Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Specimen Holdings Ltd vs Executive Engineer
2021 Latest Caselaw 295 Ori

Citation : 2021 Latest Caselaw 295 Ori
Judgement Date : 8 January, 2021

Orissa High Court
M/S. Specimen Holdings Ltd vs Executive Engineer on 8 January, 2021
                                  W.P.(C ) NO. No.36399 of 2020




                    M/S. Specimen Holdings Ltd.,....................Petitioner
                                        Vs.
                    Executive Engineer, B.E. Division, SOUTHCO,
                    Berhampur & Another............................Opp. Parties

2.   08.1.2021             This matter is taken up through Video Conferencing.
                           By way of this Writ Petition, the petitioner has
                 challenged the order dated 20.7.2018 in Case No.172/2018 of
                 GRF, Berhampur which was confirmed by judgment dated
                 17.12.2019 in Consumer Representation Case No.Omb(II) S-19 of
                 2018.
                           The brief facts of the case is that the petitioner M/s.
                 Specimen Holdings Ltd., Apollo Clinic, Main Road, Bhabanagar,
                 Berhampur, Dist-Ganjam is a General Purpose (HT) consumer
                 under opposite party no.1-Executive Engineer (Elect.), BED-I,
                 Southco, Berhampur. The petitioner had executed an agreement
                 with the opp. Parties on 22.8.2011 for power supply to his Appolo
                 Clinic with contract demand of 140KW 156 KVA. Accordingly, the
                 opposite parties supplied power in the name of the petitioner and
                 served bill on the petitioner as per its consumption of 156 KVA.
                 After two months of power supply, the petitioner requested the
                 opp. Parties for reduction of his contract demand to 110 KVA. The
                 opp. Party no.1 continued serving bills on the petitioner with the
                 contract demand of 110 KVA till December 2017 vide Annexure-3
                 series. The petitioner also requested the opp. Parties to refund the
                 meter rent of Rs.1,000/- paid by him from November 2011 till
                 November 2016, but the same was not considered. The opp. Party
                 no.1 vide his letter No.763(5) dated 01.02.2018 intimated the
                 petitioner regarding revision of bills from the period from January,
                 2012 till December 2017. Finding no other way, the petitioner
                 approached the learned GRF, Berhampur in Case No.172 of 2018
                 and being aggrieved by the order dated 20.7.2018 of the learned
                      2




GRF, Berhampur, the petitioner filed a representation dated
19.10.2018 before opp. Party no.2. The        opp.    Party   no.2   vide
order dated 17.12.2019 rejected the prayer of the petitioner with
certain modification in the order of the learned GRF, Berhampur.
Hence, this Writ Petition.
          Learned counsel for the petitioner submitted that the
petitioner has filed an application for reduction of the power supply
to its unit as per the       Regulation 66 of the OERC Distribution
(Conditions of Supply) Code-2004. However, without considering
the grievance of the petitioner in accordance with the statutory
provision, the opp. parties vide orders dated 20.7.2018 and dated
17.12.2019 have issued direction as given below.
                   Extract of Order dated       20.7.2018
        passed by the learned GRF, Berhampur in GRF Case
        No.172/2018.
        1. After verification of estimate, it is found that, the
        estimated amount towards 11 KV cable and cubical
        metering has been deposited by the complainant. But, it
        is confirmed that, 11 KV metering unit has been
        installed. So the differential amount as mentioned above
        has to be refunded in shape of adjustment in energy
        charge bills.
        2. The meter rent shall be claimed for 60 months as per
        the clause 448 of tariff order 2016-17. Once it is
        collected for 60 months, the meter rent collection should
        stop.
        3. The erroneous monthly demand charges billing has
        been detected by the respondent and claimed the
        differential demand charges, as per contract demand
        and as determined in tariff notification. So the revised
        demand charges shall be payable by the consumer as he
        has not applied for reduction of contract demand as per
        regulation 66 at any time.
         Extract of judgment dated 17.12.2019 in
        Consumer Representation Case No.Omb(II) S-19 of
        2018 is hereunder
          1.    The respondent is directed to refund the
               differential amount of cubicle meter and 11KV
               metering unit along with interest @ 1% per month.

          2.      The respondent is directed to refund the full
          meter rent collected from the petitioner along with
          interest @ 1% per month to the petitioner.
                     3




          The respondent is directed to revise the bills of
          the petitioner and serve the revise bill to the
          petitioner within 30 days from the date of receipt of
          letter of acceptance from the petitioner and file
          compliance to this Authority within 45 days.

      However, it appears from the agreement entered into
between    the   parties    dated   22.8.2011,    pursuant        to
Regulation 15 of the OERC Distribution (Conditions of
Supply) Code-2004,          the petitioner has entered into
agreement with       Opposite Party no.1 and since the
petitioner's application dated 22.8.2011 for reduction of
power supply are still pending with the opp. party no.1,
we dispose of the Writ Petition with a direction to           the
Managing Director, OERC to consider the application of
the petitioner as per the Regulation 56 of the OERC
Distribution (Conditions of Supply) Code-2004 within a
period of four weeks from the date of production of the
order passed by this Court. Till that date, the order dated
20.7.2018 passed by the learned GRF, Berhampur in GRF
Case No.172/2018           and dated 17.12.2019 in Consumer
Representation Case No.Omb(II) S-19 of 2018 passed by
the   OMBUDSMAN-II(Electricity),        OERC,     Bhubaneswar
shall remain stayed.
          It is submitted by the learned counsel for the
petitioner that the petitioner has deposited Rs.6,00,000/-
(Rupees six lakhs) towards differential claim of monthly
Demand Charges before          opp. party no.1 towards the
arrear payment. If that be so, the petitioner is directed to
deposit further amount of Rs.2,00,000/-(Rupees Two
Lakhs) with the opp. party no.1 towards arrear payment
of contract demand by 30th January, 2021.                 If the
petitioner deposited Rs.2,00,000/- by 30th January, 2021
before opp. party no.1, in such event, Opposite Party No.1
                         4




     OERC      will   consider        the application        of     the
     petitioner and no coercive action shall            be        taken
     against the petitioner till a decision is taken by the on the
     application of the petitioner.
              Learned counsel for the parties may utilize the
     soft copy of this order available in the High Court's
     website or print out thereof at par with certified copies in
     the manner prescribed, vide Court's Notice No.4587 dated
     25.3.2020.


                              .............................
                               S. Panda, J.

............................. S. K. Panigrahi, J.

sp

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter