Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

ARBP/70/2017
2021 Latest Caselaw 790 Ori

Citation : 2021 Latest Caselaw 790 Ori
Judgement Date : 22 January, 2021

Orissa High Court
ARBP/70/2017 on 22 January, 2021

ARBP No. 70 of 2017

15. 22.01.2021 1. This matter is taken up by video conferencing mode.

2. Heard Mr. N.K. Sahu, learned counsel for the Petitioner and Mr. S. Dwibedi, learned counsel for the Opposite Party.

3. The present petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 ('Act') seeks the appointment of an Arbitrator to adjudicate the disputes between the Petitioner and the Opposite Party arising out of the work order dated 12th November, 2014 under which the Petitioner was assigned the work for "External Painting of 1400 NB pipe after shot Blasting for underground and above ground pipe at Kalinganagar".

4. The case of the Petitioner is that despite issued notice to the Opposite Party for appointment of an arbitrator in terms of the arbitration clause contained in the work orders, the Opposite Party has not agreed.

5. Four objections are raised by learned counsel for the Opposite Party to the relief being granted as prayed for. First he states that for three different work orders one common petition could not be filed and there shall be three petitions. The Court considered this to be a mere technical objection. There is no harm in appointing one arbitrator to adjudicate all the disputes arising out of the three work orders, which

have arbitration clauses, considering that the disputes are between the same parties. The said objection is therefore overruled.

6. The second objection is that there is only one work order in which an arbitration clause exists. In the other two work orders to which learned counsel makes a reference, there are in fact arbitration clauses, which read as under:

"12. DISPUTES:

Any dispute, if so arising regarding contractual issues shall in the first instances are amicably resolved through offices of project controller/project manager. However, any matter all disputes which remain unresolved mutually shall to the satisfaction of the parties may be referred to arbitrator as per arbitration act 1996 and jurisdiction of Civil Courts in Bhubaneswar only."

7. Thridly, learned counsel for the Opposite Party relied on a judgment dated 4th April, 2004 of this Court in ARBP No.57 of 2011 (Ramesh Chandra Samantaray v. Executive Engineer, Rural Works Division) to urge that unless the clause states that the decision of the arbitrator will be final and binding, it cannot be treated as an arbitration clause. The Court finds that the wording of the arbitration clause in the three work orders, leaves no manner of doubt that the intention of the parties is that the decision of the arbitrator shall be binding. This of course will not take away the right

of either party to challenge the Award, if so warranted, in accordance with law.

8. Lastly, learned counsel for the Opposite Party states that the clause envisages that the parties should first try to amicably resolve the dispute through negotiation, whereas that did not happen here.

9. The present petition has been pending since 2017 and the work order was issued even earlier. In spite of there being enough opportunity even for the Opposite Party to resolve the dispute amicably, till date the dispute has remained unsettled. The Court therefore, finds no merit in the last contention of the Opposite Party, either.

10. Although the arbitration clause in one of the work orders envisages the appointment of an arbitral tribunal, the clauses in the other two envisage a sole Arbitrator. Considering that the Opposite Party is in any event not agreeing to act on the said clause, the Court considers it appropriate to direct that the disputes arising out of the three work orders shall be referred to a sole arbitrator. No prejudice can be said to be caused to the Opposite Party on that score.

11. The Court accordingly appoints Mr. Manoj Mishra, learned Senior Advocate of this Court as an Arbitrator to adjudicate the disputes between the parties. The arbitration shall take place under the aegis of the High Court of Orissa Arbitration and Mediation Centre.

12. The arbitration petition is disposed of accordingly. A copy of this order be communicated to the learned Arbitrator.

13. As restrictions are continuing for COVID-19, learned counsel for the parties may utilize the soft copy of this order available in the High Court's website or print out thereof at par with certified copy in the manner prescribed, vide Court's Notice No.4587, dated 25th March, 2020.

( Dr. S. Muralidhar ) Chief Justice

S.K.Jena/PA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter