Citation : 2022 Latest Caselaw 5245 Ori
Judgement Date : 29 September, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.4 Of 2021
(Through hybrid mode)
Jindal India Thermal Power Ltd. .... Appellant
Mr. C. Mukhopadhya, Senior Advocate
Mr. S.P.Mishra, Senior Advocate
Mr. Satyajit Mohanty, Advocate
Mr. Prashant Mehta, Advocate
Mr. Asit Kumar Dash, Advocate
Ms. Divita Vyas, Advocate
-versus-
Quartz Infra and Engineering Pvt. .... Respondent
Ltd.
Mr. Vegesna Subba Raju, in person
CORAM: JUSTICE ARINDAM SINHA
ORDER
29.09.2022 Order No.
20. 1. Mr. Mukhopadhya, learned senior advocate appears on behalf
of appellant resumes his argument. He reiterates findings in
paragraphs 242 and 243 in the award regarding his client's unfettered
right to terminate under it, held to have been qualified by right to
reduce the quantity of work, if any contingency arose. He relies on
judgment of the Supreme Court in Indian Oil Corporation Ltd. v.
Shree Ganesh Petroleum, reported in (2022) 4 SCC 463, paragraphs
43 and 44. Paragraph 44 is reproduced below.
// 2 //
"44. An Arbitral Tribunal being a creature of contract, is bound to act in terms of the contract under which it is constituted. An award can be said to be patently illegal where the Arbitral Tribunal has failed to act in terms of the contract or has ignored the specific terms of a contract.
He submits, the Tribunal in ignoring the contract term was in breach
of mandate under sub-section (3) in section 28, Arbitration and
Conciliation Act, 1996.
2. On the Tribunal having rejected his client's application under
section 27, he draws attention to paragraphs 486 and 487 in the award.
He submits, facts are that the measurement book was signed by
respondent. Relying on some scoring out, it disputed the same in the
reference. Facts are also that there was joint measurement between
respondent and the next contractor engaged by his client. His client
wanted to examine said contractor to prove said measurements, to
corroborate the measurement book disputed by respondent. This was
not allowed by the Tribunal.
3. He submits, on wrongful termination and prejudice caused
straightaway his client has demonstrated patent illegality in the award
to extent of approximately Rs.2.7 crores. Clause (iv) under sub-section
(2) in section 34 only allows for severance of award in respect of the
// 3 //
part therein on matters not submitted to arbitration. Here the case is,
the disputes were referred culminating in award of Rs.6 crores and
odd. At this point he submits, entire award is liable to be set aside on
adjudication in appeal that finding on wrongful termination and
prejudice by rejecting section 27-A application, going in favour of his
client. He relies on judgment of the Supreme Court in NHAI v. M.
Hakeem, reported in (2001) 9 SCC 1, paragraphs 2, 16, 41 and 42. He
submits, law declared is, there cannot be modification of the award by
either enhancing or reducing it.
4. There are other smaller claims, on which he would like to point
out apparent illegality as well as rejection of counter claims of his
client.
5. List on 19th October, 2022 marked at 2.00 P.M.
(Arindam Sinha) Judge Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!