via Ranibasan and Krushnanagar road under MMSY for the year 2021-22 within a time to be stipulated by this Hon'ble Court;

II. Issue direction to the Opposite Parties to pay interest 12% per annum (or at such rate as this Hon'ble Court deems just and proper) on the eligible incentive amount, from 31.03.2023 (the actual date of completion of work) till the date of actual payment;

III. The unexplained and prolonged delay in processing and approving the petitioner's incentive dues shall be declared arbitrary, unreasonable, mala fide in law and violative of Article 14 of the Constitution of India;

IV. Any other writ, order or direction may be issued as this Hon'ble Coat deems fit, just, equitable, proper and necessary in the facts and circumstances of the case.

V. And in this act of kindness, the petitioner shall as in duty bound every pray."

2. As the document forming part of writ petition evince the aforesaid undisputed facts, it is felt necessary to dispose of the writ petition as keeping the matter pending would not subserve any fruitful purpose.

3. Learned Additional Standing Counsel having appeared for opposite parties, waives issue of notice as advance copy of the writ petition had already been served upon her on 9th December, 2025.

4. Perusal of the documents enclosed with the writ petition, it is revealed that Clause 1.11 of the DTCN entitles the petitioner to avail the incentive as follows:

"1.11. For availing Incentive Clause in any project which is completed before the stipulated date of completion subject to other stipulations it is mandatory on the part of the concerned Superintending Engineers/Executive Engineers to report the actual date of completion of the project as soon as possible through fax or e-mail so that the report is received within 7 (seven) days of such completion by the concerned Superintending Engineer, Engineer-in-Chief & the Administrative Department."

4.1. Paragraph 3.5.5(V) of Note-III of OPWD Code (Volume-I) as amended by Office Memorandum dated 4th May, 2016 reads as follows:

"For availing Incentive Clause in any project which is completed before the stipulated date of completion, subject to other stipulations it is mandatory on the part of the concerned Executive Engineer to report the actual date of completion of the project as soon as possible through Fax or e-mail so that the report is received within 7 (seven) days of such completion by the concerned Superintending Engineer, Chief Engineer & the Administrative Department. ***"

4.2. Letters of Superintending Engineer dated 4th April, 2023 (Annexure-4) and the Chief Engineer (Roads), Rural Works Circle, Balasore dated 16th August, 2023 (Anneuxre-5) addressed to the Chief Engineer (Roads) Rural Works, Odisha, Bhubaneswar unequivocally reflects that the work entrusted to the petitioner was completed in all respect before 31st March, 2023, i.e., around one month three days before the stipulated date of completion. Since the work was completed much ahead of date so stipulated, i.e., 3rd May, 2023 as per agreement dated 4th June, 2022, the petitioner is entitled to claim incentive as envisaged in Clause 1.11 of the DTCN and in terms of Paragraph 3.5.5 (V) of Note-III of the OPWD Code (Volume-I).

5. Learned counsel appearing for the petitioner has referred to and cited order dated 18th March, 2021 passed in the case of Jayram Pujahari vs. State of Odisha and others, WP(C) No.30637 of 2020, wherein the following has been observed:

"6. *** Thus, timely intimation of completion of the project by the concerned Executive Engineer is a mandatory requirement under the aforesaid provision in order to avail incentive by the Contractor for early completion of the Project. The report that regard has to be intimated within a period of seven days from the date of completion of the project. Admittedly, the intimation was not sent by the Executive Engineer within the stipulated period of seven days. There is also no allegation that the Petitioner has contributed

to such delay in intimation. In view of the ratio in Prafulla Kumar Pradhan vs. State of Odisha, 2017 (I) ILR-CUT-381, the Petitioner cannot be faulted with for the delay in communication of the completion report by the Executive Engineer. The Petitioner cannot be made to suffer for no fault on his part, particularly when the authorities have accepted the fact that the Project was completed prior to the stipulated date.

7. In that view of the matter, we have no hesitation to set aside the order dated 20th August, 2020 (Annexure-1) passed by the Commissioner-cum- Secretary, Works Department, Government of Odisha, Bhubaneswar (OP No.1) in refusing the claim of the petitioner for grant of incentive."

5.1. It is submitted that the said order was carried before the Hon'ble Supreme Court of India by the State of Odisha in SLP (C) No.12359 of 2021, which came to be disposed of vide order dated 5th April, 2023 with the following observation(s):

"Learned counsel for the petitioner-State made a statement before us in compliance of our order dated 19.08.2021 & 17.09.2021, the Government of Orissa has conducted the enquiry as directed and the report has been placed on the record of the case and a SOP has also been notified on 03.03.2022. Additional affidavit is taken on record. The SOP having been finalised, the same would govern the timely completion of project and the grant of incentive for the same.

However, in so far as the present case is concerned, we see no good ground to interfere with the impugned order passed by the High Court and as such, the special leave petition, in so far as the challenge to the impugned order is concerned, stands

dismissed. Pending application(s), if any, shall stand disposed of."

5.2. Against the denial of incentive under the above Paragraph of the OPWD Code, where the work entrusted to the petitioner in Sairaj Dalai Vs. State of Odisha and others, WP(C) No.15195 of 2025 got completed before the stipulated date as per agreement, vide order dated 8th April, 2026 held as follows:

"5. On a meaningful reading of the language, words and the expressions used in the above quoted Clause, we fail to appreciate the stand taken by the authorities that it is obligatory on the part of a contractor to make an application within the specified time. The said provision does not ordain any application to be made by the contractor but mandated the Executive Engineer to report the actual date of completion of the project as soon as possible through e-mail or facsimile mail within seven days from the date of the completion thereof. The said Clause is misread, misconstrued and wrongly applied as a deterrent on the part of the contractor who appears to have been penalized for the lapses which cannot be attributable to his conduct. The bare reading of said Clause indicates that in order to avail the incentive Clause in any project completed before the actual date of completion, it is mandatory on the part of the concerned Executive Engineer to report the actual date of completion of the project through such modes within seven days therefrom.

6. It is improbable and inconceivable that a person or the authority would reap the benefit of his own wrong and deny the just and equitable claim on such score. We fail to find any words or the expressions from the said Clause as quoted above that makes it imperative on the part of

the contractor to approach the authority by making an application but it conveys a clear and laudable message that it is obligatory on the part of the authority concerned to report through such modes within the time stipulated therein. If the authority has committed a mistake or his conduct indicates some lapses and negligence on his part in not reporting the date of completion of the entire project, the contractor who should be incentivized by virtue of said Clause-34 should not be penalized.

7. Simply on the equitable principle that a person cannot reap the benefit from his own wrong, the authority on account of his lapses cannot deny the legitimate claim shifting the lapses to the shoulder of the contractor. The contractor who completed the work before handed cannot be denied such beneficial piece of the Clause which gives incentives to him who has diligently executed the work to the satisfaction of the authority.

8. We, thus, do not find that the authority can take advantage of his own lapses and/or wrong committed by him as a weapon to deny the just and equitable claim accrued to the petitioner in terms of such Clause-34 and, therefore, the order of rejection dated 8th November, 2024 is hereby quashed and set aside."

6. The letters dated 4th May, 2023 and 16th August, 2023 vide Annexure-4 and 5 respectively as referred to above clinch that the work entrusted to the petitioner has been completed one month and three days ahead of stipulated date of completion, i.e., 3rd May, 2023 as per agreement dated 4th June, 2022 (Annexure-1). The learned Additional Standing Counsel having not impeached such letters of the Superintending Engineer and the Chief Construction Engineer having admitted commencement of works on 4th

June, 2022 and completion thereof on 31st March, 2023, the legitimate claim of the petitioner cannot, thus, be denied or delayed in view of the clarified position as set forth in the aforesaid decisions.

6.1. It is, therefore, felt expedient to direct the Chief Engineer (Roads), Rural Works, Odisha, Bhubaneswar to take a decision on the recommendation made to him by the Chief Construction Engineer, Rural Works Circle, Balasore vide Letter No.3491, dated 16th August, 2023 within a period of two weeks from receipt of copy of this order in the light of discussions made supra and communicate the result thereof to the petitioner forthwith.

7. With the aforesaid observation and direction, the writ petition stands disposed of; and pending Interlocutory Application (s), if any, shall also be disposed of.

(Harish Tandon) Chief Justice

(M.S. Raman) Judge MRS/Laxmikant

Signed by: LAXMIKANT MOHAPATRA Designation: SENIOR STENOGRAPHER Reason: Authentication Location: High Court of Orissa, Cuttack Date: 09-Apr-2026 13:29:44

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter