Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Chief Engineer vs Engineering Products (I)
2025 Latest Caselaw 7362 Mad

Citation : 2025 Latest Caselaw 7362 Mad
Judgement Date : 23 September, 2025

Madras High Court

Chief Engineer vs Engineering Products (I) on 23 September, 2025

Author: N.Anand Venkatesh
Bench: N.Anand Venkatesh
    2025:MHC:2266
                                                               1                       OP No. 60 of 2018


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                            RESERVED ON : 19.09.2025

                                         PRONOUNCED ON : 23.09.2025

                                                         CORAM

                          THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH

                                                  OP No. 60 of 2018

                                                            AND

                                        ARB O.P(COM.DIV.) NO. 77 OF 2021

                OP No. 60 of 2018

                Chief Engineer
                Metropolitan Transport Project
                (Railways), Southern Railway, Egmore,
                Chennai-600 008.
                                                                                       Petitioner(s)

                                                             .Vs.
                1. Engineering Products (I)
                Limited, 3D, EC Chambers,
                No.92, G.N.Chetty Street, T.Nagar,
                Chennai-600 017.

                2.Mr.S.Balachandran
                Chief Electrical Engineer,
                Delhi Metro Rail Corporation Limited,
                Kochi.




https://www.mhc.tn.gov.in/judis              ( Uploaded on: 23/09/2025 08:41:59 pm )
                                                                   2                       OP No. 60 of 2018


                3.Mr.A.K.Sinha
                Chief Planning and Development
                Engineer, Southern Railway
                Chennai-600 003.


                4.Mr.K.Govindasai Babu
                Deputy Financial Adviser and Chief
                Accounts Officer,
                Headquarters Office, Southern Railway,
                Chennai-600 003.

                                                                                           Respondent(s)

                PRAYER
                    Original Petition filed under Section 34 of the Arbitration and

                Conciliation Act, 1996, to set aside the arbitral award of respondents 2 to 4

                dated 17.11.2014 made in relation to the disputes arising out of Agreement

                No.MTP/Civil/ 368/2000 in so far as the award under claims 5,8, and 12 are

                concerned and to direct the respondents to pay the cost to the petitioner.


                                  For Petitioner(s):       Mr.P.T.Ramkumar
                                                           Standing Counsel

                                  For Respondent(s) : Mr.K.Harishankar
                                                      and
                                                      Ms.Mithreyi Kasthurirangan




https://www.mhc.tn.gov.in/judis                  ( Uploaded on: 23/09/2025 08:41:59 pm )
                                                                    3                       OP No. 60 of 2018


                Arb O.P(COM.DIV.) No. 77 of 2021

                M/s. Engineering Projects (i) Ltd
                3-D, EC Chmabers, 92 GN Chetty
                Street,T.Nagar
                Chennai 600 017.

                                                                                            Petitioner

                                                                  .Vs.
                The Chief Engineer
                MTP (Railways)
                Southern Railways, Egmore,
                Chennai 600 008.
                                                                                            Respondent(s)

                PRAYER
                    Petition filed under Section 34 of Arbitration and Conciliation Act, 1996,

                that the Award of the Arbitral Tribunal dated 17.11.2014 made by the Arbitrators

                in       relation     to    the     disputes          arising        out        of       the   agreement

                No.MTP/CIVIL/368/2000 dated 12.09.2000 in so far as disallowing part of the

                claim No.1, 2, entire claim No.3, part of claim No.5,6, entire claim No.7, part of

                claim No.8. entire claim No.10, part of claim No.12 and entire claim No.13 are

                concerned may be set aside.


                                  For Petitioner(s):        Mr.K.Harishankar
                                                            and
                                                            Ms.Mithreyi Kasthurirangan

                                  For Respondent(s) : Mr.P.T.Ramkumar
                                                      Standing Counsel for Railways


https://www.mhc.tn.gov.in/judis                   ( Uploaded on: 23/09/2025 08:41:59 pm )
                                                                      4                       OP No. 60 of 2018


                                                         COMMON ORDER

These petitions have been filed under Section 34 of the Arbitration and

Conciliation Act, 1996 [for brevity hereinafter referred as 'the Act'] against the

award of the Arbitral Tribunal dated 17.11.2014. Insofar as

Arb.O.P(Com.Div.)No.77 of 2021, disallowing the part of the Claim Nos.1, 2,

5, 6, 8 and 12 and disallowing the entire claim in Claim Nos. 3, 7, 10 and 13 has

been put to challenge. Insofar as OP.No.60 of 2018, the award granting Claim

Nos.5, 8 and 12 has been put to challenge.

2.The respondent invited tenders for execution of MRTS Phase-II

between Thirumalai (LUZ) - Velachery, specifically for Pile Foundation and

RCC works in columns, beams and slabs of the station building at Kotturpuram

adjoining Buckingham Canal.

3.The petitioners bid was accepted by Letter of Acceptance dated

22.5.2000 for a contract value of Rs.5,52,08,490/-. The agreement was

executed on 12.09.2000 with a stipulated completion period of 12 months

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

commencing from 22.5.2000 upto 21.5.2001.

4.The completion of work was delayed due to several factors. Extension

of time was granted by the respondents under Clause 17(2) of the General

Conditions of Contract [GCC]. The work was ultimately completed on

10.11.2004 and completion certificate was also issued by the respondents.

5.Disputes arose between the parties and hence an Arbitral Tribunal was

constitued by order dated 29.01.2008. The Tribunal after hearing both sides

passed an award dated 17.11.2014. The same has been put to challenge in these

petitions by both the petitioner and the respondents with respect to certain

claims.

6.Heard the learned counsel for the petitioner and the learned counsel

appearing on behalf of the respondents.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

7.The claim made by the claimant, the substantiation made by the

claimant, the defence taken by the Southern Railways and the findings rendered

by the Arbitral Tribunal are tabulated and extracted hereunder for easy

understanding:

S.No. Description of Substantiation Defence raised Findings Claim made by the by the rendered in Claimant Respondent the Arbitral Award Claim Increase of 30% The Claimant The The Tribunal 1 on the value of submits that Respondent held that the the work done though the has sought original 12-

during the contract rejection of month extended stipulated a the claim, completion completion contending period for the period of 12 that the Rs.

months, delays delays were 5,52,08,490/ in drawings and occasioned by - Crores material supply the Claimant’s contract was on the part of failure to unrealistic the Respondent mobilize and extended the skilled labour, unjustified, work by over 3 machinery and given the years. It is planning, difficult site urged that the including conditions rates quoted repeated (coffer dam became failures of the in water, unworkable batching excavation of owing to plant. It is slum).

                                             inflation and    further         Relying on
                                             escalation. The contended        Clause 17(2)
                                             Claimant         that            of the GCC,
                                             contends that    extensions      the Tribunal

substantial work were granted found no to the value of only upon the delay ₹4,88,50,501/- Claimant’s attributable was executed request and to the during this rider claimant and extended agreements upheld the period, for were executed application of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

which reaffirming the Price reimbursement the original Variation of escalation at rates. It is Clause (PVC) 25% (₹ also the case formula as 1,22,12,625/-) of the per Railway is sought, Respondent circulars. It placing reliance that the fixed a on decisions of Claimant reasonable the Hon’ble furnished a completion Supreme Court “No Claim period of 18 permitting Certificate” months and compensation before applied PVC despite settlement of formula to contractual the final bill. works prohibitions Hence, the executed when delay is demand for beyond 12 attributable to enhanced months.

the Respondent. rates is urged Based on bill-

                                                               to be an                         wise records
                                                               afterthought                     from CC Bill

                                                               untenable.                       onwards, the
                                                                                                Tribunal
                                                                                                calculated
                                                                                                escalation at
                                                                                                Rs.
                                                                                                9,24,035/-
                                                                                                and awarded
                                                                                                this amount
                                                                                                to the
                                                                                                claimant,
                                                                                                ensuring
                                                                                                compensation
                                                                                                while
                                                                                                acknowledgin
                                                                                                g shared
                                                                                                responsibility
                                                                                                of both
                                                                                                parties.

                 Claim Payment for the        The Claimant    The                               The Tribunal
                   2   additional             submits that    Respondent                        held that the
                       quantity of coffer     though Item 8   has sought                        Respondent
                       dam                    of Annexure IVA rejection of                      failed to
                       arrangements           referred to     the claim,                        prove non-
                       made.                  cofferdams in   contending                        execution of
                                              the Buckingham that payment                       coffer dam


https://www.mhc.tn.gov.in/judis             ( Uploaded on: 23/09/2025 08:41:59 pm )



                                    Canal alone,      for cofferdam works and
                                    site conditions   works is       offered no
                                    made              governed by    justification
                                    cofferdams        Item 8 of      for
                                    necessary for     Annexure IVA differential
                                    pile caps and tie and its        treatment
                                    beams across      necessity is   between

the site. It is determined by similar pile urged that the Engineer- rows (Row E execution in-Charge. It vs. Row F). It extended to is submitted found that 4960 RM as that the coffer dams against 1000 Claimant was were RM stipulated in duly paid technically the agreement, wherever necessary for and the cofferdams Rows F, G Claimant, under were and H, given instructions and executed, their cut-off supervision of even beyond levels below the Respondent, agreed MSL.

carried out such quantities, Rejecting the works. Payment and that the claim for full for the balance Claimant had rates, the 1720 RM, signed the Tribunal amounting to final bill and adopted a Rs.96,95,000/-, variation reasonable is therefore statement rate of one-

                                    sought.           without        third
                                                      protest. The   agreement
                                                      claim is urged rate (Rs.
                                                      to be an       1,875/Rm)
                                                      afterthought   for makeshift
                                                      and            coffer dams,
                                                      unsustainable. applying
                                                                     compensator
                                                                     y
                                                                     percentages
                                                                     —50% (Row
                                                                     F), 25%
                                                                     (Row G),
                                                                     15% (Row H)
                                                                     —based on
                                                                     inspection.
                                                                     The
                                                                     admissible
                                                                     perimeter
                                                                     was fixed at



https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

858.4389m, subject to a 4% reduction for exceeding the 125% quantity limit.

Accordingly, the Tribunal awarded Rs.

12,51,604/-

for the unpaid coffer dam work.

Claim Compensation for The Claimant The The Tribunal 3 reduction in scope submits that the Respondent held that the work of station removal of has sought overall building works. station building rejection of variation in works, without the claim, execution, any default on contending even without its part, that the the purported amounts to Claimant office partial executed the building, was prevention and entire scope of only 3.73% breach of work and, in above the contract. Loss fact, exceeded agreement of profit is the agreement value. It claimed at 10% value by found that no of the value of 3.73%. It is agreed work work worth Rs. submitted that had been 80,00,000/-, works worth dropped and i.e., Rs. Rs. the 8,00,000/-. 5,75,89,250.8 Respondent’s 0/- Crores official notes were executed could not as against the serve as agreement proof of any value of Rs. contractual 5,55,20,848.90 obligation to /- Crores. construct an Hence, the office allegation of building.

reduction of Accordingly, scope or loss the claim was of profit is rejected.

baseless.




https://www.mhc.tn.gov.in/judis         ( Uploaded on: 23/09/2025 08:41:59 pm )




                 Claim Payment for      The Claimant                 The            The Tribunal
                 4     empty boring     submits that                Respondent      noted that
                                        though the                  has sought      the
                                        contract                    rejection of    Respondent
                                        specified no                the claim,      had not
                                        limit for empty             contending      disputed the
                                        boring,                     that the        quantum of
                                        abnormal                    contractor was empty
                                        depths were                 required to fix boring,
                                        encountered,                the working     thereby
                                        which could not             platform level accepting the
                                        have been                   to minimize     claimant’s
                                        anticipated                 empty boring, figures. It
                                        while quoting               and that no     held that the
                                        rates. It is                extra payment final drawing
                                        contended that              was             was issued
                                        810m of empty               admissible      during
                                        boring was                  under the       execution,
                                        carried out                 agreement. It preventing
                                        across piles,               is further      the claimant
                                        incurring Rs.               urged that the from
                                        9,80,726/- and              Claimant        foreseeing
                                        reimbursement               failed to set   and pricing
                                        is sought as the            the platform    this work at
                                        work was                    optimally,      the tender
                                        essential and               resulting in    stage.
                                        unavoidable.                excess empty Rejecting the
                                                                    boring, and     allegation of
                                                                    that the claim poor
                                                                    constitutes an planning, the
                                                                    excepted        Tribunal
                                                                    matter under emphasized
                                                                    the contract.   that the
                                                                                    claimant, as
                                                                                    an
                                                                                    experienced
                                                                                    contractor
                                                                                    chosen by
                                                                                    the Railways,
                                                                                    could not be
                                                                                    presumed
                                                                                    negligent.
                                                                                    Accordingly,
                                                                                    applying a
                                                                                    reduced rate
                                                                                    to the


https://www.mhc.tn.gov.in/judis       ( Uploaded on: 23/09/2025 08:41:59 pm )



                                                                                             undisputed
                                                                                             extra empty
                                                                                             boring
                                                                                             quantities,
                                                                                             the Tribunal
                                                                                             awarded
                                                                                             Rs.9,17,952/-.



                 Claim Compensation        The Claimant      The                             The Tribunal
                 5     towards loss of     submits that the Respondent                       rejected most
                       profits and         Respondent        has sought                      of the
                       overheads.          failed to hand    rejection of                    claimant’s
                                           over the site     the claim,                      contentions
                                           and drawings as contending                        as
                                           required under that the PVC                       unsubstantiat
                                           Section 52 of     formula was                     ed and
                                           the Contract      inapplicable,                   abstract
                                           Act, thereby      that                            statements,
                                           committing        extensions                      except the
                                           breach. Though were granted                       proven delay
                                           the contract      only at the                     in payment of
                                           period was 12     Claimant’s                      CC Bills 26
                                           months, the       request                         and 27. It
                                           work extended through rider                       held that the
                                           to 42 months      agreements                      claimant was
                                           solely due to     reaffirming                     entitled to
                                           the               original rates,                 compensation
                                           Respondent’s      and that                        for the lost
                                           delays. It is     therefore no                    opportunity
                                           further urged     escalation or                   of funds
                                           that schedule     compensation                    during the
                                           quantities were was payable.                      delayed
                                           misleading,       The claim is                    period.
                                           payments were alleged to be                       Accordingly,
                                           delayed, and      an                              the Tribunal
                                           the Claimant      afterthought.                   awarded Rs.
                                           suffered heavy                                    21,246/-
                                           cost escalation.                                  towards
                                           By applying                                       interest at
                                           Hudson’s                                          12% p.a. on
                                           formula, loss of                                  the amounts
                                           overheads and                                     of the two
                                           profit is                                         bills.
                                           quantified at Rs.
                                           277,60,000/-.




https://www.mhc.tn.gov.in/judis          ( Uploaded on: 23/09/2025 08:41:59 pm )




                 Claim Payment for the      The Claimant     The             The Tribunal
                 6     extra works done     submits that     Respondent      held that the
                       not covered by       under the        has sought      claimant had
                       the agreement        instructions and rejection of    not produced
                                            supervision of   the claim,      any proof of
                                            the Respondent, contending       the
                                            it executed      that            Respondent
                                            additional works demolition      directing
                                            such as          works were      execution of
                                            demolition of    already settled the alleged
                                            abandoned        under the final works and
                                            structures,      bill and no-    had never
                                            cable            claim           raised these
                                            protection,      certificate,    claims prior
                                            earth cutting,   that cable      to arbitration
                                            and formation    protection was proceedings.
                                            of earthen       a contractual As the claims
                                            bunds. It is     obligation      were
                                            urged that the   without any     unsubstantiat
                                            total value of   protest. The    ed, they were
                                            such works       earthwork for rejected.
                                            comes to Rs.     pile caps and
                                            36,42,025/-, for diversions was
                                            which            incidental to
                                            reimbursement the contract.
                                            is claimed.      It is
                                                             contended
                                                             that the
                                                             claims are
                                                             contrary to
                                                             the contract
                                                             and
                                                             unsupported
                                                             by any
                                                             records.

                 Claim Compensation for The Claimant                    The                   The Tribunal
                 7     idle labour      submits that it                 Respondent            acknowledge
                                        mobilized                       has sought            d idling
                                        labour,                         rejection of          caused by
                                        machinery, and                  the claim,            shared delay
                                        staff                           contending            but found
                                        immediately                     that despite          that the
                                        after the letter                67% of the            claimant had
                                        of acceptance,                  site and              provided no



https://www.mhc.tn.gov.in/judis           ( Uploaded on: 23/09/2025 08:41:59 pm )



                                             but due to the    drawings       documentary
                                             Respondent’s      being          proof of

failure to issue available, the expenditure.

                                             drawings, the     Claimant       Since
                                             workforce         failed to make compensation
                                             remained idle.    preliminary    for delays

It is contended arrangements was already that this led to such as considered infructuous winches, under Claims expenditure on chisels, 1 and 5, the idle labour bailers, power Tribunal quantified at Rs. supply, and rejected the 18,49,250/-, liner bending claim.

                                             which is sought setups. It is
                                             as                urged that the
                                             compensation. delay was due
                                                               to poor
                                                               planning by
                                                               the Claimant,
                                                               and the
                                                               department
                                                               cannot be held
                                                               liable.

                 Claim Compensation for      The Claimant     The            The Tribunal
                 8     idle Machinery        submits that     Respondent     partly upheld
                       and Plants - Loss     various          has sought     the
                       of productivity       equipment        rejection of   claimant’s
                                             remained idle    the claim,     idling claims
                                             due to the       contending     based on
                                             Respondent’s     that only two admitted
                                             defaults and     tripods were   facts and
                                             claimed          initially      reasonable
                                             compensation     brought, that market rates:

as follows: essential 1. Piling Rigs:

                                                              machinery      Accepted
                                             1.Rigs and       such as liner  Respondent’s
                                             other machinery bending         own letter
                                             (including       machines,      showing

generator, plate winches, and 2119 hours bending, etc.) – batching idling;

                                             Rs.21,41,750/-. plants were     compensation
                                                              delayed by the awarded at
                                             2.62 KVA         Claimant, and market rental
                                             Generator – Rs. that no         rate.

1,35,000/-. alternate 2. Generator:

arrangements Rejected for

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

3.Plate Bending were made. It lack of proof. Machine – idle is submitted 3. Plate from that idle Bending 01.06.2000 to periods were Machine 16.10.2000, at attributable (10hp):

Rs. 20,000/- solely to the Found 34 per month. Claimant’s days idling, poor planning awarded at

4.Batching Plant and failure to market rate – idle from mobilize (lower than 05.11.2000 to resources. claimant’s 15.04.2001, rate).

claim of Rs. 4. Batching 5,50,000/-. Plant: Held

5.Welding Respondent Transformer – failed to hand idle from over land, 01.06.2000 to causing 5.5 16.10.2000 (Rs. months 67,500/-) and delay;

                                    from                                              compensation
                                    16.10.2000 to                                     awarded at
                                    01.03.2001 (Rs.                                   market rate.
                                    33,750/-).                                        5. Concrete
                                                                                      Mixer:
                                                                                      Rejected as
                                                                                      not required
                                                                                      for the
                                                                                      project.
                                                                                      6. Welding
                                                                                      Transformers
                                                                                      : Awarded
                                                                                      partial
                                                                                      compensation
                                                                                      for 3 units at
                                                                                      a
                                                                                      conservative
                                                                                      rate.
                                                                                      Accordingly,
                                                                                      the Tribunal
                                                                                      awarded a
                                                                                      total of Rs.
                                                                                      4,09,659/-.




https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

Claim Refund of the cost The Claimant The The Tribunal 9 of empty Gunny submits that the Respondent noted that Bags recovered Respondent has sought the recovered Rs. rejection of Respondent 4,43,946/- the claim, did not towards the contending dispute the cost of empty that under claimant’s cement bags Clause 33(3) contention despite there of the GCC that cement being no clause empty cement was issued in in the contract bags are HDPE bags authorising such departmental and offered recovery. It is property and no evidence urged that since that the of supply in empty cement Claimant gunny bags.

                                          bags are not     failed to     It held that
                                          the              return them.  the recovery
                                          Respondent’s     Hence,        made on this
                                          property under recovery of     basis was

Clause 33(3) of Rs. 2,95,964/- unjustified.

                                          the GCC, the     at Rs. 2 per  Accordingly,
                                          recovery is      bag was       the Tribunal
                                          without          rightly made. awarded Rs.
                                          contractual                    2,95,964/- to
                                          basis and                      the claimant.
                                          refund is
                                          sought.

                 Claim Refund of the      The Claimant                The                   The Tribunal
                 10    rebate of 19%      submits that it             Respondent            held that a
                       offered            relied on the               has sought            negative
                                          Respondent’s                rejection of          percentage
                                          planning and                the claim,            quoted in the
                                          cooperation to              contending            tender
                                          complete the                that the              constituted a
                                          work on time,               quoted rate           firm value
                                          but due to                  was based on          accepted by
                                          misrepresentati             the Claimant’s        the Railways
                                          on, suppression             own                   and could not
                                          of facts and                assessment,           be treated as
                                          failure of                  and that              a rebate.
                                          project                     delays arose          Since the
                                          management,                 from the              claimant had
                                          the rebate                  Claimant’s            not attached
                                          granted has no              failure to            any
                                          justification.              mobilize rigs,        conditions to
                                          Refund of the               batching plant        the rate


https://www.mhc.tn.gov.in/judis         ( Uploaded on: 23/09/2025 08:41:59 pm )



                                            rebate of 19%    and                              offered, the
                                            amounting to     manpower,                        claim was
                                            Rs.              except for                       found not
                                            1,33,32,164/-    minor delay in                   maintainable
                                            upto Bill No CC- handing over                     and was
                                            32 dated         encroached                       rejected.
                                            01.02.2006 is    portions for
                                            sought for from which
                                            the Respondent. extension was
                                                             granted.



                 Claim Refund of            The Claimant     The                              The Tribunal
                 11    recovery towards     submits that the Respondent                       found that
                       cost of excess       Respondent       has sought                       wastage for
                       consumption of       recovered Rs.    rejection of                     operational
                       cement               5,80,422/- for   the claim,                       procedures
                                            alleged excess contending                         like priming
                                            cement           that excess                      and testing is
                                            consumption,     cement                           an
                                            despite the      consumption                      "indispensabl
                                            Claimant         of 2477 bags                     e" and
                                            demonstrating arose due to                        "inevitable"
                                            that usage was wastage, pipe                      part of the
                                            within the       choking, and                     work. The
                                            supplied         finishing                        Respondent's
                                            quantities.      works. It is                     own
                                            Refund of the    further                          admission of
                                            recovered sum contended                           cement use
                                            is sought.       that recovery,                   for "touch up
                                                             including                        works" and
                                                             penalty, was                     "choking of
                                                             rightly made,                    pipeline"
                                                             and that the                     supported
                                                             Claimant had                     this.
                                                             signed the                       At the same
                                                             material                         time, the
                                                             reconciliation                   Tribunal
                                                             statements                       found the
                                                             and furnished                    Claimant
                                                             no-claim                         partly at fault
                                                             certificates.                    for not
                                                                                              keeping
                                                                                              separate
                                                                                              records of
                                                                                              cement used
                                                                                              for priming,


https://www.mhc.tn.gov.in/judis           ( Uploaded on: 23/09/2025 08:41:59 pm )



                                                                                              which led to
                                                                                              confusion.
                                                                                              Considering
                                                                                              this shared
                                                                                              responsibility,
                                                                                              the Tribunal
                                                                                              ordered 50%
                                                                                              reimburseme
                                                                                              nt of the
                                                                                              recovered
                                                                                              amount,
                                                                                              awarding Rs.
                                                                                              2,72,829/-.



                 Claim Loss of business     The Claimant      The           The majority
                 12                         submits that      Respondent    held that the
                                            delay of more     has sought    Respondent’s
                                            than 30 months rejection of     withholding
                                            in execution due the claim,     of funds
                                            to the            contending    caused the
                                            Respondent’s      that delays   claimant a
                                            breach caused     were caused   financial loss
                                            late return of    solely by the from erosion
                                            deposits and      Claimant’s    of money
                                            guarantees,       failure to    value due to
                                            resulting in a    mobilize      inflation.
                                            loss of potential materials,    Applying an
                                            profits of Rs.    skilled       Annual
                                            60,00,000 /-      manpower and Monetary
                                            from alternate    poor day to   Appreciation
                                            projects.         day           Rate (AMAR)
                                                              management. of 11.08%
                                                                            (derived from
                                                                            the average
                                                                            SBI lending
                                                                            rate) to the
                                                                            withheld
                                                                            sums, the
                                                                            majority
                                                                            calculated
                                                                            compensation
                                                                            at Rs.
                                                                            4,40,370/-.

                                                                                              One
                                                                                              arbitrator


https://www.mhc.tn.gov.in/judis           ( Uploaded on: 23/09/2025 08:41:59 pm )



                                                                                              dissented,
                                                                                              awarding NIL
                                                                                              on the
                                                                                              grounds that
                                                                                              the claim was
                                                                                              speculative,
                                                                                              the contract
                                                                                              barred
                                                                                              interest on
                                                                                              guarantees
                                                                                              and no proof
                                                                                              of potential
                                                                                              profit
                                                                                              existed.

                                                                                              Accordingly,
                                                                                              by majority,
                                                                                              the Tribunal
                                                                                              awarded Rs.
                                                                                              4,40,370/-
                                                                                              for the
                                                                                              money that
                                                                                              was wrongly
                                                                                              withheld.

                 Claim Interest charges     The Respondent       The            The claim for
                 13    on the amount of     unduly delayed       Respondent     interest on
                                            payment of the
                       final bill and       final bill and
                                                                 has sought     delayed
                       security deposit     retention of the     rejection  of  release of
                                            security deposit     the claim,     security
                                            and performance      contending     deposit
                                            guarantee,           that delay in  amounts to
                                            depriving the
                                            Claimant of rightful
                                                                 final payment double
                                            funds. The           was solely due compensation
                                            Respondent is        to the         and is barred
                                            liable to pay        Claimant’s     under Clause
                                            interest of          defaults in    16(3) of the
                                            Rs.8,13,935/-
                                            (Rs.1,46,227 on      providing a    GCC, which

the final bill and site engineer, expressly Rs.6,67,708 on finalising prohibits security/guarantee) measurements payment of at 18% p.a. from , and scrutiny interest on due dates to actual payment from of documents. amounts due 10.12.2004 to It is urged to the 03.02.2006. that no contractor.

                                                                        interest is           Since this
                                                                        payable.              clause


https://www.mhc.tn.gov.in/judis           ( Uploaded on: 23/09/2025 08:41:59 pm )



                                                                                                  governs the
                                                                                                  contract, the
                                                                                                  tribunal holds
                                                                                                  that the
                                                                                                  claimant’s
                                                                                                  demand for
                                                                                                  interest on
                                                                                                  delayed
                                                                                                  payment of
                                                                                                  the final bill
                                                                                                  is untenable
                                                                                                  and therefore
                                                                                                  rejected.




8.The learned counsel for the claimant submitted that the findings that

were rendered by the Arbitral Tribunal insofar as Claim Nos.1, 2, 3, 5, 6 and 7

are concerned, it is unintelligible and it suffers from perversity and the same is

liable to be interfered by this Court. The learned counsel in order to substantiate

his submission, relied upon the following judgments:

a) Associate Builders .Vs. Delhi Development Authority reported in (2015) 3 SCC 49

b) Ssangyong Engineering & Construction Company Limited Vs. National Highways Authority of India (NHAI) reported in (2019) 15 SCC 131

c) Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd., reported in (2019) 20 SCC 1

d) Gayatri Balasamy v. ISG Novasoft Technologies Ltd., reported in (2025) 7 SCC 1

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

9.Per contra, the learned Standing Counsel appearing on behalf of the

Southern Railways justified the findings rendered by the Arbitral Tribunal

insofar as all the claims are concerned except Claim Nos.5, 8 and 12 are

concerned. The learned Standing Counsel further submitted that out of the total

claim amount of Rs.45,33,700/-, already the Southern Railways has paid a sum

of Rs.36,00,000/- to the claimant.

10.This Court has carefully considered the submissions made on either

side and the materials available on record.

11.Insofar as the Judicial approach that is expected while dealing with a

petition under Section 34, it will be relevant to take note of the judgment of the

Apex Court in Associate Builders case referred supra and the relevant portion

is extracted hereunder:

28. In a recent judgment, ONGC Ltd. v. Western Geco International Ltd. [(2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , this Court added three other distinct and fundamental juristic

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

principles which must be understood as a part and parcel of the fundamental policy of Indian law. The Court held : (SCC pp. 278-

80, paras 35 & 38-40)

“35. What then would constitute the ‘fundamental policy of Indian law’ is the question. The decision in ONGC [(2003) 5 SCC 705 : AIR 2003 SC 2629] does not elaborate that aspect. Even so, the expression must, in our opinion, include all such fundamental principles as providing a basis for administration of justice and enforcement of law in this country. Without meaning to exhaustively enumerate the purport of the expression ‘fundamental policy of Indian law’, we may refer to three distinct and fundamental juristic principles that must necessarily be understood as a part and parcel of the fundamental policy of Indian law. The first and foremost is the principle that in every determination whether by a court or other authority that affects the rights of a citizen or leads to any civil consequences, the court or authority concerned is bound to adopt what is in legal parlance called a ‘judicial approach’ in the matter. The duty to adopt a judicial approach arises from the very nature of the power exercised by the court or the authority does not have to be separately or additionally enjoined upon the fora concerned. What must be remembered is that the importance of a judicial approach in judicial and quasi-judicial determination lies in the fact that so long as the court, tribunal or the authority exercising powers that affect the rights or obligations of the parties before them shows fidelity to judicial approach, they cannot act in an arbitrary, capricious or whimsical manner. Judicial approach ensures that the authority acts bona fide and deals with the subject in a fair, reasonable and objective manner and that its decision is not actuated by any extraneous consideration. Judicial approach in that sense acts as a check against flaws and faults

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

that can render the decision of a court, tribunal or authority vulnerable to challenge.

***

38. Equally important and indeed fundamental to the policy of Indian law is the principle that a court and so also a quasi- judicial authority must, while determining the rights and obligations of parties before it, do so in accordance with the principles of natural justice. Besides the celebrated audi alteram partem rule one of the facets of the principles of natural justice is that the court/authority deciding the matter must apply its mind to the attendant facts and circumstances while taking a view one way or the other. Non-application of mind is a defect that is fatal to any adjudication. Application of mind is best demonstrated by disclosure of the mind and disclosure of mind is best done by recording reasons in support of the decision which the court or authority is taking. The requirement that an adjudicatory authority must apply its mind is, in that view, so deeply embedded in our jurisprudence that it can be described as a fundamental policy of Indian law.

39. No less important is the principle now recognised as a salutary juristic fundamental in administrative law that a decision which is perverse or so irrational that no reasonable person would have arrived at the same will not be sustained in a court of law. Perversity or irrationality of decisions is tested on the touchstone of Wednesbury [Associated Provincial Picture Houses Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 : (1947) 2 All ER 680 (CA)] principle of reasonableness. Decisions that fall short of the standards of reasonableness are open to challenge in a court of law often in writ jurisdiction of the superior courts but no less in statutory processes wherever the same are available.

40. It is neither necessary nor proper for us to attempt an exhaustive enumeration of what would constitute the fundamental policy of Indian law nor is it possible to place the expression in

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

the straitjacket of a definition. What is important in the context of the case at hand is that if on facts proved before them the arbitrators fail to draw an inference which ought to have been drawn or if they have drawn an inference which is on the face of it, untenable resulting in miscarriage of justice, the adjudication even when made by an Arbitral Tribunal that enjoys considerable latitude and play at the joints in making awards will be open to challenge and may be cast away or modified depending upon whether the offending part is or is not severable from the rest.”

12.It is also relevant to take note of the judgment of the Apex Court in

Ssangyong Engineering & Construction Company case referred supra and

the relevant portion is extracted hereunder:

76. However, when it comes to the public policy of India,

argument based upon "most basic notions of justice", it is clear

that this ground can be attracted only in very exceptional

circumstances when the conscience of the Court is shocked by

infraction of fundamental notions or principles of justice. It can be

seen that the formula that was applied by the agreement

continued to be applied till February 2013 - in short, it is not

correct to say that the formula under the agreement could not be

applied in view of the Ministry's change in the base indices from

1993-1994 to 2004-2005. Further, in order to apply a linking

factor, a Circular, unilaterally issued by one party, cannot possibly

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

bind the other party to the agreement without that other party's

consent. Indeed, the Circular itself expressly stipulates that it

cannot apply unless the contractors furnish an

undertaking/affidavit that the price adjustment under the Circular

is acceptable to them. We have seen how the appellant gave

such undertaking only conditionally and without prejudice to its

argument that the Circular does not and cannot apply. This being

the case, it is clear that the majority award has created a new

contract for the parties by applying the said unilateral Circular and

by substituting a workable formula under the agreement by

another formula dehors the agreement. This being the case, a

fundamental principle of justice has been breached, namely, that

a unilateral addition or alteration of a contract can never be

foisted upon an unwilling party, nor can a party to the agreement

be liable to perform a bargain not entered into with the other

party. Clearly, such a course of conduct would be contrary to

fundamental principles of justice as followed in this country, and

shocks the conscience of this Court. However, we repeat that this

ground is available only in very exceptional circumstances, such

as the fact situation in the present case. Under no circumstance

can any court interfere with an arbitral award on the ground that

justice has not been done in the opinion of the Court. That would

be an entry into the merits of the dispute which, as we have seen,

is contrary to the ethos of Section 34 of the 1996 Act, as has

been noted earlier in this judgment.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

13.Insofar as the scope of Section 31 and the triple test applied in Dyna

Technologies case referred supra, the relevant portions are extracted hereunder:

34.The mandate under Section 31(3) of the Arbitration Act is to have reasoning which is intelligible and adequate and, which can in appropriate cases be even implied by the courts from a fair reading of the award and documents referred to thereunder, if the need be. The aforesaid provision does not require an elaborate judgment to be passed by the arbitrators having regard to the speedy resolution of dispute.

35. When we consider the requirement of a reasoned order, three characteristics of a reasoned order can be fathomed. They are:

proper, intelligible and adequate. If the reasonings in the order are improper, they reveal a flaw in the decision-making process. If the challenge to an award is based on impropriety or perversity in the reasoning, then it can be challenged strictly on the grounds provided under Section 34 of the Arbitration Act. If the challenge to an award is based on the ground that the same is unintelligible, the same would be equivalent of providing no reasons at all. Coming to the last aspect concerning the challenge on adequacy of reasons, the Court while exercising jurisdiction under Section 34 has to adjudicate the validity of such an award based on the degree of particularity of reasoning required having regard to the nature of issues falling for consideration. The degree of particularity cannot be stated in a precise manner as the same would depend on the complexity of the issue. Even if the Court comes to a conclusion that there were gaps in the reasoning for the conclusions reached by the Tribunal, the Court needs to have regard to the documents submitted by the parties and the contentions raised before the Tribunal so that awards with inadequate reasons are not set aside in casual and cavalier manner. On the other hand, ordinarily unintelligible awards are to be set aside, subject to party autonomy to do away with the reasoned award. Therefore, the courts are required to

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

be careful while distinguishing between inadequacy of reasons in an award and unintelligible awards.

14.Keeping the above principles in mind, this Court will test the

reasoning given by the Arbitral Tribunal and the decision arrived at for each

claim.

15.Insofar as the first claim is concerned, it is basically a claim made for

escalation in cost due to the delay in the completion of the work.

16.The Arbitral Tribunal came to a categorical conclusion that the nature

of work was such that it was highly unlikely that the work could have been

completed in 12 months. However, a time frame of 12 months was fixed under

the contract. The time was not the essence of the contract since the Southern

Railways was granting several time extensions under Clause 17(2) of GCC.

The Tribunal found that it is the Southern Railways which was responsible for

the delay. Having rendered such a finding, the Tribunal went on to apply, Price

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

Variation Clause [PVC] formula for calculating the compensation for escalation

in cost.

17.In the considered view of this Court, the contract is of the year 2000

and the work was completed in the year 2004 and at that point of time, this PVC

formula was not even in force. This came into existence only in the year 2011.

Hence, as a fundamental principle, the Tribunal ought not to have applied the

PVC formula for a contract which came into existence much before the coming

into force of this formula. The error in applying this formula further gets even

more bad since both the parties were not put on notice and were not heard on

the application of the PVC formula. Therefore, it clearly amounts to violation

of principles of natural justice. If the claimant had been informed that the PVC

formula is going to be applied, atleast the claimant would have the opportunity

to oppose the same and the Tribunal should have considered the said objection.

Since this basic procedure was not followed, the Tribunal fell in error by

applying PVC formula for calculating the escalation in cost.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

18.Yet another error that was committed by the Tribunal is that the

Tribunal unilaterally without any basis fixed a period of 18 months as a

reasonable completion period. After doing so, the Tribunal took into

consideration only the period from 18.6.2001 for computation of escalation

cost.

19.There is yet another error committed by the Tribunal by apportioning a

delay of five months on the claimant. There was absolutely no scientific basis

for attributing this delay on the claimant and it was done merely on conjectures

and surmises. In the light of the above discussion, the compensation that was

computed under the heading escalation of cost suffers from patent illegality and

the reasoning is also unintelligible. Thus, there was no justification in limiting

the compensation amount to Rs.9,24,035/- under this head and the claimant will

be entitled for 30% increase in the rates by restricting the same to the quantum

of work done during the extended period and the amount claimed by the

claimant has to be necessarily awarded.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

20. The next claim pertains to the payment for the additional quantity of

coffer dam arrangements made by the claimant. Under this claim, the claimant

had provided necessary coffer dams in certain locations when the piles and tie

beams came within the close proximity to the canal necessitating creation of

working space by means of temporary coffer dams to arrest the flow of running

water as well as heavy seepage.

21.While deciding this issue, the Arbitral Tribunal has taken into

consideration an enquiry that was made from some persons who were residents

living adjacent to the site. If the Tribunal makes any such enquiry and relies

upon the statements made by those persons, obviously the claimant must be put

on notice and such statements cannot be recorded behind the back of the

claimant. This will clearly tantamount to violation of principles of natural

justice. When the claimant had made a claim for 1720 meters by providing all

the particulars, the Tribunal has restricted to 858.4389 meters and such

reduction has been made on mere conjectures and even the rates have been

reduced on ad hoc basis. This procedure followed by the Tribunal is in violation

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

of Section 28(2) of the Act, which provides as follows:

28(2) Th e

only if the parties have expressly authorised it to do so.

22.Even in technical arbitrations, the arbitrators cannot render findings on

mere conjectures and on ad hoc basis. There must be some scientific basis for

rendering findings. If that is done, the Court cannot sit over such findings of a

specialist. In this case, the findings that have been rendered for Claim No.2 and

the final compensation arrived at clearly suffers from non compliance of Section

28(2) of the Act, violation of principles of natural justice, patent illegality and it

is also unintelligible. Therefore, the compensation that was claimed by the

claimant under this head has to be granted.

23.Insofar as the third claim is concerned, the claimant claimed

compensation for removal of station building works. This claim was made with

the support of the letter dated 22.02.2001 [Ex.P.14] entrusting station building

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

works to the claimant. Despite this exhibit, the Tribunal without any reason

concluded that there is no reduction in scope merely because the over all

executed value exceeded 3.73 %. The Tribunal has gone to the extent of

holding that since there was no agreement for carrying out this work, there is no

justification for making the claim. This finding disregards the evidence

available and also it violates principles of natural justice. Moreover, the

findings of the Tribunal insofar as Claim No.3 is concerned suffers from patent

illegality due to ignorance of vital evidence. Accordingly, the claimant has

sought for 10% of the excluded work value of Rs.80,00,000/- amounting to

Rs.8,00,000/-. The quantum of compensation claimed by the claimant is

reasonable and it has some basis and it ought to have been granted by the

Tribunal.

24.The next issue pertains to Claim No.5 which has been put to challenge

both by the claimant as well as the Southern Railways. Claim No.5 pertains to

loss of profits and overheads. This claim was made due to prolongation and

variation in work. While discussing this claim, the entire finding has been

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

rendered in favour of the claimant and the Tribunal also holds that the claimant

deserves to be compensated for the lost opportunity by way of reasonable

compensation. The compensation that has been arrived at for Claim No.5 is

reasonable and the view taken by the Tribunal is probable and plausible view.

Hence, no interference is warranted.

25.Insofar as Claim No.6 is concerned, it pertains to payments for other

works done not covered by the agreement. The Tribunal has rejected this claim

on the ground that till the final bill was submitted, the claimant did not even

make any claim under this head.

26.Clause 43(1) of GCC provides that the contractor shall prepare and

furnish the engineers once in every month an account giving full and detailed

particulars of all claims for any additional expenses to which the contractor may

consider himself entitled to and all the extra and additional works ordered by

the engineer. Since this condition was not complied with, this claim has been

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

rejected. The view taken by the Tribunal is a possible and plausible view and

just because another view is possible for this Court, that is not a ground to

interfere under Section 34 of the Act.

27.Insofar as the Claim No.7 is concerned, it deals with compensation for

idle labour. The Tribunal has rendered a finding that since compensation has

been granted for Claim Nos.1 and 5, no separate compensation can be granted

for idle labour. Under this claim, the Tribunal ignored documentary evidence

on variation and prolongation which resulted in the machinery and labour being

kept idle due to respondent's failure to issue drawings. This Court must only

examine as to whether ignoring such evidence had any impact on the final

conclusion arrived at by the Tribunal. Claim No.1 pertained to escalation cost

and Claim No.5 pertained to loss of profits and overheads. The Tribunal felt

that since compensation is given under these heads, no separate compensation is

required under this head. This view taken by the Tribunal is a plausible view

which does not require the interference of this Court.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

28.Insofar as the findings rendered by the Tribunal for Claim Nos.8 - 13,

this Court finds that the reasoning given by the Tribunal does not suffer from

any perversity and the compensation that was fixed under Claim Nos.8, 9, 11

and 12 are reasonable. Therefore, the same does not warrant the interference of

this Court.

29.The upshot of the above discussion is that except Claim Nos.1, 2 and 3

where this Court has interfered with the award passed by the Arbitral Tribunal,

the findings rendered with respect to the other claims are hereby sustained.

30.The next issue is as to whether the invalid portion of the award is

severable from the valid portion of the award and the award can be modified.

Useful reference can be made to the judgment of the Apex Court in Gayatri

Balasamy v. ISG Novasoft Technologies Ltd reported in (2025) 7 SCC 1.

87. Accordingly, the questions of law referred to

by Gayatri Balasamy [Gayatri Balasamy v. ISG Novasoft

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

Technologies Ltd., 2024 SCC OnLine SC 1681] are

answered by stating that the Court has a limited power

under Sections 34 and 37 of the 1996 Act to modify the

arbitral award. This limited power may be exercised under

the following circumstances:

87.1. When the award is severable, by severing the “invalid” portion from the “valid” portion of the award, as held in Part II of our Analysis;

87.2. By correcting any clerical, computational or typographical errors which appear erroneous on the face of the record, as held in Parts IV and V of our Analysis;

87.3. Post-award interest may be modified in some

circumstances as held in Part IX of our Analysis; and/or

87.4. Article 142 of the Constitution applies, albeit, the

power must be exercised with great care and caution and

within the limits of the constitutional power as outlined in

Part XII of our Analysis.

"5. Extent of judicial intervention.-Notwithstanding

anything contained in any other law for the time being in

force, in matters governed by this Part, no judicial authority

shall intervene except where so provided in this Part.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

31. Form and contents of arbitral award.-(1) An arbitral

award shall be made in writing and shall be signed by the

members of the Arbitral Tribunal.

(2) For the purposes of sub-section (1), in arbitral

proceedings with more than one arbitrator, the signatures of

the majority of all the members of the Arbitral Tribunal shall

be sufficient so long as the reason for any omitted signature

is stated.

(3) The arbitral award shall state the reasons upon

which it is based, unless-

(a) the parties have agreed that no reasons are to be given;

or

(b) the award is an arbitral award on agreed terms under

Section 30.

(4) The arbitral award shall state its date and the

place of arbitration as determined in accordance with

Section 20 and the award shall be deemed to have been

made at that place.

(5) After the arbitral award is made, a signed copy

shall be delivered to each party.

(6) The Arbitral Tribunal may, at any time during the

arbitral proceedings, make an interim arbitral award on any

matter with respect to which it may make a final arbitral

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

award.

(7)(a) Unless otherwise agreed by the parties, where

and insofar as an arbitral award is for the payment of money,

the Arbitral Tribunal may include in the sum for which the

award is made interest, at such rate as it deems reasonable,

on the whole or any part of the money, for the whole or any

part of the period between the date on which the cause of

action arose and the date on which the award is made.

(b) A sum directed to be paid by an arbitral award

shall, unless the award otherwise directs, carry interest at

the rate of two per cent higher than the current rate of

interest prevalent on the date of award, from the date of

award to the date of payment.

Explanation.-The expression "current rate of interest" shall

have the same meaning as assigned to it under clause (b) of

Section 2 of the Interest Act, 1978 (14 of 1978).

(8) The costs of an arbitration shall be fixed by the

Arbitral Tribunal in accordance with Section 31-A.

31.The interference into Claim Nos.1, 2 and 3 are certainly a severable

part and the award passed by the Arbitral Tribunal can be modified insofar as

Claim Nos.1, 2 and 3 are concerned.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

32.In the light of the above findings, insofar Claim No.1 is concerned,

the entire compensation sought for by the claimant with respect to increase of

30% of value of work done during the extended period for the quantum of work

done during the extended period is granted. Accordingly, compensation of

Rs.1,22,12,625/- has to be paid by the Southern Railways to the claimant under

this head.

33.Insofar as Claim No.2 is concerned, for payment of additional quantity

of coffer dam arrangements made, the claimant is entitled to be paid a total

compensation of Rs.96,95,000/- as claimed by the claimant.

34.Insofar as Claim No.3 is concerned, for payment towards removal of

station building works, the claimant is entitled to be paid a total compensation

of Rs.8,00,000/- as claimed by the claimant.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

35.In the result, OP.No.60 of 2018, filed by the Southern Railways is

dismissed. Arb.OP(Com.Div.).No.77 of 2021, filed by the claimant is partly

allowed and the decision arrived at by the Tribunal insofar as Claim Nos.1, 2

and 3 are concerned stands modified and there shall be a direction to the

Southern Railways to pay a compensation of Rs.1,22,12,625/- for

Claim No.1, a compensation of Rs.96,95,000/- for Claim No.2 and a

compensation of Rs.8,00,000/- for Claim No.3 and it shall be paid along with

interest at the rate of 18% p.a., from the date of filing of the petition i.e., from

10.7.2021 till the date of actual payment. These amounts shall be paid by the

Southern Railways to the Claimant within a period of eight (8) weeks from the

date of receipt of the order with interest. No costs.

23-09-2025 Index:Yes Speaking Neutral Citation:Yes KP

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

To

1.Engineering Products (I) Limited, 3D, EC Chambers, No.92, G.N.Chetty Street, T.Nagar, Chennai-600 017.

2.Mr.S.Balachandran Chief Electrical Engineer, Delhi Metro Rail Corporation Limited, Kochi.

3.Mr.A.K.Sinha Chief Palnning and Development Engineer, Chennai-600 003.

4.Mr.K.Govindasai Babu Deputy Financial Adviser and Chief Accounts Officer, Headquarters Office, Southern Railway, Chennai-600 003.

5.The Chief Engineer, Mtp (railways) Southern Railways, Egmore, Chennai 600 008

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

N.ANAND VENKATESH J.

kp

AND ARB O.P(COM.DIV.) NO. 77 OF 2021

...

23-09-2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/09/2025 08:41:59 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter