Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.I.K.Construction vs M/S.Sathyam Educational Trust
2025 Latest Caselaw 6352 Mad

Citation : 2025 Latest Caselaw 6352 Mad
Judgement Date : 24 April, 2025

Madras High Court

M/S.I.K.Construction vs M/S.Sathyam Educational Trust on 24 April, 2025

Author: G.R.Swaminathan
Bench: G.R.Swaminathan
                                                                           AS.(MD)Nos.53 of 2019 & 174 of 2021

                          BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                         Reserved On              : 07.03.2025

                                        Pronounced On             : 24.04.2025

                                                       CORAM

                            THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN
                                               AND
                               THE HON'BLE MR.JUSTICE M.JOTHIRAMAN

                                    A.S.(MD)Nos.53 of 2019 & 174 of 2021

                     A.S.(MD)No.53 of 2019

                     M/s.I.K.Construction,
                     Rep.by its Proprietor,
                     I.Kezhson, S/o.Issac,
                     No.14/109-A, Azhagiapandiapuram,
                     Thadikkarankonam Village,
                     Thovalai Taluk,
                     Kanyakumari District                                            ... Appellant/Plaintiff

                                                            Vs.

                     1.M/s.Sathyam Educational Trust,
                       Rep.by its Chairman,
                       A.Thinagar, S/o.Athisayaraja,
                       No.35/B5, Anitha Illam,
                       Saragunaveethi North,
                       Nagercoil, Nagercoil Village,
                       Agastheeswaram Taluk,
                       Kanyakumari District.

                     2.T.Athisayaraja
                     3.A.Thanalakshmi
                     4.A.Kanimozhy                                          ... Respondents/Defendants

                     1/36




https://www.mhc.tn.gov.in/judis            ( Uploaded on: 25/04/2025 03:23:24 pm )
                                                                              AS.(MD)Nos.53 of 2019 & 174 of 2021




                     PRAYER : First Appeal filed under Section 96 of the Code of Civil
                     Procedure against the Judgement and Decree dated 28.04.2018 made in
                     O.S.No.124 of 2012 on the file of the District Judge, Kanyakumari
                     District at Nagercoil.


                                  For Appellant          : Mr.S.R.Rajagopal,
                                                           Senior Counsel,
                                                           for Mr.Puhzh Gandhi

                                  For R1                 : Mr.Veerakathiravan,
                                                           Senior Counsel,
                                                           for Mr.M.P.Senthil

                                  For R2 & R3            : No Appearance


                     A.S.(MD)No.174 of 2021

                     1.M/s.Sathyam Educational Trust,
                       Rep.by its Chairman,
                       A.Thinagar,
                       S/o.Athisayaraja,
                       No.35/B5, Anitha Illam,
                       Saragunaveethi North,
                       Nagercoil, Nagercoil Village,
                       Agastheeswaram Taluk,
                       Kanyakumari District.

                     2.T.Athisayaraja

                     3.A.Thanalakshmi
                     4.A.Kanimozhy                                                ... Appellants/Defendants

                                                              Vs.

                     2/36




https://www.mhc.tn.gov.in/judis               ( Uploaded on: 25/04/2025 03:23:24 pm )
                                                                                  AS.(MD)Nos.53 of 2019 & 174 of 2021

                     M/s.I.K.Construction,
                     Rep.by its Proprietor,
                     I.Kezhson, S/o.Issac,
                     No.14/109-A, Azhagiapandiapuram,
                     Thadikkarankonam Village,
                     Thovalai Taluk,
                     Kanyakumari District.                                                  ... Respondent/Plaintiff


                     PRAYER : First Appeal filed under Section 96 of the Code of Civil
                     Procedure against the Judgement and Decree dated 28.04.2018 made in
                     O.S.No.124 of 2012 on the file of the District Judge, Kanyakumari
                     District at Nagercoil.


                                       For Appellants        : Mr.Veerakathiravan,
                                                               Senior Counsel,
                                                               for Mr.M.P.Senthil

                                       For R1                : Mr.S.R.Rajagopal,
                                                               Senior Counsel,
                                                               for Mr.Puhazh Gandhi



                                                 COMMON JUDGMENT

(Judgment of this Court was delivered by M.JOTHIRAMAN J.)

The plaintiff preferred an appeal in AS.(MD)No.53 of 2019 to set

aside and modify the judgment and decree dated 28.04.2018 passed in

O.S.No.124 of 2012. Unsuccessful defendants have preferred an appeal

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

in AS.(MD)No.174 of 2021 to set aside the judgment and decree dated

28.04.2018 passed in O.S.No.124 of 2012.

2.For the sake of convenience, the parties are referred to as their

rank before the trial Court.

3.The plaintiff, ie., M/s.I.K.Construction, represented by its

Proprietor, I.Kezhon, has been filed a suit for recovery of money of

Rs.2,67,88,900/-, Rs.31,40,400/- and Rs.11,48,700/- with future interest

at the rate of 12% per annum from the date of last demand till the date of

realization and cost. The suit was decreed by the learned District Judge

vide judgment dated 28.04.2018 with cost and the defendant was directed

to pay a sum of Rs.3,10,78,000/- (less Rs.25,00,000/- which was paid as

per order of Hon'ble High Court) with future interest at the rate of 6% per

annum from the date of suit till the date of realization. Aggrieved over

the same, the plaintiff challenging the portion of the decree, in respect of

6% interest to the principal amount, appeal in AS.(MD)No.53 of 2019

has been filed. Aggrieved over the decree and judgment, the defendants

have preferred an appeal in AS.(MD)No.174 of 2021.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

4.The case of the plaintiff in brief as follows:-

The plaintiff is the proprietor of M/s.I.K.Construction and the first

defendant is the Chairman of the Sathyam Educational Trust. They

entered into three separate construction agreement dated 29.08.2008. As

per the agreement, the main building first block ground floor, first floor

and second floor at the rate of Rs.650/, Rs.700/- and Rs.800/- per square

feet respectively. Office building ground floor and first floor at the rate

of Rs.700/- and Rs.800/- per square feet respectively. Main building

second block ground floor, first floor and second floor at the rate of Rs.

650/-, Rs.700/- and Rs.800/- per square feet respectively. The total

amount for construction of main building first block consisting of ground

floor, first floor and second floor is Rs.3,54,88,900/-. On 29.08.2008, a

sum of Rs.25,00,000/-, on 20.09.2008 a sum of Rs.15,00,000/- and on

09.01.2010, a sum of Rs.47,00,000/- was paid by the first defendant for

the main building. The balance amount is Rs.2,67,88,900/-. Similarly,

the first defendant paid cost of construction, ie., Rs.10,00,000/- for

constructing office building on 29.08.2008 and on 20.09.2008 a sum of

Rs.20,00,000/- was paid. Totally a sum of Rs.30,00,000/- was paid and

balance amount is Rs.31,40,400/-. The said balance amount to be paid

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

by the first defendant for construction of main building second block is

Rs.11,48,700/-. The first defendant issued three cheques dated

15.10.2009 and the same were dishonoured by the Bank. Subsequently

on 09.01.2010, the first defendant has paid a sum of Rs.47,00,000/-. The

plaintiff had completed the construction work for a sum of

Rs.4,53,03,000/-, but the first defendant has paid only a sum of

Rs.1,42,25,000/-. As such, an amount of Rs.3,10,78,000/- is illegally

retained by the defendant. The defendant attempted to complete the

construction work with the help of the third party. Hence, the plaintiff

initially filed a suit in O.S.No.392 of 2010 for the relief of permanent

injunction. In the above suit, status-quo was granted, challenging the

same, the first defendant had preferred a revision before this Hon'ble

Court in CRP.(MD)Nos.2734 & 2753 of 2010 to struck off the said

plaint. In the course of hearing of CRP, an Advoate Commissioner was

appointed to look into the construction work already finished by the

plaintiff. The Commissioner filed a report on 15.02.2011. In the earlier

suit, status-qua was granted and subsequently it was stayed by this

Hon'ble Court. Now, the plaintiff's construction work is stopped. Hence,

the present suit is not hit by Order II Rule 2 of the Code of Civil

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

Procedure. Therefore, the plaintiff is entitled for recovery, a sum of Rs.

3,10,78,000/- from the defendants with interest at the rate of 12% per

annum from the date of plaint till the date of realization. Hence, the suit.

5.Brief averments stated in the written statement filed by the first and

second defendants are as follows:-

The first defendant has admitted the agreements and as per the

terms of the agreements, entire construction work should be completed,

within six months, so as to enable the first defendant to commence the

educational activities from the academic year 2009-2010. The first

defendant has admitted that he has paid a sum of Rs.55,00,000/- on

29.08.2008 and a sum of Rs.40,00,000/- on 20.09.2008 respectively. The

plaintiff has not specifically mentioned the date of completion of the

construction work in the plaint averments. The plaintiff had failed to

complete the construction work within the time fixed in the construction

agreement and thereby committed breach of contract. Thereafter, the

first defendant engaged a new contractor to continue the construction

work and complete the work in respect of two buildings. The plaintiff

remained silent and while the first defendant has proceeded with

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

construction work by engaging new contractor. Moreover, the plaintiff

has also received a sum of Rs.47,00,000/- on 09.01.2010 towards full and

final settlement. After receipt of the above said amount plaintiff started

demanding huge lump sum towards settlement. The plaintiff filed

complaints under Section 138 of the Negotiable Instruments Act, 1881

against the first defendant in C.C.Nos.240, 241 and 242 of 2010. At the

instigation of the plaintiff, his friend one Boothalingam Pillai, also filed a

complaint under Section 138 NI Act in C.C.Nos.198 and 209 of 2010.

As per clause 6 of the construction agreement dated 29.08.2008, after the

completion of work, the contractor has to serve written notice to the

defendant to conduct joint survey. But the plaintiff did not make any

request to conduct joint survey. The plaintiff already filed a suit in

O.S.No.392 of 2010 seeking permanent injunction. The plaintiff failed to

claim the balance amount in the prior suit itself. Therefore, the

subsequent suit is hit by Order II Rule 2 of Code of Civil Procedure.

Hence, the suit is liable to be dismissed with costs.

6.Based on the above pleadings, the trial Court has framed the following

issues:-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

1.Whether the plaintiff and defendant entered into three agreements for construction of building for Satyam College of Engineering at Kumarapuram, Aralvoimozhy?

2.Whether the defendant breached the contract and failed to pay the payment periodically to the plaintiff?

3.Whether the plaintiff was lethargic and slow in carrying of the construction work?

4.Whether the defendants have engaged new contract to complete the construction work?

5.Whether he suit is barred under Order 2, Rule 2 of CPC?

6.Whether the plaintiff is entitled to recover a sum of Rs.2,67,88,900/- with future interest at the rate of 12% per annum in respect of the main building first block ground floor, first floor and second floor?

7.Whether the plaintiff is entitled to recover a sum of Rs.31,40,400/- with future interest at the rate of 12% per annum in respect of the office building ground floor?

8.Whether the plaintiff is entitled to recover a sum of Rs.11,48,700/- with future interest at the rate of 12% per annum in respect of the main building second block ground floor?

9.To what relief, if any, the plaintiff is entitled?

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

7.On the side of the plaintiff, plaintiff himself examined as P.W.1,

Thiru.Navaretnam was examined as P.W.2 and Thiru.R.Lingarajan was

examined as P.W.3 and Ex.A1 to Ex.A45 and Ex.X1 were marked. On

the side of the defendants, the first defendant himself examined as D.W.1

and Thiru.S.Murugan was examined as D.W.2 and Ex.B1 to Ex.B60 were

marked.

8.Findings of the trial Court:-

i)The suit is not barred under Order II Rule 2 CPC.

ii)The first defendant was defaulted to pay construction cost as per

terms of the construction agreements.

iii)The plaintiff was continued construction work till 09.04.2010

merely on basis of dishonoured cheques and the main building were fully

constructed by the plaintiff.

iv)The Commissioner's report filed in M.P.No.1 of 2011 in CRP.

(MD)No.2753 of 2010 is also supported to the case of the plaintiff.

v)The first defendant himself admitted the claim amount, as per

Ex.A33.

vi)The case of the plaintiff has been proved through the evidence

of P.W.2 and P.W.3.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

9.Points for determination arises in these appeals is that

i)Whether the plaintiff has put up the construction as claimed for?

ii)Whether the first defendant has put up the construction as

claimed for?

iii)Whether the plaintiff is breached the contract as per the

agreements in Ex.A1 to Ex.A3?

iv)Whether the defendant/trust breached the contract and failed to

pay the payment periodically to the plaintiff?

v)Whether the plaintiff is entitled to recover the money as prayed

for in the suit?

10.The learned Senior Counsel appearing for the

appellants/defendants in A.S.(MD)No.174 of 2021 and first respondent /

first defendant in A.S.(MD)No.53 of 2019 would submit that the initial

onus of proof was not discharged by the plaintiff on the basis of the

evidence. No bills or invoice for procuring materials have been

produced. No bank transactions have been produced to substantiate the

payments made to the dealers of cement, bricks, iron rods and other raw

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

materials. He would further submit that no documentary evidence were

produced to substantiate the payments made to the masons, labours and

other workmen for completion of the construction. The trial Court

completely failed to consider the core issue that who has put up the

construction, there is no issue has been framed to that effect. No

adequate evidence or materials placed before the Court to claim huge

amount of Rs.3,10,78,000/- and absolutely no breakups have been filed.

11.The learned Senior Counsel further would submit that with

regard to the first block in the main building, a huge claim of Rs.

1,31,65,300/- has been made as if the entire construction has been over in

the second floor, but the Commissioner's report marked as Ex.A18

completely falsifies the case of the plaintiff. With regard to the second

block in main building, ground floor itself has not been completed and

there is no basis for claiming a sum of Rs.36,73,700/-. There is

absolutely no material particulars in the plaint in O.S.No.392 of 2010 as

well as the subsequent suit in O.S.No.124 of 2012 relating to the date of

completion of the construction. In O.S.No.392 of 2010, the plaintiff has

taken a stand that the amount due from the first defendant is Rs.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

3,10,78,000/- and there is no specific averment relating to the stage of

the construction as well as the work done by the plaintiff. The plaintiff

has not come with clean hands and he has produced false evidence and

also made false claims. In spite of specific date stipulated to complete

the construction, the plaintiff has not discharged his part of performance

and he did not proceed with the construction as per the terms of the

contract. The plaintiff has not sent any notice to the first defendant as

per the Clause 5 of the terms and conditions of the construction contract.

The trial Court completely over-looked that the first defendant wanted to

start the Engineering College for the academic year 2009-2010. Only in

such circumstances, the time for completion of construction was fixed as

six months ie., on or before 01.03.2009. The plaintiff categorically

admitted that he did not complete the construction work as per the

construction agreement. The plaintiff has produced Ex.A26 to

substantiate as if the materials were transported through vehicles.

However, the said documents have been proved to be false and fabricated

one by production of Ex.B57. To strengthen his contention, he has relied

upon the following judgments reported in

(i)2019 (6) SCC 2 in Jagadish Prasad Patel (Dead) through

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

Legal representatives and another Vs. Shivnanth and others to show

the burden always lies on the plaintiff to make out and establish a clear

case for granting relief and the weakness, if any on the case set up by the

defendants would not be a ground to grant relief to the plaintiff.

(ii)2013 (15) SCC 161 in Sebastiao Luis Fernandes (Dead)

through Lrs & Ors. Vs. K.V.P.Shashtri (Dead) through Lrs & Ors to

show that in terms of Section 102 of the Indian Evidence Act, the initial

onus is always on the plaintiff and if he discharges that onus and makes

out a case which entitles him to a relief, the onus shifts to the defendant

to prove those circumstances, if any which would disentitle the plaintiff

to the same.

(iii)1998 (4) SCC 539 in Panjab Urban Planning &

Development Authority Vs M/S Shiv Saraswati Iron & Steel Re-Rolling

Mills to show that the plaintiff must succeed or fail on his own case and

cannot take advantage of weakness in the defendant/respondent's case to

get a decree.

12.Per contra, the learned Senior Counsel appearing for the

appellant / plaintiff in A.S.(MD)No.53 of 2019 and respondent / plaintiff

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

in A.S.(MD)No.174 of 2021 would submit that the plaintiff had

originally filed a suit in O.S.No.392 of 2010 for bare injunction

restraining the defendant trust from engaging any other contractor to

carry out remaining construction work unless balance amount due to the

plaintiff is duly settled. Thereafter, based on the cause of action for

recovery of dues under Ex.A1 to Ex.A3 and for damages, suit in O.S.No.

124 of 2012 has been filed. The cause of action in the suit O.S.No.124 of

2012 is independent and there is no question of O.S.No.124 of 2012

being hit by Order II Rule 2 of the Code of Civil Procedure. The

defendant had filed an Interlocutory Application in I.A.No.546 of 2012

in O.S.No.124 of 2012 to reject the plaint on the very same ground that

the suit is hit by Order II Rule 2 CPC and the said application was

dismissed by an order dated 15.12.2013 and the same was become final.

13.It is an admitted fact that the plaintiff and the first defendant

have entered into three agreements dated 29.08.2008 under Ex.A1 to

Ex.A3. The first defendant has also admitted that he had paid a sum of

Rs.55,00,000/- on 29.08.2008 and Rs.40,00,000/- on 20.09.2008. Ex.A1

to Ex.A3 agreements entered between the parties for construction of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

three buildings namely main building-first block, consisting ground

floor, first floor and second floor and office building consisting ground

floor and main building-second block, consisting ground floor, first floor

and second floor. In clause 5 of Ex.A1 to Ex.A3, it has been clearly set

out that the construction will be completed in six months with the terms

and conditions set out there. Clause 5 clearly states that 20% payment

shall be made on commencement of work and thereafter 20% at each

stage of progress in construction work. There is no whisper anywhere in

the written statement that the first defendant has paid the amounts as per

Ex.A1 to Ex.A3. Following table is the break-up of amounts:

                      Exhibit                 Total Amount (in Rs.)               20% (in Rs.)
                      A1                      3,54,88,900                         70,97,780
                      A2                      3,54,88,900                         70,97,780
                      A3                      1,31,58,000                         26,31,600
                      Total                   8,41,35,800                         1,68,27,160

D.W.1 admits that 20% advance amount is payable under Ex.A1 to

Ex.A3 and that only a sum of Rs.55,00,000/- has been paid by him to the

plaintiff on the date of agreements. Admittedly, the first defendant has

not paid the amount of Rs.1,68,27,160/-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

14.According to the plaintiff, balance amount payable to him as

mentioned in the plaint is as follows:-

A.Main Building First Block

Ground Floor 16536 sq.ft*650 - Rs.1,07,48,400.00 First Floor 16536 sq.ft*700 - Rs.1,15,75,200.00 Second Floor 16536 sq.ft*800 - Rs.1,31,65,300.00

Main Building Payment:

29.08.2008- Rs.25,00,000.00 20.09.2008- Rs.15,00,000.00 09.01.2010- Rs.47,00,000.00 Total Rs.87,00,000.00

----------------------

                                Balance       Rs.2,67,88,900.00
                                              -----------------------
                     B.Office Building works completed
                           Ground Floor 8772 sq.ft * 700 -Rs.61,40,400.00

                     Advanced of payment in different date
                         29.08.2008       Rs.10,00,000/-
                         20.09.2008       Rs.20,00,000/-                            -Rs.30,00,000.00
                                                                                     ---------------------
                                               Balance                               -Rs.31,40,400.00
                                                                                     ---------------------

                     C.Main Building Second Block

                         Ground Floor on construction
                         work not yet completed                                  -Rs.36,73,700.00
                     Advanced of payment in different date

                                  29.08.2008         Rs.20,00,000/-
                                  20.09.2008         Rs.5,25,000/-               -Rs.25,25,000.00
                                                                                 --------------------






https://www.mhc.tn.gov.in/judis                    ( Uploaded on: 25/04/2025 03:23:24 pm )
                                                                                 AS.(MD)Nos.53 of 2019 & 174 of 2021

                                                   Balance                      Rs.11,48,700.00
                                                                               ---------------------
                                                   Balance Payment

                                  A) Main Building First Block                 Rs.2,67,88,900.00
                                  B) Office Building                           Rs. 31,40,400.00
                                  C) Main Building Second Block                Rs. 11,48,700.00
                                                                               ----------------------
                                                   Total                       Rs.3,10,78,000.00
                                                                               ----------------------

It is also the case of the plaintiff that against the balance payable, the

defendant made partial payments by the below mentioned cheques.

1.Cheque No.105869 dated 15.10.2009 -Rs.25,78,000.00

2.Cheque No.105870 dated 15.10.2009 -Rs.20,00,000.00

3.Cheque No.105871 dated 15.10.2009 -Rs.20,00,000.00

15.As per terms of the agreement, entire building, ie., three

buildings are to be constructed within six months from the date of

agreement dated 29.08.2008, which means it has to be completed by

28.02.2009. According to the plaintiff, aforesaid three cheques were

dishonored and the defendant requested the plaintiff to continue the

construction work and subsequently, on 09.01.2010, the defendant has

paid a sum of Rs.47,00,000/- to the plaintiff for which a separate receipt

issued wherein both plaintiff and the defendant had signed. On the other

hand, there is no denial in the written statement. However, it was argued

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

that the payment of Rs.47,00,000/- was made towards full and final

settlement. To prove the said fact, there is no pleadings and evidence and

the same is not acceptable one.

16.A perusal of Ex.A1 to Ex.A3 agreements reveals that there is no

mention about the total area to be constructed or even there is no mention

about the approximate total area to be constructed. Ex.A7 is the legal

notice issued by the plaintiff to the first defendant dated 17.04.2010

wherein it has been stated that the cheque dated 15.10.2009 bearing No.

105869 for a sum of Rs.25,78,000/- has been dishonoured. Ex.A7 to

Ex.A9 are the legal notices issued by the plaintiff to the first defendant

for the issuance of above said three cheques, which have been

dishonoured and calling upon the first defendant to pay the amount.

Ex.A13 is the copy of the plaint in O.S.No.392 of 2010 on the file of the

Subordinate Court, Nagercoil wherein it has been stated that the plaintiff

completed the main building first block ground floor work having area of

16536 sq.ft of construction and 16530 sq.ft of construction in the first

floor and 16536 sq.ft of second floor. It is also stated that the plaintiff

completed construction work in the main building second block and area

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

of 16530 sq.ft and the plaintiff completed and as such a sum of Rs.

3,10,78,000/- is illegally retained by the defendant. Further, it has also

been stated about the aforesaid three cheques issued by the first

defendant and all three cheques were dishonoured and the proceedings

under Section 138 of the Negotiable Instruments Acts is also pending

before the Judicial Magistrate No.2, Nagercoil. In Ex.A13, there is no

whisper about the fact narrated in the plaint in O.S.No.124 of 2012 and

on 09.01.2010, the defendant has paid Rs.47,00,000/- to the plaintiff, for

which, separate receipt obtained and both were signed on it. Similarly in

the plaint in O.S.No.124 of 2012, it has been pleaded that the plaintiff

completed the construction work for a sum of Rs.4,53,03,000/- and the

defendant has paid only Rs.42,22,000/- and remaining balance of Rs.

3,10,78,000/-, whereas in Ex.A13, there is no mention about the

aforesaid facts.

17.The learned Senior Counsel appearing for the respondent /

plaintiff in A.S.No.174 of 2021 and the appellant / plaintiff in A.S.

(MD)No.53 of 2019 would submit that the important document is

Ex.A33 agreement of settlement dated 02.06.2014 wherein the defendant

has admitted his liability. The execution and attestation of Ex.A33 has

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

been proved in a manner known to law. There is no pleading denying

Ex.A33 and nothing has been elicited in cross examination regaring

Ex.A33.

18.The Notary Public, who notarized the document in Ex.A33,

namely, Mr.Navaratnam has been examined as P.W.2. P.W.2 speaks

about the execution of Ex.A33 and another document signed by D.W.1

for some other transaction on the same day as Ex.A33, which document

has been marked as Ex.X1. To prove the execution of the document,

P.W.3 one R.Lingarajan attesting witness has also been examined.

19.The learned Senior Counsel appearing for the defendant would

submit that the alleged Ex.A33 compromise deed dated 02.06.2014 was

obtained by way of coercion. The plaintiff with an intention to

criminally intimidate the first defendant, lodged a false complaint dated

09.04.2014, which resulted in registering case in Cr.No.22 of 2014 by the

Anti-Land Grabbing Special Cell/DCB, Nagercoil. Based on the said

complaint, the Police authorities arrested the appellant/defendant and he

came out on bail on 16.05.2014 and appeared before the jurisdictional

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

police station regularly from 27.05.2014 till 02.07.2014. During that

period, the plaintiff with an aid of Police authorities coerced the

defendant and obtained his signature. He would submit that the plaintiff

has not taken steps to amend the plaint to incorporate the subsequent

events in the pleadings. Therefore, in the absence of any pleadings, the

alleged compromise agreement cannot be looked into for any purpose.

20.If the above submission advanced by the learned Senior

Counsel is accepted, then the plaintiff ought to have file a petition to

record the compromise before the trial Court. Admittedly, no step was

taken by the parties to settle the issue. More over, Ex.A33 came to be

existence after filing of this suit. In such circumstances, there cannot be

a full relience on the document alone. According to the plaintiff, with

regard to the first block in main building claim a sum of Rs.1,31,65,300/-

has been made, as if the entire construction has been completed in second

floor. However, in Commissioner report Ex.A18, it has been mentioned

that compared to ground and first floor portions in main building first

block, the second floor constitution is on recent origin.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

21.It is not stated in the plaint about the date of completion of

construction work either in the plaint in O.S.No.124 of 2012 or in the

plaint in O.S.No.392 of 2010 or in the notice issued by the plaintiff in

Ex.A7 to Ex.A9. However, Ex.A33 compromise agreement dated

02.06.2014 it has been mentioned that the plaintiff has completed his

work on 10.04.2010. It is not stated on which date each stage of the

construction has been completed in respect of three buildings. Ex.A26

has been relied upon to show that he transported materials in those

vehicles. The said documents have been proved as false by Ex.B 57 by

the defendant's side. There is no material placed to prove the

procurement of materials, amount spent for the purchase of materials as

well as the amount spent for labour charges. There is no explanation on

the part of the plaintiff for completing entire construction work with

respect to the main building first block without receiving payment for

completing each level of construction. As per clause 5 of the

construction agreement dated 29.08.2008, which itself shows that the

plaintiff failed to complete the construction work as per the agreement.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

22.It is not the case of the plaintiff that he has sent notice to the

first defendant to clear payment on completion of each level described in

clause 5 of the terms of the construction contract. It is the case of the

plaintiff that he has completed construction work in main building first

block and office building. However, the plaintiff did not issue notice to

the first defendant to conduct joint survey within 7 days as per clause six

of the construction agreement. A perusal of the Ex.A19, copy of the

building plan which has been relied by the plaintiff, would show that the

plaintiff has not completed the construction work as per the construction

agreement. The plaintiff has not pleaded anything about Ex.A26 which

consists book maintained by the plaintiff regarding money transaction

with the defendant and various bills.

23.The plaintiff had originally filed a suit in O.S.No.392 of 2010

on the file of the Subordinate Court, Nagercoil for bare injunction,

restraining the defendant/trust from engaging any other contractor to

carry out remaining construction work unless balance amount due to the

plaintiff is duly settled or until contract is lawfully cancelled. It is

relevant to extract Order II Rule 2 CPC as hereunder:-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

(2)Relinquishment of part of claim.—Where a plaintiff omits to sue in respect of, or intentionally relinquishes, any portion of his claim, he shall not afterwards sue in respect of the portion so omitted or relinquished.

It is pertinent to mention that based on the cause of action for dues under

Ex.A1 to Ex.A3 agreements, the plaintiff has chosen to file a suit

O.S.No.124 of 2012. The cause of action for the suit in O.S.No.124 of

2012 is independent and there is no question of O.S.No.124 of 2012 is

being hit by the Order II and Rule 2 of the Civil Procedure Code. It is

also pertinent to mention that the defendant has filed I.A.No.546 of 2012

in O.S.No.124 of 2012 to reject the plaint on the very same ground that

the suit is hit by the Order II Rule 2 CPC and the said application was

dismissed by the trial Court by an order dated 15.12.2013.

24.The college was opened by the first defendant on 24.08.2009.

As per Ex.A41, the plaintiff had caused a paper advertisement in Daily

Thanthi newspaper. It is the specific case of the plaintiff that after the

college opening function, the first defendant had handed over three

cheques Ex.A4 to Ex.A6 for a sum of Rs.65,78,000/- dated 15.10.2009

and had requested to present the cheques after his instructions.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

According to the plaintiff, on 09.01.2010, the first defendant paid a sum

of Rs.47,00,000/- to the plaintiff and the same is pleaded in the plaint.

There is no denial in the written statement. The cheque issued by the

first defendant under Ex.A4 to Ex.A6 were returned upaid and the

plaintiff chosen to file a criminal cases before the learned Judicial

Magistrate, Nagercoil under Ex.A10 to Ex.A12.

25.The learned Senior Counsel appearing for the plaintiff would

submit that the plaintiff continued the work without any payment from

the defendant. The learned Senior Counsel to strengthen his contention,

he has relied upon the judgment reported in 2006 5 SCC 588 in a case of

Anil Rishi Vs. Gurbaksh Singh to show that in terms of Section 102 of

the Indian Evidence Act, the initial onus is always on the plaintiff and if

he discharges that onus and makes out a case which entitles him to a

relief, the onus shifts to the defendant to prove those circumstances, if

any, which would disentitle the plaintiff to the same. The learned Senior

Counsel would further submit that any amount of evidence without

pleadings is inadmissible. To strengthen his contention, he has relied

upon the decision of the Hon'ble Supreme Court reported in (2018) 11

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

SCC 119 in a case of Ratanlal Vs. Sundarabai Govardhandas

Samusuka to show that the parties to a suit are always govern by their

pleadings, any amount of evidence or proof adduced without there being

proper pleadings, is had no and will not come rescue of the parties.

26.According to the plaintiff, the 1st defendant admits non-payment

and the plaintiff and the first defendant have had earlier transactions.

The plaintiff has assisted the defendant by purchasing lands as and when

requested by D.W.1 and the same is evident from Ex.A36 to Ex.A40. It

is seen from the Ex.A17-CRP(MD)No.2753 of 2010 filed by the first

defendant wherein it has been alleged that “it is submitted that

subsequently, we commenced construction work for six buildings in our

College campus to a total extent of 76000 sq.ft., so as to satisfy AICTE

norms”. Whereas in the written statement, the defendants have stated

that they have engaged new contractor to continue work and complete

the work in respect of two buildings, within the stipulated time. The first

defendant claims that he had engaged third party for alleged completion

of construction of the three buildings covered under Ex.A1 to Ex.A3,

which according to the defendant was abandoned by the plaintiff.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

Admittedly, the date of alleged abandonment has not been stated

anywhere. In the written statement, there is no mention about any name

of the contractor, who is said to have completed the construction.

27.In order to support the case of the first defendant with regard to

third party contractor, one Murugesan has been examined as D.W.2.

However, whose name has not been mentioned in the written statement.

In the chief examination of D.W.2, he states that he was given the job of

mason and centering related work between last week of November 2008

and 30.12.2010. The allegation that the so called third party contractor,

said to be D.W.2, completed construction before the approval in 2009

itself is not accepted one. D.W.2 deposed that the construction materials

would be purchased and given to him. D.W.2 admits that he has no

juniors or engineer and he does not know what is the extent of building

constructed by him in square feet. In support of construction said to

have been carried out through D.W.2, Ex.B1 to Ex.B56 have been

marked. It is seen from the records that those documents were not filed

along with written statement. A report of the Advocate Commissioner

filed in CRP.(MD)No.2734 of 2010 has been marked as Ex.A18. The

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

defendant has not filed any objection to the Advocate Commissioner's

report. A perusal of Ex.A18 shows details of construction made in the

building. According to the plaintiff, as per Ex.A18 clearly records the

construction made by the plaintiff. D.W.1 in his cross-examination,

admits that the contents of Advocate Commissioner's report are correct.

The first defendant trust has admitted breach of payment of 20% advance

even as on date of Ex.A1 to Ex.A3. The defendant cannot take

advantage of their own wrong. On the other hand, the plaintiff has

completed its part of obligation under Ex.A1 to Ex.A3.

28.It is pertinent to mention that Ex.A1 to Ex.A3 agreements are

admitted by the defendants. The plaintiff had originally filed the suit in

O.S.No.392 of 2010 on the file of the Sub Court, Nagercoil, for bare

injunction, restraining the defendant Trust from engaging any other

contractor. Thereafter, based on the cause of action for recovery of dues

under Ex.A1 to Ex.A3, the suit in O.S.No.124 of 2012 has been filed.

Admittedly, the first defendant has not paid the amount of Rs.

1,68,27,160/- as on date of Ex.A1 to Ex.A3, as on 29.08.2008 with

regard to 20% of payment shall be made at commencement of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

construction work. In cross examination, D.W.1 states that the plaintiff

had agreed that Rs.55,00,000/- as advance is sufficient. In this regard,

D.W.1 has not placed any material before the trial Court. An argument

was made as to why the plaintiff continued work without any payment

from the first defendant. D.W.1 admits the non-payment of 20% of

advance amount and the plaintiff has marked documents to show that the

plaintiff and the first defendant had earlier transaction in Ex.A36 to

Ex.A40 and the plaintiff had no reason to doubt the bonofides of the first

defendant at that time.

29.In view of the above, it is clear that the plaintiff has proved the

claim of the money under Ex.A1 to Ex.A3, on the other hand, the first

defendant trust, who claims that he engaged third party to complete the

construction, failed to prove the same. The initial burden lies on the

plaintiff is proved. The defendant has not proved the specific allegation

of completion of construction only till plinth level.

30.The learned Senior Counsel appearing for the plaintiff would

submit that the plaintiff specifically pleaded that he is entitled to the suit

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

claim along with interest under “doctrine of unjust enrichment”. The

transaction covered under Ex.A1 to Ex.A3 is a commercial transaction of

construction, therefore, the interest rate may be enhanced at the rate of

12% per annum. The learned Senior Counsel to strengthen his

contentions has relied upon the judgement of Hon'ble Supreme Court of

India reported in 1997 (10) SCC 681 in Mahesh Chandra Bansal Vs.

Krishna Swardoop Singhal to show that as regards interest pendent lite

the main part of sub Section (1) of Section 34 of the Code of Civil

Procedure prescribes that interest has to be awarded at a reasonable rate.

At this juncture, it is relevant to refer the Section 34 of the Code of Civil

Procedure, which reads as follows:-

34. Interest— (1) Where and in so far as a decree is for the payment of money, the Court may, in the decree, order interest at such rate as the Court deems reasonable to be paid on the principal sum adjudged, from the date of the suit to the date of the decree, in addition to any interest adjudged on such principal sum for any period prior to the institution of the suit, with further interest at such rate not exceeding six per cent, per annum as the Court deems reasonable on such principal sum from the date of the decree to the date of payment, or to such earlier date as the Court thinks fit :

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

[Provided that where the liability in relation to the sum so adjudged had arisen out of a commercial transaction, the rate of such further interest may exceed six per cent, per annum, but shall not exceed the contractual rate of interest or where there is no contractual rate, the rate at which moneys are lent or advanced by nationalised banks in relation to commercial transactions.

Explanation I.—In this sub-section, "nationalised bank" means a corresponding new bank as defined in the Banking Companies (Acquisition and Transfer of Undertakings) Act 1970 (5 of 1970).

Explanation II.—For the purposes of this section, a transaction is a commercial transaction, if it is connected with the industry, trade or business of the party incurring the liability.] (2) Where such a decree is silent with respect to the payment of further interest on such principal sum from the date of the decree to the date of payment or other earlier date, the Court shall be deemed to have refused such interest, and a separate suit therefore shall not lie.

31.It is relevant to cite judgment of the Hon'ble Supreme Court of

India reported in (2009) 11 SCC 60 in C.K.Sasankan Vs. Dhanalakshmi

Bank Ltd., wherein it has been held about the scope and application of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

Section 34 of the Code of Civil Procedure, according tot he provisions of

Section 34, interest is to be awarded at a reasonable rate and on the

principle amount. Although amount of interest from the date of filing of

the suit, till the date of decree and thereafter, till realization is in the

discretion of Court, as is confirmed by use of the word “may” in Section

32, but such discretion has to be exercised by Court properly, reasonably

and on sound legal principles and not arbitrarily and while doing so the

Court is also to consider the parameters, scope and ambit of Section 34

CPC. The Hon'ble Supreme Court, in a case of Rampur Fertiliser Ltd

Vs. Vigyan Chemicals Industries, reported in (2009) 12 SCC 324, has

held that “in absence of any agreement or statutory provision or a

mercantile usage, interest payable can be only at the market rate and such

interest is payable upon establishment of totality of circumstances

justifying exercise of such equitable jurisdiction. In ascertaining the rate

of interest the Court of law can take judicial notice both inflation as also

fall in bank rate of interest. The bank rate of interest both for

commercial purposes and other purposes has been the subject matter of

statutory provisions”.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

32.In Ex.A1 to Ex.A3 construction agreements, there is no clause

mention about if any party violates the terms of agreement, then, the

party aggrieved would entitle the commercial rate of interest at 12% or

more, where there is no specific clause in the agreement, the plaintiff is

not entitled for 12% interest as claimed in his plaint. The reasonable rate

of interest for the period the suit was pending and subsequent interest at

6% per annum has been decreed by the Court below, on considering the

entire evidence on the case, does not require any interference by this

Court.

33.In view of the above discussions, we are of the view that there

is no reason to interfere in the impugned judgment and decree passed by

the Court below. There is no merit in these appeals and the same are

liable to be dismissed. The points are answered accordingly.

34.In the result,

i)first appeal in A.S.(MD)No.53 of 2019 is dismissed,

ii)first appeal in A.S.(MD)No.174 of 2021 is also dismissed and

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

iii)the judgment and decree dated 28.04.2018 passed in O.S.

No.124 of 2012 on the file of the District Judge, Kanyakumari District at

Nagercoil is hereby confirmed. There shall be no order as to costs.





                                                                                  (G.R.S., J.) & (M.J.R., J.)
                                                                                             24.04.2025
                     NCC             : Yes / No
                     Index           : Yes / No
                     gns




                     To


The District Judge, Kanyakumari District at Nagercoil.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm ) AS.(MD)Nos.53 of 2019 & 174 of 2021

G.R.SWAMINATHAN,J.

and M.JOTHIRAMAN, J.

gns

Pre-Delivery Judgement made in A.S.(MD)Nos.53 of 2019 & 174 of 2021

24.04.2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 25/04/2025 03:23:24 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter