Citation : 2022 Latest Caselaw 624 Meg
Judgement Date : 26 October, 2022
Serial No. 02
Supplementary
List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 288 of 2018
Date of Decision: 26.10.2022
Star Cement Limited Vs. Union of India & Ors.
Coram:
Hon'ble Mr. Justice W. Diengdoh, Judge
Appearance:
For the Petitioner/Appellant(s) : Dr. A. Saraf, Sr. Adv. with
Mr. S.J. Saikia, Adv.
For the Respondent(s) : Dr. N. Mozika, DSG. with
Ms. A. Pradhan, Adv. for R 1.
Mr. M. Singh, Sr. Adv. with Mr. M.Z. Ahmed, Sr. Adv.
GP Capt. K. Singh Bhatti, Adv.
Ms. B. Dutta, Sr. Adv. for R 2-5.
i) Whether approved for reporting in Yes/No
Law journals etc.:
ii) Whether approved for publication
in press: Yes/No
JUDGMENT AND ORDER
1. The petitioner company is engaged in the business of
manufacturing cement and for this purpose had entered into an agreement
with the respondent No. 3 - North Eastern Coalfields for purchase of coal.
In furtherance of this purpose, the parties have entered into a Coal Supply
Agreement (CSA) (termed as Fuel Supply Agreement in this petition,
which term shall be used interchangeably herein) under the terms and
conditions set therein.
2. The petitioner on being asked by the respondent No. 4 to furnish
a bank guarantee for an amount equal to 10% of the notified based price
of the annual coal requirement for issuance of Letter of Assurance (LOA)
has furnished a bank guarantee for an amount of ₹ 1,03,86,000/- (Rupees
one crore, three lakhs, eighty-six thousand) only in favour of respondent
No. 3 vide guarantee dated 27.03.2012 issued by the State Bank of India,
Commercial Branch, Kolkata.
3. Vide letter dated 27.02.2011 the respondent No. 5 informed the
petitioner of the notification dated 26.02.2011 issued by the Coal India
Limited notifying to the effect that the coal produced by the respondent
No. 3 has increased in value and if the petitioner wants its coal to be
delivered, it has to agree to the revised price and to pay the differential
amount. It is stated that such increase in price was more than 60% than
what was agreed upon at the time when the CSA was executed.
4. The petitioner vide its letter dated 16.03.2011 has requested the
respondents to consider the said revision of price and not to resort to the
increase of almost 60% of price in a single day which is disadvantageous
to the petitioner, but the same was not accepted by the respondents.
5. The petitioner then informed the respondent No. 3 to sell the
allotted quantity of coal through E-Auction route till the petitioner was in
need of coal which shall be intimated to the respondents by giving 30
days' notice in advance. The respondent No. 3 was also requested to keep
the CSA in abeyance and no penalty on account of the same to be charged
on the petitioner. However, the respondent No. 3 issued letter dated
18.07.2011 refusing to keep the CSA in abeyance and further stated that
coal price matters do not relieve the petitioner from any obligations under
the said CSA.
6. The respondent No. 3 vide invoice dated 18.08.2011 has
demanded that the petitioner pay an amount of ₹ 54,05,390/- (Rupees
fifty-four lakhs, five thousand, three hundred ninety) only as
compensation for short lifting of the coal by the petitioner to which the
petitioner vide letter dated 27.03.2012 has requested the respondent No. 3
to withdraw the same. However, the respondent No. 5 vide letter dated
11.05.2012 has raised another invoice dated 10.05.2012 on the petitioner
for compensation for short lifting of coal for the period 2011-12, the
amount being ₹ 74,24,699.91 (Rupees seventy-four lakhs, twenty-four
thousand, six hundred ninety-nine and ninety-one paise) only.
7. The respondent No. 3 through its General Manager has issued
letter dated 29.05.2012 upon the petitioner which is a notice for
termination of the Coal Supply Agreement (CSA) on the ground that there
was a short lifting of coal by the petitioner for the year 2011-12 which was
less than 30% of the Annual Contracted Quantity (ACQ) thus attracting
clause No. 15.1.4 of the CSA.
8. The petitioner then preferred an appeal before the respondent
No. 3 dated 26.06.2012 stating that the short lifting of coal was due to the
hefty increase in the price of coal by more than 60% of what was agreed
to by the parties and that the price of coal has been paid in full by the
petitioner to the respondent company and as such, charging invoice on the
coal not lifted in the name of compensation is completely illegal. The
petitioner has also filed appeal against the invoice dated 18.08.2011,
10.05.2012 as well as the Termination Notice dated 29.05.2012 to which
the respondent company threatened to invoke the Bank Guarantee
furnished by the petitioner during the pendency of the appeals before the
respondent No. 3.
9. The petitioner being highly aggrieved by the action of the
respondent company, particularly the threat to invoke the Bank Guarantee
has approached the Guahati High Court at the Principal Bench as there
was no available Bench at Shillong at that time and the Court vide order
dated 29.06.2012 has directed the respondent authorities to consider the
appeal dated 26.06.2012 filed by the petitioner and to pass a speaking
order on merits. The Chairman, North Eastern Coalfields taking up the
appeals has decided the same and vide order dated 28.02.2013 had
dismissed the appeals. Pursuant to the dismissal of the said appeals, the
respondent company then invoked the Bank Guarantee for ₹ 1,03,86,000/-
(Rupees one crore, three lakhs eighty-six thousand) only and the State
Bank of India, Commercial Branch, Kolkata vide order dated 15.03.2013
paid the said amount to the respondent company.
10. The petitioner questioned the impugned actions of the
respondent company in increasing the price of coal by 60%, levy of
compensation vide invoices dated 18.08.2011 and 10.05.2012 and the
issue of Notice of Termination of Contract dated 29.05.2012 and has
accordingly preferred a writ petition before the Hon'ble Gauhati High
Court (Shillong Bench) numbered as WP(C) No. 47 of 2013. The Court
after hearing the parties has, vide order dated 26.11.2013 allowed the
petition.
11. The respondent company however preferred a writ appeal
against the said order dated 26.11.2013 before a Division Bench of this
Court numbered as WA No. 1 of 2014 which was disposed of vide order
dated 29.09.2016 directing the parties to take recourse of the settlement
mechanism provided in the agreement.
12. Pursuant to the direction of the Division Bench of this Court, the
representatives of the petitioner and the respondent company,
respectively, held a number of meetings on the following appeals made by
the petitioner being:
i. Waiver of ₹ 54,05,390.74 (Rupees fifty-four lakhs, five
thousand, three hundred ninety and seventy-four paise) only
claimed as compensation by the Coal India Limited for short
lifting for the period 2010-11;
ii. Waiver of ₹ 74,24,699.91 (Rupees seventy-four lakhs,
twenty-four thousand, six hundred ninety-nine and ninety-
one paise) only claimed as compensation by the Coal India
Limited for short lifting for the period 2011-12;
iii. Refund of amount of ₹ 1,03,86,000.00 (Rupees one crore,
three lakhs, eighty-six thousand) only of invoked Bank
Guarantee;
iv. Cancellation of notice of termination of CSA dated
04.02.2009;
v. To allow recalculation of the compensation for the year
2010-11 and 2011-12 as per the formula given under clause
4.5.1 of the CSA and;
vi. To allow the petitioner to lift the short-lifted quantity of coal
for the year 2011-12 as per CSA dated 04.02.2009 to
overcome/make up the short lifting which will ultimately
improve their lifting performance for the year 2011-12, as a
result of which both compensation and notice of termination
of CSA will be ineffective leading to the closure of the long
pending case.
13. The respondent company vide letter dated 08.06.2018 has
informed the petitioner of the decision taken on 10.07.2017 as regard the
appeals made by the petitioner and in effect has rejected all the appeals
made except for appeal No. 2 i.e., for waiver of compensation of ₹
74,24,699.91 (Rupees seventy-four lakhs, twenty-four thousand, six
hundred ninety-nine and ninety-one paise) only which was accepted.
14. Not being satisfied with the culmination of the proceedings
between the parties herein as regard the manner whereupon the appeal of
the petitioner company was disposed of by the respondent company which
has not conceded to most of the demand made, the petitioner has
accordingly approached this Court with this instant writ petition with a
prayer to declare as illegal the clauses 4.5, 9.1,9.2 and 15 of the said Coal
Supply Agreement and also to quash the invoices dated 18.08.2011 and
10.05.2012, Notice dated 29.05.2012, Minutes of the meeting dated
10.07.2017 and 28.08.2017 and the Final Order dated 08.06.2018.
15. Heard Dr. A. Saraf, learned Sr. counsel for the petitioner who
has submitted that the issue to be decided herein is whether liquidated
damages can be imposed if there is no loss to the party under Section 73
of the Indian Contract Act. Though there was short lifting of the coal by
the petitioner because of the increase of price upto 60%, the fact is that the
respondent No. 3 has sold the coal to some other party at a huge profit.
16. That the respondent company has imposed liquidated damages
for short lifting of the coal taking recourse to clause 4.5 of the Agreement
cannot be contemplated as facts would prove that no loss was incurred by
the respondent company. Demand for liquidated damages is not automatic
as proof of loss has to be shown by the respondent company and penalty
cannot be imposed as the stipulation in the said clause speaks of
compensation and not penalty.
17. Submitting that a perusal of clause 4.5 of the agreement would
show that the respondent company can demand compensation in case of
short lifting of coal, however compensation cannot be equated with
penalty. To further clarify this position, the learned Sr. counsel has cited
the case of Rathi Menon v. Union of India: (2001) 3 SCC 714 wherein at
para 24, the term compensation was explained as "...Though the word
"compensation" is not defined in the Act or in the Rules it is the giving of
an equivalent...." and also the case of Smt. Sova Ray & Anr. v. Gostha
Gopal Dey & Ors: (1988) 2 SCC 134 para 7 parts of which reads as
"...The expression 'penalty' is an elastic term with many different shades
of meaning but it always involves an idea of punishment..."
18. The learned Sr. counsel has submitted that the impugned
demand notice and the notice of termination of the CSA issued by the
respondent company amounts to imposition of penalty which is
impermissible in law as was held in the case of Maya Devi v. Lalta
Prasad: (2015) 5 SCC 588 para 19 wherein, it was held that "...The
imposition and the recovery of penalty on breach of a contract is legally
impermissible under the Contract Act..."
19. In this regard, the learned Sr. counsel has referred to certain
decisions in which the term liquidated damages has been explained, viz.,
the case of Fateh Chand v. Balkishan Dass: (1964) 1 SCR 515, para 8,
9, 15 & 16, Maya Devi v. Lalta Prasad: (2015) 5 SCC 588, para 19, 24,
26, Kailash Nath Associates v. Delhi Development Authority & Anr.:
(2014) 4 SCC 136, para 43, 43.1, 43.2, 43.3, 43.4, 43.5, 43.6, 43.7 & 44.
20. The learned Sr. counsel has also referred to the order dated
26.11.2013 passed by a Single Bench of this Court in WP(C) No. 47 of
2013 wherein at para 18 of the same, it was clearly observed that an
admission was made by both the learned counsels for the parties that on
failure of the petitioner to lift the coal, the same was subsequently sold
and as such, no loss was incurred by the respondent company. It is
submitted that though this order was set aside by the Division Bench since
the matter was referred for mediation and settlement, the fact remains that
the coal was not lying in the stock of the respondent company, but was
sold at a profit. There is nothing in the pleadings of the respondent
company to show that the coal was not sold and because of the short lifting
by the petitioner, loss was caused to the respondent company. The only
pleading is that because the clause in the agreement provided for
compensation in case of short lifting, the petitioner is therefore liable to
pay the compensation.
21. Mr. M. Singh, learned Sr. counsel for the respondents No. 2 to 5
has countered the submission and contentions made by the learned Sr.
counsel for the petitioner by stating at the outset, that coal is considered
an essential commodity and is scarce and in the recent past, there has
arisen an anomalous situation where the distribution of coal in the country
was not channelled properly resulting in genuine users not getting it. This
led to a number of litigation in the courts and finally, a Constitutional
Bench of the Supreme Court has directed the Government to bring out a
policy to prevent misuse of coal, such policy to include putting stringent
conditions in the contract. In this regard, the case of M/s Ashoka
Smokeless Coal India Pvt. Ltd v. Union of India & Ors: (2007) 2 SCC
640 para 188, 189 & 190 was cited by the learned Sr. counsel to submit
that when the terms of the contract between the parties herein was
prepared, this aspect of the matter was taken note of.
22. Since the petitioner company has failed to comply with the terms
of the contract, that is, there was no lifting of the coal during the relevant
period, only then the respondent Company, in view of the demand in the
market and the fact that the space was needed, diverted the coal, not with
a profit oriented motive, but for the purpose of circulation of the same.
23. Another contention raised by the learned Sr. counsel for the
respondents No. 2-5 is that under the contract agreement between the
parties, clause 16 speaks of 'Force Majeure' which is a circumstance or
situation which arises in course of the contractual period causing loss to
either parties not attributable to any specific action on their part. However,
the proviso to the said clause stipulates that a Force Majeure act shall not
include economic hardship, equipment failure or breakdown other than
those specifically set forth. In the case of the petitioner, any loss cause out
of short lifting or non-lifting cannot be a condition for exemption or for
demand of compensation.
24. The learned Sr. counsel has also confirmed that in compliance
with the order dated 29.09.2016 of the Division Bench of this Court
directing for settlement and negotiation between the parties, the petitioner
company having set out its request considered as appeal before the
respondent company, after sitting together and having considered the
issues presented, the respondent company has, finally taking everything
into consideration have, vide the letter No. M&S/Legal/cmc/369 dated
08.06.2018 (Annexure-XXXIII of the writ petition) informed the
petitioner company that all the appeals made have not been accepted
except for the appeal for waiver of compensation for ₹ 74,24,699.91 for
the year 2011-12 was accepted and stands cancelled.
25. Yet another contention raised by the learned Sr. counsel for the
respondents No. 2-5 is on the issue of maintainability of this writ petition.
It is submitted that if on the issue of compensation or loss suffered in terms
of the contractual provisions, whether a writ would lie?
26. Referring to the case of Fateh Chand (supra) relied upon by the
petitioner, the learned Sr. counsel for the respondents No. 2-5 has
submitted that in that case, there was a contractual dispute which arises
from a suit which was dealt with in a complete trial and eventually, the
matter reached the Supreme Court where the Hon'ble Supreme Court has
decided the matter as reflected in the said judgment. However, in this
instant case, there is no trial but a writ was instead filed. Therefore, the
ratio of this judgment is not applicable to the case of the petitioner, it is
submitted.
27. The issue of 'res judicata' has also been raised by the learned Sr.
counsel for the respondents No. 2-5 who has submitted that the petitioner
in this writ petition has made identical prayer as those made in the earlier
writ petition which has since been disposed of by this Court. Whether
such successive writ applications can be moved in the same court on the
same cause of action? The answer is no, since the provision of res judicata
as incorporated in section 11 of the Code of Civil Procedure(CPC) though
may not strictly be applicable to successive writ applications, however the
general principle of res judicata is applicable as could be noticed from a
number of decisions of the Apex Court and High Courts, some of which
are cited being the case of M.S.M. Sharma v. Dr. Shree Khrishna Sinha
& Ors: AIR 1960 SC 1186 para 8; Radha Shyam Datta & Ors v. Patna
Municipal Corporation: AIR 1956 Patna 182, para 12; Shamsul Haque
Dastgirali v. The Assistant Custodian of Evacuee Property: AIR 1958
Madhya Pradesh 82, para 2; Daryao & Ors v. State of U.P. & Ors: AIR
1961 SC 1457, para 9 & 10.
28. It is also the submission of the learned Sr. counsel for the
respondents No. 2-5 that the dispute between the parties herein raised
some pertinent questions on the factual aspect, as to what would be the
exact loss caused to the petitioner or the respondent company, or if the
allegation that the respondent company has sold off the coal to others at a
huge profit, then what is the amount received is also a question of facts
which can only be determined by a civil court of competent jurisdiction
and as such, the petitioner cannot raise these issues before a writ court.
29. As to whether a writ is maintainable in a contractual matter, the
learned Sr. counsel has cited the case of Kerala State Electricity Board &
Anr v. Kurien E. Kalathil & Ors: (2000) 6 SCC 293, para 10, 11 & 12
wherein the Hon'ble Supreme Court has held that if a term of contract is
violated, ordinarily the remedy is not a writ petition under Article 226 of
the Constitution of India. The case of Godavari Sugar Mills Limited v.
State of Maharashtra & Ors: (2011) 2 SCC 439, para 8 was also cited in
this regard in which it was held that a petition under Article 226 of the
Constitution of India will not be entertained to enforce a civil liability
arising out of a breach of contract.
30. Another issue raised by the learned Sr. counsel for the
respondents is whether in a non-statutory contractual matter on the ground
that such contract is based on the superior bargaining power of one party
to such contract and whether the concept of arbitrariness,
unreasonableness, unfairness or irrationality can be brought before a writ
court while making a challenge to the same, considering the fact that the
principles of natural justice, fair play and legitimate expectation may not
have any role to play in such a situation. It is submitted that the Hon'ble
Supreme Court while dealing with a case of non-statutory contract has
held that the application of the principles or natural justice has no role to
play in such cases. This refers to the case of M/s Radhakrishna Agarwal
& Ors v. State of Bihar & Ors.: (1977) 3 SCC 457, para 23 & 25.
31. The case of Bareilly Development Authority & Anr. v. Ajai Pal
Singh & Ors.: (1989) 2 SCC 116, para 21, 22 & 23 as well as the case of
Assistant Excise Commissioner & Ors. v. Issac Peter & Ors.: (1994) 4
SCC 104, para 26 was cited to support the case of the respondents as far
as the applicability of the principles of arbitrariness, fair play and
unreasonableness is concerned.
32. It is finally submitted that under the facts and circumstances of
the case of the parties, this petition is devoid of merits and the same has to
be dismissed. Alternatively, this Court, if deemed fit can also direct the
petitioner company to approach the competent civil court for redressal of
its grievances.
33. In reply, the learned Sr. counsel for the petitioner has submitted
that the contention of the respondents that a writ application will not lie in
contractual matters is not the correct law as the Hon'ble Supreme Court in
the case of Unitech Limited and Ors v. Telengana State Industrial
Infrastructure Corporation (TSIIC) & Ors: 2021 SCC Online SC 99 has
clearly held that the exercise of jurisdiction of the Court under Article 226
of the Constitution cannot be ousted only on the basis that the dispute
pertains to the contractual arena. This is for the simple reason that the State
and its instrumentalities are not exempt from the duty to act fairly merely
because in their business dealings they have entered into the realm of
contract (para 41).
34. The argument advanced by the parties have been duly taken note
of by this Court. It may however be pointed out that the respondent No.
1/Union of India represented by the learned DSG has not advanced any
argument being considered only a formal party.
35. The parties having been heard in this matter, the issue of 'res
judicata' may be decided at the outset before one proceed to discuss the
contentious issues involved.
36. The authorities cited by the learned Sr. counsel for the
respondents as regard 'res judicata' would reveal that it has been accepted
that the provisions of res judicata as incorporated in Section 11 of the Code
of Civil Procedure may not strictly apply to successive writs application,
however the general principle of res judicata can be made applicable to
writ applications also. Consequently, once a decision is made on merit
under Article 226, a subsequent writ cannot be moved in the same court
on the same cause of action.
37. The contention of the respondents in this case is that this Court
on an earlier occasion has already dealt with the same facts and prayer of
the petitioner for issuance of directions or order on the challenge to
clauses 4.5, 9.1, 9.2 and 15 of the CSA dated 04.02.2009 as well as the
invoices for compensation dated 18.08.2011 and 10.05.2012 along with
the termination notice dated 29.05.2012 and also against the order dated
28.02.2013 wherein the bank guarantee was forfeited by the petitioner
company, the same having been decided in W. P.(C) No 47 of 2013 vide
order dated 26.11.2013 and which decision was later overturned in W.A.
No. 1 of 2014 vide order dated 29.09.2016, therefore the petitioner seeking
similar relief against the respondents in this instant writ petition cannot be
allowed, being hit by the principle of res judicata.
38. Though the contention of the respondents as regard the identical
contents of the prayer in the earlier petition and that this petition is correct,
however the respondent has failed to notice that the developments in the
dispute between the parties herein did not end only on the disposal of the
matter in W.P. (C) No 47 of 2013, but on appeal, the Division Bench of
this Court in W.A. No 1 of 2014 has directed the parties to take recourse
to the settlement provision made available in the FSA itself and has
annulled the decision made in W.P. (C) No 47 of 2013 only to allow the
parties to approach the matter on a fresh platform.
39. In this regard, the observations of the Division Bench may be
culled out to come to an understanding that having been relegated to the
'Settlement Mechanism' found within the provisions of the CSA, the field
is open to the parties to agitate the matter ab initio. The observations reads
thus:
"....When the parties are being relegated to the agreed settlement, it does appear necessary that the order impugned be annulled and also to make it clear that none of the observations made in the impugned order or even in this judgment shall be having any bearing on settlement of dispute by the parties in terms of the mechanism provided in the agreements..."
40. It is also on account of the said direction of the Division Bench
of this Court that the petitioner company has made an appeal before the
respondent company for waiver of the compensation amount of ₹
54,05,390.74 for the year 2010-11, ₹ 74,24,699.91 for the year 2011-12,
refund of Bank Guarantee of 1,03,86,000.00 etc, that the final order of the
respondent company conveyed through communication dated 08.06.2018
was made wherein only one appeal, that is waiver of compensation of ₹
74,24,699.91 was accepted and the rest rejected. This, in the opinion of
this Court has changed the texture of the litigation and additional cause of
action has arisen which has paved the way for the petitioner to approach
this Court by way of this instant writ petition. The principle of res judicata
is therefore found not applicable to the present case.
41. Much has been said by the parties as to whether a writ is
maintainable in a contractual matter to the extent that relevant authorities
have been cited by both sides, for and against. The case of Kerala State
Electricity Board (supra) and other similar cases have been cited by the
respondents to impress upon this Court that a dispute as regard the terms
of agreement in a contract cannot be the subject matter of a writ
proceedings, but would have to be pursued before a competent civil court.
42. As a counter to this, the petitioner have maintained that the Apex
Court have, time and again, in appropriate cases, held that a writ petition
is maintainable in contractual matter involving the Instrumentalities of the
State. The case of ABL International Ltd. & Anr. v. Export Credit
Guarantee Corporation of India Ltd. & Ors.: (2004) 3 SCC 553 has been
cited to support this contention wherein at para 27 of the same, it was held
that:
"27. From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.
(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable."
43. Again the case of Unitech Limited & Ors (supra) at para 41 was
also referred to which reads as follows:
"41. Therefore, while exercising its jurisdiction under Article 226, the Court is entitled to enquire into whether the action of the State or its instrumentalities is arbitrary or unfair and in consequence, in violation of Article 14. The jurisdiction under Article 226 is a valuable constitutional safeguard against an arbitrary exercise of state power or a misuse of authority. In determining as to whether the jurisdiction should be exercised in a contractual dispute, the Court must, undoubtedly eschew, disputed questions of fact which would depend upon an evidentiary determination requiring a trial. But equally, it is well-settled that the jurisdiction under Article 226 cannot be ousted only on the basis that the dispute pertains to the contractual arena. This is for the simple reason that the State and its instrumentalities are not exempt from the duty to act fairly merely because in their business dealings they have entered into the realm of contract. Similarly, the presence of an arbitration clause does oust the jurisdiction under Article 226 in all cases though, it still needs to be decided from case to case as to whether recourse to a public law remedy can justifiably be invoked. The jurisdiction under Article 226 was rightly invoked by the Single Judge and the Division Bench of the Andhra Pradesh in this case, when the foundational representation of the contract has failed. TSIIC, a state instrumentality, has not just reneged on its contractual obligation, but hoarded the refund of the principal and interest on the consideration that was paid by Unitech over a decade ago. It does not dispute the entitlement of Unitech to the refund of its principal."
44. Looking into the facts and circumstances of this case, since the
contentious issue revolves around the interpretation of Clause 4.5 of the
said CSA as to whether the word 'compensation' can also mean 'penalty'
or 'liquidated damages', all other actions resorted to by the respondent
company being subsequent thereto, the same can be resolved at this forum
and as such, this Court is of the view that this writ is maintainable.
45. Even otherwise, going by the history of the litigation between
the parties, the court was approached by the petitioner in the year 2013
and even almost ten years down the line, no closure of the same have been
made, this lapse of time is also a factor as to why this Court would choose
to end the dispute between the parties without sending the petitioner to a
civil court for institution of a suit. In this connection, para 54 of the "ABL
International Ltd." (supra) case is referred to when it was held that:
"54. Apart from the above reasons given by us to interfere with the judgment of the Appellate Bench of the High Court, we have one other good reason why we should not drive the appellants to a suit. The claim of the appellants was rejected by the respondent in the year 1994. The respondent challenged the basis of rejection by way of a writ petition in the year 1996. The objection as to the maintainability of the petition was rejected by the High Court by its judgment dated 15-5-1997. We are now in the end of the year 2003. We at this distance of time and stage of litigation, do not think it proper to relegate the parties to a suit. To direct the appellants to approach a civil court at this stage would be doing injustice to the appellants. In this view of ours, we are supported by a number of decisions of this Court like in Shambhu Prasad Agarwal v. Bhola Ram Agarwal:(2000) 9 SCC 714 wherein this Court though noticed the fact that the appellants had an alternate remedy for issuance of a letter of administration, it refused to dismiss the appeal on the grounds: (SCC p. 715, para 5) Since considerable time has elapsed, the interest of justice demands that the proceeding should come to an end as early as
possible and that the appeal should not be dismissed merely on highly technical ground."
46. Moving forward, what has been the focus of the petitioner in this
case, is the issue of compensation demanded by the respondent company
as is present in Clause 4.5 of the CSA which was consequent to the failure
of the petitioner company to lift the coal or for short lifting of the coal, for
which the said demand for compensation for the year 2010-2011 and
2011-2012 was accordingly made. It is apparent that this is not a demand
for compensation, but an imposition of penalty since the definition of the
word 'compensation' according to Black's dictionary means 'equivalent
in money for the loss sustained' which was not the case here as no loss
was incurred to the respondent company on the short lifting of the coal by
the petitioner company. The admitted fact being that the respondent
company has already sold the coal not lifted by the petitioner company
and there is no pleading that loss was incurred as a result of such sale.
47. On compensation, the provision of Section 74 of the Indian
Contract Act, 1872 speaks of compensation for breach of contract where
penalty is stipulated for. The Hon'ble Supreme Court in the case of
Kailash Nath Associates v. Delhi Development Authority & Anr: (2015)
4 SCC 136, has summarised the law on compensation for breach of
contract at para 43, 43.1, 43.2, 43.3, 43.4, 43.5, 43.6, & 43.7 and 44 quoted
below as:
"43. On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the court cannot grant reasonable compensation.
43.2. Reasonable compensation will be fixed on well-known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act. 43.3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the section. 43.4. The section applies whether a person is a plaintiff or a defendant in a suit.
43.5. The sum spoken of may already be paid or be payable in future.
43.6. The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded.
43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application.
44. The Division Bench has gone wrong in principle. As has been pointed out above, there has been no breach of contract by the appellant. Further, we cannot accept the view of the Division Bench that the fact that DDA made a profit from re- auction is irrelevant, as that would fly in the face of the most basic principle on the award of damages - namely, that compensation can only be given for damage or loss suffered. If damage or loss is not suffered, the law does not provide for a windfall."
48. In fact, the only stand of the respondent company is that the
petitioner by short lifting of the coal, has violated the terms of the CSA
and as a result, has cause loss of use of space and goodwill to the
respondent company. The very term compensation found in clause 4.5 of
the Agreement has been wrongly used to impose the cost demanded from
the petitioner company, that is, ₹ 54,05,390.74 (Rupees fifty-four lakhs,
five thousand, three hundred ninety and seventy-four paise) for the year
2010-11 and ₹ 74,24,699.91 (Rupees seventy-four lakhs, twenty-four
thousand, six hundred ninety-nine and ninety-one paise) for 2011-12,
which can only be construed as an imposition of penalty and thus
impermissible in law.
49. In this regard, the reliance of the petitioner in the case of Fateh
Chand (supra) is found relevant, though the argument of the respondents
that the ratio cannot be applied herein as the decision was made with
regard to a suit cannot be accepted as the counter of the petitioner that
once the Supreme Court has passed a judgment, it becomes binding on all
courts in India as per Article 141 of the Constitution of India is the correct
proposition.
50. In the case of Fateh Chand (supra), the Apex Court at para 8, 10,
15 & 16 of the same has held as follows:
"8. The section is clearly an attempt to eliminate the sometime elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages and stipulations in the nature of penalty. Under the common law a genuine pre-estimate of damages by mutual agreement is regarded as a stipulation naming liquidated damages and binding between the parties: a stipulation in a contract in terrorem is a penalty and the Court refuses to enforce it, awarding to the aggrieved party only reasonable compensation. The Indian Legislature has sought to cut across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty.
10. Section 74 of the Indian Contract Act deals with the measure of damages in two classes of cases (i) where the contract names a sum to be paid in case of breach and (ii) where the contract contains any other stipulation by way of penalty. We are in the present case not concerned to decide whether a contract containing a covenant of forfeiture of deposit for due performance of a contract falls within the first class. The measure of damages in the case of breach of a stipulation by way of penalty is by Section 74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the Court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to all the circumstances of the case. Jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to maximum stipulated; but compensation has to be reasonable, and that imposes upon the Court duty to award compensation according to settled principles. The section undoubtedly says that the aggrieved party is entitled to receive compensation from the party who has broken the contract, whether or not actual breach. Thereby it
merely dispenses with proof of "actual loss or damages"; it does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of contract can be awarded to make good loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach.
15. Section 74 declares the law as to liability upon breach of contract where compensation is by agreement of the parties predetermined, or where there is a stipulation by way of penalty. But the application of the enactment is not restricted to cases where the aggrieved party claims relief' as a plaintiff. The section does not confer a special benefit upon any party; it merely declares the law that notwithstanding any term in the contract predetermining damages or providing for forfeiture of any property by way of penalty, the court will award to the party aggrieved only reasonable compensation not exceeding the amount named or penalty stipulated. The jurisdiction of the court is not determined by the accidental circumstance of the party in default being a plaintiff or a defendant in a suit. Use of the expression "to receive from the party who has broken the contract" does not predicate that the jurisdiction of the court to adjust amounts which have been paid by the party in default cannot be exercised in dealing with the claim of the party complaining of breach of contract. The court has to adjudge in every case reasonable compensation to which the plaintiff is entitled from the defendant on breach of the contract. Such compensation has to be ascertained having regard to the conditions existing on the date of the breach.
16. There is no evidence that any loss was suffered by the plaintiff in consequence of the default by the defendant save as to the loss suffered by him by being kept out of possession of the property. There is no evidence that the property had depreciated in value since the date of the contract provided; nor was there evidence that any other special damage had resulted. The contract provided for forfeiture of Rs. 25,000 consisting of Rs. 1039 paid as earnest money and Rs. 24,000 paid as part of the purchase price. The defendant has conceded that the plaintiff was entitled to forfeit the amount of Rs. 1,000 which was paid as earnest money. We cannot however agree with the High Court that 13 percent of the price may be regarded as reasonable
compensation in relation to the value of the contract as a whole, as that in our opinion is assessed on an arbitrary assumption. The plaintiff failed to prove the loss suffered by him in consequence of the breach of the contract committed by the defendant and we are unable to find any principle on which compensation equal to ten percent of the agreed price could be awarded to the plaintiff. The plaintiff has been allowed Rs. 1,000 which was the earnest money as part of the damages. Besides he had use of the remaining sum of Rs. 24,000, and we can rightly presume that he must have been deriving advantage from that amount throughout this period. In the absence therefore of any proof of damage arising from the breach of the contract, we are of opinion that the amount of Rs. 1,000 (earnest money) which has been forfeited, and the advantage that the plaintiff must have derived from the possession of the remaining sum of Rs. 24,000 during all this period would be sufficient compensation to him. It may be added that the plaintiff has separately claimed mesne profits for being kept out of possession for which he has got a decree and therefore the fact that the plaintiff was out of possession cannot be taken, into account in determining damages for this purpose. The decree passed by the High Court awarding Rs. 11,250 as damages to the plaintiff must therefore be set aside."
51. So compensation means 'equivalent in money for a loss
sustained'. In this case, since there is no evidence that any loss was
suffered by the respondent company as a consequence of the default by
the petitioner company, or for short lifting of the coal, to quantify such
compensation at about fifty four lakhs for the year 2010-11 and about
seventy four lakhs or so, for the year 2011-12, demand to be compensated
for the same is not proper as it has assumed the form of a penalty which
was not provided for under clause 4.5 of the CSA.
52. To allow the respondent company to impose penalty or to
demand compensation (supra) when, as a consequence of the short lifting
of the coal by the petitioner, the respondent company was able to sell it
off to some other parties, presumably at cost price or with profit,
realisation of the compensation from the petitioner company would only
tantamount to realisation of double monetary benefit which is not
acceptable, since the law or the provision of the CSA does not
contemplates such a situation.
53. On an overall analysis, taking into account the import of the
many authorities cited by the parties, some of which have been considered
relevant herein and was accordingly quoted or referred to, others which
are not found relevant and thus not quoted, this Court is of the considered
opinion that it is not open to the respondent company to impose penalty in
the guise of demand for compensation from the petitioner company.
54. The relevant provision of law upon which the concept of 'bank
guarantee' is founded is Sections 126 and 127 of the Indian Contract Act,
1872. A bank guarantee can be said to be an assurance given by a bank on
behalf of a customer which undertakes to pay or discharge the liability of
a debtor in case of any default. A bank guarantee essentially stems out of
a contractual obligation to reassure a third-party creditor that his financial
interest will not be affected in case of loss or in the event of default. By
issuing bank guarantee, a bank ordinarily undertakes to pay the amount
specified in the guarantee on demand made by a beneficiary in accordance
with the terms and conditions agreed to by the parties. A conditional
guarantee is one which presupposes a claim under the guarantee on proof
of breach of the terms of the contract or any loss occurring as a result of
such breach. The object of a bank guarantee is to ensure due performance
of the contract or it can also be towards security deposit for a contract.
55. Generally, courts would exercise restraint on prayer to injunct a
bank guarantee being invoked or to encash the same except on two
grounds namely; fraud and secondly, irretrievable injury, where a creditor
is restrained from exercising his right of encashment. If the bank guarantee
has come about as a result of fraud on the part of the creditor, the whole
transaction is vitiated. The other exception to the encashment of a bank
guarantee is irretrievable harm or injustice to one of the parties.
56. The prayer of the petitioner company in this case to restrain the
respondent company to encash the bank guarantee can only be on the
ground of irretrievable injury or injustice. In the case of Dwarikesh Sugar
Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. & Anr: AIR
1997 SC 2477, the Hon'ble Supreme Court speaking on bank guarantee
has observed at para 20 as:
"20. Numerous decisions of this Court rendered over a span of nearly two decades have laid down and reiterated the principles
which the Courts must apply which considering the question whether to grant an injunction which has the effect of restraining the encashment of a bank guarantee. We do not think it necessary to burden this judgment by referring to all of them. Some of the more recent pronouncements on this point where the earlier decisions have been considered and reiterated are Svenska Handelsbanken v. M/s. Indian Charge Chrome, (1994) 1 SCC 502: (1993 AIR SCW 4002), Larsen & Toubro Ltd. v. Maharashtra State Electricity Board, (1995) 6 SCC 68: (1975 AIR SCW 4134), Hindustan Steel Workers Construction Ltd. v. G.S. Atwal & Co. (Engineers) Pvt. Ltd. (1995) 6 SCC 76: (1995 AIR SCW 3821) and U.P. State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568: (1997 AIR SCW 694). The general principle which has been laid down by this court has been summarised in the case of U.P. State Sugar Corporation's case as follows: (at p. 697 of AIR SCW):
"The law relating to invocation of such bank guarantees in by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficial is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour, it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The Courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take the advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country."
Dealing with the question of fraud it has been held that fraud has to be an established fraud. The following observations
of Sir John Donaldson, M.R. in Bolivinter Oil S.A. v. Chase Manhattan Bank, (1984) 1 All ER 351, are apposite:
"The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge .It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank to have it charged."
(emphasis supplied)
57. On the facts of this case, as noted above, the fact that Clause 4.5
binds the parties as far as short lifting of the coal is concerned, inasmuch
as, it was incumbent upon the purchaser/petitioner company to maintain
the agreed level of ACQ (Annual Contracted Quantity), short lifting of the
same to be visited by a demand of compensation, this being part of the
Agreement, the same cannot be questioned by any of the parties. However,
as observed, the fact that no compensation can be demanded as there was
no loss incurred as a result of the short lifting since the same coal was sold
off to some other party, the petitioner company cannot be faulted for
seeking injunction on invocation of the security deposit/bank guarantee as
in the opinion of this Court, invocation of the bank guarantee would result
in irretrievable loss and injury to the petitioner company. Considering the
time factor as regards the proceedings, this Court having observed that
sending the parties to the civil court would not serve the ends of justice,
pending final settlement between the parties herein, restraining the
respondent company from encashing the bank guarantee is reasonable and
justifiable.
58. What flows from the above proposition is that the respondent
company cannot be allowed to gain from the drawback of short lifting of
the coal by the petitioner company solely on the ground that no loss was
incurred in the process thereof, the notice for termination of the
Agreement is also not found justified by this Court. The same is not
allowed.
59. Consequently, the prayer of the petitioner is found reasonable
and the same is hereby allowed.
60. The respondent No. 3 is hereby directed to rescind its demand of
compensation from the petitioner company for the sum of ₹ 54,05,390.74
(Rupees fifty-four lakhs, five thousand, three hundred ninety and seventy-
four paise) for the year 2010-11 and ₹ 74,24,699.91 (Rupees seventy-four
lakhs, twenty-four thousand, six hundred ninety-nine and ninety-one
paise) for 2011-12 and to refund the Bank Guarantee as well as to refrain
from putting into effect the notice for termination of the CSA dated
29.05.2012.
61. Since the dispute between the parties could not be resolved
through the settlement process as directed by the Division Bench of this
Court and since the petitioner as a result of the breakdown of the same has
now approached this Court with this instant petition, the matter having
been finally decided judicially herein, it stands to reason that the final
order of the respondent company dated 08.06.2018 is hereby set aside and
quashed to the extent indicated above.
62. Petition disposed of. No costs.
Judge
Meghalaya 26.10.2022 "D. Nary, PS"
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!