Citation : 2023 Latest Caselaw 5586 Ori
Judgement Date : Rasmi Ranjan Mohapatra vs
ORISSA HIGH COURT : C U T T A C K
W.P.(C) NO.13359 OF 2023
An Application under Articles 226 & 227 of the Constitution of India.
Rasmi Ranjan Mohapatra : Petitioner
-Versus-
State of Odisha & ors. : O.Ps.
For Petitioner : Mr.J.K.Mohapatra, Adv.
For O.Ps. : U.K.Sahoo, ASC
JUDGMENT
CORAM :
JUSTICE BISWANATH RATH JUSTICE M.S.SAHOO
Date of Hearing & Date of Judgment : 10.05.2023
Per Biswanath Rath, J. The Writ Petition involves the following prayer:-
<In the aforesaid circumstances, it is humbly prayed that this Hon9ble Court be pleased to admit the writ petition, issue notice to the Opposite Parties calling for show cause as to why this writ application shall not be allowed and if the Opposite Parties fail to file any show cause or file insufficient cause the writ petition be allowed, the order dt.26.08.2022 passed by the Principal Secretary to Govt. Department of Works under Annexure-4 be quashed and necessary direction be passed to release the differential amount payable to the petitioner due to
// 2 //
enhancement of minimum wages of labour during execution of work within a stipulated period.=
2. Background involving the case appears to be in the attempt to
challenge the order passed by the Principal Secretary to Government,
Works Department, O.P.1, on 26.8.2022, the Petitioner-Contractor
claims, pursuant to the tender for the work <Site Development for
Construction of proposed Kendriya Vidyalaya No.6 at Pokhariput,
Bhubaneswar=, the Application submitted by the Petitioner was accepted
being the lowest tenderer for the contract value of Rs.1,04,22,714/-. In
the process, the Petitioner was communicated with the acceptance of
tender by the Superintending Engineer, Bhubaneswar (R & B) Division-
III, O.P.4, vide letter dated 27.3.2012. As a development, an agreement
was executed between the Petitioner and the Executive Engineer, vide
assigning agreement no.-2 P1/2012-13. The Petitioner has averment
through Paragraph-3 of the Writ Petition that the work under contract
was to be commenced from 10.4.2012 and to be completed by 9.8.2012.
However, the work was actually completed on 2.8.2014. The Petitioner
also claims, the delay in finishing the work occurred for some reason at
the instance of the Department. There is however pleading that there has
been extension of contract till 2.8.2014. It is in the premises that in
execution of the work, there has been enhancement in the minimum
// 3 //
wages by way of revised minimum wages Notification by the Competent
Authority, taking que from the decision in Mahesh Prasad Mishra vrs.
State of Odisha & ors. Reported in 2012(Supp.-I) OLR 1035, the
Petitioner submitted representation approaching the Competent
Authority for release of additional labour wages. For no attending to the
request of the Petitioner, it appears, the Petitioner filed a Writ Petition
bearing W.P.(C) No.7926/2021, which Writ Petition came to be disposed
of by a Division Bench of this court on 7.2.2022 directing the
Engineering-cum-Secretary to Government, Works Department to take a
decision on the representation of the Petitioner within a period of two
months from the date of receipt of copy of the order, vide Annexure-2. It
is claimed, upon receipt of the order of this Court, a Technical
Committee was constituted on 21.4.2022 taking five numbers of
Technical Experts. It is claimed, the Technical Committee prepared a
report on 13.6.2022 observing the Petitioner to be entitled to get the
differential amount arising out of enhancement of minimum wages as
appearing at Annexure-3. It is taking some observations of the
Committee, the Petitioner claims, there has been illegal rejection of the
claim of the Petitioner on his entitlement of enhanced minimum wages
// 4 //
by the Principal Secretary to Government by its order dated 26.8.2022
resulting filing of the Writ Petition.
3. Mr.J.K.Mohapatra, learned counsel for the Petitioner in the
above factual background claims, there has been clear observation in the
Committee report entitling the Petitioner to differential minimum wages
and there has been mechanical consideration of such observation by the
Principal Secretary to Government. Mr. Mohapatra, learned counsel for
the Petitioner thus prays this Court for interfering with the impugned
order, vide Annexure-4 thereby setting aside the same and granting
appropriate relief in terms of the Committee observation.
4. Mr.U.K.Sahoo, learned Additional Standing Counsel
appearing for the O.Ps., however, taking this Court to the plea of the
Petitioner at Paragraph-3 of the Writ Petition contended, the period of
work in the contract remaining from 10.4.2012 to 9.8.2012 and the
revision Notification applying with effect from 6.10.2012 with stipulated
date of completion stated to be 9.8.2012, the notification pressed herein
has no application to the case at hands. Mr. Sahoo, learned Additional
Standing Counsel also contends, for undisputedly, the actual date of
completion on 2.8.2014, there is no application of this revised minimum
wages Notification to the case of the Petitioner. Further also taking this
// 5 //
Court to the final observation of the Committee, vide Annexure-3, Mr
Sahoo attempted to take support of the said observation and objected the
entitlement of the Petitioner thereby submitting that there has been right
consideration by the Competent Authority in the rejection of the claim of
the Petitioner as appearing at Annexure-4 requiring no interference in the
impugned order.
5. Considering the rival contentions of the Parties, this Court
finds, undisputedly, the work period remains to be within 10.4.2012 till
9.8.2012. However, there has been extension taking the actual date of
completion of the work to be 2.8.2014. For P-1 agreement filed by the
Petitioner appearing at Page-10 of the Brief, Clause-33(a) of the
agreement reads as follows :-
<Clause-33(a)- The contractor shall not employ for the purpose of this contract any person who is below the age of twelve (12) years and shall pay to each labourer for work done by such labourers fair wages. PWD No.-22059 Dtd.-16.08.77.=
In Clause-33(a), fair wage means, wages, whether for time or piece work
prescribed by the State Public Works provided that where higher rate has
been prescribed under the Minimum Wages Act, 1948. Wages at such
higher rate should be considered. This Court here taking into
consideration the introduction of revised minimum wages circular even
taking into account the actual date of completion of work to be 2.8.2014,
// 6 //
from the pleadings herein, nowhere finds, there has been actual payment
of higher wages dependent on the introduction of minimum wages
circular. To add to this, this Court finds, the Writ Petition is in a second
round litigation. In the first round of litigation, the Petitioner moved this
Court in W.P.(C) No.7926/2021 on the selfsame issue, but in the said
writ petition even there was no pleading on payment of higher wages, if
any. This Writ Petition appears to have been disposed of by this Court
with the direction as follows :-
4. Considering such submissions, this Court without expressing any opinion on the merits of the case, directs Opposite Party No.1-Engineer-in-Chief-cum-Secretary, Works Department, Government of Odisha to take a decision on the above noted representation of the Petitioner in accordance with law within a period of two months from the date of receipt of a copy of this order and communicate result of such exercise to the Petitioner.=
6. It appears, pursuant to such direction, Government thought it
appropriate to form a Technical Committee to look into the claim of the
Petitioner. The Committee in its proceeding on the claim of the
Contractor observed as follows :-
<II. Details of Claims of the Contractor :- The Contractor in his letter dated 16.10.2020 in the address of E.I.C.-cum-Secretary to Govt., Works Department with copy to Chief Engineer, Buildings, Odisha had claimed for differential cost of enhanced Minimum Wages enhanced from Rs.90/- to Rs.150/- with effect from 09.10.2012 vide Notification No.-1942
// 7 //
dated 09.10.2012 in the line of the Order of Hon9ble High Court in W.P.(C) No.11158 of 1996 between Sri Suryamani Nayak vrs. Odisha State Housing Board and Others.=
7. On the disclosures in the representation through Paragraph-D
at Page-21 of the Brief, the Committee observed as follows :-
<D. Details of Compliance on the Representation :-
The S.E. Bhubaneswar (R & B) Division-III, Bhubaneswar has submitted a information sheet to Works Deptt. Vide Lt. no.1561 Dt.11.03.2022. In replythe S.E. has mentioned that Sri Rashmi Ranjan Mohapatra <A= Class contractor was given an affidavit for not claiming any escalation and compensation during the extended period.=
Through Paragraph-D, it becomes clear that the Contractor had given an
undertaking by way of affidavit for not claiming any escalation and
compensation during the extended period.
8. This apart, on examination of the case of the Petitioner
dependent on the observation and direction of this Court in Paragraph-F,
it is observed as follows:-
<F.Examination of Order of Hon9ble High Court By the Technical Committee:
The Technical Committee examined the Order of Hon9ble High Court in their Order No-2 dated 07.02.2022 with reference to the judgments given by the Hon9ble Court on similar case like order dated 17.11.2011 In the Writ Petition bearing W.P.(C) No.- 29271 of 2011 between Sri Mahesh Prasad Mishra Vrs.
State of Odisha and order dated 25.03.2019 of Hon9ble High Court, Odisha in W.P.(C) No-20724 of 2018
// 8 //
between M/S Bhagabati Build & Construction Pvt. Ltd. vrs. State of Odisha as well as the views of Learned Advocate General, Odisha in his letter No-27646 dated 09.12.2020 on order dated 25.03.2019. In the Writ Petition bearing W.P.(C) No-29271 of 2011 between Sri Mahesh Prasad Mishra Vrs. State of Odisha and other the Hon9ble High Court, Odisha in their order dated 17.11.2011 opined that <the expression 8Escalation9 used in the agreement ordinarily means, an agreement allowing for adjustment up and down according to change in circumstances as in cost of material in a Works Contract or in cost of living in a wage agreement. The expression 8escalation9 would not bring within its sweep higher rate of wages which a contractor is otherwise liable to pay in view of the notification issued by the State Government under the provision of Minimum Wage Act, 1948, failing which he may have to face criminal prosecution. No equitable reason is also there to give extended meaning to the expression and bring such enhanced rate of wages within the area of compensation since payment itself made to the workers at higher rate is pursuance to a statutory notification issued under the provision of the Minimum Wages Act, 1948 and the claim of the contractor on that score is not for his own enrichment.= Hon9ble High Court, Odisha had also referred to the decision of Hon9ble Supreme Court, India in Tarapore and Co Vrs. State of Madhya Pradesh wherein the Apex Court had clearly held that the payment of wages as per the rate fixed under Minimum Wage Act is a statutory obligation and although the term of the contract is silent about payment of minimum wages, the contractor is statutorily bound to pay the minimum wages to the workers. The Hon9ble Court had also referred the judgment passed by the Division Benches of High Court, Odisha in similar cases between Suryamani Nayak Vrs. State of Odisha, Surendranath Kanungo Vrs. State of Odisha and M/S Nilagiri Corporation Society Vrs. State of Odisha. In view of aforesaid statement of Law which has been declared by the Hon9ble Supreme Court followed by the
// 9 //
Division Benches of High Court Odisha, the Hon9ble High Court Odisha directed the Govt. Of Odisha to reimburse the enhance minimum wages to the petitioner Mahesh Prasad Mishra which has been implemented.=
Coming to the finding of the Committee at Paragraph-G
claims to be observed as follows:-
<G. Finding of the Technical Committee:-
The Technical Committee after due deliberation of the various judgments on similar cases as referred by Hon9ble High Court, Orissa, views of Learned Advocate General of Odisha in similar case and the representation of the Petitioner Contractor in his letter dated 16.10.2020 is of the opinion that present case i.e. W.P.(C) No-7926 of 2021 between Sri Rasmi Ranjan Mohapatra vrs. State of Odisha is covered within the per view of the order passed by Hon9ble High Court, Odisha in W.P.(C) No-29271 of 2011 between Mahesh Prasad Mishra Vrs. State of Odisha. The Committee unanimously recommends that as per the above mentioned order of Hon9ble High Court, Odisha dated 07.02.2022 in W.P.(C) No-7926 of 2021, Sri Rasmi Ranjan Mohapatra is eligible to get the differential amount arises out of enhancement of minimum wages as notified by the Govt. of Odisha in Labour & ESI Department in their Notification No-8536 dated 06.10.2012 on the value of work scheduled to be executed after date of enhancement of minimum wages as per the approved work programme or as per actual execution whichever is less and as per actual involvement of labour component for such works as per analysis.=
For the findings of the Committee, the Committee unanimously
recommended that the Petitioner would be eligible to get the differential
amount arises out of enhancement of minimum wages as notified by the
Government of Odisha in Labour & ESI Department in their Notification
// 10 //
No.8536 dated 6.10.2012 on the value of work scheduled to be executed
after the date of enhancement of minimum wages as per the approved
programme or as per the actual execution whichever is less and as per
actual involvement of labour component for such works as per analysis.
9. Keeping in view the report of the Committee, the Principal
Secretary to Government following the direction of this Court required
to take decision, vide Annexure-4 came to observe as follows :-
<AND WHEREAS, the claim of labour escalation of the petitioner contractor in the instant case is for the period from 09.10.2012 (date of Notification in Gazette) to 02.08.2014 (date of actual completion of the work). At the same time, it is observed that the said period from 09.10.2012 to 02.08.2014 is covered under extended time period beyond the original intended completion period and during the said extended period, the delay being attributable to the contractor, penalty has been imposed for delayed completion of work in the Office of the Superintending Engineer, Bhubaneswar (R&B) Division No.III. It is also observed that Clause 31(b) of the contract agreement clearly postulates that for reimbursement of increased wage rate, one of the pre- condition is that work has to be carried out within stipulated time or extension thereof is not attributable to the contractor. In the instant case, the delay in completion of the work is clearly attributable to the contractor and for which penalty has been imposed.=
10. Reading through the above, this Court finds, there has been
taking into account the provision contained in Clause-33(b) of the
contract agreement and thereby there is denial of the claim of the
// 11 //
Petitioner. This Court finds, there is no infirmity in such bill of the
Competent Authority.
11. To add to the above, reading the Gazette Notification
involved herein on the enhancement of minimum labour wages, this
Court finds, the revised minimum wages have no automatic application
to all cases. In bringing in such claim a contractor has to first satisfy that
there is such provision in the agreement and secondly there must be
proof in release of enhanced wage. This contingency must prevail to
avoid unjust enrichment to the contractors as benefit in fact does not go
to the real beneficiaries.
12. It is on the restriction through Clause-31(b) of the contract
agreement and no establishing of payment of escalated wages to the
labourers, this Court finds, Contractors are busy in taking advantage of
the decision in Mahesh Prasad Mishra (supra) and attempting to earn this
amount for themselves, which is not permissible in the eye of law.
13. It is at this stage, Mr. Mohapatra, learned counsel for the
Petitioner seeks leave of this Court to rebuild the contractor9s case to fit
into revised minimum wage circular.
This Court first of all finds, there is no foundation to such
claim, secondly lot of exercises have been done at different ends by
// 12 //
different competent authorities and thirdly the issue raised here is almost
ten years back leaving no scope to entertain such request in 2023. In the
ultimate outcome, this Court finds, there is no defect in the impugned
order requiring to interfere in the same. The Writ Petition thus stands
dismissed and in the circumstance, there is no order as to cost.
(M.S.Sahoo) (Biswanath Rath)
Judge Judge
Orissa High Court, Cuttack.
The 10th May, 2023/M.K.Rout, A.R.-cum-Sr.Secy.
Signature Not Verified Digitally Signed Signed by: MANOJ KUMAR ROUT Designation: Astt.Registrar-cum-Sr.Secretary Reason: Authentication Location: High Court of Orissa Date: 15-May-2023 18:06:41
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!